Job Loss Analysis

Department: DES JLA Type:


Created Date: 25-03-19 Work Type:
Last Review Date: Work Activity:

JLA Owner
Owner’s Name Position
Abdul Rafiq HES Officer

Development Team
Development Team Member Name Position
Abdul Rafiq HES Officer
Usman Site Engineer
Permit Holder

Reviewers:
Reviewer Name Position Date Approved

Personal Protective Equipment (PPE) Selected Comments


Safety Shoes
Hard Hat
Safety Glasses
Fire Resistant Clothing
Face Shields
Goggles
Lifeline/Body Harness
Hearing Protection
Air Purifying Respirator
Supplied Air Respirator - SCBA
Welding Hood
Welding/Pipe Clothing
Welding Mask/Goggles
Personal Floatation Device
Long pants
Long sleeve shirt
Gloves
Other
Safety Cones/Barricades
Safety Vest
Knee Pads
Caution Tape
Substantial leather footwear
Winter Clothing

Place asterisk (*) next to


Essential Safeguards
No. Job Steps Potential Hazard Specific Safeguards
1
Steel handling and loading Injury to worker by load or sharp
edge. ( cut , hand , foot or back Supervisor to conduct daily crew
injury) meeting prior to start work.

Use proper PPEs.

2
Obstcles on area. May cause tripping and sliping Carry out good housekeeping and
hazard. stacking of material accordingly.

Supervisor to conduct daily crew


meeting prior to start work.

Area shall be barricaded properly.

3
Steel cutting by hand tool Inappropriate tools can lead to an All hand tools must be in good
Injury to worker condition.
No homemade hand tools to be
used at site

Workers using the tools shall be


trained and well aware of the pecific
hazards associated with the use of
tools.

Fit for duty gloves shall be used


while using the tools.

Unauthorised person shall not


allowed in working area.
4
Hazard Analysis Tool
Instructions: Complete the JLA for the task to be conducted per the scope of the permit and work plan. Identify each individual
job step, the hazards present with each step, and then identify the safeguards to eliminate or mitigate each of the hazards.
Use the common safeguards list to help identify safeguards for each of the hazards. Put an "X" in each box that applies and
transfer those safeguards to the "specific safeguards" sections of the JLA above.

Common Safeguards List

The safeguard list below is not a complete list of safeguards for work. Each hazard from each job step in the JLA needs to be
completely evaluated for the best safeguard using the hierarchy of controls. The safeguards below are typical and are provided to
help the JLA developers with some of the most common safeguards.
C1 - Hydrocarbon / G3 - Dropped Objects Mo4 - Manual Handling
Toxic Vapors and Liquids o Barricade below o Assisted lifting >50lbs
o Verify Zero Energy o Mesh Fencing o Review Lift Techniques
o Maintain Ventilation o Netting below Mo5 - Mobile Equipt / Traffic
o Review SDS o Tool Lanyards o Traffic Watch
o Respiratory Protection o Cover and Label Floor Openings o Hard Barricades
o Continuous Monitoring (specify) o Good Housekeeping o Spotter while moving
o Liquid Containment Me1 - Power Tools o Identify Sensitive Equipment
o Know Wind Direction o Barricade Area o Secure Load
o Skin / Body Protection o Guards & handles in place o Travel Plan Pre-Approved
C2 - Fumes / Dusts / Fibers o Focus on Line of Fire Risk o Lane Closure
o Use Wet Techniques o Stable Body Position o Signs / Cones
o Adequate Ventilation o Inspect Tools & Cord / Hoses P1 - Pressure
o Barricade/Signs o Secure Loose Clothing o Verify Zero Energy
o No pressurized air for cleaning Me2 - Rotating Equipment o Proper Pressure Rated Hose
o Respiratory Protection o Verify Zero Energy o Whip Checks/Full Flow Stop Checks
E1 - Electrical Hazards o Restrain equipment o Break Containment Away
o Verify Zero Energy Mo1 - Cut/Pinch/Crush S1 - Noise
o Ensure Grounding/Bonding o Cut Resistant Gloves o Hearing Protection
o Barricades / Signs o Communication Plan o Alt. Communication Plan
o CPR Certified Standby o Guards / Barricades T1 - Heat / Cold Stress Hazards
o GFCI Required o Cap Sharp Edges/Impalement Haz o Stay Hydrated
o Review Procedure Steps o Review Potential Pinch Points o Active Heat Stress Monitoring
G1 - Fall Hazards Mo2 - Slip/Trip/Walking Surface o Break every ______ min.
o Inspect Scaffold before use o Review Tripping Hazards o Cold Weather PPE / Gloves
o Fall Protection Equipment o Flag Potential Trip Hazards T2 - Hot Cold Surfaces
o Proper Tie Off Point o Check Ground Conditions o Wrist Protection/Gauntlets
o Excavation/Open Hole Barricaded o Store tools out of walkways o Allow for cooling time
o SR Lanyard if <20 feet (6 meters) o Secure Cords/Hoses o Barricade / Barriers
o Discuss Rescue Plan Mo3 - Line of Fire T3 - Fire Hazards
G2 - Lifting / Rigging o Barricade Line of Fire Zone o Fire Watch on Duty
o Check for Load Ratings o Identify LOF Hazards o Charged Extinguishers / Fire Hose
o Certified Rigger o Focus on Hand & Body Placement o Remove Flammables and Combustibles
o Communications Plan in Place OTHER HAZARDS TO CONSIDER
o Qualified Crane Signal Person Lighting Weather
o Adequate Use of Tag-lines SIMOPS Sensitive Equipment
o Rigging/Crane Inspection Current Radiation Human Factors
o Barricade Lift Zone Biological SSE