Villa Baseline

ID Task WBS Task Name Duration Start Finish Predecessors Successors Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1
2 1 UNIT-1 BaseLine For VILLA (Group 5 Suhail Group) 162 days Wed 06-02-19 Thu 19-09-19 1%

3 1.1 Preliminary Approvals and Survey 10 days Wed 06-02-19 Tue 19-02-19 30%
4 1.1.1 Acceptance of LOA. 1 day Wed 06-02-19 Wed 06-02-19 7,8,5,6 100%
5 1.1.2 Preliminary Survey before Starting the works 2 days Thu 07-02-19 Fri 08-02-19 4 6 100%
6 1.1.3 Approvals for Temporary Connection (I.e Water , Electricity
2 days etc.)
Mon 11-02-19 Tue 12-02-19 4,5 7 0%
7 1.1.4 Approval of Design And Drawing 3 days Wed 13-02-19 Fri 15-02-19 4,6 8,11,12 0%
8 1.1.5 Approval of Working Methodology , Testing Plan and
2 days
Safety Plan
Mon 18-02-19 Tue 19-02-19 4,7 10,12 0%
9 1.2 SUB-STRUCTURE 32 days Mon 18-02-19 Tue 02-04-19 0%
10 1.2.1 Excavation/cutting for level adjustment 3 days Wed 20-02-19 Fri 22-02-19 8 12 0%
11 1.2.2 Roadbase 2 days Mon 18-02-19 Tue 19-02-19 7 12 0%
12 1.2.3 Leveling & Compaction 1 day Mon 25-02-19 Mon 25-02-19 8,7,10,11 13 0%
13 1.2.4 PCC for Foundation 1 day Tue 26-02-19 Tue 26-02-19 12 14 0%
14 1.2.5 Footing Steel Reinforcement 2 days Wed 27-02-19 Thu 28-02-19 13 15 0%
15 1.2.6 Footing Shutters 1 day Fri 01-03-19 Fri 01-03-19 14 16 0%
16 1.2.7 Footing Casting 1 day Mon 04-03-19 Mon 04-03-19 15 17 0%
17 1.2.8 Neck Column Steel Reinforcement and Shuttering3 days Tue 05-03-19 Thu 07-03-19 16 18 0%
18 1.2.9 Neck Column Casting 1 day Fri 08-03-19 Fri 08-03-19 17 19 0%
19 1.2.10 Neck Column Curing 1 day Mon 11-03-19 Mon 11-03-19 18 20 0%
20 1.2.11 Backfilling After Footing 1 day Tue 12-03-19 Tue 12-03-19 19 21 0%
21 1.2.12 PCC for Tie Beam 1 day Wed 13-03-19 Wed 13-03-19 20 22 0%
22 1.2.13 Tie Beam Steel Reinforcement and Shuttering 3 days Thu 14-03-19 Mon 18-03-19 21 23 0%
23 1.2.14 Tie Beam Casting 1 day Tue 19-03-19 Tue 19-03-19 22 24 0%
24 1.2.15 Tie Beam De-shutter & Curing 3 days Wed 20-03-19 Fri 22-03-19 23 25,30 0%
25 1.2.16 Water Proofing 1 day Mon 25-03-19 Mon 25-03-19 24 26 0%
26 1.2.17 Backfilling After Tie Beam 1 day Tue 26-03-19 Tue 26-03-19 25 27 0%
27 1.2.18 Grade Slab Casting 5 days Wed 27-03-19 Tue 02-04-19 26 30 0%
28 1.3 SUPER STRUCTURE 74 days Wed 03-04-19 Mon 15-07-19 0%
29 1.3.1 GROUND FLOOR to FIRST FLOOR 32 days Wed 03-04-19 Thu 16-05-19 0%
30 1.3.1.1 Ground to First Floor - Columns Reinforcement15 days Wed 03-04-19 Tue 23-04-19 24,27 31 0%
31 1.3.1.2 Ground to First Floor - Columns & Shutter 3 days Wed 24-04-19 Fri 26-04-19 30 32 0%
32 1.3.1.3 Ground to First Floor - Columns Casting 2 days Mon 29-04-19 Tue 30-04-19 31 33 0%
33 1.3.1.4 First Floor - Slab & Beams Shutter 3 days Wed 01-05-19 Fri 03-05-19 32 34 0%
