Tablet Integration Project for National Aquarium

Student’s Name:

Course Name:

Instructor’s Name:

Spring 2019
Table of Contents
Executive Summary ........................................................................................................................ 3

Project Charter ................................................................................................................................ 4

Team Skills ..................................................................................................................................... 6

Procurement Process ....................................................................................................................... 7

Proposal Evaluation and Selection................................................................................................ 13

Project Plan ................................................................................................................................... 14

Project Scope Statement ........................................................................................................... 14

Work Break Down Structure .................................................................................................... 14

Task List.................................................................................................................................... 15

Responsibility Matrix................................................................................................................ 16

Resources Discussion................................................................................................................ 17

Schedule .................................................................................................................................... 18

Cost ........................................................................................................................................... 19

Gantt Chart ................................................................................................................................ 20

Network Diagram...................................................................................................................... 21

Critical Task List....................................................................................................................... 22

Discussion ................................................................................................................................. 23

Closing .......................................................................................................................................... 24

Conclusion .................................................................................................................................... 25

Lesson Learned ............................................................................................................................. 25


Tablet Integration Project

Executive Summary
The National Aquarium is the non-profit public aquarium having aim to provide the educating

facility to visitor about aquarium aquatic life and encourage their conversation effort. The

aquarium facility can hold about 2M Gallons water and have more that 17K different types of

animals which include birds, reptiles, fishes, and mammals etc. around the globe. The company

main aim is to educating visitor about the animals and provide them opportunity to learn and get

knowledge about animals from different species. The project will be about the “Smart Table” in

which tablets are purchased or procured for National Aquarium which can provided to the visitor

and they can take the digital tour of aquarium as well as provide them the exceptional customer

experience. Tablet can answer the question about the animal details as well as all answer about the

facilities related to the aquarium. The main purpose of the tablets is to provide the complete guide

to visitor throughout several exhibits along with providing the information specifically about the

aquatic life in different zones. Table used in our project contains the interactive guide and

information for visitor to enhance and improve the experience of visiting. The main hardware

required in this project is table and its protection because of the daily use and software application

for the Aquarium to be run on the tablet. So, RFP is issued to acquire the tablet and software.

Process of selection will be chosen by the project manager to chose the contractor to fulfills the

business needs. Team can also update the database of aquarium along with networking capabilities

which can ensure that all requirements are meet. The project deadline is six months and total cost

for the project assigned by top management of National Aquarium is $1,000,000.

Page | 3
Tablet Integration Project

Project Charter
Project Title: Integration of Tablet in National Aquarium

Project Start Date: March 30, 2019

Budget Information: $1,000,000

Project Manager:
Project Objectives: To implement the usage of tablet in the National Aquarium for visitor to
enhance their experience during visit.

 Table, Tables cases and stands will be procured.

Success Criteria:
 Project should be completed under the budget, scope and within deadline.
 Product acceptance from visitors and all project stakeholders.

Approach:
Approach follow in the project is to procure the tablet for aquarium. As aquarium also has the
capability of Wi-Fi network so tablet can be place only in the aquarium so there is no need to
improve and enhance the network facility. Project manager has the main responsibility to chose
the contractor. Contract can handle tablet installation along with cases and stands as well as internet
connection with aquarium network. The project is tested in 3 phases in 1st tablets are installed and
tested and then in next phases tablets are connected with the network and validate and verified
according to the requirements. The National aquarium can acquire approx. 3000 tablets.

Roles and Responsibilities:


Name Role Organization/Position Contact
Person 1 Project Manager National abc@123.com
(Manages Overall Aquarium/Project
Project) Manager
Person 2 Ensure project is on National abc@123.com
track. Aquarium/Project
Coordinator

Page | 4
Tablet Integration Project

Person 3 Upgrade and manage National abc@123.com


existing database Aquarium/Database
Administrator
Person 4 Configure RFP and National abc@123.com
evaluate the proposal Aquarium/Technical
of contractors Engineer
Person 5 Manage all issues in National Aquarium/ abc@123.com
the project Technical Support
Person 6 Responsible for all National abc@123.com
expenses in the Aquarium/HR
project. Manager
Person 7 Responsible to National bc@123.com
Manage the Aquarium/Software
Engineer

Sign-off:

Person 1

Person 2

Person 3

Person 4

Person 5

Person 6

Page | 5
Tablet Integration Project

Team Skills
Team skills required to achieve the project goals and objectives is Project Manager, Project
Coordinator, Database Administrator, Technical Engineer and HR Manager. These skills are
assigned to our project team and IT Dept can update the existing database and servers. The current
network has the capacity to handle all tablets and visitors’ smart devices. Team can work together
on each task of project to accomplish project goals and objectives.

