You are on page 1of 154

A Danish Field

Platforms and Pipelines


Decommissioning Programmes

Decommissioning Programmes
A Danish Field Platforms and Pipelines

APPENDIX A: Environmentally sound recycling and scrapping of offshore platforms

A1 Offshore Deconstruction

A2 Removal of platforms

A3 Transportation of platforms

A4 Onshore decommissioning

APPENDIX B: Environmental challenges associated with decommissioning

APPENDIX C: Decommissioning in the North Sea, Weather Windows, (this report is not attach)

Participating Companies

Offshoreenergy.dk www.offshoreenergy.dk

Ramboll Oil & Gas, www.ramboll.com

Semco Maritime www.semcomaritime.com

Blue Water Shipping www.bws.dk

Stena Recycling A/S www.stenarecycling.com


Page 1 of 56 
 
 

 
 
 
 
 
 
 

A Danish Field
Platforms and Pipelines
Decommissioning Programmes

 
 

June 2013 

 
   

Page 2 of 56 
 
Table of Contents
1  INTRODUCTION ................................................................................................................................................7 
1.1  Decommissioning Programmes for  a Danish Field ..............................................................................7 
1.2  Document Sections Comprising the  Two Decommissioning Programmes ........................................9 
2  EXECUTIVE SUMMARY .....................................................................................................................................9 
2.1  Removals ................................................................................................................................................ 10 
2.2  Pipelines ............................................................................................................................................... 10 
2.3  Time schedule ....................................................................................................................................... 11 
3  BACKGROUND ............................................................................................................................................... 12 
3.1  Decommissioning of the Field  Facilities ........................................................................................... 12 
3.2  Environmental Conditions ................................................................................................................. 12 
3.2.1  Biological Assessment ............................................................................................................... 12 
3.2.2. Commercial fisheries ........................................................................................................................... 17 
3.2.3.. Shipping .............................................................................................................................................. 18 
3.2.5. Environmental issues to assess .......................................................................................................... 19 
4  ITEMS TO BE DECOMMISSIONED .................................................................................................................. 20 
4.1  Platforms (Programme  1) ................................................................................................................... 20 
4.1.1  Description .................................................................................................................................. 20 
4.1.2  History .......................................................................................................................................... 21 
4.1.3  Condition ..................................................................................................................................... 21 
4.2  Pipelines (Programme 2) ....................................................................................................................... 21 
4.2.1  Description .................................................................................................................................. 21 
4.2.2  History .......................................................................................................................................... 22 
4.2.3  Condition ..................................................................................................................................... 22 
5  INVENTORY OF MATERIALS .......................................................................................................................... 22 
5.1  Major  Platform Materials ..................................................................................................................... 22 
5.2  Platform Hazardous  Materials ............................................................................................................. 25 
5.3  Pipeline Materials .................................................................................................................................. 26 
6  POTENTIAL RE‐USE OPPORTUNITIES ............................................................................................................. 26 
6.1  Topsides and Jackets ........................................................................................................................... 26 
6.2  Pipelines ................................................................................................................................................ 27 
7  LONG LIST OF DECOMMISSIONING OPTIONS, AND SELECTION OF A SHORT LIST ....................................... 27 
7.1  Option  Identification Process ............................................................................................................ 27 
7.2  Decommissioning Options for  the  Platform Topsides ....................................................................... 27 
7.2.1  Leave in‐situ ................................................................................................................................. 27 

Page 3 of 56 
 
7.2.2  Re‐use in‐situ ............................................................................................................................... 28 
7.2.3  Re‐use in another  location ......................................................................................................... 28 
7.2.4  Remove  and recycle..................................................................................................................... 28 
7.2.5  Rigs  to reefs  disposal .................................................................................................................. 28 
7.2.6  Deep sea disposal ........................................................................................................................ 28 
7.2.7  Delay decommissioning awaiting novel  new  technology ....................................................... 28 
7.3  Possible Topside  Removal  Methods ................................................................................................... 29 
7.3.1  Installation reversal  using  heavy  lift  vessel  (HLV) ................................................................... 29 
7.3.2  Topside  integrated removal  using  semi‐submersible crane  vessel  (SSCV) ........................... 29 
7.3.3  Topside  integrated removal  using  novel  new technology ..................................................... 29 
7.3.4  Piece  small  topsides removal....................................................................................................... 29 
7.3.5  Shear‐leg  and grab ....................................................................................................................... 30 
7.3.6  Removal  using  drilling jack‐up  rig ............................................................................................. 30 
7.4  Decommissioning Options for  the  Platform Jackets ......................................................................... 30 
7.4.1  Leave in  place ............................................................................................................................... 30 
7.4.2  Re‐use in‐situ ............................................................................................................................... 30 
7.4.3  Re‐use in another  location ......................................................................................................... 30 
7.4.4  Remove  and recycle..................................................................................................................... 31 
7.4.5  Rigs  to reefs  disposal .................................................................................................................. 31 
7.4.6  Deep sea disposal ........................................................................................................................ 31 
7.4.7  Delay decommissioning awaiting novel  new  technology ....................................................... 31 
7.5  Possible Jacket  Removal  Methods ...................................................................................................... 31 
7.5.1  Installation reversal  using  heavy  lift  vessel  (HLV) ................................................................... 31 
7.5.2  Jacket  removal  using  novel  technology ................................................................................... 32 
7.5.3  Piece small  jacket  removal ......................................................................................................... 32 
7.5.4     Direct lift of jacket ......................................................................................................................... 32 
7.5.5  Shear‐leg  and grab ....................................................................................................................... 32 
7.5.6  Further Development of the Versa‐truss Principle .................................................................... 32 
7.6  Decommissioning Options for  the Pipelines ...................................................................................... 33 
7.6.1  Decommission and leave in‐situ ................................................................................................ 33 
7.6.2  Re‐use in‐situ ............................................................................................................................... 33 
7.6.3  Re‐use in  other  locations ............................................................................................................ 33 
7.6.4  Remove  and recycle  or dispose in landfill ..................................................................................... 33 
7.7  Pipeline  Removal  Methods ................................................................................................................. 33 
7.7.1  Reverse  S‐lay ................................................................................................................................. 33 

Page 4 of 56 
 
7.7.2  Cut and lift ................................................................................................................................... 34 
7.7.3  Surface  tow .................................................................................................................................. 34 
7.7.4  Controlled depth  tow ................................................................................................................. 34 
8  COMPARATIVE ASSESSMENT OF SHORT LIST OF OPTIONS AND SELECTION OF PREFERRED OPTION ........ 34 
8.1  Option  Selection Methodology ........................................................................................................... 34 
8.2  Comparative Assessment and  Selection of  Preferred  Option  for  Topsides .................................. 35 
8.2.1  Description of Topsides Removal  Options ................................................................................ 35 
8.2.2  Comparative Assessment and cost of  Topsides Removal  Options ........................................ 37 
8.2.3  Summary  of Selected  Topsides  Decommissioning Options ................................................... 37 
8.3  Comparative Assessment and  Selection of  Preferred  Option  for  Jackets ...................................... 38 
8.3.1  Description of Jacket  Removal  Options .................................................................................... 38 
8.3.2  Comparative Assessment of Jacket  Removal  Options ............................................................ 41 
8.3.3  Summary  of Selected  Jacket  Decommissioning Options ........................................................ 41 
8.4  Comparative Assessment and  Selection of  Preferred  Option  for  Pipelines .................................. 42 
8.4.1  Description of Pipeline  Decommissioning Options ................................................................ 42 
8.4.2  Comparative Assessment of  Pipeline  Decommissioning Options ......................................... 44 
8.4.4  Summary of Selected Pipeline Decommissioning Option ............................................................. 45 
8.5  Disposal of Decommissioned Material .............................................................................................. 45 
9  WELL DECOMMISSIONING ............................................................................................................................ 46 
9.1  Description .......................................................................................................................................... 46 
9.2  Drill  Cuttings ........................................................................................................................................ 46 
9.3  Well  Decommissioning Plan ............................................................................................................... 47 
10  ENVIRONMENTAL IMPACT ASSESSMENT ................................................................................................. 47 
10.1  Introduction and  method .................................................................................................................. 47 
10.2  Results  of the  environmental assessment ....................................................................................... 47 
10.2.1   Expected results .............................................................................................................................. 47 
11  COSTS ........................................................................................................................................................ 48 
12  SCHEDULE .................................................................................................................................................. 49 
13  PERMITS AND CONSENTS .......................................................................................................................... 50 
14  MONITORING AND MAINTENANCE .......................................................................................................... 50 
14.1  Platforms .............................................................................................................................................. 50 
14.1.1 I n t e r i m   safety  management ...................................................................................................... 50 
14.1.2 P o s t ‐decommissioning survey  and debris  removal .................................................................. 50 
14.2  Pipelines ................................................................................................................................................ 50 
14.2.1 I n t e r i m   safety  management ...................................................................................................... 50 

Page 5 of 56 
 
14.2.2 P o s t ‐decommissioning survey  and debris  removal .................................................................. 51 
14.3  Post‐decommissioning  Environmental Survey ................................................................................ 51 
15  PROJECT MANAGEMENT .......................................................................................................................... 51 
15.1  Project  management ........................................................................................................................... 51 
16  REFERENCES .............................................................................................................................................. 52 
17  GLOSSARY OF TERMS AND ABBREVIATIONS ............................................................................................ 53 
 

Page 6 of 56 
 
1 INTRODUCTION
 
 
1.1 Decommissioning Programmes for a Danish Field
 
 
A typical Danish Field 

A typical Danish Field comprises five wellhead platforms, A, B, C, D and E, a combined wellhead and 
processing platform, F, a processing platform, G, two processing and accommodation platforms, B and 
C, and two gas flare stacks, G and F.  

The  A,  B,  C  and  D  platform  complex  is  located  about  3  km  from  the  F  platforms,  while  E  is  an 
unmanned satellite platform ½ km from F.  
 
At the Field, there are receiving facilities for the production from the adjacent K and R satellite fields. 
The Field installations also provide the H Field with injection water.  
 
After final processing, the oil is via the riser platform, GE transported to shore. The gas is at platform F 
pre‐processed and for final processing transported to T.  
Treated production water from central platform and its satellite fields is into the sea discharged. 
 
In the Field, there are accommodation facilities for about 100 persons on the C platform and 5 persons 
on the B platform. 
 
In 1966 was the Field discovered and was on stream brought in 1971 and lies some 250km off the west 
coast  of  Jutland.  It  has  been  subjected  to  various  upgrades  to  improve  and  maximize  production 
during its lifetime, including additional platforms F in the 1980’s, upgrade, demanding and compressor 
reconfiguration in mid‐1990’s. Production from the Field is near future expected to cease within a. At 
Cessation of Production, it is estimated that the operator will have produced 101, 8 million m3 of oil 
and 22723 Nm 3 of gas at the entire Field  
 

Page 7 of 56 
 
   

Figure  1.1.1 Location of  the Field 


 
As  the Field facilities are expected no longer to serve their intended purpose within the next 5 to 
10 years, a group of Esbjerg companies (Offshoreenergy.dk, Semco, Stena, Blue Water Shipping and 
Ramboll)  have,  as  an  exercise  for  coming  decommissioning  of  offshore  facilities  in  the  North 
Sea,  prepared  the  Decommissioning  Programmes  covering  the  elements  of  a  typical  Field 
facilities corresponding to separate Notices (Section 29 of Petroleum Act 1998) as detailed below: 
 
Decommissioning  Programme  1  covers  the four  Field  platforms  A, B, C and D  
 
Decommissioning Programme 2 covers the infield pipelines 3 km 16" and 12" from D to F and 
the 2 km 10"pipelinfrom B to E.  
 
In order to present the background and the inter‐related activities involved for the facilities covered 
in these Decommissioning Programmes, they are as one document presented.  
 
These  Decommissioning  Programmes  are  prepared  in  accordance  with  the  requirements  of  the 
OSPAR convention 1998.  
 
 
   

Page 8 of 56 
 
 

1.2 Document Sections Comprising the Two Decommissioning Programmes


 
 
For  ease  of  reference,  the  following  Table  1.2.1  identifies  the  sections  in  this  document covering 
the three Decommissioning Programmes. 
 
   
  Document Heading Decommissioning Decommissioning
Programme 1 Programme 2
  Description Fixed Steel Platforms Infield Pipelines

Reference A, B, C and D 3 km 16" D-F


3 km 12" D-F
2 km 10" B-E
 
Introduction 1 1
 
  Executive Summary 2 2
  Background 3 3
 
  Items to be 4.1 4.2
  Decommissioned
  Inventory of Materials 5.1 & 5.2 5.3
Potential Re-use 6.1 6.2
Opportunities
Short List of 7.1 – 7.5 7.6 – 7.7
Decommissioning
Options
Comparative 8 8
assessment of Short List Gl
& Selected Options o
Well decommissioning 9 -
Environmental Impact 10 10
Assessment
Costs 11 11
Schedule 12 12
  Permits and Consents 13 13
  Monitoring and 14.1 14.2
  Maintenance
 
  Project Management 15 15
  References 16 16
  Glossary, Terms & Abbr. 17 17
 
Table 1.2.1 – Document Sections Comprising the Two  Decommissioning Programmes 

2 EXECUTIVE SUMMARY
 
This  document  presents  an  assessment  of  the  potential  decommissioning  options  for  the  Field 
facilities and pipelines and the process adopted to select the preferred options. 
 
In 1966 was the field discovered and was on stream brought in 1971 and lies some 250km off the west 
coast  of  Jutland.  It  has  been  subjected  to  various  upgrades  to  improve  and  maximize  production 
during its lifetime, including additional platforms F in the 1980’s, upgrade, demanding and compressor 
reconfiguration in mid‐1990’s. Production from the Dan Field is near future expected to cease within a. 
Page 9 of 56 
 
At Cessation of Production, it is estimated that the operator will have produced 101, 8 million m3 of oil 
and 22723 Nm 3 of gas at the entire Field  
 
 
The  decommissioning  programmes  present  plans  for  the  total  removal  of  the  A,  B,  C  and  D 
platforms  from  the  site  and  their  return  to  shore  for  re‐use,  recycling  or disposal  as  appropriate.  
They also present plans for the decommissioning of the three pipelines by in‐situ decommissioning 
or by removal to shore for re‐use, recycling or disposal as appropriate. 
 
This  document  describes  how  Offshoreenergy.dk,  Semco,  Stena,  Blue  Water 
Shipping and Ramboll, have: 
 
Reviewed a range of potential options for decommissioning the wells, platforms and 
pipelines.  
Examined   the   advantages   and   disadvantages   in   terms   of   safety,   technical   feasibility, 
environmental impact, effect on other users of the sea, and cost; 
Selected   a   short   list   of   options   that   would   achieve   the   desired   outcome   for   the 
decommissioning; 
Considered the environmental impact for the recommended options; 
Developed an appropriate consolidated programme for the 
implementation. 
 
The  studies  and  programmes  support  the  conclusion  that  the  following  options  represent 
acceptable  methods  of  decommissioning  the  wells  and  facilities  in  terms  of  safety, 
environmental and  social impact, and economic value: 
 

2.1 Removals
 

Following  the  permanent  plugging,   d e c o m m i s s i o n i n g   o f   w e l l s ,   and  preparing  the 


facilities,  the platform topsides will be completely removed to shore for dismantling by  any of the 
following methods: 
Installation reversal using heavy lift vessels (HLVs); or 
Integrated removal using large semi‐submersible crane vessels (SSCVs); or 
Integrated removal using novel single lift technology; or 
Piece small removal. 
 
Jackets will  be completely removed to shore for dismantling by: 
Installation reversal using HLV; or 
Removal using added buoyancy and or direct lifting. 
 
Due to the age and condition of the structures and equipment, it is unlikely considered that re‐use 
opportunities will be forthcoming, recycling rather than disposal will be maximised. 
 
This  is  in  accordance with  the  presumption of  removal  for  offshore  installations contained  in 
OSPAR decision 98/3 
 
2.2 Pipelines
 

The  pipelines have a history of stable burial demonstrated by survey records. Using a comparative 
assessment  of  the  technical,  safety,  environmental  and  societal  impacts  it  is  recommended  that 
pipelines will be decommissioned by: 
 
In‐situ  decommissioning, with  appropriate  remedial  work  at  pipe  ends  and  crossings  by  Re‐ 

Page 10 of 56 
 
trenching, burying or cutting out offending sections where practical. 
 
The  area  will  be  subject  to  a  post  decommissioning  environmental  survey,  and  the  pipelines 
will remain  the operator  responsibility  and  will  be  subject  to  an  agreed  monitoring  programme 
to ensure the lines remain free of hazards to other sea users. 
 

2.3 Time schedule


 
 
Cessation of Production 2015
Clean & Make-safe
Well Decommissioning
Module Segregation and Pre-Lifting
Pipeline Cleaning
Platform Removal (Window)
Pipeline Decommissioning (Window)
Onshore Disposal (Window)
Debris Clearance & Final Survey
 
2015 2016 2017 2018 2019 2020 2021 2020

Figure  2.3.1 – The Field Decommissioning Overall  Project  Plan

Page 11 of 56 
 
 

3 BACKGROUND
 
 
3.1 Decommissioning of the Field Facilities
 

It  is  proposed  that  the  decommissioning  of  the  Operator‐operated  platforms  facilities  will  be 
performed  in  a  phased  manner  following  the  permanent  abandonment  of  the  platform  wells, 
isolation  and  making  the  facilities  hydrocarbon‐free.      The  planned  phases  of  the 
decommissioning are  as follows: 
 
 Pre‐decommissioning inspections, surveys and engineering development studies. 
 Plugging and permanent abandonment of the wells. 
 Removal of residual hydrocarbons from the platform facilities and associated pipelines. 
 Removal to shore of the platform structures and equipment. 
 In‐situ decommissioning of the pipelines. 
 Post decommissioning seabed clearance and surveys. 
 Onshore dismantling and disposal. 

 
 

3.2 Environmental Conditions


This  section  presents  information  on commercial activities and biological features characteristic of 
the  North  Sea,  focusing  at  the  location  around  the  field.  The  subjects  described  in  the  following 
chapters include: 

 Biological assessment 
 Commercial fisheries 
 Shipping 

Overview of typical environmental concerns within decommissioning projects is in Appendix B given,  
prepared in support of this decommissioning report.   

3.2.1 Biological Assessment


The report "Scientific basis for a management plan for the North Sea and Skagerrak, 2010" /1/ 
describe Natural resources and environment in the North Sea. Areas of particular value and 
vulnerability are also in the report described. This report is as basis documentation for describing the 
state of the North Sea area in general used and the surrounding area of the field.  

In  shallow  areas  in  the  North  Sea,  e.g.  at  the  field,  the  processes  at  the  sea  bottom  and  in  the 
upper  water  column  is  closely  connected.  The  plankton  production  is  during  the  winter  limited 
by  low  temperature  and  reduced  light  conditions.  Factors  such  as  increased  nutrients  supply 
from land and vertical mixing of the water is contributing to an increase nutrient content within 
the  upper  water  column.  Increased  light  conditions  and  reduced  vertical  mixing  of  the  water 
during  the  autumn  creates  an  ideal  condition  for  growth  of  phytoplankton,  which  forms  the 
nutrient basis for the marine food chain. Figure 3.2.1 illustrates the ecosystem of the North Sea.  

Page 12 of 56 
 
Figure 3.2.1 The pelagic and benthic ecosystem in the North Sea /1/. 

The  benthic  fauna  in  the  North  Sea  consists  of  species  that  varies  with  sediment  composition, 
water depth, temperature and oceanic currents. In addition to be of significance for consuming 
organic  matter  within  the  sediments,  the  benthic  fauna  also  constitute  important  nutrient 
source for fish such as cod, haddock and flatfish. The seabed of the Dan field consist primary of 
silty  sand  and  the  area  is  dominated  by  species  such  as  polychaetes  (worms)  and  ophiuroids 
(brittle  stars)  that  typical  thrive  in  silt  sediment.  There  is  not  expected  benthic  species  of 
particular sensitivity in the area around the field.  

The North Sea constitute habitat for many fish species, of which the commercial fish species 
consists of herring, mackerel, horse mackerel, sprat, Norwegian pout, cod, haddock and sand eel. 
In the central North Sea the fully‐grown herrings are by young herrings replaced, there is 
occurrence of sprat and the dominant cod species includes whiting and haddock. The central 
North Sea is by primary production characterized and consists generally of less amount fish 
compared to the areas further north. The east North Sea constitutes the main habitat for flatfish, 
important areas for sand eel and habitat for herring and cod.  

The field lies within extensive areas used as spawning grounds by sprat, horse mackerel, sand eel 
and mackerel, see Figure 3.2.2. Spawning seasons for sprat in the North Sea typically takes place 
from the spring to the late autumn. The spawning season for sand eel is the winter period 
December and January, while both the horse mackerels and mackerel are spawning between the 
middle of May and throughout July, with a maximum in the middle of June.  

Page 13 of 56 
 
Figure 3.2.2 Distribution and spawning grounds within the location of the field. Upper left: sprat, upper right: 
sand eel, lower left: horse mackerel and lower right: mackerel.

The North Sea constitutes generally an unsuitable habitat for mammals due to the thorough 
shallow water depth. However, some of the smaller species cross the North Sea during migration 
and in the search for food. The species dominating the area around the field include porpoise, 
minke whale and white‐nosed dolphin. The general distribution of porpoise and minke whale, and 
observations of the white‐nosed dolphin is presented in Figure 3.2.3.  

Page 14 of 56 
 
Figure 3.2.3Upper left and right: distribution of minke whale and porpoise respectively. Lower: observation of 
white‐nosed dolphin.    

The numbers and distribution of the species varies between different years due to the variation of 
pray. Furthermore, whales in general migrate over large areas and can therefore not be regarded as 
restricted to isolated zones. However, Figure 3.2.3 shows that porpoises have a high density within 
the area around the field. 

The common seals species, grey seal and harbour seal, are present in the North Sea. Both 
species typical occur close to shore, but the grey seals have been known to cross the North Sea 
in the search for food. None of these two species is of particular concern with regards to 
sensitivity, and as their presence primarily are close to shore, decommissioning work is not 
expected to be of high concern with respect to grey seals and harbour seals as   

In addition to constituting an important area for fish and mammals, the North Sea is also of great 

Page 15 of 56 
 
value for the seabirds. More than 10 million seabirds are present in the area each year. Nesting 
seabirds found in the North Sea include the following: 

 Arctic petrel (Polarkjove) 
 Great Cormorant (Storskarv) 
 Eider duck (Edderfugl) 
 Mew Gull (Stormmåge) 
 Lesser Black‐backed Gull (Sildemåge) 
 Herring gull (Sølvmåge) 
 Great Black‐backed Gull (Svartbak) 
 Kittiwake (Ride) 
 Common Tern (Fjordterne) 
 Arctic Tern (Havterne) 
 Guillemot (Lomvi) 
 Puffin (Søpapegøje) 
 Razor‐bill auk (Alk) 
 Black Guillemot (Teist) 

The field is located offshore relative far from the coast and the geographic distribution of seabird 
within this area depends primarily on nourishment basis as the birds follow the fish stock. The 
central part of the North Sea is not of critical importance with respect to the seabirds. However, 
the periods of which the seabirds have high vulnerability should be into consideration taken with 
respect to removal of an installation. Seabirds have in general high vulnerability during the 
breeding and moulting period as well as during wintering. Table 3.2.1 presents an overview of key 
periods within the life cycle of seabirds. These periods can be as a general guideline seen for 
periods of which the seabirds can be of particular vulnerability for interference.

Table 3.2.1 Key periods for the seabirds.

Activity Jan. Feb. Mar. Apr. Jun Jul. Aug. Sept. Oct. Nov. Dec.

Breed Coastal zone

Swimming Offshore banker/deep


(Migration) basins

Moulting Coastal zone/sub coastal


zone

Flying migration All zones

Overwintering Sub coastal zone Sub coastal zone

Possible impacts associated with decommissioning activities offshore are generally time‐limited and 
on local scale. Areas of high relevance with respect to vulnerability include the areas of mammals and 
seabirds occurrence in addition to the spawning areas. Natural resources distributed along the coast 
are not considered as actual risk potential. Impacts on benthic fauna or possible vulnerable seabed 

Page 16 of 56 
 
habitats are expected to be limited as the activities are generally taking place in restricted zones.   

3.2.2. Commercial fisheries


Applied the statistics of the fishing activity within the area of relevance of a specific decommissioning 
project as a basis documentation for assessments of possible impacts on the fishing industry. The 
installation is located within area of the North Sea, which has an average biological production, which 
is also given in the statistic of the fishing industry.  

The fishing activity in the North Sea constitutes a large economical industry. Danish fishing vessels had 
a gross income of approximately DKK 1.9 milliard in 2011 /2/. Species of large economic value in the 
North Sea in general include sand eel, herring, plaice, mackerel and cod. Distribution of some of the 
fish species with the most economical value is presented in Figure 3.2.2.1. The red square represents 
the location of the Field.  

Page 17 of 56 
 
Figure 3.2.2.1 Distribution of in the North Sea, 2000‐2004.The maps shown the average rate of catch /3/.  

Figure 3.2.2.1 shows that the area around the Field is of a relative high important commercial fishing 
value compared to surrounding areas. Oil and gas installations have a safety zone established around 
each specific field, where fishing is not permitted. During the work of removal of an installation, 
temporary fishing restriction can be given due to occupation of areas. However, after the installation 
is the zones removed of temporary fishing restriction and the safety zones can be reopened, which 
will have a long‐term positive impact with respect to the fishing industry. Both the execution phase 
and the long‐term perspective with respect to possible impacts on the fishing activities are to be as 
part assessed of a decommissioning project.  

3.2.3.. Shipping
The North Sea is in general an area with high shipping activity. The field is located in an area of 
moderately high shipping activity, with common shipping routes nearby, see Figure 3.2.3.1.  The 
white point represents the location of the Field.  

The Field 

Figure 3.2.3.1 The distribution of shipping activity around the field (Data from August 2009 to July 2010). 

Seen from the figure above there is a markedly high ship activity nearby the field, however there are 
no major long distance routes in vicinity. The nearby activity is due to the presence of the 
installations, thus no major ship routes will be affected by vessels used for the removal operation.   
 
During the removal of an oil and gas installation possible conflicts with the shipping activity can be an 
issue with respect to occupation of a larger area around the installation. From this, the 
Page 18 of 56 
 
decommissioning activities need to be notified. In addition, updating of chart data and alternative 
routes for the shipping activities may be necessary during the removal of an installation.  
 
The decommissioning activities itself will have a time limited effect on the shipping activity during the 
removal of the installation. Nevertheless, the removal  of  the  platforms  will  have  a  long‐term 
positive  impact  when  completed, as restricted zones within the location of a specific installation can 
be reopened.   
 
Risk related to ship collisions during removal of the installations is to be quantified. The risk varies 
mainly with the extent of shipping activity in the area, the duration of the removal and the operations 
needed to be performed. The shipping activity around the area of the field can be described based on 
e.g. Automatic Identification System (AIS) data and available literature of relevance e.g. RKU‐
Nordsjøen (OLF, 2006, RKU‐Nordsjøen. Oppdatering av regional konsekvensutredning for 
petroleumsvirksomhet i Nordsjøen) and available management plan (Kystverket og 
Sjøfartsdirektoratet 2010. Helhetlig forvaltningsplan for Nordsjøen og Skagerrak. Statusbeskrivelse for 
skipstrafikk. TA‐2666/2010).

3.2.5. Environmental issues to assess


Decommissioning of oil and gas installation can potentially cause environmental impacts. Possible 
environmental impacts both in the short and long term, including the execution phase and end 
disposal, is to be addressed for the specific installation. Issues that should be addressed include the 
following: 

 Energy consumption 
 Emissions to air (NOx, CO2, SOx) 
 Planned and unplanned discharge of contaminants (metals, organic pollutants including oil 
components) to sea, water or ground 
 Impacts on habitats and protected species 
 Drill cuttings pile material at the seabed 
 Aesthetic impacts (noise, odour, visual impacts) 
 Waste management and resource utilisation 
 Littering 
 Marine traffic 
 Other unexpected accidents. 

A specific installation could have various disposal alternatives. For the relevant disposal options 
environmental impact assessment should be addressed in line with the specific installation and 
disposal option. Natural resources and environmental conditions within the relevant area of influence 
for decommissioning activities are to be as key basis documentations applied for assessments of 
possible environmental impacts. Environmental assessments and technical feasibility constitute the 
basis for selection of a decommissioning option.  

Page 19 of 56 
 
4 ITEMS TO BE DECOMMISSIONED
 
This   section   provides   a   description   of   the   platforms and   pipelines   to   be decommissioned 
and their layout in the Dan field. 
 
 
4.1 Platforms (Programme 1)
 

4.1.1 Description
 
The target for the decommissioning in the Field is the four oldest platforms, named A, B, C and D.  
)

Figure  4.1.1 Photograph illustrating  a   t y p i c a l   o l d   platforms


 
The  old platform complex consists of  a  four‐leg fixed  steel platform, which  is  by  bridges linked  to 
two four‐legged fixed steel platform supporting six and ten wells respectively and one flare platform. 
 
The  larger  four‐legged  platform  called  B  has  accommodation and  some  utility  equipment  with  a 
helideck  on  top.    The  accommodation  facilities  have  been  reduced  to  emergency  overnight 
facilities  but  the helideck remains in use.  The boat‐landing platform and access, has been from the 
sea removed. 
 
 
 
The  B  and  D  platforms  are  small  four‐legged  platforms  installed  as  a  minimal  facilities 
wellhead  platform.    They  support  six  and  ten  conductors  respectively.  The  topside  contains 
wellheads and manifolds. A crane is also present at each platform. 
 
The  C  platform  is  a  three‐leg  platform  with  flare facilities and a flare tower. 
 
The overall weights of the old platforms are in presented Table 4.1.1.1. 
 
       

Page 20 of 56 
 
 
Platform B A D C
Topside weight 1,694 236 524 137
(tonnes)
Jacket weight * 1,150 950 965 450
(tonnes)
Total (tonnes) 2,844 1,186 1,489 587
 
Table 4.1.1.1 – Overall  Weights  of Platforms 
 
Note:  * Only the weight of pile sections, which are to be together with the jacket removed, is included. 
 
 

4.1.2 History
 
The platforms in the old field were over a period installed from 1970 to 1972. They were originally 
manned platforms that were converted in the 1980’s to “normally unmanned  installations”  (NUIs) 
with  limited  accommodation facilities.    
 
 

4.1.3 Condition
 
In general, the primary structures, wells and process facilities of all the platforms are to be in good 
condition considered for their age.  The condition should be monitored and maintained to allow safe 
operation  and  decommissioning.  However,  some  redundant  parts  of  the  platforms,  including  all 
walkways at the top of the jackets have not been maintained and have been cordoned off.   These 
areas should not be relied upon for safe access.  Detailed consideration will be given to safe access 
for decommissioning. 
 

4.2 Pipelines (Programme 2)


 
4.2.1 Description
 
There  are  three  pipelines  to  be  decommissioned  in  the  field.  T hese  are  inter‐  platform 
pipelines from D to F and B to E.    
 
Summary details of all three pipelines are in Table 4.2.1.1 shown. 
 
   

Page 21 of 56 
 
     
  Pipeline No. D-F D-F B-E
Route D-F F-D B-E
Length (km) 3.0 3.0 1.884
Year Installed 1971 1977 1977
Nominal diameter (in) 16 12 10.25
Wall thickness (mm) 18.3 17.5 12.7
Material API5LX42 API5LX52 API5LX52
External wall coating Coal tar enamel Coal tar enamel Coal tar enamel

Concrete coating 1.5 1.5 1.5


thickness (in)
Anode material Zinc Zinc Zinc
Service Wet gas Oil/condensate Oil/condensate
Trenched Yes Yes Yes
Self- burial status (in 100% 100% 100%
2004)
Crossing Crossed by FA-K Crossed by FA-K 10" None
10" pipeline pipeline
Crossed by FA-R 6" Crossed by FA-R 6"
pipeline pipeline

Table 4.2.1.1 – Pipeline  Details 
 

4.2.2 History
 
The pipelines in the field are all trenched and naturally, backfilled and no mattresses were adjacent 
installed to any of the platforms in the field. Regular  surveys  have  indicated  that  the  burial  depth 
of  the  lines  has  remained  generally stable over this period.   
 
Refer to Appendix E for details of the burial history of the pipelines. 
 
 

4.2.3 Condition
 
Little  information  is  available  regarding  the  external  condition.    It  is  assumed  that  the  1.5”  thick 
external concrete coating (reinforced with small‐diameter chicken wire mesh) of the three pipelines 
installed  in  the  1970s  will,  having  exceeded  their  design  life  by  now,  be  experiencing  some 
deterioration  and  that  the  concrete  outer  coating  may  be  subject  to  spalling  if  the  pipelines  are 
extracted from the seabed.  
 

5 INVENTORY OF MATERIALS
 
 
5.1 Major Platform Materials
 
The inventory of the various materials on each of the platforms is presented in the tables below:
   

Page 22 of 56 
 
 
   
Item No. Description Weight (tonnes) Material

1 Structural steel 712 Carbon steel


2 Piping 460 Carbon steel
3 Vessels 237 Carbon steel
4 Mechanical equipment 156 Carbon steel
5 Electrical & instrument cables 5 Plastic coated copper
6 Cable trays 24 Galvanized steel
7 Electrical cabinets & equipment 14 Miscellaneous
8 HVAC/Architectural 1 Miscellaneous
9 Safety (includes fire water piping) 61 Carbon steel
10 Decking 24 Timber
  Total 1694  
 
Table 5.1.1 – Inventory of B Platform Topsides 

 
 
   
Item No. Description Weight (tonnes) Material
1 Jacket structure 945 Carbon steel
2 Piles (see Note 1 below) 190 Carbon steel
3 Risers 0 Carbon steel
4 Risers 0 SS Duplex
5 Anodes (see Note 2 below) 15 Aluminium alloy
  Total 1150  
 
Table 5.1.2 – Inventory of  B Platform Jacket 

 
   
Item No. Description Weight (tonnes) Material

1 Structural steel 150 Carbon steel


2 Piping 60 Carbon steel
3 Vessels 15 Carbon steel
4 Mechanical equipment 2 Carbon steel
5 Electrical & instrument cables 1 Plastic coated copper
6 Cable trays 1 Galvanised steel
7 Electrical cabinets & equipment 2 Miscellaneous
8 HVAC/Architectural 3 Miscellaneous
9 Safety 2 Carbon steel
  Total 236  
 
Table 5.1.3 – Inventory of  A Platform Topsides  (estimated values, see Note 3 below) 

Page 23 of 56 
 
 
   
Item No. Description Weight (tonnes) Material
1 Jacket structure 750 Carbon steel
2 Piles (see Note 1 below) 185 Carbon steel
3 Anodes (see Note 2 below) 15 Aluminium alloy
  Total 950  
 
Table 5.1.4 – Inventory of A Platform Jacket 

 
   
Item No. Description Weight (tonnes) Material
1 Structural steel 290 Carbon steel
2 Piping 58 Carbon steel
3 Vessels 77 Carbon steel
4 Mechanical equipment 48 Carbon steel
5 Electrical & instrument cables 2 Plastic coated copper
6 Cable trays 8 Galvanized steel
7 Electrical cabinets & equipment 5 Miscellaneous
8 HVAC/Architectural 15 Miscellaneous
9 Safety (includes fire water piping) 15 Carbon steel
10 Decking 6 Timber
  Total 524  
 
Table 5.1.5 – Inventory of D  Platform Topsides 

 
   
Item No. Description Weight (tonnes) Material

1 Jacket structure 750 Carbon steel


2 Piles (see Note 1 below) 185 Carbon steel
3 Riser 15 Carbon steel
4 Anodes (see Note 2 below) 15 Aluminium alloy
  Total 965  
 
Table 5.1.6 – Inventory of D  Platform Jacket 

 
   
Item No. Description Weight (tonnes) Material
1 Structural steel 125 Carbon steel
2 Piping 4 Carbon steel
3 Mechanical equipment & vessels 2 Carbon steel
4 Electrical & instrument cables 1 Plastic coated copper
5 Cable trays 3 Galvanised steel
6 Electrical cabinets & equipment 2 Miscellaneous
7 HVAC/Architectural 0 Miscellaneous
8 Decking 0 Timber
  Total 137  

Page 24 of 56 
 
 
Table 5.1.7 – Inventory of  C  Platform Flare 
 
   
Item No. Description Weight (tonnes) Material
1 Jacket structure 300 Carbon steel
2 Piles (see Note 1 below) 140 Carbon steel
3 Riser 0
0 Carbon steel
4 Anodes (see Note 2 below) 10 Aluminium alloy
  Total 450  
 
Table 5.1.8 – Inventory of C  Platform Jacket 
 
Note 1:  The pile weight included in the above tables is the weight of the piles to be removed from 
3m below seabed level. 
Note 2:    The anode  weight  included in  the  above tables  is  the original weight with  no  allowance 
for degradation of the anodes. 
Note  3:    Estimated  values  have  been  presented.  Documented  values  have  not  been  available. 
These values will be if necessary checked and updated when the data become available. 
 
 
 
5.2 Platform Hazardous Materials
 
The following hazardous materials have been as being either identified present or potentially 
present on the platform topsides and will require appropriate handling: 
 
   
Hazardous Description
Material
Asbestos The corrugated wind walls on the platforms are from material constructed likely to
contain asbestos in the coating.
Asbestos is also to be in solid form assumed present in pipe gasket material.
All material will be transported onshore and handled and disposed of by
approved methods.
Paint The original paint used on the platforms is to contain lead assumed that might
give off toxic fumes if flame cutting is used.
LSA LSA has not been in any pipework detected or vessels; however, its absence is
to be by on-site confirmed testing.
Heavy Metals Heavy metals such as Mercury and Lead are to be present expected inside
instruments, batteries and the like. This equipment will be to shore transported
intact and disposed of onshore by appropriate approved methods.
Radioactive Minute amounts of radioactive isotopes may be present in smoke detectors.
Isotopes These detectors will be to shore transported intact and disposed of onshore by
appropriate approved methods.
 
Table 5.2.1 – Hazardous  Materials  in the Field 

Page 25 of 56 
 
 

 
 
5.3 Pipeline Materials
 
The inventory of the various materials on each of the pipelines is presented in the table below: 
 
 
Pipeline No. D-F D-F B-E
   
Material Unit
Carbon steel Tonnes 747.1 2331.7 491.7
Duplex stainless steel Tonnes - - -
Coal tar enamel Tonnes 32.2 145.9 33.0
Neoprene Tonnes - - -
Bitumen enamel Tonnes - - -
Zinc/Aluminium anodes Tonnes 3.4 12.1 3.7
Reinforced concrete Tonnes 782.5 2197.8 506.8
 
Table  5.3.1.1 – Inventory of  the Field Pipelines 
 
 
 
 

6 POTENTIAL RE‐USE OPPORTUNITIES


 
There is a desire to treat decommissioned facilities in accordance with the Waste Hierarchy, which 
stipulates  that  re‐use  is  preferred  to  recycle,  and  recycle  preferred  to  disposal.      A  study  of 
the  potential    re‐use    of    the    field    facilities    has    determined    some    possible    re‐use 
opportunities.  These possibilities are presented in this section. 
 

6.1 Topsides and Jackets


 

Reference  is  made  to  Appendix  1,  Part  A1.  There  is  no  known  potential  for  re‐use  of  any  of  the 
topsides  and  jackets  in  their  current  locations.  Considering  the  depleted  Dan  reservoir,  for  the 
topsides  and  jackets  to  be  re‐used  in‐situ,  a  re‐use  of  the  field  would  have  to  be  found.        A 
possibility  c ould  be  to  the  use  of  the  field  for  CO2  sequestration  or  gas  storage.  This  has 
however, not been considered seriously to do: 
 
― CO2  sequestration is not yet a mature technical or commercial opportunity.  The industry 
estimate is that it is at least 5 years away from reality; 
― The reservoir is mainly an oil reservoir. 
― It is unlikely that the existing wells could be re‐usable for injection due to their design 
and condition; 
― It is not economical considered, or desirable from a safety point of view, to retain the Dan 
facilities in a dormant state for at least 5 years pending an opportunity. 
 
There  is  little  potential  for  re‐use  of  the  A,  B,  C  and  D  topsides,  flare  tower  and  jackets  in  new 
locations because of their age and condition.   
 
Possible  re‐use  options  require  the  facilities  to  be  recovered  to  shore  for  detailed inspection, 
cleaning and refurbishment.  This makes the re‐use of whole platforms economically less attractive 
than modern cost‐efficient platforms.  Platform components may be however, recovered to shore, 
refurbished and  re‐used.   Although re‐use is  unlikely  considered for  the  platforms discounted. 
Page 26 of 56 
 
 

 
 
6.2 Pipelines
 
As for the platforms, there is no known potential for re‐use of any of the pipelines in their current 
locations. 
 
Potential  options  for  re‐use  elsewhere  require  the  pipelines  to  first  be  recovered  to  shore  for 
detailed inspection, cleaning, refurbishment and r e‐certification. This m a k e s  t h e  r e ‐use o f  
p i p e l i n e s  technically and economically unfeasible. 

7 LONG LIST OF DECOMMISSIONING OPTIONS, AND SELECTION OF A


SHORT LIST
 
This section presents the potential decommissioning options for the old Fields facilities identified by 
Offshoreenergy.dk, Semco, Blue Water Shipping and Ramboll Oil & Gas 
 
Note that in preparation for any of the following decommissioning options, the facilities should be 
inspected for safe access, and, where necessary, remedial work should be to ensure carried out, that 
the facilities are safe for the access required by the decommissioning project.   This work should be 
part of the overall decommissioning project scope. 
 
As  well  as  ensuring  safe  access,  the  facilities  and  pipelines  should  be  de‐pressurized  and 
hydrocarbon‐ freed prior to  decommissioning.   In  the case of  the pipelines, this might  involve the 
installation  of  temporary  pig  launchers  and  receivers  at  the  platform  topsides  for  pigging  with 
sphere  pigs  to  clear  the  bulk  of  the  pipeline  contents.    The  pipelines  will  then  be  flushed  with 
seawater and  sampled to meet a  specified target,  hydrocarbon cleanliness level  of  no  worse  than 
produced water discharge of 30mg/l.   The fluids generated from all  of the hydrocarbon freeing will 
be contained and disposed of appropriately according to legislative requirements. 
 

7.1 Option Identification Process


 

A  number  of  study‐projects  have  been  carried  out  to  generate  a  list  of  possible  generic  options 
for  decommissioning  the Danish oil and gas field facilities.  Reference is made to Appendix 1, part 
A1. 
 
The generated list included different options, but no attempt was made to rate them with regard to 
practicality, cost, safety or environmental impact.    
 
This  ‘long  list’  of  decommissioning  options  that  resulted  is  from  these  projects  described  and 
briefly assessed  for  legislative  compliance  below.    Some  options  were  as  part  rejected  of  this 
process, leaving a short list for further assessment in Section 8.0. 
 

7.2 Decommissioning Options for the Platform Topsides


 
7.2.1 Leave in‐situ
 
This  is  not  a  legally  or  environmentally  acceptable  option,  regardless  of  whether  the  facilities 
are maintained, and therefore it was rejected. 
 

Page 27 of 56 
 
 

7.2.2 Re‐use in‐situ


 
The possible in‐situ re‐uses for the topsides include using them as: 
Renewable energy hub 
Fish farm 
Prison 
Military applications 
Navigation beacon 
Communications hub 
CO2  sequestration or gas storage 
 
All  these  options  are  opportunity  driven  and  can  only  be  considered  if  the  opportunity  arises 
within  the  right  time  frame.  There  would  be  significant  issues  that  would  have  to  be  resolved 
about  ownership  and  responsibility  of  removal  at  the  ultimate  end  of  their  useful  life.      This 
option  was rejected. 
 

7.2.3 Re‐use in another location


 
This  option  requires  the  topsides  to  first  be  to  shore removed,  cleaned and revamped. Based on 
the cost implications, the option was rejected. 
 

7.2.4 Remove and recycle

This  is  one  of  the  most  likely  futures  for  the  topsides  because  of  the  low  probability  of  finding 
a suitable re‐use opportunity.  Various removal methods were reviewed and are described later in 
this section. 
 

7.2.5 Rigs to reefs disposal


 
This might have been a practical option for the jackets.  However, the permits necessary for this 
method of disposal are not likely to be forthcoming foreseeable.  This option was rejected. 
 

7.2.6 Deep sea disposal


 
This  method  of  disposal  is  not  legally  acceptable  in  North  East  Atlantic  waters  under  OSPAR 
obligations.  This option was rejected. 
 

7.2.7 Delay decommissioning awaiting novel new technology


 
Reference is made to Appendix 1, part A2. A number of marine contractors are known to be in the 
process of producing novel concept designs for offshore equipment that are specifically tailored to 
meet  the  offshore  platform  decommissioning  market.      The  concepts  include  jack‐up  platforms 
and  floating  barges.   Initial  research indicates that the equipment, if developed, is not likely to be 
available  within  a  suitable  timeframe  to  be  acceptable  for  the  field  decommissioning  schedule.  
This option was therefore rejected. 
 
 
 
 
 

Page 28 of 56 
 
 

Decommissioning Option Status


Leave in-situ Rejected
Re-use in-situ Rejected
Re-use in other location Rejected
Remove and recycle Further consideration
Rigs to reefs disposal Rejected
Deep sea disposal Rejected
Await new technology Rejected
 
Table 7.2 – Summary  of Topsides Decommissioning Options 
 

7.3 Possible Topside Removal Methods


 
From the  review  of  the  topside decommissioning options, the  only viable options  involve removal 
of the topsides to shore.  The following possible removal methods were considered. 
 

7.3.1 Installation reversal using heavy lift vessel (HLV)


 
This  removal  method  is  simply  the  reverse  of  the  installation  sequence  for  each  of  the  platform 
topsides.   The work can be undertaken using an HLV of approximately 1,600 tonne lifting capacity. 
Prior  to  the  major  lifting  operations,  preparation  works  are  required  to  disconnect  and  isolate 
topside packages, attach lifting points and riggings, internally sea‐fasten loose items on the topsides 
and cut the topsides from the jackets.    
 

7.3.2 Topside integrated removal using semi‐submersible crane vessel (SSCV)


 
This  method  is  applicable  to  the  B  topsides  that  were  installed by  HLV  employing many  major 
lifts.   The SSCV concept involves removing the entire topside (lift weight 2,400 – 2,800 tonnes) in a 
single lift.   Substantial preparation work would be  necessary to  connect, strengthen the decks  and 
install  lifting  beams  for  an  integrated  lift.   This  method  is  not  applicable  for  the  smaller topsides 
as they are already for single major lift removal considered under the HLV option. 
 

7.3.3 Topside integrated removal using novel new technology


 
A number of potential novel methods of removing the topside were in a single piece 
considered. They each involve high marine work content. 
 
Versa‐truss is a proprietary hinged framing arrangement that, when attached to two barges and the 
barges  pulled  together,  will  lift  the  load  attached  to  the  top  of  the  framing.    This  method  has 
been for installing successfully used and removing topsides in the Gulf of  Mexico. See Appendix A, 
part A2.  It  is,  however,  technically  more  challenging  in  the  North  Sea  environment.   Substantial 
preparation work  would  be  necessary to  strengthen the  decks  and  install lifting  beams  and  lower 
tie members. 
 

7.3.4 Piece small topsides removal


 
A  marine work  vessel,  most  probably a  jack‐up  barge set  up  next  to  the  platform, would  support 
this topside  removal  method.    The  labour  force  from  the  vessel  would  dismantle  the  topsides 

Page 29 of 56 
 
 

into  sections  that  can  be  easily  handled  by  the  available  platform  and  vessel  cranes.      The 
individual pieces will be loaded onto supply boats for transport to shore. 
Another advantage is to utilize the same jack‐up for plugging of the wells. While the plugging takes 
place, the dismantling of modules and equipment can by the crew on board be performed. 
 

7.3.5 Shear‐leg and grab


 
The shear‐leg and grab method is a  method that is sometimes in salvage operations employed.   It 
involves the use of hydraulic guillotines and grabs to break up facilities in a crude manner and dump 
the pieces in barges for transport to shore. 
The shear‐leg option used as an alternative lifting method might be feasible. 
 
However,  it  is  unlikely  to  be  an  acceptable  method  for  decommissioning  platforms  because  of 
safety  issues,  hazardous  material  handling issues  and  the  likelihood of  debris  falling  into  the  sea.  
This method was rejected. 
 

7.3.6 Removal using drilling jack‐up rig


 
The use of a jack‐up  to  install  small  platforms  such  as  Dagmar and Valdemar  in the  Danish  North 
Sea  was  by  Ramboll  Oil  &  Gas  and  Maersk  Oil  initially  developed.    This  reverse  method  is  of 
topside removal  considered, to be the best option for the Dan topsides. 
 
 
Removal Method Status
HLV Too expensive
SSCV Too expensive
Novel technology Not feasible
Piece small Further consideration
Shear-leg and grab Rejected
Jack-up Rig Further consideration
 
Table 7.3 – Summary  of Topsides Removal  Methods 
 
7.4 Decommissioning Options for the Platform Jackets
 

7.4.1 Leave in place


 
As for the topsides, this is not a legally or environmentally acceptable option, regardless of 
whether, the structures are maintained and is therefore rejected. 
 

7.4.2 Re‐use in‐situ


 
As  the  in‐situ  re‐use  of  the  jackets  is  reliant  upon  the  re‐use  of  the  topsides,  this  option  was 
similarly rejected.  See section 7.2.2 above. 
 

7.4.3 Re‐use in another location


 

Page 30 of 56 
 
 

It is technically possible that the jackets may be re‐usable in new locations. However, the jackets are 
of such an age that re‐use is not feasible. 
 

7.4.4 Remove and recycle


 
This  is  one  of  the  most  likely  futures  for  the  jackets  because  of  the  low  probability  of  finding 
a suitable re‐use opportunity.  Various removal methods were reviewed and are described later in 
this section. 
 

7.4.5 Rigs to reefs disposal


 
This  might  be  a  practical  option  for  the  jackets  in  the  North  Sea  and  might  have  some 
environmental  benefits.  The  permits  necessary  for  this  method  of  disposal  are  not  likely  to  be 
forthcoming  in  the  future.  Nevertheless,  in  the  Gulf  of  Mexico,  this  is  an  accepted  method  of 
disposing of the jackets. It also has a positive effect on the fishing possibilities in the vicinity. Japan is 
constructing  similar  jackets  for  fishing  purposes.  However,  because  of  the  environmental  problems, 
this option was rejected. 
 

7.4.6 Deep sea disposal


 
As  for  the  topsides, this  method of  disposal is  not legally acceptable in  North  East  Atlantic waters 
was under OSPAR obligations and rejected.  

7.4.7 Delay decommissioning awaiting novel new technology


 
As  for  the  topsides,  initial  research  of  novel  new  concepts  indicates  that  the  equipment,  if 
developed,  is  not  likely  to  be  available  within  a  suitable  timeframe to  be acceptable schedule for 
the Dan field decommissioning. Therefore, this option was rejected. 
 
 
Decommissioning Option Status
Leave in-situ Rejected
Re-use in-situ Rejected
Re-use in other location Rejected
Remove and recycle Further consideration
Rigs to reefs disposal Rejected
Deep sea disposal Rejected
Await new technology Rejected
 
Table 7.4 – Summary  of Jackets  Decommissioning Options 
 
7.5 Possible Jacket Removal Methods
 
From the review of  the  jacket decommissioning options, the  only  viable  methods involve  removal 
of the jackets to shore.  The following were possible removal methods considered. 
 

7.5.1 Installation reversal using heavy lift vessel (HLV)


 
As  described earlier,  this  removal  method is  simply the  reverse  of  the  installation sequence.   The 

Page 31 of 56 
 
 

work  can  be  undertaken  using  an  HLV  of  approximately  1600  tonnes  lifting  capacity.   Prior  to 
the  major  lifting  operations,  preparation  works  are  required  to  separate  the  risers  and  J‐tube 
connections  from  pipelines  and  hose  bundles,  clear  any  debris  on  the  jackets,  install  lifting 
points  and  cut  the piles below seabed level.   
 

7.5.2 Jacket removal using novel technology


 
A  novel removal method entails floating the jacket by adding buoyancies below the waterline and 
towing  it  to  a  deep‐water  quayside  where  it  can  be  lifted  onshore  by  an  in‐shore  crane  barge.  
Once onshore, the jacket could be refurbished for re‐use or broken up for recycling. 
 
It is only practical deemed to float the jackets vertically because the bottom of jacket dimensions is 
not compatible with rotating them for floating and towing in the horizontal position.   
 

7.5.3 Piece small jacket removal


 
This jacket removal method would be supported by  a diving support vessel (DSV).   Using remotely 
operated vehicles (ROVs) and divers operating from the DSV, the jacket would be into sections that 
can be by the vessel cranes handled.  The individual pieces will be loaded onto supply boats  divided 
for  transport  to  shore.      This  method  was  rejected,  because  of  the  risks  associated  with  the 
excessive diving content in the operations and the potential instability of a sectioned jacket. 
 

7.5.4 Direct lift of jacket


 

This method is developed by Ramboll Oil & Gas and is in essence a direct off lifting of the jacket from 
the sea bottom to the barge by using a system of cables and winches. See Appendix A, A2  

7.5.5 Shear‐leg and grab


 
As for the topsides, this is unlikely to be an acceptable method for decommissioning jackets because 
of safety issues and the likelihood of debris falling into the sea.  This method was rejected. 
 

7.5.6 Further Development of the Versa‐truss Principle


This method for jacket removal is also by Ramboll Oil & Gas developed based on the well‐known Versa‐
truss principle. The principle is described in chapter 8.3.1.2 and in details in Appendix A, A2 

 
Removal Method Status
HLV Further consideration
Novel technology (buoyancy) Further consideration
Piece small Rejected
Shear-leg and grab Rejected
Direct off lifting of jacket Further consideration
Developed Versa-truss id Consideration
Further i
 
Table 7.5 – Summary  of Jackets  Removal  Methods 

Page 32 of 56 
 
 

 
7.6 Decommissioning Options for the Pipelines
 

7.6.1 Decommission and leave in‐situ


 
This  is  an  acceptable  decommissioning  option  for  subsea  lines  when  certain  criteria  such  as 
cleanliness,  stability  and  safety  for  other  uses  are  of  the  sea  met  particularly  when  the  lines  are 
trenched and buried.  This option was considered as being worthy of further consideration. 
 

7.6.2 Re‐use in‐situ


 
Such an option is closely reliant upon the in‐situ re‐use of the platforms.  See section 7.2.2.  It is only 
practical  if  an  opportunity  for  re‐use  arises  within  the  right  period.    This  not  being  the  case,  the 
option was rejected. 
 

7.6.3 Re‐use in other locations


 
It  is  technically  possible  that  relatively  new  pipelines  will  be  reusable  in  new  locations.    The 
pipelines,  however,  are  past  their  design  life  and  are  of  such  an  age that re‐use is  not  a feasible 
solution. This option was rejected. 

7.6.4 Remove and recycle or dispose in landfill


 
This is a possible option and various removal methods were reviewed and are described later in this 
section. 
 
Decommissioning Option Status

Leave in-situ Further consideration


Re-use in-situ Rejected
Re-use in other location Rejected
Remove and dispose in landfill Further consideration
 
Table 7.6 – Summary  of Pipelines Decommissioning Option 
 
Recycling of the pipeline sections is not likely to be practical due to the difficulties of removing the 
coatings  and  material  contamination.  Disposal  in  landfill  is  therefore  the  most  likely  disposal 
method for the pipelines in the event that they are to shore recovered. 
 

7.7 Pipeline Removal Methods


 
From  the  review  of  the  pipeline  decommissioning  options,  one  of  the  viable  options  involve 
removal of the pipelines to shore.  The following were possible removal methods considered. 
 

7.7.1 Reverse S‐lay


 
This  method  involves  using  a  pipeline  lay‐barge  vessel  to  pull  the  pipeline  onto  the  vessel  deck 
where  it  will  be  cut  into  sections  for  transport  to  shore.      This  method  has  been  used  to 
Page 33 of 56 
 
 

recover  sections  of  unburied  pipeline  during  installation  operations,  due  to  weather  or  logistical 
interruptions, or sections damaged during installation.  This is an acceptable methodology for new 
pipelines but is not preferred and highly risky for pipelines close to or past their design lives due to 
the deterioration of the coatings and the general uncertainty of pipeline integrity. 
 

7.7.2 Cut and lift


 
This method requires the pipeline to be fully uncovered before it is cut into sections on the seabed 
using  a  special  cutting  tool  attached  to  an  ROV.      The  sections  would  then  be  to  the  water 
surface  lifted  and transported to  shore.    This  methodology has  a  high  safety risk  exposure but  is 
practical considered for short pipeline sections that are not buried. 
 

7.7.3 Surface tow


 
In this option, the pipeline would be uncovered and have buoyancy units attached along its length 
such that it floats to the surface of the sea.  It could then be towed to shore or to a re‐use location. 
The  practical  difficulties  involved  with  this  methodology  combined  with  the  safety  considerations 
associated with the large diving content, however, exclude this method from further consideration. 
 

7.7.4 Controlled depth tow


 
This method is similar to the surface tow except that chains are to the lines attached to make them 
float at  a  controlled depth off the seabed.  This  method was  for the  same reasons rejected as  for 
the surface tow method. 
 
 
Removal Method Status
Reverse S-lay Further consideration
Cut and lift Further consideration
Surface tow Rejected
Controlled depth tow Rejected
 
Table 7.7 – Summary  of  Pipelines  Removal  Methods 
 
 

8 COMPARATIVE ASSESSMENT OF SHORT LIST OF OPTIONS AND


SELECTION OF PREFERRED OPTION
 
This  section  presents  the  short  list  assessment  and  selection  process  of  the  decommissioning 
options for the Field facilities & pipelines.   The short‐listed options are first briefly described (more 
detail is available in Appendix A), and then a comparative assessment is carried out for each option 
– leading to a preferred option. 
 

8.1 Option Selection Methodology


 
Offshoreenergy.dk,  Semco,  Blue  Water  Shipping  and  Ramboll  Oil  &  Gas  carried  out  a  brief 
assessment and selection  of  options from the  feasible short‐list identified  in  the  previous  section. 
Each of the options was with regard examined to the following: 

Page 34 of 56 
 
 

 
Technical risk  and  complexity; 
Personnel safety.   
Environmental  and  social  impact.    A  detailed  environmental  impact  assessment  for  each 
option is given in Appendix C, with a summary presented in this section: 
Energy  consumption.   
Cost.   A high‐level cost estimate has been for each option made. 
 
This section presents a summary of the above assessments, along with a summary of the preferred 
decommissioning options for the Field facilities. 
 
Any  option  that  was  considered  ‘not  acceptable’  in  any  of  the  categories  was  from  further 
consideration  rejected  unless  constraints  could  be  to  mitigate  the  ‘not  acceptable’  rating  placed.  
Because of the above process, were the preferred decommissioning methods derived. 
 

8.2 Comparative Assessment and Selection of Preferred Option for Topsides


 
All of the short‐listed decommissioning options for the Field platforms topsides require them to be 
removed to shore.   The comparative assessments were  therefore on  the removal methods carried 
out. 
 

8.2.1 Description of Topsides Removal Options


 
The  Field  platform  topsides  were  in  single  lifts  installed  with  the  maximum  lift  weight  of 
approximately 1400 tonnes.    
 
The  selected  topside  removal  methods  are  described  in  greater  detail  in  Appendix  A  and 
summarized  below.      Some  of  the  topside  removal  methods  are  dependent  upon  the  platform 
involved. 
 

8.2.1.1 Installation reversal using HLV


 
This method of topside removal is simple for the topsides that were as a single lift installed, i.e. A, C 
and  D.    A  slightly  more  complicated  methodology  is  required  for  the  larger  platform  B, which 
were with multiple topside lifts installed. 
 
Prior  to  lifting  off  these  topsides,  it  is  necessary  to  carry  out  preparation  or  reverse  hook‐up 
work. The  preparatory  work  includes  separating  the  risers,  caissons  and  J‐tubes  from  the  jacket; 
rigging the conductors (if not removed during well plugging and abandonment) and topside for lift; 
preparing the leg cuts and internal sea fastening. 
 
Once  the  preparation work  is  complete, an  HLV  will arrive  to  prepare  to  remove  the  topsides 
modules. 
 
After  anchoring  and  mooring  a  cargo  barge  alongside,  the  HLV  will  attach  the  lift  rigging  to  the 
crane hook,  cut  the  deck  legs  and  lift  the  platform  topsides  modules  onto  the  cargo  barge.   The 
modules  will  then  be  sea‐fastened  to  the  barge  and  the  barge  will  be  towed  to  shore.    The 
conductors may be lifted and removed when the cargo barge is being prepared. 
 
 
 

Page 35 of 56 
 
 

8.2.1.2 Topside removal using SSCV


 
This method involves lifting the topsides of the platforms in one single lift using a twin crane semi‐ 
submersible crane vessel of lift capacity in excess of 3,000 tonnes.  This method is only applicable to 
the B topsides as the others are within the single lift capability of an HLV. 
 
In order to lift the B topsides in a single piece, it will be necessary to install lifting beams under the 
deck and to undertake deck strengthening. 
 
The  SSCV  will  arrive  at  location  once  all  the  preparatory  work  is  complete.   After  attaching  the 
lift rigging and cutting the deck legs, the topside will be as a single unit lifted and placed on a cargo 
barge. 
 

8.2.1.3 Topsides removal using novel technology (Versa‐truss)


 
Versa‐truss  is  a  proprietary  arrangement  for  lifting  platform  decks  and  the  like  without  the  use 
of conventional  cranage  or  jacks.   The  picture  (Fig  8.2.1.1)  below  demonstrates  how  the system 
works.

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Figure  8.2.1.1 
 
The Versa‐truss option is applicable to the removal of three Field platform topsides. 
The flare tower has to be lifted by a HVL in one piece. 
 
In order to remove the topsides in this manner, it will be necessary to strengthen and install lifting 
lower  tie  members  between  the  deck  legs.   The  Versa‐truss  equipment  will  be  fitted  out  inshore 
on barges and towed to site, where the barges will be anchored out.   The system will be fitted up 
to  the prepared decks  and the  deck legs  cut.    The  barges  will  then be  winched together and  the 
deck  will lift  off  the  jacket.    The  deck  and  the  barges  will  then  move  forward  and  lower  the 
deck  onto  a transport barge for transit to shore. 
 

8.2.1.4 Piece small removal of topsides


 
This topside removal method will be undertaken by a marine work vessel, most probably a jack‐up 
barge  that  will  break  the  platforms  up  into  sections  that  can  be  easily  handled  by  the 
available cranes.  The individual pieces will be loaded onto supply boats for transport to shore. 
 
It is envisaged that a large crawler or ringer crane might be on the deck of the jack‐up, which would 

Page 36 of 56 
 
 

be able to handle 100 tonnes lifts at most parts of the platforms. 
 
 

8.2.2 Comparative Assessment and cost of Topsides Removal Options


 
All of the options are technically feasible.   The  reverse installation and SSCV  options are similar in 
terms of technical  risk  but the novel  lift technologies  carry  a  higher  technical  risk  due to the 
difficulties  of  operating  in  the  shallow  water  and  high  tide/currents  of  the  SNS.      The  piece‐
small option also carries higher technical risk due to the longer offshore deconstruction duration. 
 
For the four platforms, the costs for the HLV and SSCV options are likely to be similar. 
 
For  the smaller platforms (A, D and C), the piece‐small options are similar, with the use of Jack‐up 
options the solution is likely to be significantly cheaper. 
 

8.2.3 Summary of Selected Topsides Decommissioning Options


 
Based on  the  comparative assessment, the  method of removal  for  all  the  Field topsides  might be 
the installation reversal using HLV.   This is a technically proven  method  and  is  simply  the  reverse 
of  the  original  installation  sequence.    The  operation  is subject to standard offshore construction 
personnel safety risk and environmental risk exposures that can be managed.  There are a number 
of contractors, who can offer this removal service in the North Sea. 
 
For  the  larger  topsides  (B),  a  feasible alternative to  the  HLV  removal  option  might be a  single lift 
removal  using  SSCV.   The  topsides  would  first  have  to  be  structurally  linked  and  strengthened, 
such that the multiple packages can be lifted in one piece.  This would require a significant amount 
of offshore preparatory work but it avoids the need to isolate and individually rig the packages for 
separate  lifts.    This  method  is  rated  similar  in  terms  of  technical,  personnel  safety  and 
environmental  risks  to  the  HLV  option.    However,  this  alternative  removal  method  limits  the 
number of contractors who can perform the offshore as well as the onshore work. 
 
For  the  smaller  topsides  (A,  D  and  C),  a  feasible  alternative  to  the  HLV  removal  option  is  piece 
small  removal  using  a  Jack‐up.    This  option  has  an  increased  offshore  scope  and  duration.  As 
such, it has higher technical, personnel safety and environmental risks when compared to the HLV 
option.  These risks would have to be properly managed during execution. 
 
There  can  be  other  acceptable  removal  methods  for  the  topsides  and  jackets  using  novel 
technologies commensurate with  contractors’ experience and  resources as  described in  Section 7. 
These  cannot  be  discounted and  ought  to  be  assessed  on  a  case‐by‐case basis  at  the  contracting 
stage of the project. 
 
Although  a  number  of  removal  were  methods  identified,  none  of  the  short‐listed  topsides  was 
removal methods rejected outright.    As  such, notwithstanding the  above assessment, contractors 
tendering  for  the  decommissioning  work  will  not  be  excluded  from  offering  other 
decommissioning methods that are commensurate with their experience and resources.   However, 
any  alternative  method  proposed  by  a  contractor  would  be  reviewed  to  ensure  that  it  meets  or 
exceeds all of the assessment criteria. 
 
     
Platform Component Selected Preferred Possible
Decommissioning Option Removal Option Alternatives
Larger Topsides Remove to shore for re-use, HLV SSCV;
(B) recycling or disposal Novel technology
Page 37 of 56 
 
 

Smaller Topsides Remove to shore for re-use, HLV Piece small;


(A, D and C) recycling or disposal Novel technology
 
Table 8.2.4 – Summary  of  Selected  Topsides Decommissioning Options 

8.3 Comparative Assessment and Selection of Preferred Option for Jackets


 
All of the short‐listed decommissioning options for the Field platform jackets require them to be 
removed to shore.  The comparative assessments were therefore carried out on the removal 
methods. 
 
8.3.1 Description of Jacket Removal Options
 
Only three methods of jacket removal were deemed feasible after the review of the long list of 
options. These methods are: 
 
 Installation reversal using HLV 
 Jacket removal using added buoyancy 
 Novel direct off‐lifting of the jacket 
 
 

8.3.1.1 Installation reversal using HLV


 
As with the topsides, it is necessary to carry out some preparation works prior to lifting the jacket. 
This involves removal of the connections between the  pipelines and the risers and J‐tubes and the 
cutting  of  the  piles  below  mud‐line.  The  connection  of  the  lift  rigging  for  the  jacket  will  also  be 
carried out in the preparation phase to save the more expensive HLV time. 
 
The  subsea  work  of  cutting  the  lines  and  clearing  the  seabed  will  be  by  a  diving  support  vessel 
(DSV)  supported.  It  is  that  most  of  the  work  envisaged  may  be  by  ROVs  accomplished  however, 
some manual diving is  also to  be  necessary expected. The other preparation work involves cutting 
the piles and installing the lift rigging. 
 
When the preparation work is complete the HLV will arrive and anchor  in position. The  jacket will 
be on a cargo barge lifted and placed where it will be sea fastened and transported to shore. 
 

8.3.1.2 Jacket removal using novel technology


 
Added buoyancy tanks. 
This  method  of  removing  the  jackets  might  involve  adding  buoyancy  in  the  form  of  tanks  to  the 
jackets in order that they will float clear of the seabed are after the piles cut. This will enable them 
to be towed to a deep‐water inshore location where they can be lifted clear of the sea by a shear‐
leg barge.   The shear‐leg will then moves to a nearby quayside and place the jackets on land. 
 
The  preparation  works  necessary  for  this  operation  include  those  required  for  the  HLV  removal 
method plus the attachment and de‐ballasting of the buoyancy tanks. 
 
Novel direct off lifting. 
However,  dealing  with  relatively  small  jackets,  an  innovative  removal  system  as  outlined  at  the 
figures 8.3.1  to  8.3.6 below is invented by Ramboll.  It  gives  a  diagrammatic representation of  the 
jacket removal method in which the jacket is pulled in a vertical position to the barge. When the 
"turning point has been reached, the jacket is pulled into a horizontal position and transported to 
shore. 
Page 38 of 56 
 
 

 
Figure  8.3.1  Figure  8.3.2 
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 
 

‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 
Figure  8.3.3  Figure  8.3.4 
 

Page 39 of 56 
 
 

 
Figure  8.3.5  Figure  8.3.6 

Versa‐truss principle, further developed 
 
As described in Appendix 2, the Versa‐truss principle can be used for removal of the jacket as well. 
Nevertheless, the method has before not been used and is therefore in a conceptual study phase. 
The principle is below roughly outlined: 

             

              

The principle is to align two barges alongside the jacket. A‐frames on the barges are attached to the top of the 
jacket and the barges are by the use of winches together pulled and cables. When the jacket is sufficiently 
lifted free of the sea‐bottom a set of supporting beams are from one barge pushed to the other. Finally, the 
jacket is lifted to a horizontal position and safely sea‐fastened for transportation to shore. 

Page 40 of 56 
 
 

8.3.2 Comparative Assessment of Jacket Removal Options

8.3.2.1 Technical risk and complexity


All the options are technically feasible. The reverse installation carries the lowest risk, as it is a well 
technique proven which can be by a number of contractors carried out.    The added buoyancy 
technology carries a higher technical risk due to the difficulties of operating in the North Sea. 

However, the direct off lifting of the jacket by the use of winches on‐board the transportation barge 
seems to represent an economical advantageous feasible solution. 

The Further developed Versa‐truss principle represents a viable solution containing known 
technologies. 

8.3.2.2 Costs
 
The cost of the HLV option is likely to be 50‐75% of the cost of the buoyancy option due to the high 
cost of fabricating the buoyancy tanks and the amount of marine activity. 

However, the direct lifting of the jacket is estimated to approximately 80% of the HLV option. Thus, 
the direct lifting of the jacket as described above seems to be a cheap solution.  

The Further developed Versa‐truss principle contains relatively cheap elements to implement and 
thus might    be the cheapest solution. 

8.3.3 Summary of Selected Jacket Decommissioning Options


 
Based  on  the  comparative  assessment  considering  the  above  criteria,  the  preferred  methods  of 
removal for all the old Field jackets are the novel  direct lifting method and the Further developed 
Versa‐truss  principle.    These  are  technically  simple  methods  and  are  s i m p l e   a n d   f a i r l y  
e a s y .   The  operations  are  subject  to  standard  offshore  construction  personnel  safety  risk  and 
environmental risk exposures that  can  be  managed.  There  are  a  number  of  contractors, who  can 
offer this removal service in the North Sea. 
 
Although  two  preferred  removal  methods  were  identified,  the  alternative buoyancy option  is  not 
rejected  outright.  As  such,  notwithstanding  the  above  assessment,  contractors  tendering  for  the 
decommissioning  work  will  not  be  excluded  from  offering  other  decommissioning  methods  that 
are  commensurate  with  their  experience  and  resources.    However,  any  alternative  method 
proposed  by  a  contractor  would  be  reviewed  to  ensure  that  it  meets  or  exceeds  all  of  the 
assessment criteria. 
 
 
     
Platform Component Selected Preferred Possible
Decommissioning Option Removal Option Alternatives
Jackets Remove to shore for re-use, HLV Novel technology
(All) recycling or disposal (buoyancy)
 
Table 8.3.4 – Summary  of  Selected  Jacket  Decommissioning Options 
 

Page 41 of 56 
 
 

8.4 Comparative Assessment and Selection of Preferred Option for Pipelines


 

8.4.1 Description of Pipeline Decommissioning Options


 
The possible decommissioning options  for  pipelines are decommission in‐situ,  or  remove to  shore 
for disposal in landfill. 
 

8.4.1.1 Decommission in‐situ


 
Decommissioning pipelines  in‐situ  require  their  ends  to  be  cut  from  the  platforms  at  the  base  of 
the risers  and  made  safe  from  being  a  potential  snagging  hazard  for  other  users  of  the  sea  once 
the  platforms  are  removed.  Any  exposed  sections  or  spans  along  their  lengths  that  may  pose  a 
snagging hazard would have to be similarly remedied. 
 
Such remedy can be achieved by: 
‐ Re‐trenching and burying of any exposed sections; 
‐ Recovery of mattresses where their condition allows safe lifting; 
‐ Cutting  out  the  offending  sections  for  recovery  to  shore  for  disposal  and  remedying  the  cut 
ends as above. 
 
In  addition,  where  there  are  mitigating  reasons 
achieved by: 
‐    Dumping rock over the exposed sections; 
‐    Covering the exposed sections with mattresses; 
 
As the pipelines would be flushed clean of contaminants at this stage, the ends can be open to the 
sea left.   The  pipelines  would  become  more  stable  in  the  seabed  when  seawater  filled  than  they 
were when oil/gas‐filled during their service lives. 
 
A leave in situ solution will require remedial works to ends, crossings and significant spans as part of 
the scope.  
 

8.4.1.2 Remove pipelines by reverse S‐lay for on‐shore disposal


 
This  pipeline  decommissioning  method  removes  the  pipelines  by  a  reversal  of  the  method  used 
to  lay  the  line. It involves pulling the  pipe  back up the  stinger on  the  lay‐barge and cutting it  into 
suitable lengths to enable it to be shipped to shore on a cargo barge. 
 
 
The sequence of initiating the pipeline recovery is shown in Figure 8.4.1 below. 
 

Page 42 of 56 
 
 

Page 43 of 56 
 
 

 
 

 
Figure  8.4.1 – Pipeline  Removal  b y Reverse  S‐Lay 
 

8.4.1.3 Remove pipelines by subsea cut and lift for on‐shore disposal
 
This  method entails the  decommissioning of  the pipelines by exposing the lines, cutting them  into 
short lengths on the seabed, lifting them above water and transporting them to shore for disposal. 
 
In order to cut and lift the pipelines it would be necessary to unbury them along their entire length. 
This could be by either done jetting the soil away from the pipes or by ploughing a trench along the 
pipes.  Because of the relatively loose sand on the seabed, the jetting method is more suitable. 
 
The  pipeline cutting and removal could be undertaken with  a  diving support vessel.   The  majority 
of the pipe cutting and rigging work could be undertaken by purpose adapted ROV however a crew 
of  divers  would  be  on‐board  the  vessel  to  undertake  specific  tasks  and  in  particular 
intervention  for unplanned events. 
 

8.4.2 Comparative Assessment of Pipeline Decommissioning Options


 

8.4.2.1 Technical risk and complexity


 
The  activities  required  for  decommissioning  in‐situ  and  the  required  remedial  operations  are 
considered routine operations and  do not have significant technical risk.    Removing new pipelines 
by  reverse S‐lay is  within  the  technical capability  of  existing purpose‐built pipe‐lay vessels.   Diving 
preparatory  work  will  be  required  to  install  the  pulling  head  for  the  pipe‐lay  vessel  to  pick  the 
pipeline  up  at  one  end  and  to  install  an  anchor  pile  at  the  other  pipeline  end.    The  removal 
operation would be increasingly more complex if  the burial depth is significant and  if  the integrity 
of  the  pipe  or  the  coating  is  poor.      This  removal  method  is  therefore  to  be  technically  risky 
considered  for  the  Dan  pipelines  as  they  are  to  have  experienced  expected  some  deterioration 
having passed their design lives by the time of decommissioning. 
 
The  cut  and  lift  removal  method  requires  the  pipeline  to  be  unburied  and  an  automated  and 
repetitive  subsea  pipeline cutting  technique to  be  developed.  Uncovering can  be  achieved by the 
conventional remotely operated  methods of  using  either a  pipeline plough or  ROV‐operated mass 
flow equipment.     The   cutting   techniques  would   require   development  from   those   used   for  
subsea conductor and jacket leg cuts.   The  cut lengths would have to  be  recovered to  the  surface 
efficiently  using  specially  adapted  lifting  bars.      There  would  be  uncertainty  regarding  the 
reliability  of  this specially designed equipment.    
 

Page 44 of 56 
 
 

8.4.2.2 Costs
Due to the minimum activities and resources required, decommissioning in‐situ is  the lowest cost 
option, with an order of magnitude lower cost.  There is, however, a long‐term cost commitment 
for on‐going monitoring.  The frequency of such monitoring should be based on a risk analysis. 
 

8.4.4 Summary of Selected Pipeline Decommissioning Option


 
From the foregoing comparative assessment, decommissioning the pipelines by leaving them in‐situ 
in  a  flushed,  water‐filled  and  stably  buried  condition  is  the  recommended  option.  The 
environmental and  energy  consumption  impacts  of  this  option  are  mitigated  by  the  limited  
remediation  work required to make them safe from being a snagging risk due to their substantially 
buried and stable status.  
 
The trenched pipelines are naturally back‐filled.  Filling the pipelines with seawater will increase the 
lines  weight/buoyancy  ratio  by  a  factor  of  between  1.4  and  1.8  further  improving  their  buried 
stability. 
 
Remedial work  will  be carried out  at  pipeline ends  and crossings to mitigate any  risk to  other  sea 
users.  The  final  selection  of  these  measures  will  be  subject  of  detailed  design  and  further 
engagement with stakeholders. 
 
These lines will continue to be monitored as indicated in section 15. 
The  removal  options  are  not  preferred  as  the  pipelines  are  unlikely  to  be  fully  recycled  or  re‐used 
elsewhere and therefore would be to landfill sites only to be re‐buried sent on land.  In addition, the 
removal  options  incur  greater  exposures  to  personnel  safety,  are  technically  higher  risk,  and  much 
higher cost due to the pipelines being mostly buried. 
 
 
   
Component Selected Decommissioning Option
Pipelines Leave in-situ, flood and remedy exposed ends, crossings
and significant spans
 
Table 8.4.5  – Summary  of  Selected  Pipeline  Decommissioning Option 
 
8.5 Disposal of Decommissioned Material
 

Disposal  preference  is  by  the  Waste  Hierarchy governed,   w h i c h   states  that  re‐use  is  preferred 
to recycle and recycle preferred to scrap as described in Section 6.  Although there is no known re‐
use opportunity for any of the Field facilities, it is not  discounted and will be pursued with the on‐ 
shore disposal contractor within a period that is yet to be specified.  All hazardous materials will be 
appropriately  handled,  and  disposed  of  in  accordance  with  the  relevant  legislations.    The  bulk  of 
the  recovered  platform  material  is  expected  to  be  recycled,  with  possibly  some  residues  that 
are difficult to separate out scrapped and sent to approved landfill sites. 
 
Once removed from the field the topsides, jackets, and pipelines will be transported to an onshore 
decommissioning facility.   This  facility  will be  licensed for  the  decommissioning activities including 
the  handling  and  disposal  of  any  hazardous  materials  that  may  be  present.   As  such,  the facility 
will have appropriate quarantine. 
 
The hierarchy of how the platform and pipeline components are disposed of is as follows: 

 Refurbishment for re‐use as unit 
 Removal of equipment for reuse 
Page 45 of 56 
 
 

 Segregation of pipes for reuse (recovered end sections and hose bundles) Segregation of 
steelwork and other materials for re‐use 
 Segregation of materials for re‐cycling 
 Segregation of materials (including hazardous materials) for disposal 

 
Platform components, pipelines, etc. arriving at the quayside of the disposal facility on cargo barges 
or vessel decks will be offloaded by appropriate means.  This may be by crane however; larger deck 
sections are more likely to be offloaded using multi wheeled bogies. 
 
Once  on  the  quayside,  any  components  will  be  cleaned  with  marine  fouling  off  and  the 
fouling material is either as feed stock material reused for the cement industry or disposed of and 
sent to landfill sites approved. 
 
Any  large component scheduled for re‐use, possible re‐use will be stored in a designated area of 
the facility for refurbishment, or preservation until its future is determined. 
 
Other  components  that  are  not  viable  for  re‐use  as  a  single  unit  will  be  stripped  out  and  any 
equipment and/or materials suitable for re‐use piece small will be stored and preserved in suitable 
warehouses or designated storage areas. 
 
Any recovered concrete coated pipeline sections will have their anodes removed and collected for 
recycling.   Where  it  is  deemed  practical will  the  concrete coating be  on the pipelines stripped off 
and  collected for  use  as  hard‐core  leaving  the  steel  pipes  in  a  condition  suitable  for  re‐cycling  in 
smelters. 
 
Other materials will collected be by type and stored in separate areas for transhipment to smelters 
or other recycling facilities. 
 
Materials  not  suitable  for  any  of  the  above  treatment  (including  hazardous  materials  such  as 
asbestos, LSA contaminated materials, heavy metals and the like) will be collected and transported 
off site for disposal in landfill and/or other approved disposal facilities. 
All wastes will be in accordance dealt with the appropriate legislation  
 

9 WELL DECOMMISSIONING
 
9.1 Description
 
 
There are 16 oil producing wells in the old Field.  The first well was in 1969 drilled prior to platform 
installation and the last drilling activity in the field was in 1982. 
 

9.2 Drill Cuttings


 
A  1986  seabed  survey  completed  after  the  majority  of  wells  had  been  drilled  indicated  that 
there were  no  harmful  impacts  on  the  local  biota.  From  regular  ROV  seabed  surveys  carried  out 
since  at all  the  Dan platforms, it  has  been determined that  no  visible  drill  cuttings exist  at  any  of 
the platforms (refer Appendix C6).   The lack of any drill cuttings is  due to the seabed erosion that 
exists  at  the  platform  locations  combined  with  the  fact  that  no  drilling  activities  have  been 
undertaken at any of the platforms since 1982.  
 
Page 46 of 56 
 
 

9.3 Well Decommissioning Plan


 
The  platforms  in  the  old  Field  are  likely  to  cease  production  from  July  2015.    A  programme  of 
well  decommissioning  should  commence  in  d u e   t i m e   b e f o r e   2015.   This  will  involve  flushing 
and  cleaning  the  wells  before  setting  permanent  plugs  at  appropriate  depths  according  to  the 
specific features of the reservoirs,  in  order  to  abandon  the  wells.   The  fluids  generated  from  the 
flushing will be  contained and disposed of in compliance with applicable legislations. 
 

10 ENVIRONMENTAL IMPACT ASSESSMENT


 
A detailed assessment of the environmental impact for the decommissioning of the old Field should 
be prepared in due time before 2015. 
In Appendix B of this report an extensive Environmental, assessment report is included. 
 

10.1 Introduction and method


 
The  environmental  risks  associated  with  each  of  the  preferred  options  for  decommissioning  the 
Field  platforms  and  pipelines  should  be  assessed  using  a  methodology  based  on  the  following 
principles:  
 
The assessment could be broken down into a number of steps:  
 
Each  of  the  short‐listed  options  to  be  reviewed  to  identify  the  potential  causes  of 
environmental risks in each of the activities involved in these options. 
The  potential  “receiving  environment”,  including  natural  and  social  aspects  would  be 
assessed in order to identify and characterize any sensitive elements. 
The  risks  identified  and  the  relevant  environmental  sensitivities  to be  brought  together 
in order to describe and quantify the effects of each decommissioning option.   The risks to 
be  quantified  in  accordance  with  pre‐defined  consequence  and  probability  criteria.      The 
assessment  would  be  based  on  experience  and  the  knowledge  of  outcomes  of  similar 
events, published information or expert judgment.  Any control or mitigation measures that 
may be in effect when the activity is carried out are also taken into account. 
An  overall  risk  rating  to  be  assigned  to  each  aspect  of  the  decommissioning  option 
under  consideration  using  a  two‐dimensional  Risk  Assessment  Matrix  based  on  the 
principle that risk is a product of the two factors: probability and consequence 
 

10.2 Results of the environmental assessment


 
The environmental impact assessment might provide a method of:  
 
Assessing the relative environmental “performance” of each option; 
Determining if any of the options offered a significantly “better” or “worse” 
environmental performance than others, and 
Evaluating if any apparent differences in environmental “performance” were real 
and significant. 
 

10.2.1 Expected results


 
All  of  the  preferred  decommissioning options  have  the  potential  to  cause  environmental  impact, 
both because of planned activities and because of possible emergency or accidental events. 
Page 47 of 56 
 
 

 
None of the options is to have any risks expected in the ‘highly significant’ category, i.e. risks that 
would  be  intolerable  and  would  represent  a  major  constraint  for  the  option.    All  of  the  options 
have a small  number  of  risks  that  could be  rated  as  ‘significant’  (i.e.  the  project  should  seek  to 
incorporate further risk‐reduction measures and/or demonstrate that the risk will be ALARP).  All of 
the options also have a large number of risks that are ‘not significant‘ rated (i.e. indicating that the 
risk is acceptable but should be managed to achieve continuous improvement). 
 
Many  of  the  risks  might  arise  because  of  activities  and  operations  that  are  offshore  commonly 
performed in  the  Danish North Sea.   These activities and  their consequences are well understood, 
and  may  be  subject  to  a  range  of  potential  mitigation  measures  depending  on  regulatory 
requirements  and  project‐  and  site‐specific  circumstances.    Other  risks  arise  from  accidental 
events  and,  again,  there  is  a  range  of  mitigation  measures  that  is  applied  subject  to  regulatory 
requirements and the project‐specific level of risk. 

11 COSTS
 
This section summarizes the process to derive the overall cost estimates of the proposed activities 
for the decommissioning of the old Field facilities. 
 
Each  of  the  short‐listed  decommissioning  options  was  progressed  to  an  initial  conceptual  work 
execution plan and a conceptual cost‐estimate phase.  The platform removals could be executed in 
a number of ways depending on  the  vessels  available  and  the  detailed  programme  offered  by 
the  selected  contractor.    The ultimate  cost  will  be  subject  to  a  number  of  decisions  to  be  made 
during  the  project  development  phases.      Excluding  the  well  decommissioning  costs,  the  initial 
estimate  of  the  total  costs  for  the removal of the Field platforms (topsides and jackets) covering 
the  activities  identified  below  is  approximately  DKK  500  million,  being  split  as  follows                      
Million DKK: 
 
Programme One –      Topside and Jacket removal (B, A, D and C):                        450 
 
Programme Two –      Interfield Pipelines (D‐F 12" + 16" and B‐E 10"):                    50 
 
Future Pipeline Survey costs (cost per field survey)                                                     3 
 
The work scope covered by this overall cost includes: 
 
 Conceptual engineering studies and offshore surveys 
 Engineering design for pipelines and topsides cleaning 
 Procurement  
 Pipelines cleaning 
 Topsides cleaning and equipment isolation 
 Offshore surveys 
 Maintenance activities to ensure safe access 
 Engineering design for removal 
 Preparation for removal and disposal 
 Offshore removal of facilities and hose bundles 
 Remediation of pipeline ends and exposures Seabed debris clearance 
 Transportation to shore 
 Onshore dismantling and disposal 
 Project management 
Page 48 of 56 
 
 

Where  possible,  execution  synergy  opportunities  with  other  on‐going  work  in  the  area  are  being 
pursued to  help  reduce  the  decommissioning  costs.   Cost‐savings  may  be  possible  by  combining 
offshore activities to create a campaign scenario leading to: 
 
 Benefits of scale in contracts for the hire of vessels and the disposal of waste; 
 Efficient use of accommodation vessels and barge time; 
 A reduction in the relative costs for mobilisation and demobilisation; 
 The  greatest possible use  of  any  temporary grillage, temporary steel, slings,  or  lifting  aids 
that would have to be used; 
 A  reduction  in  the  design  and  project  management  cost  for  decommissioning  in  a 
combined campaign 

12 SCHEDULE
 
Well  decommissioning on  the Field is expected to  commence  in  the spring of  2015.   A  schedule 
has been  developed which balances the following drivers: 
 
 Avoid prolonged delay, which would extend safety exposure and incur operational costs; 
 Allow contractors maximum flexibility over timing in order to optimize costs. 

 
Current  expectations  are  that  well  decommissioning  activities  will  continue  through  2015/16 
before removal operations begin in 2017. It is the intent that schedule flexibility will be given to the 
removal contractor to allow operations to be between 2016 and 2020 carried out to assist resource 
availability. 
 
Final  timing  will  depend  on  availability  of  equipment  for  decommissioning  of  the  wells  and 
marine  vessel  spread  for  removal  of  the  platforms.  The  proposed  is  schedule  of  activity  shown 
below. At this stage, these are indicative timings and durations. The indicative programme provides 
relatively  wide  windows for  offshore activities, which are  not  necessarily continuous, but  indicate 
timely removal. 
 
 
 
 
Cessation of Production 2015
Clean & Make-safe
Well Decommissioning
Module Segregation and Pre-Lifting
Pipeline Cleaning
Platform Removal (Window)
Pipeline Decommissioning (Window)
Onshore Disposal (Window)
Debris Clearance & Final Survey
 
2015 2016 2017 2018 2019 2020 2021 2022

Figure  13.1 –Field Decommissioning Overall  Project  Plan

Page 49 of 56 
 
 

13 PERMITS AND CONSENTS


 
The  proposed  programmes for  the  decommissioning of  the  Field  platforms and pipelines will  fully 
comply  with  all  applicable  Danish  and  international  legislations  covering  activities  offshore  and 
onshore.   The  programmes  are  principally  governed by  the  OSPAR 1998.   
 

14 MONITORING AND MAINTENANCE


 
This  section  describes  the  planned  monitoring  and  maintenance  activities  in  the  Field  for  the 
offshore removal operations and after their completion. 
 

14.1 Platforms
 
14.1.1 I n t e r i m safety management
 
It  is  possible  that,  due  to  the  flexible  execution  schedule  that  will  be  offered  to  the 
decommissioning contractors, the offshore removal operations could be over a number of discrete 
operations  undertaken.  The  topsides  of  certain  platforms  may  be  prepared  for  removal  in  one 
offshore campaign but the preparation and removal of other topsides may take place at a separate 
time.   This is similar for the jackets.  Limitations will be placed on the contract schedule to ensure 
that agreed completion dates are within basic safety guidelines achieved. 
 
In  the  event  of  gaps  in  the  decommissioning  operations,  appropriate  interim  measures  as  are 
deemed necessary, such as temporary navigational aids, will be put in place to ensure that there is 
safe access to the facilities, and that the facilities do not present a hazard to other users of the sea. 
A  final  decision  on  what  safety  measures  will  be  used  will  be  taken  in  discussion  with  the 
contractor taking into consideration the decommissioning methods and schedules. 
 

14.1.2 P o s t ‐decommissioning survey and debris removal


 
A  post  decommissioning  side  scan  sonar  survey  of  the  areas  up  to  500m  around  the  platforms 
could be undertaken to identify any debris.  Any unexplained anomalies could be visually surveyed, 
and any man‐made objects which could present a risk to other users of the sea, should be removed 
to  shore  for disposal.   Evidence  that  the  seabed  is  free  of  such  obstructions, detailing  the  survey 
plots  and  recovery  logs  of  items  should  be  provided  to  the  authorities  upon  completion  of  the 
decommissioning work as part of the project close out report. 
 

14.2 Pipelines
 

14.2.1 I n t e r i m safety management


 
As  for  the  platforms,  the  offshore  operations  relating  to  the  pipelines  could  be undertaken over 
a  number of  discrete operations.   Appropriate interim  safety  measures as  are deemed necessary, 
such as  temporary navigational aids, should therefore be put in place to ensure that the  pipelines 
do not  present a hazard to other users of the sea.    A final decision on which safety measures will 
be  used  will  be  taken  in  discussion  with  the  contractor,  taking  into  consideration  the 

 
 

decommissioning methods and schedules. 
 
For decommissioning the pipelines in‐situ, any interim snagging hazards before decommissioning of 
the line is finalised should be buoyed and guarded. 
 
 

14.2.2 P o s t ‐decommissioning survey and debris removal


 
A  post  decommissioning side  scan  sonar  survey  along  a  100m  corridor  each  side  of  the  pipeline 
routes should be undertaken to identify any debris for removal to shore for disposal. Evidence that 
the seabed conditions do not present a hazard to other users of the sea should be provided to the 
authorities upon completion of the decommissioning work as part of the project close out report. 
 
A  longer‐term  monitoring  programme  should  be  carried  out  for  the  pipelines  that  are  to  be 
decommissioned in‐situ  to  ensure  stability  and  safety for  other  users  of  the  sea.    These  pipelines 
should be retained in the Operator’s North Sea pipeline survey programme.   
 

14.3 Post‐decommissioning Environmental Survey


 
Following  platform  removal,  the  area  should  be  subject  to  an  environmental  survey,  including 
representative sediment  sampling  for  chemical and  biological  analysis.  The  post‐decommissioning 
environmental survey  scope  will  be  agreed with  the  Danish authorities,  and  survey  results  will  be 
supplied.  
 

15 PROJECT MANAGEMENT
 
This section provides information on the planned management process for the decommissioning of 
the Dan field platforms and pipelines. 
 

15.1 Project management


 
The  old  Field  decommissioning  project  will  follow  the  internal  project  management  rules  and 
guidelines with special emphasize on the following: 
 
Engineering design 
Preparation for removal and disposal 
Offshore removal 
Offshore remedy operations 
Transportation to shore 
Onshore dismantling and disposal 
 
If appropriate, a company representative will be posted to the contractor’s offices and sites at key 
stages of the work to ensure compliance with procedures and principles. 
   

 
 

16 REFERENCES
 
/1/ Ottersen, G, Postmyr, E and Irgens, M (eds.), 2010. Faglig grunnlag for en forvaltningsplan for 
Nordsjøen og Skagerrak: Arealrapport. KLIF. TA‐nummer 2681/2010. 
/2/ Ministry of Food, Agriculture and Fisheries, The Danish AgriFish Agency, 2012, 
http://www.statistikbanken.dk/statbank5a/SelectVarVal/Define.asp?MainTable=FISK2&PLanguage=0
&PXSId=0 
/3/ ICES, 2008, "ICES‐FishMap", http://www.ices.dk/marineworld/fishmap/ices/. 

 
 

 
 

17 GLOSSARY OF TERMS AND ABBREVIATIONS


 

ALARP   As Low as Reasonably Practical 
Anthropogenic   The term for a substance or impact that arises from human activity. 
Anodes   Blocks of alloy (aluminium & zinc) that protect steel against corrosion. 
 

Benthic communities  The assemblages of plants and animals that live on and in the seabed. 
Benthos  The bed of the sea and the water column immediately above it. 
BPEO   Best Practicable Environmental Option 
Biodiversity   A measure of the variety of living organisms found at a site. 
Biogenic reefs   Reefs comprising the living or dead parts of marine organisms. 
 

Caissons   Caissons are vertical steel pipes attached to the legs of the jacket, 
running from the topsides down into the water column. They are 
used to import seawater and discharge permitted aqueous waste 
to the sea. 
Cetaceans’   Collective name for the group of marine mammals comprising whales, 
dolphins, and porpoises. 
CO2 (te)   Carbon dioxide tonnes equivalent, a measure of total greenhouse gas 
emissions. 
Cold  cutting   A cold method of cutting that does not require hot gas, i.e. hacksaw, 
diamond wire, abrasive water jet etc. 
Conductors   Steel tubes running from the wells on the seabed to the topsides. 
Cuttings  The fragments of rock generated during the process of drilling a well. 
 

