Name of Project: - 220 KV S/S GIS Madhuban Bapudham

Date of Start of work: -29/12/2016

Scheduled Date of Completion: - 28/06/2018

CIVIL Works:

1) Main gantry FDN: - 33/33


Auxiliary FDN: - 233/242 (Remaining 9 nos. LA foundation will be completed after placing of T/F
on T/F Plinth.

2) Transformer Plinth: - 4/4 (83%- chilling tank work is in progress)


3) Trench: - 710/735 (96%)
4) Road: - 602/ 615 (96%)
5) Control room building: 74% (Painting & tile work in progress) (All GIS halls of 33KV, 132KV
& 220 KV are completed, cleaned and handed over for erection work)
6) 33 KV GIS Hall: 90%
7) 132 KV GIS Hall: 90%
8) 220 KV GIS Hall: 90%

Men power working at Site: - 56


Overall Civil work Progress: - 88%

Electrical Works: -

1) Earth mat laying: - 95%


2) Main Structure Erection: - 100 %
Auxiliary Structure Erection: - 99 %

3) Main structure earthing: - 80%


Auxiliary structure earthing: - 75 %
Trench Earthing: - Yet to start

4) Outdoor Equipment Erection: - 90 %


5) Indoor GIS Erection: - 10 %
6) Transformer Erection: - Yet to start
7) Testing & Commissioning: - Yet to start

Overall Electrical Progress works: - 54%


Men power working at Site: -

Combined progress of Works: - 72%

BOTTLENECKS: - Erection Engineer of M/S. Siemens is required deadly now for 220 KV & 132
KV GIS modules erection activities.
Name of Project: - 220 KV S/S (Hybrid) Pratap Vihar

Date of Start of work: -12/12/2016

Scheduled Date of Completion: - 11/03/2018

CIVIL Works:

1) Main gantry FDN: - 64/64


Auxiliary FDN: - 216/216
Hybrid Pass: - 28/28

2) Transformer Plinth: - 4/4 (65%) all plinth work completed only one no T/F received radiator
bank foundation work has not started due to insufficient man power.
3) Trench in RM: - 285/690 (48%) work in progress.
4) Road in RM: - 00/350(12%) toe wall in progress
5) Control room building: (67%) Flooring work in progress

Overall Civil work Progress: - 69.5%

Men power working at Site: - 21

Electrical Works: -

1) Earth mat laying: - 100 %


2) Main Structure Erection: - 100 %
Auxiliary Structure Erection: - 100%

3) Main structure earthing: - 50 %


Auxiliary structure earthing: - 20 %
Trench Earthing: - Yet to Start

4) Equipment Erection: - Yet to Start


5) Transformer Erection: - Yet to Start
6) Testing & Commissioning: - Yet to Start

Overall Electrical Progress work: - 46 %

Men power working at Site: - NIL


Combined progress of Works: - 60 %

BOTTLENECKS: - 54 Man power required for completion of work earliest. While from last two
months average 10 men are working at site. “HGIS (PASS-Module) for 220 KV / 132 KV & 33 KV
has not been reached at site so far. Inspection call for 132 KV / 33 KV PASS-Modules has not been
raised by the firm so far.