Project Manager: Manage the overall project and main aim is to meet the project scope, cost and
schedule.

Project Coordinator: Responsible to manage and monitor the project overall schedule. Gather
information about the project performance progress from team member and track all things will
be on the schedule and make the corrective decisions.

Database Administrator: Update and manage the database of the company and responsible to
add missing information i.e. facts related to additional environment.

Technical Engineer: Assist and manage the overall IT operations of the company and all
hardware and network connections issues.

Technical Support: Assist and manage the all hardware operation regarding the tablets and server
of the application.

HR Manager: Sign and approve the budget and expenses required for the budget.

Software Engineer: Manage the bugs, issues and errors of the application which is installed on
the tabled.

Page | 6
Tablet Integration Project

Procurement Process

Request for Proposal


Background or Introduction
The main aim of this RFP will be to have the firms, company and organization which can address

the service required at the considerate price specifically. Our company will be looking for the firm

or organization which can provide the tablets. Hence, we are accepting the proposal with the

response to this RFP (Request for Proposal) for finding the quality source or firm which can

provide the high-quality services. On other hand prices will be the significant factor and other

criteria can form the basis of decision awarded by us and fully described below in the section of

evaluation factors.

Organization Contact Information


Firm who are interested with the proposed proposal would use the information given below to

contact us:

Email: company.expert@org.pk

Tel: 0900-78601

Requirements and Submission Guidelines


Guidelines which are applied for the proposed proposal are:

 Only experienced firm and qualified tablet companies can submit the proposals

 Technical proposal would be provided to get the overview of solution proposed.

 The proposal about prices should be provided which can indicate the project overall fixed

cost.

Page | 7
Tablet Integration Project

 If any of the firm or individual has different terms and conditions then they can also submit

that along with proposal. All of the term and condition would be subjected in order to

negotiate.

 Tables Requirements: Display 7.0 Inches, Ports and jacks, Retina Display, 4GB RAM,

256GB ROM.

 Tablet Case Requirements: Metallic Case should prevent all kind of damages.

 Table Stand Requirements: Metallic Case compatible with table and contains the protector

guard in order to prevent damage as well as the lock that no one can steal the tablet. Rotator

can also be installed to change the view of tablet.

 Submitted propose must be signed by the authority or authority representative.

Schedule and RFP


The schedule of RFP is:

Issuance of RFP: All of the proposal must be issued by end of the next month (17/07/2019)

Issuance of RFP All of the proposals must be issued at end of


the next month
Sending Feedback to Bidders which are not 17/07/2019 to 13/08/2019
selected and send the email to top bidders
which are selected
Negotiation with bidders 14/08/2019 to 27/09/2019
Awarding and Signing Contract with the best 28/08/2019
select bidder

The project completion will be set on the 11/12/2019. If the bidder thinks that it should be end

early or later then they are open to share their proposed decision. Their proposal can be evaluated

according to that.

Page | 8
Tablet Integration Project

Decision Making Criteria


The following criteria will be used for rating the proposals of bidders:

 Cost is the major facto which can be checked first including the total ownership cost

assessment.

 How requirements (which are set in the RFP) are responded in the proposal.

 We can must check about the related previous or past experience along with work

performance of firms or individual who send proposal.

 Previous or past work sample is required also.

 At last we can check or test bidders experience, skills and expertise along with their staff.

Company cannot tolerate and support the favoritism as well as corruption but can reserve all of the

rights which are awarded to the bidder and that can present excellent value which are given above.

Project Summary
The National Aquarium of Baltimore is attempting to make its experience for visitors immersive

and interactive. They plan on achieving this by allowing visitors the option to enhance their

experience by using tablets. These tablets will allow users to get a more in depth look at specific

things throughout their visit to the Aquarium. This will enhance their experience and give them a

memory to remember for the rest of their lives.

Page | 9
Tablet Integration Project

Apple Proposal
Organization Background and Summaries
Apple was founded by Steve Jobs, Ronal Wayne and Steve Wozniak in the April 1976 to develop

and sold out the Apple I personal computer and it will be incorporated by the Apple Computer,

Inc. 1977 January after that the sales of Apple II computer will be grown up very quickly and the

company sales and revenue increase day by day and the company become very famous having the

top trending products. In August 2010, the company have operated in 3012 retail stores in ten

countries along with online stores where both hardware and software products will be sold out.

Company was named Apple Computer Inc. previously in first 30 but later on January 2007 the

word computer will be removed to reflect the ongoing expansion of the company into the market

of electronics consumer in addition to the focus on the PC traditionally (Apple Inc | American

Company, n.d.). In Sept. 2009 Apple has the 34,300 employees (full-time) and 2500 temporary

employees around the world and annual sales worldwide is $42.91 in the ending of Sept. 2009.

Unique reputation in the market or industry will be developed by the Apple. For different as the

philosophy of the comprehensive aesthetic design to Apple distinct advertising.

Our Solution
The business wants to improve the experience of visitor by implementing tablets in the aquarium

for visitor. So, there are the requirement of 2600 tablets (IPAD) which are to be installed in the

aquarium and 400 tablets are used for the mobile experience. You can purchase the IPAD stand of

your own choice with their cases and our team can being installation soon when you accept and

sign-off the contract with. Then we can also ensure that all IPAD implemented by us can be

monitored and use by Wi-Fi network by National Aquarium IT Department.

Page | 10
Tablet Integration Project

Why US?
We are running company from many years and we have worked on millions of projects and our
benchmark will be in the top of smart devices industry and 5-stras raring of customers. We can put
the perfect team together for your project. Our main aim is to finish project until the clients are
satisfied completely with result produced by our company.

Process
At Apple, we can always make sure that you can get the product according to you need and
expectation. Once the big accepted, we can arrange the personal meeting with your project
manager to gather all requirement for installation of Tablets and connection process of network so
there will be no things missed. We can return to the headquarters to proceed working on project
and we are 24/7 available to assist you and want you to satisfy with high quality Results.

Deliverables
 Installation of Tables and Mobile Experience Tablets
 Installation of Tablet Stands
 Case for Tablets

Page | 11
Tablet Integration Project

Company Proposal
Cost Section
For this project as a team we have decided to divide the project according to our skills and expertise
so, managing project will be made very easy to accomplish project goals and objectives. We
decided to increase the prices of tickets as well as fee for membership. The increase will be minor
and it doesn’t have any effect on the customer because this increase in cost also provide the extra
facility to customer or client. We decided to increase 5usd on the ticket and 10usd on member ship.
Additionally, 5usd will be charge who want to feel the mobile experience by renting the tablets.
Children below 5 years doesn’t charge any ticket and for all visitor ticket prices will be 40usd.
Member ship for 1 years per person is 150usd. For the table chosen is IPAD Air 2 and its price is
good and this is latest model and we have chosen this because of latest technology and 3000 tablets
will be purchase at price of $400,000.

Technical Section
The objective of this section is to provide the application support to the customer where the can
connect their own devices and install app on their smart phones and also installed on the tablets
purchase by the Apple. This app can enhance the user experience and provide the facility to the
visitor to learn about the animals and aquarium other famous things. So, application have the
database in which all answer to the questions are stores and application is installed on the tablets
by company. Tablet will be connected over the network of national aquarium and users can also
connect their smart phones over the network.

Management Section
The management provide the opportunity to achieve the goals of the project. The purpose of this
project plan to understand the different aspects of project. It shows the planning, designing and
management of the project. The documentation of the project is very important. Project Plan can
help top management to get the clear vision and understanding about project. It can also facilitate
project manager to do feasibility analysis along with each stage as well as to get idea about that
how much project is important for the market, and what will be the project scope. When the proper
documentation of the project is done then any person can easily understand the project.

