ID WBS Task Name Duration Start Finish Resource Names Predecessors r 30, '19 Apr 13, '19 Apr

Duration Start Finish Resource Names Predecessors r 30, '19 Apr 13, '19 Apr 27, '19 May 11, '19 May 25, '19 Jun 8, '19 Jun 22, '19 Jul 6, '19 Jul 20
M F T S W S T M F T S W S T M F T S W S T M F T S W S T
1 1 Hilton IT Programming and Training 60 days Mon 4/15/19 Mon 7/8/19 Hilton Hilton

2 2 Hilton Plaza Project Hand Over Plan 71 days? Wed 4/10/19 Wed 7/17/19 PMC

3 2.1 Hotel Opening 67 days? Mon 4/15/19 Wed 7/17/19

9 2.2 Health and Safety Req. 28 days? Mon 4/15/19 Fri 5/17/19

33 2.3 MEP 40 days? Mon 4/15/19 Tue 6/11/19 Ofoq

58 2.4 Façade Painting 30 days Wed 4/10/19 Wed 5/15/19

61 2.5 Building Admin Handover 20 days? Mon 4/15/19 Tue 5/7/19 PMC

72 2.6 Landscape Handover 46 days? Sun 4/14/19 Wed 6/19/19

73 2.6.1 Old Swimming Pool and Dec 15 days Mon 4/15/19 Thu 5/2/19 Alecon Alecon

74 2.6.2 New Swimming Pool and Deck 25 days Mon 4/15/19 Tue 5/14/19 Alecon Alecon

75 2.6.3 Kids Aqua and Deck 25 days Mon 4/15/19 Tue 5/14/19 EMAK EMAK

76 2.6.4 Sea View Landscape 15 days Mon 4/15/19 Thu 5/2/19

77 2.6.4.1 Alecon Hardscape 10 days Mon 4/15/19 Thu 4/25/19 Alecon Alecon

78 2.6.4.2 Beach Side Sahara Wall 15 days Mon 4/15/19 Thu 5/2/19 Redcon Redcon

79 2.6.5 Entrance View Landscape 46 days? Sun 4/14/19 Wed 6/19/19

80 2.6.5.1 Gabion Zone No . 1 28 days? Mon 4/15/19 Fri 5/17/19 Redcon

81 2.6.5.1.1 Engineering 0 days Mon 4/22/19 Mon 4/22/19 4/22

82 2.6.5.1.1.1 Gabion road Proposal 0 days Mon 4/22/19 Mon 4/22/19 Okoplan 4/22

83 2.6.5.1.2 Procurement 13 days Wed 4/24/19 Thu 5/9/19

84 2.6.5.1.2.1 Electrical Manholes cover delivery 0 days Wed 4/24/19 Wed 4/24/19 Alecon 4/24

85 2.6.5.1.2.2 3 brothers up light delivery 0 days Thu 5/9/19 Thu 5/9/19 Redcon 5/9

86 2.6.5.1.3 Construction 28 days? Mon 4/15/19 Fri 5/17/19

87 2.6.5.1.3.1 Civil Activity 28 days? Mon 4/15/19 Fri 5/17/19

88 2.6.5.1.3.1.1 Shera Road Shaping 15 days Mon 4/15/19 Thu 5/2/19 Redcon Redcon

89 2.6.5.1.3.1.2 Shera Garnett wall cladding 15 days? Wed 4/17/19 Sat 5/4/19 Redcon 88SS+2 days Redcon

90 2.5.10.5.1.3.1.5 S.O.G of Gabion road 7 days Fri 5/3/19 Thu 5/9/19 Redcon 88 Redcon

91 2.6.5.1.3.1.4 Electrical 11km Manholes insulation 2 days? Fri 5/10/19 Mon 5/13/19 Alecon 90 Alecon

92 2.6.5.1.3.1.5 Electrical 11km Manhole Cover installation 1 day? Tue 5/14/19 Tue 5/14/19 Alecon 91 Alecon

93 2.6.5.1.3.1.6 Shera Road interlock install 3 days Wed 5/15/19 Fri 5/17/19 Redcon 92 Redcon

94 2.6.5.1.3.1.7 Elofoq R.O. House keeping 3 days Sat 4/20/19 Tue 4/23/19 Ofoq Ofoq

95 2.6.5.1.3.1.8 Gabion Road Manhole cover installation 1 day? Wed 4/24/19 Wed 4/24/19 Alecon 94 Alecon

96 2.6.5.1.3.1.9 interlock Gabion road install 5 days Thu 4/25/19 Wed 5/1/19 Redcon 95 Redcon

97 2.6.5.1.3.1.10 Shara fences increase hight 19 days Mon 4/15/19 Mon 5/6/19

98 2.6.5.1.3.1.10.1 RC feancs Columns 10 days Mon 4/15/19 Thu 4/25/19 Redcon Redcon

99 2.6.5.1.3.1.10.2 Block Work 10 days Wed 4/17/19 Mon 4/29/19 Redcon 98SS+2 days Redcon

100 2.6.5.1.3.1.10.3 Plastering Work 10 days Fri 4/19/19 Wed 5/1/19 Redcon 99SS+2 days Redcon

101 2.6.5.1.3.1.10.4 Painting Work 5 days Thu 5/2/19 Mon 5/6/19 Redcon 100 Redcon

102 2.6.5.1.3.2 Electrical Activity 18 days? Fri 4/19/19 Thu 5/9/19

103 2.6.5.1.3.2.1 first fix lighting Shara Road 15 days Fri 4/19/19 Mon 5/6/19 Redcon 89SS+2 days Redcon

104 2.6.5.1.3.2.2 second fix lighting Shara Road 2 days? Tue 5/7/19 Wed 5/8/19 Redcon 103 Redcon

