You are on page 1of 1

As per I.P.

C NO : 14 DATE : Oct -2006


Recovery towards dismantled usable materials

WORK EXECUTED
Item.
DESCRIPTION UNITS RATE (Rs.) UPTO DATE UPTO PREVIOUS THIS PERIOD
No
QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT
6.02 Dismantling of existing cross drainage structures
including disposal of resulting materials and or
salvaging usable materials complete as per Tech.
Spec. Cl. 202

a) Brick / Stone structures Nos 1.65 35,509.860 58,591.27 35,509.860 58,591.27 - -


c) Hume pipe of 900mm dia m 1055 - - - - -
c) Hume pipe of 650/600mm dia m 890 504.800 449,272.00 504.800 449,272.00 - -
Stone Slab Sq.m 11 -
7.02 Dismantling existing bridge structure including - -
disposal of resulting material
and/or salvaging usable materials complet as per
Tech. Spec. Cl. 202

a) Brick / Stone structures Nos 1.65 48,566.503 80,134.73 48,566.503 80,134.73 - -


c)Reinforcement Kg 11 21,040.500 231,445.50 21,040.500 231,445.50 - -
d) Pipe over 900mm dia m 1055 232.500 245,287.50 232.500 245,287.50 - -
Stone Slab Sq.m 11 -
TOTAL 1,064,731 TOTAL 1,064,731 TOTAL -

For Contractor: For Consultant: For Consultant: For Consultant:

Sr. Quantity Surveyor Dy. Resident Engineer Resident Engineer


Date: Date: Date: Date: