1 External Sand stone cladding Remaining Cladding work shall be completed

2 Internal paint work Internal paint shall be completed

3 Internal flooring (Floor Tiles) Completed

4 MS grill ventilator Paint on grills shall be completed

5 External landscaping and Plinth protection Repair of damaged areas

6 Electrical Wiring All points shall be checked and tested

Switch boards shall be checked and properly


7 Electrical switch board and lights installation
aligned
Connection in External DB shall be done
8 Electrical connection with external DB
properly

9 Rain water pipes Shall be installed

10 Bottom Khurra below rain water pipe Shall be constructed as per drawing

1: Shall be completed as per BOQ


11 Roof treatment
2: Khurra at roof shall be constructed
Hand hole shall be constructed and MS cover
12 Hand hole around Gate valve
shall be fixed

13 Septic tank cover slab Cover slab shall be completed & sealed properly

14 Vent pipe Shall be fixed properly & Cowel shall be placed

15 Enamel paint on Doors Final coat shall be done

16 Toilet signage Signage plates shall be installed

17 Fiber shed over ventilators Gaps shall be filled with silicone

18 Wire Mesh in ventilators Wire mesh in ventilators shall be fixed

ISSUED BY: