Hyundai Nishat Motors Project

Shop drawing status


A Approved Updated on: 16th Feb, 2019
B Approved with comments, Resubmission not required
C Approved with comments, Resubmission required
D Rejected
E Submitted for review/Approval
Steam System Water supply RLNG Drainage Firesuppression
Sr. No. Area
Site review HO review Comments Site review HO review Comments Site review HO review Comments Site review HO review Comments Site review HO review Comments
HNMPL-TMC-RLNG-GT1-001 8325-HNML-PMC-DR-PS-001: B
A A D A A A E
1 External services sheet 1/3: D for site review
2 TCF toilets D A B
3 TCF office toilets C A B
4 Paint shop C C D D
5 Canteen kitchen A E
6 Warehouse toilet C
7 Body shop toilet C B A
8 Canteen locker room B E
9 PDI toilet A
10 Canteen toilet B