Professional Documents
Culture Documents
Bernard Cvijanovic
Senior Sales Manager, ArcelorMittal Commercial RPS
Buenos Aires, 24th August 2011
1
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
A bit of history…
2
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Types of steel sheet piles – 1
U - section
Z - section
Combined wall
3
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Types of steel sheet piles – 2
Wx (cm3/m)
30 000
• temporary, small excavations / 25 000
retaining structures: 20 000
W x < 2 500 15 000
• marine structures (<12.0m dredge 10 000
5015
level) / deep excavations: 5 000
3200
W x < 5 000 4800 4000
0
• large quay walls / deep cofferdams: U-type Z-type HZM/AZ Pipe/AZ
Wx > 5 000
4
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Hot rolled Z and U type steel sheet piles (2011)
AZ 13 AZ 18 AZ 26 AZ 48
Z type
AZ 13-770 AZ 18-700 AZ 26-700 AZ 38-700N
PU 12 PU 18 PU 22 PU 28 PU 32
GU 7N GU 13-500 GU 16-400
U type
AU 16 AU 20 AU 25
5
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Old range of HZ / AZ (since 1990’s)
23
17
1050
462
6
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Steel grades for hot rolled steel sheet piles
8
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
CASE STUDY
Unterinntalbahn (Brenner) project – Austria
• Carried out by
9
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Challenges
• All retaining walls initially designed in concrete – sheet pile combined walls not
previously used in Austria as temporary structure
• Proximity to existing (running) railway line and roads, and to buildings
• Proximity to river Inn and risk of flooding
• Existing groundwater level
• Multiple crossing over/under river, roads and existing railway
• Multiple construction methods
– Conventional tunneling (including under compressed air)
– Cut-and-cover method with underwater concreting
– Shield tunneling method
• Many different cross sections along the 40km track
10
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
New range of HZ-M
Nb of h t s w
sections (mm) (mm) (mm) (mm)
w/4
w tmax tmax
r t
h h1 y y h y y
h h1 y y s s
s
11
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Comparison HZ-M / HZ
Iy Wel,y * G100%
(cm 4/m) (cm 3/m) (kg/m2)
Combination C23
Combination 12
12
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
New HZ-M production facility
13
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Performance of new HZ-M range
HZ-M
HZ…. 12 & 24
Infill sheet pile: AZ18-700
13 265 18 895
14
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Driving tests HZ king piles
15
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Driving tests AZ sheet piles
16
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Driving tests – water jetting
tubes
15 ÷ 25 bar Water
Pump Tank
17
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Declutching detection: DIXERAN
Detail A
18
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Cut & cover building phases – 1
19
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Driving of sheet piles
20
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Example of driving plan
HZ-AZ combined walls and PU anchor walls
21
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Driving of sheet piles
HZ-AZ combined walls and PU anchor walls
22
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Driving of sheet piles
Introduction of sealant – use of driving template
23
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Driving of sheet piles
PU anchor wall
24
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Dredging works
25
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Cut & cover building phases – 2
26
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Underwater works supervised by divers
27
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Anchoring & concreting
28
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Dewatering of trenches
29
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Cut & cover building phases – 3
30
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Finishing concreting works after dewatering
31
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Tunnel construction / introduction of tunneling
machine in finished dry trench
32
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Removal of sheet piles for re-use or sale
33
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Temporary sheet pile retaining wall for
safety shaft
34
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Proximity to roads and existing railway
35
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Congonhas Airport, Sao Paulo, Project Location
h
August 2011
Bridge abutments
50
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Straight web steel sheet piles AS 500
• gravity structure
300 mm ≤ L ≤ 500 mm
• deep wharfs / quays / breakwaters / cofferdams
testing: EN10248-1
• structures founded on bedrock
• no anchors
51
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Types of cells
Circular cells
junction pile
Diaphragm cells
52
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
CASE STUDY
Solis hydroelectric dam, Switzerland
53
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Looking for a solution – 1
54
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Looking for a solution – 2
55
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Original design – complex double-walled sheet pile
cofferdam with 6 levels of struts
56
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
After optimization…
57
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Section along cofferdam
Lake bed
Silty lake sediments
φ ∼ 20-24°
γ ~ 19-21 kN/m3
• 528 sheet piles (AS500-9.5 and AS500-12) with a total tonnage of 859 kt were delivered.
58
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
A logistical challenge
Spreader beam
with attachment
for handling of
long piles
59
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Putting into place the circular template
60
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Installation
junction pile
61
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
After excavation and drainage
62
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Next step – reuse of sheet piles and conversion
from temporary to permanent cofferdam!
63
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Dique de Carena, Puerto General Belgrano, Bahia
Blanca
70
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Tug-boat quay in Paraíso, Panama Canal
AS 500-12.0
20 circular cells
φ = 15.0 m, L = 18.5 – 20.0 m
≈ 3000 t
71
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Circular Cell Structure
E-METHANEX Berth, Damietta, Egypt
72
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Diaphragm Cell Structure
Essar Quay wall, Hazira, India
73
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Agenda
74
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Durability of steel structures
75
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Introducing AM LoCor™
76 76
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
Agenda
77
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011
ArcelorMittal Sheet Piling ⇒ Foundation Solutions
78
Buenos Aires, 24th August 2011 Foundations Conference Argentina 2011