Demersal   The term for organisms that live on or close to the seabed 
DSV  Diving Support Vessel 
 

EA   Environmental Act 
EC  European Commission 
EIA   Environmental Impact Assessment. A formal process, which assesses the 
potential environmental impacts from a proposed activity. 
EU  European Union 
 

Fauna   The collective term for all animals. 
FAR   Fatal Accident Rate 
Fish Safe   Fish Safe is a computer‐based early warning system developed by UKOOA 
for the fishing industry to warn of the presence of underwater 
equipment and pipelines. 
Flora   The collective term for all plants. 
 
 

GJ   Gigajoule, a unit of energy equal to 1,000,000,000 joules. 
Grillage   A welded framework of beams and plates several metres high 
built on a vessel or barge to support the weight of a load. 

 
 

 
 

HAZID   Hazard Identification 
HSE  Health and Safety Executive 
HLV   Heavy Lift Vessels, used to install or remove offshore facilities. 
Hook‐up   The process of connecting all the pipework and other 
utilities in the topsides so that offshore production can 
begin. 
Hot Cutting   Method of cutting using hot gas i.e. oxy‐acetylene. 
Hydrocarbons   Any compound containing only hydrogen and carbon. 
 

ICES  International Council for the Exploration of the Sea, an 
organisation that coordinates and promotes marine research in 
the North Atlantic. 
ICP  Independent Competent Party 
IRPA   Individual Risk Per Annum. 
 

Jacket   The steel structure that supports the topsides. The lower section, or 
“legs” of an offshore platform. 
 

Km   Kilometre 
kp   Key Point 
 

LSA scale   Low Specific Activity scale, derived from naturally occurring 
radioactive minerals in the rock strata. 
 

M  Metre (a unit of length). 
m/s   Metre per second. 
Mattresses   Heavy mats used to protect and stabilise facilities on the seabed. 
MARPOL   International Convention regarding pollution from shipping 
Modules   Structural units, which are which are assembled to form the 
platform topsides. 
 
 

NGO  non‐governmental organization. 
 

OSPAR   Oslo and Paris Convention 

 
 
 
 

Pelagic   Organisms living in the water column. 
PEP  Project Execution Plan. 
Phytoplankton   The collective term for the microscopic plants that drift or float in the water 
   column. Phytoplankton consists mainly of microscopic algae. They are the  
  primary producers in the sea and form the basis of food for all other forms of  
  aquatic life. 
Pig   A device with blades or brushes inserted in a pipeline for cleaning purposes. 
  The pressure of the stream of fluid behind the pig pushes the pig along the 
  pipeline to clean out rust, wax, scale and debris. These devices are also called  
  scrapers. An instrumented pig is a device made of rubber or polyurethane  
  that has electronic devices. An instrumented pig is run through a pipeline to 
  record irregularities that could represent corrosion. An instrumented pig is  
  also called a smart pig. 
Pigging   The act of forcing a device called a pig through a pipeline for the 
purposes of displacing or separating fluids and cleaning or inspecting 
pipelines. 
Piles   Heavy beam of concrete or steel driven into the seabed as a foundation 
or support for the jacket structure. 
Pinnipeds   Collective name for the group of marine mammals comprising seals, sea 
lions and walruses. 
Plug   Rubber or cement fitting, filling the well to seal it. 
PLL   Potential for Loss of Life ‐ is one of the prime outputs of a QRA. It 
provides a simple long term total measure of societal risk to all personnel 
from an activity and is expressed as the number of fatalities per specified 
time period. Though not an 
absolute measure, it can however be used to compare societal risk 
between activities. 
Polychaete   The class of annelid worms which possess distinct segments. 
 

QRA   Quantitative Risk Assessment 
 

ROV  Remotely Operated Vehicle 
Riser   A steel conduit connecting a pipeline to the production installation. 
 

SAC   Special Area of Conservation. Areas considered to be important for 
certain habitats and non‐bird species of interest in a European 
context. 
Shear‐leg   Heavy Lift Crane Barge 
Span   A stretch of pipeline, which has become unsupported. 
SSCV  Semi‐Submersible Crane Vessel (also Heavy Crane Vessel) 
 

Te  Tonne, a metric unit of mass equal to 1,000 kilogrammes. 
Topsides   The term used to describe all the decks, accommodation and 
process modules that are located on top of the jacket. 
Trench   A long deep furrow or ditch in the seabed. 
Trenched   Placed in a trench. 
 

Umbilical   Cable and tubing‐like structure that provides utilities and 
communication to sub‐sea equipment to allow it to be operated. 
Units   The units throughout the document are imperial and 
metric, used appropriately as within the oil and gas 
industry. 
 
 
 
 

Vessel  spread   The fleet of vessels used for any particular activity or operation. 

 
 
VOC  Volatile Organic Compound. 
 

Wellhead   The system of spools, valves and assorted adapters that provide pressure 
   control of a production well.    

X‐mas  Tree   Christmas  Tree. The set of valves, spools  and fittings connected to the 
top of a well to direct  and control the  flow of formation  fluids  from the 
well. 
 

Zooplankton   The collective  term  for the animals  that  float/drift  in the  water column. 
 
 
 

 
 

  

Appendix A
A1
  

   

Environmentally sound recycling and scrapping of offshore


platforms
  
  
  
Offshore Deconstruction 
 
 
 
 
 
 
 
 
June 2013  
   

 
 

Table of contents 
1  Introduction..................................................................................................................................................... 3 
1.1  Dan Field Complex ................................................................................................................................... 3 
2  Dan B Platform ................................................................................................................................................ 3 
2.1  Dan B Topside ‐ dimensions and weight ................................................................................................. 4 
3  References ....................................................................................................................................................... 5 
3.  Drawings ...................................................................................................................................................... 5 
3.2  Documents .............................................................................................................................................. 5 
4  Preparatory work for removal of topside ....................................................................................................... 6 
5  Removal ........................................................................................................................................................... 8 
5.1  Offshore Deconstruction in smaller pieces ............................................................................................. 8 
5.2  Lifting ....................................................................................................................................................... 8 
5.3  Removal Schedule ................................................................................................................................... 8 
6  Safety ............................................................................................................................................................... 8 
7  WIV Layout ...................................................................................................................................................... 9 
7.1  Dimensions of WIV .................................................................................................................................. 9 
7.2  Crane Reach at Large Area ...................................................................................................................... 9 
7.3  Crane Reach at Small Area .................................................................................................................... 10 
8  Crane Capacity ............................................................................................................................................... 12 
8.1  Large Area ‐ R = 35 m ............................................................................................................................ 12 
8.2  Small Area ‐ R = 75 m ............................................................................................................................ 13 
9  Geometric constraints ................................................................................................................................... 13 
9.1  Removal directly to WIV ........................................................................................................................ 13 
9.2  Removal to Barge .................................................................................................................................. 14 
10  Sea fastening ............................................................................................................................................. 15 
11  Load‐in/Lift‐in ............................................................................................................................................ 16 
12  Manpower ................................................................................................................................................. 16 
12.1  Hook Down at the site ........................................................................................................................... 16 
12.2  Engineering ............................................................................................................................................ 16 
12.3  Thrid Party approval .............................................................................................................................. 16 
13  Unit Prices ................................................................................................................................................. 16 
14  Risk assessment ......................................................................................................................................... 17 
14.1  Risk Register .......................................................................................................................................... 17 
14.2  Risk Matrix ............................................................................................................................................. 18 
 
   
 
      
  
 

1 Introduction
With reference to the OSPAR (Oslo‐Paris Commission) convention, all topsides and jackets weighing 
less than 10,000 Tonnes, must be dismantled and transported to shore within a year after the 
production ceases.  
  
This document contains the presentation concerning the disposal of a typical Danish North Sea Topside 
by a Wind farm Installation Vessel (WIV).   
  
For the purpose of describing the method, the Field B Topside has been chosen to represent a typical 
topside.  
  

1.1 Dan Field Complex


The production system in the Field Complex was originally to receive high‐pressure crude oil designed 
from the wellhead platforms and to separate gas, oil and water in three stages.  
The separated gas was to the flare system piped, where it was burnt, while the oil was pumped 
through the pipeline to the GC tanker loading buoy's facilities originally via the Field SBM, which was 
later transferred to GC.  
  
After completion of the Field Two Phase Flow Project in 1984, the flow of gas and oil from the first 
stage separator was measured. The two streams were then combined downstream of their respective 
flow metering devices for two‐phase transportation via the subsea pipeline to GC's separation 
facilities.  
  
On completion of the Field Modification Project (1987), the separation facilities on B, with the 
exception of the test separator, were redundant made. The crude/water/gas production was piped to 
F via E and via the existing 10" E ‐ B line and a new 10" pipeline from E to F.  
  
After installation of F, in 1995 Development, the flow in the pipeline from E was reversed. E production 
joined the A production on B. From B, fluid from A, E and the test separator is routed to D for export to 
F via the new 16” pipeline.  
  
     

2 The Field B Platform


The B Platform is the main platform in the Field Complex and is a four legged production platform with 
dimensions at the stabbing point levels of 14.6 m x 14.6 m. The B Platform has three deck levels, Lower 
Deck EL.(+) 21,200 m which supports the three bridges leading to Platform A, Platform C and Platform 
D, Main Deck in EL.(+) 29,200 m containing process equipment, power and accommodation facilities 
and Heli Deck in El.(+) 37,600 m.   
  
  

 
      
  
 

  

The  B 
platform

Figure  1: The Field Complex  
 
2.1 Field B Topside ‐ dimensions and weight
The total expected dry weight of the Field B topside is 1050 Tonnes, with Helideck weighing approx. 150 
Tonnes and Topside Module incl. equipment etc. weighing approx. 900 Tonnes, ref. /doc1/.  
The outline of the platform is approx. 30 x 30m including the Helideck, and approx. 25 x 25m without the 
Helideck ref. /dwg1‐3/.  
  
Ref. the layout depicted in Figure 1, the platform can be approached from north. However, in that area, 
pipelines to other platforms must be into account taken when positioning the WIV.  
  
  

 
      
  
 

Approx  .   150  Tonnes  

Approx. 900 Tonnes 
incl.   Bridge Landings   

 
Figure  2 :  Fiel B  Weights  
 

3 References
3. Drawings
Ref. No.:   No.:   Title:  Date:  Rev.:  
/dwg. 1/   x‐01‐01039‐0000   Elevations of Trusses 1 & 2  05.01.1984  0  
/dwg. 2/   x‐01‐01040‐0000   Elevations of Trusses A & B  05.01.1984  0  
/dwg. 3/   x‐01‐01002‐0001   Helideck Framing Plan  30.04.1992  1  
/dwg. 4/   x‐01‐01041‐0000   Jacket and Deck Elevation  05.01.1984  0  
              

Table 1: Reference drawings 

3.2 Documents
Ref. No.:   No.:   Title:  Date:  Rev.:  
Dan Field Platform  14.11.2003 
/doc. 1/   02489‐R‐001   B  
Weight Report  
              

Table 2: Reference documents 
  
       

 
      
  
 

4 Preparatory work for removal of topside


Before any dismantling or removal option operations begin, it will be necessary to prepare the topside 
to ensure that all safety and environmental risks are minimized.   
  
This process involves topside cleaning and engineering.   
The cleaning programme is to remove chemicals designed and hydrocarbons, and major steps involved 
in the cleaning operation would be:   
  
1. Removing all hydrocarbons, chemicals and residues from the production systems by purging 
and flushing.  
2. Isolating equipment from all power and production inputs and outputs.   
3. Opening systems and removing any remaining production residues, chemicals and other 
materials using specialised cleaning equipment and personnel, where required. Ensuring that 
all materials/residues are stored correctly and disposed of via the appropriate and approved 
disposal route  
4. On completion of the cleaning operation, tagging all systems and clearly identifying the plant 
condition. Third party to confirm systems are cleaned and where identified as non‐hazardous 
possible.   

5. Engineering of all plant equipment and systems, including positive isolation of electrical, 
instrumentation and process systems to prevent possible injury to personnel during 
dismantling.  

6. Assessment of the structural integrity of the topside. This will among other things include: 3D 
scans, UT of primary joints and thickness testing of primary structural elements  

7. Structural engineering of existing structures including re‐calculation of existing pad eyes for 
lifting, design of new pad eyes for lifting if none exists, design of reinforcements and re‐
analysis of structures for sea‐transportation.  

8. Procedures for the cut off phase must be established  
9. Procedures for the lifting phase must be established  
10. Once cleaning and engineering is complete, the topside module is prepared for removal. 
Depending on the type of removal is method that adopted, this scope of work could include 
some, or all of the following steps: disconnecting piping, electrical wiring and other services, 
removing or cutting the pipeline risers and caissons.  
11. Separating the structural connections, walkways and stairs between the module and the 
jacket.   

12. Adding additional strengthening or temporary reinforcement to modules, as required.   

13. Removing or securing any loose equipment.   
 
      
  
 

14. Installing or reinstating lifting points on modules, as required.  
       

 
      
  
 

5 Removal
5.1 Offshore Deconstruction in smaller pieces
Offshore Deconstruction of topside modules is a proven method of dismantling topside structures. The 
module and its components can be into smaller manageable pieces cut, using hydraulic shears and 
other cutting techniques. These pieces can be using the WIV “Pacific Orca” removed and transported 
to shore on its deck.  
Overall, topside structural integrity is on the integrity dependant of individual module, so a progressive 
dismantling programme would require careful planning to ensure the overall structural integrity and 
safety of personnel since progressive deconstruction could render large portions of the remnant 
structure unstable  
5.2 Lifting
The removal of a number of ancillary items such as the crane, boom, adjoining bridges, heli deck etc. 
should be before removal of the topside undertaken.  
It is considered possible to remove the topside as a single lift, but it will also be possible to remove the 
helideck before lifting of the topside.  
  
Lifting can be using the WIV “Pacific Orca” undertaken and the topside sections can be to shore 
transported either on cargo barges or on the deck of the WIV barge itself.   
5.3 Removal Schedule
The removal schedule is in principle shown in Figure 3 below:  
  

Activities           

Stop for            
Production          
Well     
     
Abandonment     
   
Cleaning     
Phase     
      
Concept 
Selection        
Engineering  
Hook Down  
 
Removal of 
Topside  
Figure 3: Removal Schedule  

6 Safety
Safety plans must be established, but since the wells are shut down and all equipment is 
decommissioned and emptied, the platform will be “cold” and hazardous events are not very likely to 
occur, thereby minimizing the need for precautionary measures.   
      

 
      
  
 

7 WIV Layout
The capacity of the WIV deck is to 15T/m2 given, which is well above the demands.  

7.1 Dimensions of WIV

Capacity of 
WIV Deck: 
15T/m2 

Approx. area 
for storage ~ 
45 x 24 m    
  

Approx. area 
for storage ~   
45 x 34 m 
  

  

     
7.2 Crane Reach at Large Area
 
 
 
      
  

 
Figure  5: Crane capacity at large loading area  
 
  

 
 
 
 
 
 
 
 
 
 
 
 
R = 35 m Crane Capacity = 
1050 T  
  
At R = 35  
Crane is able to reach the 
centre of the large loading 
area 

  

  
 

7.3 Crane Reach at Small Area

       
 

  

At R = 75  
Crane is able to reach the 
centre of the large loading 
  
area 
R = 75 m 
     
     
Crane capacity = 200 T       

Figure   6 :  Crane capacity   at small loading   area  


 

    

 
      
  
 
  

8 Crane Capacity
8.1 Large Area ‐ R = 35 m
  

1050  T  

 
Figure  7:   Crane Capacity at Large Area    
  
  
     

       
 

8.2 Small Area ‐ R = 75 m


  

200 T   

 
Figure   8: Crane Capacity at Small Area    
     

9 Geometric constraints
The crane must be able to reach the platform while keeping a safe distance. The necessary 
minimum distance between WIV and platform is set to 20 m.  
 

  

9.1 Removal directly to WIV


  

 
      
  
 
  

20 m  

R = 35 m    

Outline of 
platform    

 
Figure 9:   Removal directly to WIV  
    
  

9.2 Removal to Barge


Removal directly to barge will impose another restriction, since the barge has to be located at the 
end of the WIV. The safe distance from WIV to Barge is set at approx.  
10m which gives a distance to the centre of the barge of 55 m.   