105 2.6.5.1.3.2.3 third fix lighting of Shara Road 1 day? Thu 5/9/19 Thu 5/9/19 Redcon 104 Redcon

106 2.6.5.1.3.2.4 CCTV First Fix Shata Road 15 days Fri 4/19/19 Mon 5/6/19 Redcon 89SS+2 days Redcon

107 2.6.5.1.3.2.5 CCTV second fix lighting Shara Road 2 days? Tue 5/7/19 Wed 5/8/19 Redcon 106 Redcon

108 2.6.5.1.3.2.6 CCTV third fix lighting of Shara Road 1 day? Thu 5/9/19 Thu 5/9/19 Quantum 107 Quantum

109 2.6.5.2 Retaining Wall Lift Station Zone No.2 32 days? Sun 4/14/19 Thu 5/23/19 Redcon

110 2.6.5.2.1 Procurement 0 days Sun 4/14/19 Sun 4/14/19 4/14

111 2.6.5.2.1.1 Electrical Manholes cover delivery 0 days Sun 4/14/19 Sun 4/14/19 Redcon 4/14

112 2.6.5.2.1.2 3 brothers up light delivery 0 days Sun 4/14/19 Sun 4/14/19 Redcon 4/14

113 2.6.5.2.1.3 Gravito Materil Delivery 0 days Sun 4/14/19 Sun 4/14/19 Redcon 4/14

114 2.6.5.2.1.4 Lift Station covers 0 days Sun 4/14/19 Sun 4/14/19 Palm 4/14

115 2.6.5.2.1.5 Tank Repair Material 0 days Sun 4/14/19 Sun 4/14/19 Redcon 4/14

116 2.6.5.2.2 Construction 26 days? Mon 4/22/19 Thu 5/23/19

117 2.6.5.2.2.1 Civil Activity 26 days? Mon 4/22/19 Thu 5/23/19

118 2.6.5.2.2.1.1 11 Km Cable lenghtening third fix 2 days? Mon 4/22/19 Tue 4/23/19 Alecon Alecon

119 2.6.5.2.2.1.2 Retaining wall plastering frist coat 4 days Wed 4/24/19 Mon 4/29/19 Redcon 118 Redcon

120 2.6.5.2.2.1.3 Retaining Wall Plastering filling 9 days Tue 4/30/19 Wed 5/8/19 Redcon 119 Redcon

121 2.6.5.2.2.1.4 Retaining Wall Gravito 5 days Thu 5/9/19 Wed 5/15/19 Redcon 120 Redcon

122 2.6.5.2.2.1.5 S.O.G of Retaining Road 6 days Thu 5/16/19 Thu 5/23/19 Redcon 121 Redcon

Project: Hilton Hand Over Plan Task Progress Summary External Tasks Deadline
Date: Mon 4/22/19 Split Milestone Project Summary External Milestone

Page 1
ID WBS Task Name Duration Start Finish Resource Names Predecessors r 30, '19 Apr 13, '19 Apr 27, '19 May 11, '19 May 25, '19 Jun 8, '19 Jun 22, '19 Jul 6, '19 Jul 20
M F T S W S T M F T S W S T M F T S W S T M F T S W S T
123 2.6.5.2.2.1.6 Water Tank Repiar 5 days Wed 4/24/19 Tue 4/30/19 Redcon Redcon

124 2.6.5.2.2.1.7 Lift Station RC framwork 3 days? Mon 4/22/19 Wed 4/24/19 Palm Palm

125 2.6.5.2.2.1.8 Lift Station Repair 5 days? Thu 4/25/19 Wed 5/1/19 Palm 124 Palm

126 2.6.5.2.2.1.9 Lift Station insulation 3 days Thu 5/2/19 Sat 5/4/19 Palm 125 Palm

127 2.6.5.2.2.1.10 Lift Station Cover installation 1 day Sun 5/5/19 Sun 5/5/19 Palm 126 Palm

128 2.6.5.2.2.1.11 Rump House Keeping 0 days Wed 4/24/19 Wed 4/24/19 Palm 4/24

129 2.6.5.2.2.1.12 Rump House Keeping 0 days Wed 4/24/19 Wed 4/24/19 Ofoq 4/24

130 2.6.5.2.2.2 MEP Activity 19 days? Tue 4/30/19 Wed 5/22/19

131 2.6.5.2.2.2.1 Electrical Manholes insulation 1 day? Tue 4/30/19 Tue 4/30/19 Alecon 119 Alecon

132 2.6.5.2.2.2.2 Lift Station Tie in 1 day? Thu 5/2/19 Thu 5/2/19 Palm 125 Palm

133 2.6.5.2.2.2.3 Fountain Lift station Tie in 3 days Sun 5/5/19 Tue 5/7/19 Redcon 126 Redcon

134 2.6.5.2.2.2.4 Hydro Green main irrigation line Tie in 5 days? Thu 5/16/19 Wed 5/22/19 Hydrogreen 121 Hydrogreen

135 2.6.5.2.2.3 Electrical Activtiy 13 days? Tue 4/30/19 Tue 5/14/19

136 2.6.5.2.2.3.1 First fix lighting Retaining wall 9 days Tue 4/30/19 Wed 5/8/19 Redcon 119 Redcon

137 2.6.5.2.2.3.2 second Fix lighting Retaining Walls 3 days Thu 5/9/19 Mon 5/13/19 Redcon 136 Redcon

138 2.6.5.2.2.3.3 third Fix Lighting Retaianing Wallls 1 day? Tue 5/14/19 Tue 5/14/19 Redcon 137 Redcon

139 2.6.5.2.2.3.4 First Fix CCTV Retaining Wall 9 days Tue 4/30/19 Wed 5/8/19 Redcon 136SS Redcon

