SN Description Unit No. Length Breadth Height QTY Rate Amount


1 Earthe work in excavation
Plinth beam at 3-3 cft 1 25.00 2.25 1.00 56.25
Plinth beam at 4-4 cft 1 26.41 2.25 1.00 59.42
Plinth beam at 5-5 cft 1 27.72 2.25 1.00 62.36
Plinth beam at 6-6 cft 1 28.49 2.25 1.00 64.10
Plinth beam at 7-7 cft 1 30.77 2.25 1.00 69.22
For footing F39 cft 1 6.50 6.50 7.00 295.75

Total quantity of earth work in excavation 607.11 8.75 5312.22


2 Back filling
Half of earth work in excavation cft 303.56

Total quantity of back filling 303.56 5.00 1517.78


3 Dressing
Plinth beam at 3-3 cft 1 25.00 2.25 - 56.25
Plinth beam at 4-4 cft 1 26.41 2.25 - 59.42
Plinth beam at 5-5 cft 1 27.72 2.25 - 62.36
Plinth beam at 6-6 cft 1 28.49 2.25 - 64.10
Plinth beam at 7-7 cft 1 30.77 2.25 - 69.22
For footing F39 cft 1 6.50 6.50 - 42.25
sides cft 4 6.50 - 7.00 182.00

Total quantity of Dressing 535.61 3.00 1606.83


4 Boulder soling
For footing F39 cft 1 6.50 6.50 1.00 42.25

Total quantity of Dressing 42.25 91.95 3884.89


5 PCC work
Plinth beam at 3-3 cft 1 25.00 1.50 0.33 12.38
Plinth beam at 4-4 cft 1 26.41 1.50 0.33 13.07
Plinth beam at 5-5 cft 1 27.72 1.50 0.33 13.72
Plinth beam at 6-6 cft 1 28.49 1.50 0.33 14.10
Plinth beam at 7-7 cft 1 30.77 1.50 0.33 15.23
For footing F39 cft 1 6.33 6.33 0.33 13.22

Total quantity of PCC work 81.72 225.00 18387.46


5 PCC for RCC work
Plinth beam at 3-3 cft 1 25.00 0.75 1.50 28.13
Plinth beam at 4-4 cft 1 26.41 0.75 1.50 29.71
Plinth beam at 5-5 cft 1 27.72 0.75 1.50 31.18
Plinth beam at 6-6 cft 1 28.49 0.75 1.50 32.05
Plinth beam at 7-7 cft 1 30.77 0.75 1.50 34.61
Column above Plinth beam (C) cft 2 1.00 1.00 8.00 16.00
Column above PB (C19 to C34) cft 16 1.50 1.50 8.50 306.00
Column C3 to C5 cft 3 1.50 1.50 2.62 17.71
Column C6 to C18 cft 13 1.50 1.50 2.62 76.75
For footing F39 cft 1 6.00 6.00 0.75 27.16
For trapozoid area cft 1 11.22 11.22

Total quantity of PCC for RCC work 610.52 300.00 183156.81


6 Shuttering work
Plinth beam at 3-3 (PCC area) cft 2 25.00 - 0.33 16.50
Plinth beam at 4-4 cft 2 26.41 - 0.33 17.43
Plinth beam at 5-5 cft 2 27.72 - 0.33 18.29
Plinth beam at 6-6 cft 2 28.49 - 0.33 18.80
Plinth beam at 7-7 cft 2 30.77 - 0.33 20.31
For footing F39 cft 4 6.50 - 0.33 8.58
Plinth beam at 3-3 (RCC area) cft 2 25.00 - 1.50 75.00
Plinth beam at 4-4 cft 2 26.41 - 1.50 79.23
Plinth beam at 5-5 cft 2 27.72 - 1.50 83.15
Plinth beam at 6-6 cft 2 28.49 - 1.50 85.47
Plinth beam at 7-7 cft 2 30.77 - 1.50 92.30
Plinth beam at 8-8 cft 2 32.80 - 1.50 98.40
Column above Plinth beam (C) cft 4 1.00 - 8.00 32.00
Column above PB (C19 to C34) cft 64 1.50 - 8.50 816.00
Column C3 to C5 cft 12 1.50 - 2.62 47.23
Column C6 to C18 cft 52 1.50 - 2.62 204.67
For footing F39 cft 4 6.00 - 0.75 18.11

Total quantity of shuttering work 1731.47 50.00 86573.47


7 Steel reinforcement work
Qty of steel kg 2932.38 2932.38

Total quantity of steel reinforcement 2932.38 13.00 38120.94


Total value of Pipe shed 338560.40
Sum of 13% Vat 44012.85
Total value of Pipe Shed including 13% VAT 382573.25

……………………………………… ……………………………………… ………………………………………