Professional Documents
Culture Documents
Load estimates are the summation of heat transfer elements into (gains) or out of (losses) the
spaces of a building. Each heat transfer element is called load components, which can be
assembled into one of three basic groups, external space loads, internal space loads and system
loads. To properly understand the workings of the various external, internal and system load
components, the following items need to be gathered from a set of plans, existing building
surveys or occupant interviews:
• Use of the spaces within the building (offices, conference room, lab, data
center)
we Calculate the summer sensible load for the West Street Video Building using the Heat load
calculation methods divided the whole system into two zones ,calculated heat transfer for
slabs,wall,doors,window,floor,and roof of each zone
.
1 Load Calculation For Left side
Cooling
Lat. Elev. Heating (MWB)
Location
(N) (Ft) (F)
Baltimore 39 154 11 75
Fs = 0.73
Udoor=0.4Btu/h.F.ft2
qdoor=0.4*20.4*64
qdoor=522.4 Btu/hr
Figure 2 door Plan drawing
Qcfm=213.33 cfm
qvent=1.08*213.33*64
Qvent=14745.36 Btu/hr
Awindow=Area of window=72*3ft2=216ft2
Heat Load
qwindow CalculationBtu/hr
=12026.88 For Roof
Btu/hr
QRoof =URoof*ARoof* (to-ti) ……. (eq.7)
Where
o 2
R=5*3= 15 Btu/h F.ft
ARoof=40 *40=1600ft2
QRoof =0.066*1600*64
QRoof=6758.5 Btu/hr
2 Heat Load Calculation for Right Side
Fs=0.73
Phldu=Perimeter of slab=40+40+40=120ft
Qslab=0.73*120*64
Qslab=5606.4 Btu/hr
Qdoor=0.4*20.4*64
Qdoor=522.4 Btu/hr
Store Ventilation/infiltration Heating Load:
Qvent=Store Ventilation Load
Qcfm=0.5*16*1600/60
Qcfm=213.33 cfm
Now putting above values in eq.9 we have
qvent=1.08*213.33*64
Qvent=14745.36 Btu/hr
Thermal Resistance OF Wall material:
R-Value
Wall Material Refrance/Table
(h*f*ft/Btu)
R-Total 16.41
Adoor= 3*6.8ft2
Qwall=0.06*1683.6*64
Qwall=6465 Btu/hr
Where
o 2
R=5*3= 15 Btu/h F.ft
ARoof=40 *40=1600ft2
QRoof =0.066*1600*64
QRoof
QRoof=6758.5 Btu/hr
Heat Transfer through For Wall
Qwall=Uwall*Awall* (to-ti) ……. (eq.6)
Adoor= 3*6.8ft2
Qwall=0.06*1897.2*64
Qwall=7284.5 Btu/hr
Total Head Load Calculation for Left Side
Qvent
14745.36
Qslab 5606.5
Qdoor
522.4
Qroof
6758.5
Qwall
7284.5
Total
34917.26
Table 1 LHS Load Calculation
Qslab 5606.4
Qwall
6465
Qdoor
522.4
Qwindow
12026.88
Qroof
6758.5
Qvent
14745.4
Total 46124.58
Table 1 RHS Load Calculation
Qs=34917.5+46124.58
Qs=81042.08 Btu/hr
Qs= 81042.08/12 Ton of Referigeration
Qs=6.75 tor
II. Equipment Sizing
(1) at point (3) for acceptable indoor air quality and energy saving. The mixture is then
represented as
supplied to the room through the supply fan, supply duct, and ceiling diffuser
(6). Supply air then absorbs the sensible and latent load from the space, becoming the space
air (2).
Room air is returned back to the cooling unit again and forms a closed cycle. Part of the
return air is exhausted to balance the outdoor air intake and infiltration
So
Assumptions:
Let Relative humidity =50%
Supply temperature = 57 0F
As we we maintain 50%
So
Wreturn=80
Wsupply=50
So Given equation
ql=4680*1616*(80-50)
Assumptions:
Let Relative humidity =50%
Supply temperature = 57 0F
qs=46124.58 Btu/hr
As we we maintain 50%
So
Wreturn=80
Wsupply=50
So Given equation
ql=4680*2134*(80-50)
So
Total Cfm=2134+1616
12000Btu/hr =1ton=3.5KW
So
Total CFM=3750
And
Fan efficiency=80%
Fan Hp = 3750*14.7/(3979*0.8)
Psychrometric analysis also enables the designer to account for other smaller loads that may be
imposed on the system such as ducts and fans in equipment sizing. By identifying the different
state points of the air as it passes through the duct system and over the supply and return fans,
the volume flow rates of air computed by the analysis become necessarily inclusive of the
effects of the ducts and fans in equipment sizing.