140 2.6.5.3 waterfall & lobby fountain Zone No. 3 24 days? Sun 4/14/19 Mon 5/13/19 Redcon

141 2.6.5.3.1 Engineering 3 days? Tue 4/23/19 Thu 4/25/19

142 2.6.5.3.1.1 New Parapet above Rump Shop Drawing 1 day? Tue 4/23/19 Tue 4/23/19 Redcon Redcon

143 2.6.5.3.1.2 Side Security Room Marble Flooring shop Drawing 1 day? Thu 4/25/19 Thu 4/25/19 Redcon Redcon

144 2.6.5.3.2 Procurement 13 days? Sun 4/14/19 Wed 5/1/19

145 2.6.5.3.2.1 Civil Activity 0 days Sun 4/14/19 Sun 4/14/19 4/14

146 2.6.5.3.2.1.1 Fountain Azmldo delivery Material 0 days Sun 4/14/19 Sun 4/14/19 4/14

147 2.6.5.3.2.1.2 Fountain Marble Delivery Material 0 days Sun 4/14/19 Sun 4/14/19 4/14

148 2.6.5.3.2.1.3 Grantte Plate Delivery Material 0 days Sun 4/14/19 Sun 4/14/19 4/14

149 2.6.5.3.2.2 MEP Activity 0 days? Thu 4/25/19 Thu 4/25/19 4/25

150 2.6.5.3.2.2.1 IT manholes Cover 0 days? Thu 4/25/19 Thu 4/25/19 Redcon 4/25

151 2.6.5.3.2.2.2 Electrical Manholes Cover 0 days? Thu 4/25/19 Thu 4/25/19 Redcon 4/25

152 2.6.5.3.2.2.3 Fountain Supplier Pump and filter 0 days? Thu 4/25/19 Thu 4/25/19 Fountain Supplier 4/25

153 2.6.5.3.2.3 Electrical Activity 13 days? Sun 4/14/19 Wed 5/1/19

154 2.6.5.3.2.3.1 Imported Fountain Lighting Fixtures 0 days? Tue 4/30/19 Tue 4/30/19 Client 4/30

155 2.6.5.3.2.3.2 3 Brothers Lighting Fixtures 0 days? Sun 4/14/19 Sun 4/14/19 Client 4/14

156 2.6.5.3.2.3.3 Main Distribution and sub Board Panels 0 days Wed 5/1/19 Wed 5/1/19 Redcon 5/1

157 2.6.5.3.2.3.4 Fountain Power Cable Delivery 0 days Mon 4/29/19 Mon 4/29/19 Redcon 4/29

158 2.6.5.3.2.3.5 Lighting Network Cable Delivery 0 days Mon 4/29/19 Mon 4/29/19 Redcon 4/29

159 2.6.5.3.2.3.6 Fountain Supplier Panels 0 days Sun 4/14/19 Sun 4/14/19 Fountain Supplier 4/14

160 2.6.5.3.2.3.7 IT Cables Delivery 0 days Sun 4/14/19 Sun 4/14/19 United System 4/14

161 2.6.5.3.2.3.8 CCTV Delivery 0 days Sun 4/14/19 Sun 4/14/19 Quantum 4/14

162 2.6.5.3.3 Construction 24 days? Mon 4/15/19 Mon 5/13/19

163 2.6.5.3.3.1 Civil Activity 23 days Mon 4/15/19 Fri 5/10/19

164 2.6.5.3.3.1.1 PALM Store Evacuation 0 days Mon 4/22/19 Mon 4/22/19 Palm 4/22

165 2.6.5.3.3.1.2 Mechanical Room finishing 19 days Mon 4/15/19 Mon 5/6/19

166 2.6.5.3.3.1.2.1 Mechanical Room internal insulation 2 days Mon 4/15/19 Tue 4/16/19 Redcon Redcon

167 2.6.5.3.3.1.2.2 internal insulation Plastering 3 days Wed 4/17/19 Fri 4/19/19 Redcon 166 Redcon

168 2.6.5.3.3.1.2.3 Equipment Footing pouring 1 day Sat 4/20/19 Sat 4/20/19 Redcon 167 Redcon

169 2.6.5.3.3.1.2.4 Ceramic tiles install 3 days Mon 4/22/19 Wed 4/24/19 Redcon 168 Redcon

170 2.6.5.3.3.1.2.5 External Room insulation 4 days Thu 4/25/19 Tue 4/30/19 Redcon 169 Redcon

171 2.6.5.3.3.1.2.6 External Marble instalation 6 days Wed 5/1/19 Mon 5/6/19 170

172 2.6.5.3.3.1.3 Waterfall finishing 14 days Mon 4/15/19 Wed 5/1/19

173 2.6.5.3.3.1.3.1 internal insulation Plastering 3 days Mon 4/15/19 Wed 4/17/19 Redcon Redcon

174 2.6.5.3.3.1.3.2 External insulation 2 days Thu 4/18/19 Fri 4/19/19 Redcon 173 Redcon

175 2.6.5.3.3.1.3.3 waterfall sub-base filling 5 days Mon 4/22/19 Fri 4/26/19 Redcon 174,164 Redcon

176 2.6.5.3.3.1.3.4 Waterfall sand filling 3 days Mon 4/29/19 Wed 5/1/19 Hydrogreen 175 Hydrogreen

177 2.6.5.3.3.1.4 Lobby Fountain finishing 23 days Mon 4/15/19 Fri 5/10/19

178 2.6.5.3.3.1.4.1 internal insulation 3 days Mon 4/15/19 Wed 4/17/19 Redcon Redcon

179 2.6.5.3.3.1.4.2 Azmldo installation 5 days Thu 4/18/19 Tue 4/23/19 Redcon 178 Redcon