Page | 12
Tablet Integration Project

Proposal Evaluation and Selection


Proposal Evaluation
We have received the several proposals in which most of the proposal are very well. We found
that some of the proposal doesn’t followed our requirement but some of them follow each and
everything. This can allow us to finalized the companies. We then found that Apple is the best
proposal because their proposal have meet all of the requirement and layout of proposal is very
professional In the section process we can find out the more details about why Proposal of Apple
is accepted.

Selection Process
As team, we decided that proposal which is chosen can effectively and efficiently meet our
company goals. We believe their proposal can increase the prices of ticker slightly to earn money
for our project will be effective solution and it doesn’t require additional time and work. We also
like their tablets because their company is one of the most leading company in the world. Also,
their tablets (IPAD) specification) is also fit to our requirements. We agreed with their proposal so
and the proposed schedule of project is done in the appropriate time and we believe the project is
completed within deadline as schedule of project is not too long and also not too short.

Page | 13
Tablet Integration Project

Project Plan
Project Scope Statement
Project is about purchasing some sort of smart tablet that visitors could carry with them to serve
as a digital guide as they toured the Aquarium. 3000 tablets will be purchased for aquarium. This
tablet help visitor to know about different animals and species of Aquarium. People face the many
problems while visit aquarium, they don’t know about animals’ name and their characteristics and
they also have issue in direction of aquarium. This tablet helps not only in question answer but
also provide directions to specific locations in the Aquarium. This project help visitor to get
answers of any questions during tour and make their experience best about aquarium.

Work Break Down Structure

Page | 14
Tablet Integration Project

Task List
WBS Task Name Task Discussion
Tablet Integration in National
1
Aquarium
1.1 Initiate Begin Project
Assignment of Project roles and
Assign Project Roles and
1.1.1 responsibilities to team
Responsibilities
members
1.1.2 Prepare Project Charter Develop charter for project
1.1.3 Estimate Deadline Prepare project schedule
1.2 Plan Project Planning
1.2.1 Determine Resources Estimate Resources
1.2.2 Determine Cost Estimate project cost or budget
1.2.3 Determine Tablet Prepare plan for table
Analyze area where tablets are
1.2.4 Analyze Area
installed
Check the networking
1.2.5 Determining Network connection of National
Aquarium
Check suitable area for tablet
1.2.6 Check place
installation
Prepare Work Breakdown
1.2.7 Implement WBS
Structure
1.3 Execution Project Execution
Decide about the procurement
1.3.1 Procurement Decision
process
1.3.2 RFP Develop RFP
Receive and Choose one
1.3.3 Accept Proposals
Proposal
1.3.4 Outsource Project to Apple Give project to Apple Company
Develop QR Code for Smart Implementation of QR codes
1.3.5
Devices
1.4 Monitor and Control Project Controlling
Preparing wavier for using
1.4.1 Develop Wavier form
tablet.
1.4.2 RACI Matrix Develop Responsibility Matrix
1.4.3 Discussion on Resources Resource Utilization
1.4.4 Stakeholders Identification Identify Project Stakeholders
1.4.5 Preliminary Scope Statement Prepare Project Scope
1.4.6 Evaluation Evaluate Project
1.4.7 Review and Edit Testing and Maintenance
1.5 Closing
Presentation to Top
1.5.1 Presentation
management
1.5.2 Critical Success Factors Define Success Factors
1.5.3 Lesson Learned Lesson Learned in project.

