PENTARCH BUILDERS

NEAR OLD MASJID,


THUCKALAY ROAD,
VALLUVAR JN, THIRUVITHANCODE
CELL : +8903672577,7907037425
BILL OF QUANTITY OF RESIDENTIAL BUILDING
APRIL MONTH - 2019

ALL DIMENSIONS ARE IN FEET AND INCHES


SITE-ANJUVANAM THERU
CLIENT-ASHIK
SI.NO DESCRIPTION L B D QUANTITY RATE
1 LABOUR
1 CIVIL WORK - - - 750.00 320.00
TOTAL AMOUNT
1 EARTH WORK EXCAVATION
1 EARTH WORK EXCAVATION 194.75 2.75 2.50 1,338.91 10.00
TOTAL AMOUNT
2 FOUNDATION W0RK
1 D.R MASONRY 194.75 2.00 2.00 779.00 43.00
2 R.R MASONRY 194.75 1.50 1.50 438.19 43.00
3 CEMENT - - - 15.00 400.00
4 SAND - - - 150.00 62.00
TOTAL AMOUNT
3 TIE BEAM M20 (1:1.5:3)(SIZE 9''X6'')
1 TIE BEAM 194.75 0.75 0.50 73.03
2 CEMENT - - - 20.00 400.00
3 SAND - - - 70.00 62.00
4 0.75''JELLY - - - 40.00 43.00
5 4 NOS OF 8MM BAR - - - 310.00 60.00
6 6MM STRPS 7'' C/C - - - 190.00 60.00
TOTAL AMOUNT
4 HALLOW BLOCK WORK
1 BLOCK 6'' THK - - - 1,260.00
2 NOS OF BLOCK 10' HGT - - - 2,570.00 35.00
3 CEMENT - - - 15.00 400.00
4 SAND - - - 110.00 62.00
TOTAL AMOUNT
5 DOORS & WINDOWS
1 MAIN DO0R - - - 1 60,000.00
2 DOOR 1 - - - 3.00 18,000.00
3 DOOR 2 - - - 2.00 3,000.00
4 WINDOW 3 - - - 3.00 13,000.00
5 WINDOW 2 - - - 1.00 9,000.00
6 VENTILATION - - - 2.00 3,200.00
TOTAL AMOUNT
3 LINTEL&SUNSHADE M20(1:1.5:8)
1 LITEL BEAM 194.75 0.75 0.50 73.03
2 CEMENT - - - 25.00 400.00
3 SAND - - - 80.00 62.00
4 0.75''JELLY - - - 50.00 43.00
5 4 NOS OF 8MM BAR - - - 350.00 60.00
6 6MM STRPS 7'' C/C - - - 230.00 60.00
TOTAL AMOUNT
3 ROOF CONCRETE 5'' M20(1:1.5:3)
1 ROOF CONCRETE - - - 282.48
3 CEMENT - - - 50.00 400.00
4 SAND - - - 135.00 62.00
5 0.75''JELLY - - - 255.00 43.00
6 STEEL 800.00 60.00
TOTAL AMOUNT
3 PARAPET WALL 3' HEIGHT
1 H.BLOCK 4.5'' THK 194.75 3.00 0.23 134.38
2 NOS OF BLOCK 3' HGT - - - 300.00 20.00
3 CEMENT - - - 3.00 400.00
4 SAND - - - 10.00 62.00
TOTAL AMOUNT
3 PLASTERING
1 GROUND FLOOR INNER 1:5 194.75 - 10.00 1,947.50 -
2 CEILING 1:4 - - 775.00 -
3 PARAPET WALL 1:5 389.50 - 3.00 1,168.50 -
4 OUTER 1:5 194.75 - 12.20 2,375.95 -
5 CEMENT - - - 100.00 400.00
6 SAND - - - 510.00 62.00
TOTAL AMOUNT
3 PAINTING,ELECTRICAL&TILES WORK
1 ONE COAT PRIMER - - - L.S
2 ELECTRICAL - - -
3 TILE WORK - - - 700.00 100.00
TOTAL AMOUNT
3 ADDITIONAL WORK
1 OUTSIDE STAIRCASE - - - - LS
2 FINISHING - - - - LS
TOTAL AMOUNT
GARAND TOTAL AMOUNT
AMOUNT

240,000.00
240,000.00

13,389.06
13,389.06

33,497.00
18,842.06
6,000.00
9,300.00
67,639.06

-
8,000.00
4,340.00
1,720.00
18,600.00
11,400.00
36,060.00

89,950.00
6,000.00
6,820.00
102,770.00

60,000.00
54,000.00
6,000.00
39,000.00
9,000.00
6,400.00
174,400.00
-
10,000.00
4,960.00
2,150.00
21,000.00
13,800.00
51,910.00

20,000.00
8,370.00
10,965.00
48,000.00
87,335.00

6,000.00
1,200.00
620.00
7,820.00

-
-
-
-
40,000.00
31,620.00
71,620.00

50,000.00
70,000.00
70,000.00
190,000.00

20,000.00
20,000.00
40,000.00
1,082,943.13
CALCULATE BRICKS
SI.NO DESCRIPTION L B D QUANTITY VOLUME
1 VOLUME OF BRICK (WM) 0.24 0.086 0.1 0.002064 4
2 VOLUME OF BRICK 0.23 0.076 0.112 0.00195776

CONCRETE QUANT
VOLUME DRY VOLUME VC BAG SAND AGG
282.50 435.05 62.15 49.72 124.30 248.60

282.48
CALCULATE BRICKS -1:6
NOS BRICK VOLUME MORTAR VOLUME DRY VOLUME CEMENT CFT BAGS
1,937.98 3.7941085271 0.2058914729 0.2738356589 56.3319069767 1.126638

CONCRETE QUANTITY
M.SAND CFT
0.234716 8.287832
PENTARCH BUILDERS

NEAR OLD MASJID,


THUCKALAY ROAD,
VALLUVAR JN, THIRUVITHANCODE
CELL : +8903672577,7907037425
ESTIMATION AND MODE OF PAYEMENT
MAY
MONTH - 2019
SITE-ANJUVANAM THERU
CLIENT-ASHIK
A.ESTIMATION COST
SI.NO DESCRIPTION SQ.FT RATE
1 BUILDUP AREA GF 825.00 1,085,000.00
TOTAL AMOUNT 1,085,000.00
B.PAYEMENT PERIOD
PERCENTAGE TOTAL
SI. No DESCRIPTION
OF PAYMENT AMOUNT
1 INITIAL AMOUNT FOR FOUNDATION WORK 15% 162,750.00
2 STARTING STAGE OF WOOD WORK 9% 97,650.00
3 H.BLOCK WORK GF 14% 151,900.00
5 LINTEL AND SUNSHADE GF 5% 54,250.00
6 THE GROUND FLOOR ROOF CONCRETE 11% 119,350.00
7 FINALE STAGE FOR H.BLOCK WORK PARAPET 4% 43,400.00
8 PLASTERING WORK GF 10% 108,500.00
9 MARBONITE WORK GF 10% 108,500.00
10 ELECTRICAL & PLUMBING WORK 12% 130,200.00
11 FINAL STAGE OF WOOD WORK 5% 54,250.00
12 PRIMER AND FINAL STAGE OF WORK 5% 54,250.00
TOTAL AMOUNT 1,085,000.00
TEN LAKHS AND EIGHTY FIVE THOUSAND ONLY/-

PLACE - OWNER SIGN