180 2.6.5.3.3.1.4.3 Grantte Plate installation 5 days Wed 4/24/19 Tue 4/30/19 Redcon 179 Redcon

Project: Hilton Hand Over Plan Task Progress Summary External Tasks Deadline
Date: Mon 4/22/19 Split Milestone Project Summary External Milestone

Page 2
ID WBS Task Name Duration Start Finish Resource Names Predecessors r 30, '19 Apr 13, '19 Apr 27, '19 May 11, '19 May 25, '19 Jun 8, '19 Jun 22, '19 Jul 6, '19 Jul 20
M F T S W S T M F T S W S T M F T S W S T M F T S W S T
181 2.6.5.3.3.1.4.4 External Insulation 5 days Wed 5/1/19 Sun 5/5/19 Redcon 180 Redcon

182 2.6.5.3.3.1.4.5 Marble installation 5 days Mon 5/6/19 Fri 5/10/19 Redcon 181 Redcon

183 2.6.5.3.3.1.5 Crubstone remaining work 3 days Thu 5/2/19 Sat 5/4/19 Redcon 176 Redcon

184 2.6.5.3.3.1.6 Interlock Remaiang Work 6 days Sun 5/5/19 Fri 5/10/19 Redcon 183 Redcon

185 2.6.5.3.3.2 MEP Activity 13 days? Mon 4/29/19 Mon 5/13/19

186 2.6.5.3.3.2.1 Fountain Drainage Tie- out 2 days Wed 5/1/19 Thu 5/2/19 Redcon 170 Redcon

187 2.6.5.3.3.2.2 Fountain Water Source Tie - out 2 days Fri 5/3/19 Sat 5/4/19 Redcon 186 Redcon

188 2.6.5.3.3.2.3 Waterfall Drainage Tie- out 2 days Wed 5/1/19 Thu 5/2/19 Redcon 180 Redcon

189 2.6.5.3.3.2.4 Waterfall Water Source Tie - out 2 days Fri 5/3/19 Sat 5/4/19 Redcon 188 Redcon

190 2.6.5.3.3.2.5 Irrigation Network 13 days? Mon 4/29/19 Mon 5/13/19

191 2.6.5.3.3.2.5.1 Waterfall main line tie in 4 days Mon 4/29/19 Thu 5/2/19 Hydrogreen 175 Hydrogreen

192 2.6.5.3.3.2.5.2 Sub-network installation 5 days Wed 5/1/19 Sun 5/5/19 Hydrogreen 170 Hydrogreen

193 2.6.5.3.3.2.5.3 Sand filling 4 days Mon 5/6/19 Thu 5/9/19 Hydrogreen 192 Hydrogreen

194 2.6.5.3.3.2.5.4 Gress Patching 2 days? Fri 5/10/19 Mon 5/13/19 Hydrogreen 193 Hydrogreen

195 2.6.5.3.3.3 Electrical Activity 21 days? Mon 4/15/19 Wed 5/8/19

196 2.6.5.3.3.3.1 Electrical Power Cable Network and Manhole 12 days? Thu 4/25/19 Wed 5/8/19

197 2.6.5.3.3.3.1.1 Manhole Poring 5 days Thu 4/25/19 Wed 5/1/19 Redcon Redcon

198 2.6.5.3.3.3.1.2 Manhole Insulation 1 day? Thu 5/2/19 Thu 5/2/19 Redcon 197 Redcon

199 2.6.5.3.3.3.1.3 Manhole lenghtening 4 days Fri 5/3/19 Mon 5/6/19 Redcon 198 Redcon

200 2.6.5.3.3.3.1.4 Manhole cover installation 1 day? Tue 5/7/19 Tue 5/7/19 Redcon 199 Redcon

201 2.6.5.3.3.3.1.5 Cable Termunation 1 day? Wed 5/8/19 Wed 5/8/19 200,156

202 2.6.5.3.3.3.2 IT Network and Manhole 20 days? Mon 4/15/19 Tue 5/7/19

203 2.6.5.3.3.3.2.1 Manhole Poring 1 day? Mon 4/15/19 Mon 4/15/19 Redcon Redcon

204 2.6.5.3.3.3.2.2 Manhole Insulation 1 day? Tue 4/16/19 Tue 4/16/19 Redcon 203 Redcon

205 2.6.5.3.3.3.2.3 Manhole lenghtening 10 days Thu 4/25/19 Mon 5/6/19 United System 204 United System

206 2.6.5.3.3.3.2.4 Manhole cover installation 1 day? Tue 5/7/19 Tue 5/7/19 Redcon 205 Redcon

207 2.6.5.3.3.3.3 CCTV Network 12 days Mon 4/22/19 Sun 5/5/19

208 2.6.5.3.3.3.3.1 CCTV Conduts Frist Fix 3 days Mon 4/22/19 Wed 4/24/19 Redcon Redcon

209 2.6.5.3.3.3.3.2 CCTV Conduts lenghtenig 3 days Thu 4/25/19 Mon 4/29/19 Redcon 208 Redcon

210 2.6.5.3.3.3.3.3 CCTV Installation third Fix 3 days Tue 4/30/19 Thu 5/2/19 Quantum 209 Quantum

211 2.6.5.3.3.3.3.4 CCTV Network termunation 3 days Fri 5/3/19 Sun 5/5/19 Quantum 210 Quantum

212 2.6.5.3.3.3.4 Lighting Network 16 days? Mon 4/15/19 Fri 5/3/19 Redcon

213 2.6.5.3.3.3.4.1 lighting Network Frist Fix 1 day? Mon 4/15/19 Mon 4/15/19 Redcon Redcon

214 2.6.5.3.3.3.4.2 Lighting Network Secound Fix 1 day? Tue 4/16/19 Tue 4/16/19 Redcon 213 Redcon

215 2.6.5.3.3.3.4.3 Lighting Network third Fix 1 day? Tue 4/30/19 Tue 4/30/19 Redcon 214,154 Redcon

216 2.6.5.3.3.3.4.4 Lighting Network Termunation 3 days? Wed 5/1/19 Fri 5/3/19 Redcon 215,156 Redcon

217 2.6.5.3.3.3.5 BMS Lighting Network 0 days Tue 4/30/19 Tue 4/30/19 4/30

218 2.6.5.4 Main entrance founrain Zone No. 4 46 days? Sun 4/14/19 Wed 6/19/19 Redcon

219 2.6.5.4.1 Engineering 0 days Mon 4/22/19 Mon 4/22/19 4/22

220 2.6.5.4.1.1 Side Secuirty Room Design Release 0 days Mon 4/22/19 Mon 4/22/19 Okoplan 4/22

221 2.6.5.4.1.2 Grantte Plate Design Perposal 0 days Mon 4/22/19 Mon 4/22/19 Okoplan 4/22

222 2.6.5.4.2 Procurement 10 days? Sun 4/14/19 Thu 4/25/19

223 2.6.5.4.2.1 Civil Activtiy 0 days Sun 4/14/19 Sun 4/14/19 4/14

224 2.6.5.4.2.1.1 Fountain Azmldo delivery Material 0 days Sun 4/14/19 Sun 4/14/19 Redcon 4/14

225 2.6.5.4.2.1.2 Fountain Marble Delivery Material 0 days Sun 4/14/19 Sun 4/14/19 Redcon 4/14

226 2.6.5.4.2.1.3 Secuirty Room Glass Clading 0 days Sun 4/14/19 Sun 4/14/19 Redcon 4/14

227 2.6.5.4.2.1.4 Sliding Door Secuirty Room 0 days Sun 4/14/19 Sun 4/14/19 Client 4/14

228 2.6.5.4.2.2 MEP Activity 10 days? Sun 4/14/19 Thu 4/25/19

229 2.6.5.4.2.2.1 IT manholes Cover 0 days? Thu 4/25/19 Thu 4/25/19 Redcon 4/25

230 2.6.5.4.2.2.2 Electirical Manholes Cover 0 days? Thu 4/25/19 Thu 4/25/19 Redcon 4/25

231 2.6.5.4.2.2.3 Fountain Supplier Pump and filter 0 days? Thu 4/25/19 Thu 4/25/19 Fountain Supplier 4/25

232 2.6.5.4.2.2.4 Secuirty Room A/C system 0 days Sun 4/14/19 Sun 4/14/19 Redcon 4/14

233 2.6.5.4.2.2.5 Air Curtain of Secuirty Room 0 days Sun 4/14/19 Sun 4/14/19 Redcon 4/14

234 2.6.5.4.2.3 Electrical Activtiy 0 days Sun 4/14/19 Sun 4/14/19 4/14

235 2.6.5.4.2.3.1 X- Ray Secuirty Gate equipment 0 days Sun 4/14/19 Sun 4/14/19 Client 4/14

236 2.6.5.4.2.3.2 Imported Fountain Lighting Fixtures 0 days Sun 4/14/19 Sun 4/14/19 Client 4/14

237 2.6.5.4.2.3.3 3 Brothers Lighting Fixtures 0 days Sun 4/14/19 Sun 4/14/19 Client 4/14

238 2.6.5.4.2.3.4 Main Distrubation and sub Board Panels 0 days Sun 4/14/19 Sun 4/14/19 Redcon 4/14

Project: Hilton Hand Over Plan Task Progress Summary External Tasks Deadline
Date: Mon 4/22/19 Split Milestone Project Summary External Milestone

Page 3
ID WBS Task Name Duration Start Finish Resource Names Predecessors r 30, '19 Apr 13, '19 Apr 27, '19 May 11, '19 May 25, '19 Jun 8, '19 Jun 22, '19 Jul 6, '19 Jul 20
M F T S W S T M F T S W S T M F T S W S T M F T S W S T
239 2.6.5.4.2.3.5 Fountain Power Cable Delivery 0 days Sun 4/14/19 Sun 4/14/19 Redcon 4/14

240 2.6.5.4.2.3.6 Lighting Network Cable Delivery 0 days Sun 4/14/19 Sun 4/14/19 Redcon 4/14

241 2.6.5.4.2.3.7 Fountain Supplier Panels 0 days Sun 4/14/19 Sun 4/14/19 Fountain Supplier 4/14

242 2.6.5.4.2.3.8 IT Cables Delivery 0 days Sun 4/14/19 Sun 4/14/19 United System 4/14

243 2.6.5.4.2.3.9 CCTV Delivery 0 days Sun 4/14/19 Sun 4/14/19 Quantum 4/14

244 2.6.5.4.3 construction 46 days? Mon 4/15/19 Wed 6/19/19

245 2.6.5.4.3.1 Civil Activtiy 30 days Mon 4/15/19 Tue 5/21/19

246 2.6.5.4.3.1.1 Mechincal Room finishing 23 days Mon 4/15/19 Fri 5/10/19

247 2.6.5.4.3.1.1.1 Mechincal Room internal insulation 5 days Mon 4/15/19 Fri 4/19/19 Redcon Redcon

248 2.6.5.4.3.1.1.2 interinal insultation Plastring 5 days Sat 4/20/19 Thu 4/25/19 Redcon 247 Redcon

249 2.6.5.4.3.1.1.3 Equipment Footing pouring 3 days Fri 4/26/19 Tue 4/30/19 Redcon 248 Redcon

250 2.6.5.4.3.1.1.4 Cerimce tiles install 5 days Wed 5/1/19 Sun 5/5/19 Redcon 249 Redcon

251 2.6.5.4.3.1.1.5 Externail Room insulation 5 days Mon 5/6/19 Fri 5/10/19 Redcon 250 Redcon

252 2.6.5.4.3.1.2 main enterances finishing 30 days Mon 4/15/19 Tue 5/21/19

253 2.6.5.4.3.1.2.1 Mechanical Room internal insulation 5 days Mon 4/15/19 Fri 4/19/19 Redcon Redcon

254 2.6.5.4.3.1.2.2 internal insulation Plastering 5 days Sat 4/20/19 Thu 4/25/19 Redcon 253 Redcon

255 2.6.5.4.3.1.2.3 Equipment Footing pouring 5 days Fri 4/26/19 Thu 5/2/19 Redcon 254 Redcon

256 2.6.5.4.3.1.2.4 Ceramic tiles install 5 days Fri 5/3/19 Tue 5/7/19 Redcon 255 Redcon

257 2.6.5.4.3.1.2.5 External Room insulation 5 days Wed 5/8/19 Tue 5/14/19 Redcon 256 Redcon

258 2.6.5.4.3.1.2.6 External Marble instalation 5 days Wed 5/15/19 Tue 5/21/19 Redcon 257 Redcon

259 2.6.5.4.3.1.3 Secuirty Room finishing 29 days Mon 4/15/19 Mon 5/20/19

260 2.6.5.4.3.1.3.1 Secuirty Room excvation 3 days Mon 4/15/19 Wed 4/17/19 Redcon Redcon

261 2.6.5.4.3.1.3.2 secuirty Room footing 5 days Thu 4/18/19 Tue 4/23/19 Redcon 260 Redcon

262 2.6.5.4.3.1.3.3 Secuirty Room RC Columns 6 days Wed 4/24/19 Wed 5/1/19 Redcon 261 Redcon

263 2.6.5.4.3.1.3.4 Secuirty Room RC slab 6 days Thu 5/2/19 Tue 5/7/19 Redcon 262 Redcon

264 2.6.5.4.3.1.3.5 Secuirty Room Building Work 3 days Wed 5/8/19 Fri 5/10/19 Redcon 263 Redcon

265 2.6.5.4.3.1.3.6 Alminuim Calading 3 days Mon 5/13/19 Wed 5/15/19 Redcon 264 Redcon

266 2.6.5.4.3.1.3.7 Painting Work 3 days Thu 5/16/19 Mon 5/20/19 Redcon 265 Redcon

267 2.6.5.4.3.2 sub-base irrigation Failling 5 days Mon 5/13/19 Fri 5/17/19 Redcon 264 Redcon

268 2.6.5.4.3.3 Crubstone remaining work 5 days Mon 5/20/19 Fri 5/24/19 Redcon 267 Redcon

269 2.6.5.4.3.4 Interlock Remaiang Work 5 days Mon 5/27/19 Sat 6/1/19 Redcon 268 Redcon

270 2.6.5.4.3.5 MEP Activtiy 46 days? Mon 4/15/19 Wed 6/19/19

271 2.6.5.4.3.5.1 Fountain Drainage Tie- out 1 day? Mon 4/15/19 Mon 4/15/19 Redcon Redcon

272 2.6.5.4.3.5.2 Fountain Water Source Tie - out 1 day? Mon 4/15/19 Mon 4/15/19 Redcon Redcon

273 2.6.5.4.3.5.3 Irrigation Network 13 days Mon 5/20/19 Wed 6/12/19

274 2.6.5.4.3.5.3.1 Sub-network installation 5 days Mon 5/20/19 Fri 5/24/19 Hydrogreen 267 Hydrogreen

275 2.6.5.4.3.5.3.2 Sand filling 5 days Mon 5/27/19 Sat 6/1/19 Hydrogreen 274 Hydrogreen

276 2.6.5.4.3.5.3.3 Gress Patching 3 days Mon 6/10/19 Wed 6/12/19 Hydrogreen 275 Hydrogreen

277 2.6.5.4.3.5.4 Secuirty Room A/C network 3 days Mon 5/13/19 Wed 5/15/19 Redcon 264 Redcon

278 2.6.5.4.3.5.5 Electrical Activtiy 46 days? Mon 4/15/19 Wed 6/19/19

279 2.6.5.4.3.5.5.1 Secuirty Room electrical Activity 9 days Thu 5/16/19 Tue 5/28/19

280 2.6.5.4.3.5.5.1.1 Secuirty Room Fris Fix 3 days Thu 5/16/19 Mon 5/20/19 Redcon 277 Redcon

281 2.6.5.4.3.5.5.1.2 Secuirty Room Scound Fix 3 days Tue 5/21/19 Thu 5/23/19 Redcon 280 Redcon

282 2.6.5.4.3.5.5.1.3 Secuirty Room Third Fix 3 days Fri 5/24/19 Tue 5/28/19 Redcon 281 Redcon

283 2.6.5.4.3.5.5.2 Electrical Power Cable Network and Manhole 17 days? Thu 4/25/19 Wed 5/15/19

284 2.6.5.4.3.5.5.2.1 Manhole Poring 5 days Thu 4/25/19 Wed 5/1/19 Redcon Redcon

285 2.6.5.4.3.5.5.2.2 Manhole Insulation 3 days Thu 5/2/19 Sat 5/4/19 Redcon 284 Redcon

286 2.6.5.4.3.5.5.2.3 Manhole lenghtening 5 days Sun 5/5/19 Thu 5/9/19 Redcon 285 Redcon

287 2.6.5.4.3.5.5.2.4 Manhole cover installation 3 days Fri 5/10/19 Tue 5/14/19 Redcon 286 Redcon

288 2.6.5.4.3.5.5.2.5 Cable Termunation 1 day? Wed 5/15/19 Wed 5/15/19 Redcon 287 Redcon

289 2.6.5.4.3.5.5.3 IT Network and Manhole 13 days Mon 4/15/19 Tue 4/30/19

290 2.6.5.4.3.5.5.3.1 Manhole Poring 5 days Mon 4/15/19 Fri 4/19/19 Redcon Redcon

291 2.6.5.4.3.5.5.3.2 Manhole Insulation 1 day Sat 4/20/19 Sat 4/20/19 Redcon 290 Redcon

292 2.6.5.4.3.5.5.3.3 Manhole lenghtening 6 days Mon 4/22/19 Mon 4/29/19 Quantum 291 Quantum

293 2.6.5.4.3.5.5.3.4 Manhole cover installation 1 day Tue 4/30/19 Tue 4/30/19 Redcon 292 Redcon

294 2.6.5.4.3.5.5.4 CCTV Network 13 days? Mon 4/15/19 Tue 4/30/19

295 2.6.5.4.3.5.5.4.1 CCTV Conduts Frist Fix 3 days Mon 4/15/19 Wed 4/17/19 Redcon Redcon

296 2.6.5.4.3.5.5.4.2 CCTV Conduts lenghtenig 6 days Thu 4/18/19 Wed 4/24/19 Redcon 295 Redcon

Project: Hilton Hand Over Plan Task Progress Summary External Tasks Deadline
Date: Mon 4/22/19 Split Milestone Project Summary External Milestone

Page 4
ID WBS Task Name Duration Start Finish Resource Names Predecessors r 30, '19 Apr 13, '19 Apr 27, '19 May 11, '19 May 25, '19 Jun 8, '19 Jun 22, '19 Jul 6, '19 Jul 20
M F T S W S T M F T S W S T M F T S W S T M F T S W S T
297 2.6.5.4.3.5.5.4.3 CCTV Installation third Fix 3 days Thu 4/25/19 Mon 4/29/19 Quantum 296 Quantum

298 2.6.5.4.3.5.5.4.4 CCTV Network termunation 1 day? Tue 4/30/19 Tue 4/30/19 Quantum 297 Quantum

299 2.6.5.4.3.5.5.5 Lighting Network 18 days? Mon 5/20/19 Wed 6/19/19

300 2.6.5.4.3.5.5.5.1 lighting Network Frist Fix 5 days Mon 5/20/19 Fri 5/24/19 Redcon 267 Redcon

301 2.6.5.4.3.5.5.5.2 Lighting Network Secound Fix 5 days Fri 5/24/19 Thu 5/30/19 Redcon Redcon

302 2.6.5.4.3.5.5.5.3 Lighting Network third Fix 5 days Sat 6/1/19 Thu 6/13/19 Redcon 301 Redcon

303 2.6.5.4.3.5.5.5.4 Lighting Network Termunation 3 days Fri 6/14/19 Tue 6/18/19 Redcon 302 Redcon

304 2.6.5.4.3.5.5.5.5 BMS Lighting Network conncetion 1 day? Wed 6/19/19 Wed 6/19/19 Redcon 303 Redcon

305 2.6.5.5 Club Car Tunies Court Zone 5 40 days? Sun 4/14/19 Tue 6/11/19 Redcon

306 2.6.5.5.1 Engineering 0 days Sun 4/14/19 Sun 4/14/19 4/14

307 2.6.5.5.1.1 Club Electrical Socket Shop Drawing 0 days Sun 4/14/19 Sun 4/14/19 4/14

308 2.6.5.5.1.2 Tunies court Stairs shop drawing 0 days Sun 4/14/19 Sun 4/14/19 4/14

309 2.6.5.5.2 Procurement 0 days Sun 4/14/19 Sun 4/14/19 4/14

310 2.6.5.5.2.1 Club Car Power Socket Material Delivery 0 days Sun 4/14/19 Sun 4/14/19 4/14

311 2.6.5.5.2.2 IT Manholes Cover 0 days Sun 4/14/19 Sun 4/14/19 4/14

312 2.6.5.5.2.3 Plumping Manholes Cover 0 days Sun 4/14/19 Sun 4/14/19 4/14

313 2.6.5.5.3 Construction 40 days? Mon 4/15/19 Tue 6/11/19

314 2.6.5.5.3.1 Civil Activtiy 32 days Wed 4/24/19 Tue 6/11/19

315 2.6.5.5.3.1.1 Tunies Court Shaping activity 17 days Wed 4/24/19 Tue 5/14/19

316 2.6.5.5.3.1.1.1 Patching of side shoring 8 days Wed 4/24/19 Fri 5/3/19 Redcon Redcon

317 2.6.5.5.3.1.1.2 shaping level of Tunies Court 9 days Sat 5/4/19 Tue 5/14/19 Redcon 316 Redcon

318 2.6.5.5.3.1.2 sub-base irrigation Failling 5 days Wed 5/15/19 Tue 5/21/19 Redcon 317 Redcon

319 2.6.5.5.3.1.3 Crubstone remaining work 5 days Wed 5/22/19 Tue 5/28/19 Redcon 318 Redcon

320 2.6.5.5.3.1.4 Interlock Remaiang Work 5 days Wed 5/29/19 Tue 6/11/19 Redcon 319 Redcon

321 2.6.5.5.3.2 MEP Activtiy 38 days? Mon 4/15/19 Sat 6/1/19

322 2.6.5.5.3.2.1 Plumbing netwoek and manhloes activtiy 1 day? Mon 4/15/19 Mon 4/15/19 Redcon

323 2.6.5.5.3.2.1.1 Plumbing pipeing network 1 day? Mon 4/15/19 Mon 4/15/19 Redcon Redcon

