Cost per % of total

Sno Description
Sqft cost
A Civil works
1 Excavation 15.964 0.9
2 Anti-termite treatment 0.107
3 Sub-structure - Water proofing 3.965 0.2
RCC works, Block work, Plaster,
4 Misc civil works 966.769 52
Total 986.805 53.1
B Finishing Work
1 Flooring 142.01 7.6
2 Kitchen platform with sink 21.414 1.2
3 Entrance lobby 9.156 0.5
4 Wood works 67.819 3.6
5 Water proofing 12.742 0.7
6 Gypsum plaster 36.522 2
7 P.O.P false ceiling 6.498 0.3
8 External plastering 20.824 1.1
9 Internal plastering 21.263 1.1
10 Staircase painting 1.912 0.1
11 Lift shaft painting 0.345
12 Duct painting 2.532 0.1
13 Ceiling plastering 7.623 0.4
14 Aluminium work 46.198 2.5
15 M.S Railing 11.163 0.6
16 Façade work 6.19 0.3
Total 414.211 22.1

C Service work
1 Plumbing 51.573 2.8
2 CP Sanitary 44.453 2.4
3 Firefighting 23.435 1.3
4 Electrical 76.444 4.1
5 Lifts 82.408 4.4
6 IBMS 16.336 0.9
7 Solar water system 4.395 0.2
8 DG Set 6.592 0.4
Total 305.636 16.5

Initital total ( A+B+C) 1706.652 91.7


Site Establishment 33.018 1.8
Electrical & Water charges 1.5% 26.339 1.4
Contingencies for temp.works 17.559 0.9
EHS budget 8.779 0.5
CONSTRUCTION COST / Sqft 1792.347 96.3