Page | 15
Tablet Integration Project

Responsibility Matrix
Task Name Person 1 Person 2 Person 3 Person 4 Person 5 Person 6 Person 7
Initiate
Assign Project R R R R R R R
Roles and
Responsibilities
Prepare Project R R I I I I I
Charter
Estimate R R I I I I I
Deadline
Plan
Determine R R I I I A I
Resources
Determine Cost R R I I I I I
Determine R I I R C I I
Tablet
Analyze Area R R A C I C I
Determining A A C R R I A
Network
Check place R R I I I I I
Implement WBS R R I I I I I
Execution
Procurement R R A A A R R
Decision
RFP R R R R R R R
Accept Proposals R I I I I I I
Outsource R I I I I I I
Project to Apple
Develop QR A I I R R I R
Code for Smart
Devices
Monitor and
Control
Develop Wavier R R I I I I I
form
RACI Matrix R R I I I I I
Discussion on R R R R R A/C R
Resources
Stakeholders R R I I I I I
Identification
Preliminary R I I I I I I
Scope Statement
Evaluation A R I C C I C
Review and Edit A R I C C I C

Page | 16
Tablet Integration Project

Closing
Presentation R R R R R R R
Critical Success R R I I I I I
Factors
Lesson Learned R R R R R R R

R: Responsible, A: Accountable, C: Consulted and I: Informed

Resources Discussion
Resources used in this project is listed below:
Human Resources

Human resources include team members, project manager, stakeholder and employees of
Aquarium. These resources are most important to complete project on time. Without human
resources project not able to complete.

Training

We will be providing training to staff and tell how to update tablets time to time. Give training to whole
staff so they familiar with operation system and done changes with time if any needed.

Tablets

The priority of our project is search for tablet. We search different tablets in the market and compare
specifications of these tablets and choose best one which under budget and meets our requirements. we
need 3000 tablets for this project. After purchasing tablets, next step is to connect these tablets with
database of aquarium so these tablets able to answer different question of users.

Maintenance

when project come to final stage there is need to maintain the services of tablets that provide by
national Aquarium. Tablet will be set after each use. If tablet is break by any users, then there is
need to buy new tablet or may repair this tablet.

Cost

Cost is the total budget to complete this project, total budget is USD $1,000,000. This is the
estimated cost for the project which may be change during project, some variance occurs between
actual and estimated cost of project. But this variance not be negative.

Page | 17
Tablet Integration Project

Schedule

Page | 18
Tablet Integration Project

Cost

Page | 19
Tablet Integration Project

Gantt Chart

Page | 20
Tablet Integration Project

Network Diagram

Page | 21
Tablet Integration Project

Critical Task List


Critical Tasks Duration Start Finish
Assign Project Roles and Responsibilities 10 days Sat 3/30/19 Thu 4/11/19
Prepare Project Charter 5 days Fri 4/12/19 Thu 4/18/19
Estimate Deadline 8 days Fri 4/19/19 Tue 4/30/19
Determine Tablet 15 days Wed 5/1/19 Tue 5/21/19
Analyze Area 7 days Wed 5/22/19 Thu 5/30/19
Determining Network 5 days Fri 5/31/19 Thu 6/6/19
Check place 5 days Fri 6/7/19 Thu 6/13/19
Implement WBS 8 days Fri 6/14/19 Tue 6/25/2019
Procurement Decision 15 days Wed 6/26/19 Tue 7/16/19
RFP 20 days Wed 7/17/19 Tue 8/13/19
Accept Proposals 10 days Wed 8/14/19 Tue 8/27/19
Outsource Project to Apple 10 days Wed 8/28/19 Tue 9/10/19
Develop QR Code for Smart Devices 15 days Wed 9/11/19 Tue 10/1/19
Develop Wavier form 6 days Wed 10/2/19 Wed 10/9/19
RACI Matrix 6 days Thu 10/10/19 Thu 10/17/19
Discussion on Resources 7 days Fri 10/18/19 Mon 10/28/19

Page | 22
Tablet Integration Project

Stakeholders Identification 4 days Tue 10/29/19 Fri 11/1/19


Preliminary Scope Statement 4 days Mon 11/4/19 Thu 11/7/19
Evaluation 12 days Fri 11/8/19 Mon 11/25/19
Review and Edit 10 days Tue 12/10/19 Tue 12/10/19
Presentation 1 day Wed 12/11/19 Wed 12/11/19
Critical Success Factors 1 day Wed 12/11/19 Wed 12/11/19
Lesson Learned 1 day Thu 1/23/20 Thu 1/23/20

Discussion
Critical Task will be highlighted in the RED Path in the Gantt Chart give above. Critical path are
longest duration of the project ad they must be completed under the time to achieve the project
success. This can help our team to identify the most important task in the project and provide the
higher level of insight into the project timeline and relationship between the tasks of the project.

