4"ø PVC 45 deg. Elbow 12 length 65.00 780.

00
4"x3''ø PVC wye reducer 7 length 68.00 476.00
4"ø pvc coupling 4 pcs. 65.00 260.00
4"ø pvc 1/8'' bend 3 pcs. 65.00 195.00
4"ø pvc sweep tee 3 pcs. 65.00 195.00
3"ø 45 deg. Elbow 3 pcs. 65.00 195.00
2"ø 90 deg. elbow 3 pcs. 65.00 195.00
sub-total 33310.00
B. TILES & ACCESSORIES
b.1. Portland cement 38 bags 275.00 10450.00
b.2. Washed sand 1.8 cu.m 1000.00 1800.00
60 X60 floor Tiles 240 pcs. 112.00 26880.00
20 X30 Glazed Tiles 385 pcs. 36.00 13860.00
20 X 20 Unglazed Tiles 180 pcs. 18.00 3240.00
Tile Trim 12 length 118.00 1416.00
Tile Grout 2 pack 68.00 136.00
Tile Adhesive 18 bags 390.00 7020.00
sub-total 25672.00

XII.
A.
a.1. PAINTING WORKS
a.2. WALLING 232(2) sq.m
a.3. Latex Flatwall 12 gal. 445.00 5340.00
B. Latex Gloss (refer to owners color choice) 12 gal. 568.00 6816.00
b.1. Latex (baseline) 2 gal. 568.00 1136.00
b.2. CEILING 47 sq.m
b.3. Enamel Flatwall 6 gal. 445.00 2670.00
C. Enamel Gloss 6 gal. 548.00 3288.00
C.1. Paint Thinner 12 gal. 398.00 4776.00
C.2. PAINTING ACCESSORIES
C.3. 8" Roller Brush 8 pcs. 68.00 544.00
C.4. 2' Paint Brush 2 pcs. 45.00 90.00
C.5. Paint Tray Mixer 4 pcs. 135.00 540.00
C.5. Putty Knife w/o Handle 8 pairs 32.00 256.00
# 120 cc Sand Paper 40 pcs. 32.00 1280.00
# 1000 cc Sand Paper 30 pcs. 32.00 960.00
sub-total 27696.00

Total Material Cost 621731.80


Total Labor Cost 45% 214,555.28
Total Construction Cost 836,287.08

Prepared by:

ENGR. RUMIL C. LAPLAP


Civil Engineer

Approved:

CHRISTIAN JOBEBS A. BENIGA


Owner