34 1.3.1.5 First Floor - Slab & Beams Reinforcement 2 days Mon 06-05-19 Tue 07-05-19 33 35 0%
35 1.3.1.6 Shuttering for Staircase 2 days Wed 08-05-19 Thu 09-05-19 34 36 0%
36 1.3.1.7 Reinforcement for Staircase 2 days Fri 10-05-19 Mon 13-05-19 35 37 0%
37 1.3.1.8 First Floor - Slab & Beams Casting 1 day Tue 14-05-19 Tue 14-05-19 36 38 0%
38 1.3.1.9 Casting of Staircase 2 days Wed 15-05-19 Thu 16-05-19 37 40,52SS+3 days 0%
39 1.3.2 FIRST FLOOR to ROOF 33 days Fri 17-05-19 Tue 02-07-19 0%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Page 1
Villa Baseline
ID Task WBS Task Name Duration Start Finish Predecessors Successors Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
40 1.3.2.1 First to Roof Floor - Columns Reinforcement 7 days Fri 17-05-19 Mon 27-05-19 38 41 0%
41 1.3.2.2 First to Roof Floor - Columns & Shutter 4 days Tue 28-05-19 Fri 31-05-19 40 42 0%
42 1.3.2.3 First to Roof Floor - Columns Casting 1 day Mon 03-06-19 Mon 03-06-19 41 43 0%
43 1.3.2.4 Roof Floor - Slab & Beams Shutter 6 days Tue 04-06-19 Tue 11-06-19 42 44 0%
44 1.3.2.5 Roof Floor - Slab & Beams Reinforcement 5 days Wed 12-06-19 Tue 18-06-19 43 45 0%
45 1.3.2.6 Roof Floor - Slab & Beams Casting 2 days Wed 19-06-19 Thu 20-06-19 44 46 0%
46 1.3.2.7 Deshuttering -Roof Floor Slab 8 days Fri 21-06-19 Tue 02-07-19 45 48,55SS+3 days 0%
47 1.3.3 ROOF 9 days Wed 03-07-19 Mon 15-07-19 0%
48 1.3.3.1 Parapet Wall - Reinforcement 4 days Wed 03-07-19 Mon 08-07-19 46 49 0%
49 1.3.3.2 Parapet Wall - Shutter 3 days Tue 09-07-19 Thu 11-07-19 48 50 0%
50 1.3.3.3 Parapet Wall - Casting 2 days Fri 12-07-19 Mon 15-07-19 49 68,69,70,71 0%
51 1.4 FINISHING 77 days Mon 20-05-19 Tue 03-09-19 0%
52 1.4.1 Block Work 45 days Mon 20-05-19 Fri 19-07-19 38SS+3 days 53SS+3 days 0%
53 1.4.2 Plaster Preparation 45 days Thu 23-05-19 Wed 24-07-19 52SS+3 days 54SS+3 days 0%
54 1.4.3 Internal Plaster 45 days Tue 28-05-19 Mon 29-07-19 53SS+3 days 56SS+3 days 0%
55 1.4.4 Wet Area Waterproofing 2 days Wed 26-06-19 Thu 27-06-19 46SS+3 days 60 0%
56 1.4.5 Primary Painting Internal & First Stucco 45 days Fri 31-05-19 Thu 01-08-19 54SS+3 days 57,73SS+4 days 0%
57 1.4.6 1 Screed for water proofing 1 day Fri 02-08-19 Fri 02-08-19 56 58,59,60 0%
58 1.4.7 Hardware fittings for doors- Brass antique for main
2 days
door and stainless
Mon 05-08-19
steel for theTue
other
06-08-19
doors 57 66 0%
59 1.4.8 window- UPVC white colors window with mosquito 7 days
net and MSMon grill05-08-19 Tue 13-08-19 57 60 0%
60 1.4.9 Flooring- Living, Dinning,Kitchen and Bedrooms are7 days
vitrified tileWed
of NITCO
14-08-19
of 2'x2' Thu 22-08-19 57,59,55 61,62,63,64 0%
61 1.4.10 Bathroom - Anti-skid ceramic tile flooring 7 days Fri 23-08-19 Mon 02-09-19 60 74 0%
62 1.4.11 Nitco tile dadoing 5 days Fri 23-08-19 Thu 29-08-19 60 75 0%
63 1.4.12 Chromium plated fittngs 3 days Fri 23-08-19 Tue 27-08-19 60 76 0%
64 1.4.13 Kitchen- ceramic glazed tile dadoing 5 days Fri 23-08-19 Thu 29-08-19 60 65 0%
65 1.4.14 Granite counter with stainless steel sink and 3 days Fri 30-08-19 Tue 03-09-19 64 80 0%
drain board
66 1.4.15 RCC staircase - granite cladding for trades and 7 days Wed 07-08-19 Thu 15-08-19 58 67 0%
risers
67 1.4.16 Steel railing with wooden hand rail 4 days Fri 16-08-19 Wed 21-08-19 66 77 0%
68 1.4.17 Fencing- Picket fencing 3 days Tue 16-07-19 Thu 18-07-19 50 78 0%
69 1.4.18 Car Park- Concerte finish 3 days Tue 16-07-19 Thu 18-07-19 50 81 0%
70 1.4.19 Open Utility- Concrete Finish 3 days Tue 16-07-19 Thu 18-07-19 50 82 0%
71 1.4.20 Terrace- terracotta tiles 2 days Tue 16-07-19 Wed 17-07-19 50 83 0%
72 1.5 ELECTRICAL 66 days Thu 06-06-19 Thu 05-09-19 0%
73 1.5.1 BSES Power supply of 5KW 10 days Thu 06-06-19 Wed 10-07-19 56SS+4 days 74,75,76,77,78,79,80,81,82,83,84 0%
74 1.5.2 Legrand Modulus switches and sockets with 2 days Tue 03-09-19 Wed 04-09-19 73,61 86 0%
copper wiring of Anchor or equivalent
75 1.5.3 Backup genrator 1 KW power for each unit with 2 days Fri 30-08-19 Mon 02-09-19 73,62 86 0%
automatic changeover switch
76 1.5.4 A/C points in living and bedrooms 2 days Wed 28-08-19 Thu 29-08-19 73,63 86 0%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Page 2
Villa Baseline
ID Task WBS Task Name Duration Start Finish Predecessors Successors Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Mode Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
77 1.5.5 TV and Telephones points for living and 2 days Thu 22-08-19 Fri 23-08-19 73,67 86 0%
bedrooms
78 1.5.6 Provision for intercom facility from security 2 days Fri 19-07-19 Mon 22-07-19 73,68 86 0%
cabin to each unit
79 1.5.7 Exhaust fans points in Kitchen and Bathroom 2 days Thu 11-07-19 Fri 12-07-19 73 86 0%
80 1.5.8 Aquagaurd point in kitchen 2 days Wed 04-09-19 Thu 05-09-19 73,65 86 0%
81 1.5.9 Ceiling fan points in living , dinning, and 2 days Fri 19-07-19 Mon 22-07-19 73,69 86 0%
bedrooms
82 1.5.10 Night lamp point in all bedrooms 2 days Fri 19-07-19 Mon 22-07-19 73,70 86 0%
83 1.5.11 Adequate light points in all rooms 2 days Thu 18-07-19 Fri 19-07-19 73,71 86 0%
84 1.5.12 washingmachine point in utility 2 days Thu 11-07-19 Fri 12-07-19 73 86 0%
85 1.6 Testing , Commissioning and Handover 10 days Fri 06-09-19 Thu 19-09-19 0%
86 1.6.1 Testing & Commissioning 9 days Fri 06-09-19 Wed 18-09-19
84,74,75,76,77,78,79,80,81,82,83
87 0%
87 1.6.2 Handover 1 day Thu 19-09-19 Thu 19-09-19 86 0%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Page 3