Page | 23
Tablet Integration Project

Closing
Discussion of the Activities Needed to Clouse out the Project
Closing out project can involve to gain the final product and services acceptance from visitors and
project stakeholders. Project output include lessons learned and project charter. Project stakeholder
needs to be involved in the meeting to discuss the acceptance of project and successful project
completion depend upon the scope, time and budget evaluation. Once project is accepted, then
project deliverables is transferred to the National Aquarium.

Discussion of Project Critical Success Factors for Project


In order to achieve success in project, the factors followed are:

 Follow scope, deadline and cost or budget.


 Tablets must be proved in order to ensure the daily usage of visitor.
 Tablets should provide access to information about aquarium to the visitors.
 The overall product can must provide the enjoyable experience during the visit to
aquarium.

Page | 24
Tablet Integration Project

Conclusion
The recommendations made to avoid and overcome the problems of the project and to recover the

project. First things to recovery the project will be to perform the evaluation for the project overall

which include the project review or an audit by using the series of standard questions to identify

the severity and key problems in the project. This can allow to priories the recovery activity and

planning of project so that the most serious problems will be tackled first, and rest of the problem

will be solved in series. While reviewing there are some area finds where the bleeding would be

stop for an instance if the scope will be unstable and changing forever, an introduction of the

change control process which is strict must help to stabiles as well as firm up the scope. This

project is completed by following proper estimation plans. The main purpose is to underrated

project different aspect. Documentation is important for every project it help the stakeholder to

understand system.

Lesson Learned
Person 1
During the whole project development lifecycle, I learned that project scheduling is most

important for the success of project. The schedule of project must be realistic. Its biggest challenge

to meet the deadlines of project and develop project according to estimated time. If the schedule is

not realistic then it’s not possible that team meets the deadlines.

Person 2
I leaned that communication is most important during the project. The team communication is

more important in project. The daily progress report is generated and discus it with another team

member. All the team members work on the same place, so coordination of team member is

necessary. The manager of the project is must be responsible person. They manage the whole

Page | 25
Tablet Integration Project

project and manage the whole team members. They take decision about the project. Every team

member done its own work and share detail with other team member. The communication plays

vital role in project, but extra communication between team members diverts the attention of team

member from work. The communication also done in level those not divert the attention of team

members form project. The benefit of communication between team members is they share

information with each other. The meeting between team also done they give feedback to each other

and resolve defects. The team members also interact with each other via email. Send important

documents to each other through email. The announcement is also done through emails.

Person 3
I have leaned many things because of this project, the main thing I focus is that management is

most important for project success. So, project manager must be skilled person who have

experience how to control and managed project resources, risk and other factors. I learned how to

build WBS, Gantt chart. I also learned many communication techniques.

Person 4
I have done many projects before this project. The most important thing I learned from this project

is how to identify, managed and control risk. The mitigation plan is developing to decide how to

overcome these risks that occurs during project. The risk is control by the project manager. If the

functionality of the project is effect, then some delay will be acceptable. Component delay can

also be minimizing if the project schedule is properly design and the team of the project is

following these schedules. If the proper plan is following, then there is a chance we minimize this

risk and achieve our milestone in time frame. When the plan is followed, and we achieve our

milestones then the cost of project remains in control, so we also minimize the risk of our budget.

Page | 26
Tablet Integration Project

Person 5
From this project I have learned that how project can be efficiently managed and how IT support
can help company to achieve the goals and objectives of the project. Working as Technical
engineer I have improved my experience and knowledge in the IT support and maintenance.

Person 6
From this project I have learned that how cost of project will be managed and how we can keep
the track of cost. Also, this project can give me an opportunity to enhance my experience about
the resource estimation and how can we utilize them in the project efficiently and effectively.

Person 7

This project can help me out to enhance my project management skills and knowledge because in
project I have viewed the all aspect of project which can be considered to accomplish the project
goals and objectives by following the project management approaches and strategies. This can
help me in future when I work on some project as a software engineer to manage its operation by
following the rules and principles of software engineering and project management.