324 2.6.5.5.3.2.1.2 Manhole RC pouring 1 day? Mon 4/15/19 Mon 4/15/19 Redcon Redcon

325 2.6.5.5.3.2.1.3 Manhole insulation activity 1 day? Mon 4/15/19 Mon 4/15/19 Redcon Redcon

326 2.6.5.5.3.2.1.4 Manhole forced line Test and Balance 1 day? Mon 4/15/19 Mon 4/15/19 Fountain Supplier Fountain Supplier

327 2.6.5.5.3.2.2 Irrigation Network 8 days? Wed 5/22/19 Sat 6/1/19

328 2.6.5.5.3.2.2.1 Sub-network installation 5 days Wed 5/22/19 Tue 5/28/19 Redcon 318 Redcon

329 2.6.5.5.3.2.2.2 Sand filling 3 days Wed 5/29/19 Sat 6/1/19 Redcon 328 Redcon

330 2.6.5.5.3.2.2.3 Gress Patching 1 day? Sat 6/1/19 Sat 6/1/19 Redcon Redcon

331 2.6.5.5.3.3 Electrical Activty 1 day? Mon 4/15/19 Mon 4/15/19

332 2.6.5.5.3.3.1 IT Network and Manhole 1 day? Mon 4/15/19 Mon 4/15/19

333 2.6.5.5.3.3.1.1 Manhole Poring 1 day? Mon 4/15/19 Mon 4/15/19

334 2.6.5.5.3.3.1.2 Manhole Insulation 1 day? Mon 4/15/19 Mon 4/15/19

335 2.6.5.5.3.3.1.3 Manhole lenghtening 1 day? Mon 4/15/19 Mon 4/15/19

336 2.6.5.5.3.3.1.4 Manhole cover installation 1 day? Mon 4/15/19 Mon 4/15/19

337 2.6.5.5.3.3.2 Lighting Network 1 day? Mon 4/15/19 Mon 4/15/19

338 2.6.5.5.3.3.2.1 lighting Network Frist Fix 1 day? Mon 4/15/19 Mon 4/15/19

339 2.6.5.5.3.3.2.2 Lighting Network Secound Fix 1 day? Mon 4/15/19 Mon 4/15/19

340 2.6.5.5.3.3.2.3 Lighting Network third Fix 1 day? Mon 4/15/19 Mon 4/15/19

341 2.6.5.5.3.3.2.4 Lighting Network Termunation 1 day? Mon 4/15/19 Mon 4/15/19

342 2.6.5.6 Gate, Fountain amd Parking Area Zone No. 6 1 day? Mon 4/15/19 Mon 4/15/19 Redcon

343 2.6.5.6.1 Engineering 1 day? Mon 4/15/19 Mon 4/15/19

346 2.6.5.6.2 Procurement 1 day? Mon 4/15/19 Mon 4/15/19

353 2.6.5.6.3 Construction 1 day? Mon 4/15/19 Mon 4/15/19

364 2.6.5.7 Laundry Route Zone No. 7 45 days? Mon 4/15/19 Tue 6/18/19

365 2.6.5.7.1 Demolish Extension extsisting wall 7 days Mon 4/15/19 Mon 4/22/19 Ofoq Ofoq

366 2.6.5.7.2 Construct Retaining Wall 15 days Mon 4/15/19 Thu 5/2/19 Redcon Redcon

367 2.6.5.7.3 Laundry route civil work palm side 30 days? Fri 5/3/19 Tue 6/18/19 Redcon 366 Redcon

368 2.6.5.7.4 Laundry route civil work extension side 30 days Fri 5/3/19 Tue 6/18/19 Redcon 365,366 Redcon

369 2.6.5.7.5 Sahara Road 10 days Mon 4/15/19 Thu 4/25/19 Redcon Redcon

370 2.6.5.7.6 Road Above Gabion 17 days Mon 4/15/19 Sat 5/4/19

371 2.6.5.7.6.1 Wall Cladding 10 days Mon 4/15/19 Thu 4/25/19 Redcon Redcon

372 2.6.5.7.6.2 Pave Road 7 days Fri 4/26/19 Sat 5/4/19 Redcon 371 Redcon

Project: Hilton Hand Over Plan Task Progress Summary External Tasks Deadline
Date: Mon 4/22/19 Split Milestone Project Summary External Milestone

Page 5
ID WBS Task Name Duration Start Finish Resource Names Predecessors r 30, '19 Apr 13, '19 Apr 27, '19 May 11, '19 May 25, '19 Jun 8, '19 Jun 22, '19 Jul 6, '19 Jul 20
M F T S W S T M F T S W S T M F T S W S T M F T S W S T
373 2.6.5.7.7 Road to Laundry Enterance 20 days Mon 4/15/19 Tue 5/7/19 Redcon Redcon

374 2.6.5.7.8 Retaining Wall and Road 20 days Mon 4/15/19 Tue 5/7/19 Redcon Redcon

375 2.6.5.7.9 Soft Scape 30 days Mon 4/15/19 Tue 5/21/19 Hydrogreen Hydrogreen

376 2.7 IT 30 days? Mon 4/15/19 Tue 5/21/19

384 2.8 Furniture 63 days? Wed 4/17/19 Mon 7/15/19

389 2.9 Elevators 20 days Mon 4/15/19 Tue 5/7/19

398 2.10 Owner Supplied Material 28 days? Mon 4/15/19 Fri 5/17/19

403 2.11 Master Key 30 days Sat 4/20/19 Tue 5/28/19 PMC PMC

Project: Hilton Hand Over Plan Task Progress Summary External Tasks Deadline
Date: Mon 4/22/19 Split Milestone Project Summary External Milestone