       
 

Crane Capacity at 55 m is 500 Tonnes, i.e. the Field B Topside Module will have to be offshore in 
smaller pieces deconstructed in order for the WIV crane to be able to place.  

10 Sea fastening
Sea fastening at the deck will have to be to allow for easy stabbing/fastening designed to minimize 
the risk and later easy removal once the WIV is at shore with the structures.  
  
The sea fastening must be by a Marine Warranty Surveyor certified.  
  

The parts on the barge.    

R = 55m    
Crane    Capacity    =  500 T   

Outline of 
platform  

 
R = 55 m   

  
Figure 10 : Removal to  Barge  
  

  
Barge   

 
      
  
 
  

11 Load‐in/Lift‐in
When arriving to shore, the topside module must be lifted either onto the quay or loaded in with the 
use of multi‐wheel trailers.  
  

  
  
    

     

12 Manpower
12.1 Hook Down at the site
Resources needed for the hook down phase of the Field B Topside is estimated to be:  
  
• 120 pers. (60 pers in day/night shift) in 4 months   ~172,800 hours  
  

12.2 Engineering
Resources needed for the engineering phase of the Field B Topside is estimated to be:  
  
• ~10 pers in 360 days          ~ 20,000 hours  
  

12.3 Third Party approval


 
• ~1 pers in 360 days         ~   1,500 hours  
  
  
  
  
   
  
     

13 Unit Prices
This section contains unit prices for central parts of the hook down job:  
  
  
• Cleaning of piping          900 DKK/m  
• Pad eyes : 10‐50 mm thickness       50 DKK/kg  
• Pad eyes : 50‐100 mm thickness       70 DKK/kg  
• Scaffolding          130 DKK/Ton  
• Generator 150 kVA ( 15 – 20 pers )      35,000 DKK/month  
• Sea fastening          40 DKK/kg  

       
 

14 Risk assessment
14.1 Risk Register

 
 

 
      
  
 
  

14.2 Risk Matrix



  

  

  

       
  
  

Appendix A
A2
  
  
  
Environmentally sound recycling and scrapping of offshore
platforms
  
  

Removal of platforms
 
 
 
 
 
 
 
 
 
 
June 2013  

 
Table of contents
1  Introduction ................................................................................................................................................ 2 

2  Planned decommissioning vessels. ............................................................................................................ 2 

2.1  Summary of planned lifting vessels. ........................................................................................................... 2 
3  Decommissioning alternatives valid for the harbour of Esbjerg ................................................................ 2 

3.1  Dismantling of topsides using. Jack‐up. ..................................................................................................... 2 
3.1.1  Alternative 1 ........................................................................................................................................... 3 
3.1.2  Alternative 2 ........................................................................................................................................... 3 
3.1.3  Summary of possible modifications ....................................................................................................... 4 
3.2  Disassembly of jacket's ............................................................................................................................... 4 
3.2.1  Alternative 1 ........................................................................................................................................... 4 
3.2.2  Alternative 2 ........................................................................................................................................... 5 
3.2.3  Alternative 3 ........................................................................................................................................... 5 
Annex 1 Drawings to illustrate the lifting procedures ............................................................................................ i 

Annex 2 Description of the selected alternative planned decommissioning projects ........................................... ix 

 
 
 
 
  
 
 
 
 
 
 

 
 
1    
 
1 Introduction
  
The present document contains a brief description of existing or planned decommissioning vessels as 
well as a review of alternatives drawn up in connection with the current project.  
  
2 Planned decommissioning vessels.
As described elsewhere, dismantling of platforms is a budding market, which is to experience a 
tremendous growth expected in the coming years, where many of the existing offshore platforms, also 
in the North Sea area, will be decommissioned.  In relation to the OSPAR (Oslo‐Paris Commission) 
convention, all topsides and jackets, that weighs less than 10,000 Tonnes, be dismantled and 
transported to shore within a year after the production ceases. It is thus not currently for North Sea 
area allowed to dump platforms for the creation of fishing reefs, a procedure which has been used 
extensively in the Gulf of Mexico.  
  
An immediate obvious possibility of dismantling would be a reversible use of the very same crane 
vessels, which have been in connection with the initial installation used. These have, however, 
because of the large demand and a high degree of monopoly, for a number of years been very 
expensive. Consequently, a part of the larger consortiums has developed new ideas of vessels 
designed for disassembly of large platforms. Annex 4 provides a very brief description of some of the 
methods/vessels, which seems most advanced/most serious. This is included to give an idea of the 
market and must therefore not be as a complete review of possible disassembly principles regarded.  
  
2.1 Summary of planned lifting vessels.
  
It  appears  to  all  listed  projects  in  annex  4  that  the  focus  is  primarily  on  dismantling  of  the  major 
platforms. Also that they all require access to a dry dock to deliver the jacket whereas a topside will be 
able  to  be  transported  on  a  standard  barge  and  then  delivered  on  the  quay  via  traditionally  used 
methods.  
  
The mentioned alternatives would probably be too costly to use in dismantling of smaller platforms. 
However, the "Versa truss" system seems so flexible that it should be into consideration taken. 
Likewise, the traditional lifting vessels should be, already on the market, considered.  
  
3 Decommissioning alternatives valid for the harbour of Esbjerg
It is elsewhere in the project concluded that the establishment of a dry dock in Esbjerg would be too 
expensive. This means that for jacket disassembly it is necessary to establish alternatives to the 
methods listed in annex 4. For topsides the listed alternative might be possible solutions, but probably 
too expensive, as they are designed for larger modules. Hence, alternatives are also here required.  
  
3.1 Dismantling of topsides using. Jack‐up.
  
On the topsides, the project focused on the use of jack‐ups, which most likely is available on the site 
for the decommissioning of wells. By the use of an existing jack‐up, there might be restrictions on both 
the lifting capacity and working radius.  
Based on the above the following describes the subsequent possible jack‐up modifications to increase 
lifting capacity, working radius and flexibility in the dismantling process.  
  
Jack‐ups have been successfully on numerous occasions used for the installation of small topsides and 
jacket's and therefore it is of course possible to reverse this process. The limitations lie mainly in the 

2    
 
lifting capacity and reach. For a typical jack‐up the lifting capacity (draw works) will be in the order of 
680 mT (rotary load + setback load), while the skidding capacity typically will be significantly less. The 
target weight of this project is to 1000 mT defined. Typical sizes for the working area (the distance a 
cantilever can be skidded) is approximately 14 m along the cantilever and 3.5 m to 4.0 m laterally.  
  
3.1.1 Alternative 1  
  
Modification 1  
  
The limited working radius restricts the number of platforms which could be directly lifted by the jack‐
up,  skidded  and  lowered  it  onto  a  barge.  For  disassembly  of  the  topsides,  it  would  therefore  be 
tempting to mount a for example a 300 mT revolving crane near a jack‐up leg. It will thus be possible 
to  move  topsides  in  smaller  parts  (piece  small)  for  temporary  storage  on  the  jack‐up  deck.  The 
installation  of  the  aforementioned  crane  will  be  required  as  a  minimum  to  utilize  the  jack‐up  for 
disassembly.  In  this  connection,  there  should  be  a  focus  on  the  safety  of  the  individual  "un‐handy" 
lifts.  In  addition,  the  cost  of  the  extensive  offshore  work  for  shielding  of  welding  and  cutting 
operations, from possible gas leaks and establishment of various scaffolding, should be assessed. The 
key,  however,  will  be  to  establish  environmentally  sound  measures  to  ensure  against  oil,  chemicals 
and paint scrap to the sea.   
  
  
Modification 2  
  
With the limitations on the working area of the cantilever with the current project, it will not be 
possible to skid modules or parts thereof free of jacket for subsequent lowering onto a barge. If the 
draw works of jack‐up should be in connection with the disassembly used, the cantilever arm needs to 
be to approximately 14 m extended.  
  
The lifting capacity is on the assumption based that the moment of the cantilever beam and the 
reaction on the edge of the hull must not exceed the similar sizes from the drilling operation. The 
derrick weight is set at 420 mT. This gives a capacity of 282 mT (if the moment in the cantilever is 
critical size) and 428 mT (if the reaction to hull edge is critical). Both values are significantly below the 
target value of 1000 mT.  
  
Modification 3  
  
It is estimated that an increase of cantilever capacity (same moment capacity + ca. 5000 tm) is 
achieved by a moderate intervention. For example, cantilever beams are with 2 x 2 plates 40x5100 
mm2 reinforced.     
  
3.1.2 Alternative 2  
  
Modification 1  
  
300 mT rotating crane installed near a jack‐up leg.  
  
Modification 2  
  
Cantilever beams extended with 14.0.  
  
Modification 3  
  

3    
 
The supports for the  drilling  Tower to  be in order for the Tower modified  to  be skidded toward the 
centre of the jack‐up during a lift. This increases the moment capacity to approximately 6000 tm.  
  
Based on the above the lift capacity is to 457 mT (if the cantilever moment is critical size) calculated 
and 692 mT (if the reaction to hull is the critical size). Hence the same capacity are achieved as for the 
modification 2 (alt 1) without the cantilever being reinforced.  
  
However, this requires a relatively large interference, because all the electricity cables, tubes and mud 
hoses, etc. must be disengaged during each operation.  
Modification 4  
  
If chosen to perform the modification it is natural to reinforce the cantilever beams at the same time 
so that the reaction by hull edge is the critical size and lifting capacities can thus be 692 mT. The 
bending moment in the cantilever is by approximately 7500 tm increased. The gain can be performed 
with the equivalent of 2 x 2  40x5100 mm2 plates as by modification 2 (alt 1). In a detailed design, it 
should be documented that the increased torque of after approx. 7500 tm can be absorbed by the 
jack‐up ´ in a global context.  
  
Modification 5  
  
A lifting capacity of 1000 mT will require a more comprehensive reinforcement of the cantilever and 
supports.  On the other hand, a requirement for a lifting weight of 1000 mT gives rise to a moment 
increase  of  120%  equivalent  to  18000  tm.  Such  an  increase  could  only  be  through  a  detailed  study 
documented.  
  
  
3.1.3 Summary of possible modifications  
  
It is concluded that as a minimum the installation of a revolving crane with a lifting capacity of about 
300 mT is required. By using this crane, appropriate sizes of the modules can be stored on jacket‐up 
until the parts can be onto a barge lifted.  
  
The cantilevers current capacity of approximately 680 mT cannot immediately be used as the range is 
not sufficient to modules to be lifted free of the jacket and subsequently lowered onto the barge.  
  
An extension in the order of 14 m is required.  The capacity is in relation to the starting point reduced. 
With a moderate modification, which involves the cantilever beams to be strengthened, lifting 
capacity can be documented to approximately 428 mT, which is below 50% of target value of 1000 mT.  
  
A further increase in capacity for the target value of 1000 mT will only be through detailed studies 
documented.  
  
The selected solution must be on an assessment based of the costs of increased offshore work and risk 
of environmental impact by using existing jack‐up versus the cost of the proposed jack‐up conversions.  
  
3.2 Disassembly of jacket's
  
3.2.1 Alternative 1  
  
Disassembly of jacket is using a jack‐up rig  
  
Disassembly of the jacket by the use of a jack‐up rig is simple by lifting smaller parts weighing less than 
jack‐up's lifting capacity, where the jacket is parted by using, for example, "abrasive water‐cutting". 
4    
 
The current part is lifted a couple of metres above the water surface, then a barge can be placed 
below the lifting point, and thus either sailing directly to port or mounted temporarily until the barge 
is full.  
  
3.2.2 Alternative 2  
  
Disassembly of jacket is using a converted barge  
  
This method can be a reversible launching considered, as the jacket is at the end of a converted barge 
pulled up. Principles of the method shown in the drawings 1600‐01‐01 to 1600‐01‐03 attached in 
annex 1, and the following description should be together with the drawings read.  
  
Indicative calculations show that a large barge without problems will be able to ballast to withstand 
the current load at the end. Calculations indicates further that there will be wire forces in the order of 
a few thousand tonnes, which through use of blocks will have reasonable dimensions.   
  
The  dominating  uncertainty  in  the  preliminary  calculations  is  in  the  dynamic  amplification  factors 
used,  and  thus  it  is  important  through  model  experiments  or  detailed  calculations  of  the  dynamic 
behaviour of the system clarified hence to assess whether the limitations in the weather window are 
acceptable.  In  this  context,  it  is  important  to  assess  the  safety  against  that  platform  because  of,  for 
example,  slamming  forces  on  jacket  bottom  combined  with  accelerations  from  movements  of  the 
barge. Theoretically a quiet immersion by constantly keeping the platform's gravity enough behind the 
turning point. By the use of "hold back" wires, connected to the top of the MSF, it is ensured that, the 
wire pulling down on the barge is not also dragging the jacket too far forward. Statically, it is possible 
via measurements of the wires to determine the forces of gravity location continuously, but dynamics 
and wave/slamming forces will cause an uncertainty in the estimate.  
  
  
3.2.3 Alternative 3  
  
Disassembly of the jackets using buoyancy elements  
  
The  use  of  buoyancy  elements  have  considered  been.  The  method,  however,  is  not  appropriate 
considered  and  sufficiently  attractive  in  the  current  situation.  The  method  is  considered  to  be 
primarily associated with too much uncertainty regarding the stability of the jacket construction. From 
the moment the jacket is from the piles released, there is no counter force from i.e. a crane and hence 
the whole operation is entirely dependent on the interaction between the individual buoyancy centres 
functioning satisfactorily.  
Thus, detailed analyses of the system are required before the method's applicability can be confirmed.  
  
Although no further reflections on this method presently are made, the method represents a potential 
opportunity, which might be included in the considerations for a specific project.  
  
  
  
  
    

5    
 
Annex 1 Drawings to illustrate the lifting procedures
  
  
  
Disassembly of topsides using a jack‐up rig.  
  
1600‐02‐01    Rev. A    Demontering af topside, – Fase 1  
1600‐02‐02    Rev. A    Demontering af topside, – Fase 2  
  
Disassembly of jacket's using. converted barge:  
  
1600‐01‐01    Rev. A    Jacket demontering vha. ombygget pram, fase 1‐2.  
1600‐01‐02    Rev. A    Jacket demontering vha. ombygget pram, fase 3‐4.  
1600‐01‐03    Rev. A    Jacket demontering vha. ombygget pram, fase 5‐6.  


 
  
 

ii  
 
  

 
 

iii  
 
  

 
 

iv  
 
  


 
  
 

 
 

vi  
 
  

vii  
 
  

 
 

viii  
 
  
Annex 2 Description of the selected alternative planned
decommissioning projects
  
 Versa truss  
 MPU Heavy Lifter  
 Pieter Shelte Catamaran  
 Offshore Shuttle  
  
 

ix  
 
  
 

”Versa truss”  
  

  
  


 
  
”MPU Heavy Lifter”  
  

  

xi  
 
  
  
”Pieter Schelte Catamaran”  
  

  

xii  
 
  
  

  
  
  
”Offshore Shuttle”  
  

xiii  
 
  

xiv  
 
Appendix A
A3
  

  

Environmentally sound recycling and scrapping of


offshore platforms
  
  
  
  
Transportation
  
  
  
  
  
June 2013 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
   

 
Table of Contents
1  Introduction ............................................................................................................................................... 2 
2  Conclusion ................................................................................................................................................. 3 
3  Transportation ........................................................................................................................................... 3 
3.1  Installation vessel .............................................................................................................................. 3 
3.2  Selection of barge .............................................................................................................................. 5 
4  Fastening of Structures ............................................................................................................................. 7 
4.1  Topsides ............................................................................................................................................. 7 
4.1.1  Method 1‐Chain hoists .................................................................................................................. 7 
4.1.2  Method 2‐Tension stays ................................................................................................................ 8 
4.2  Jacket ................................................................................................................................................. 8 
4.3 Method 1‐Chain hoist .............................................................................................................................. 9 
4.4 Metode 2‐Tension rods ........................................................................................................................... 9 
4.5 Annex 1   Transport arrangement drawings ................................................................................................ x 
4.6 BILAG 2      Accelerations of barge and topside .......................................................................................... xi 
4.7 Annex 3 Accelerations of barge and jacket ................................................................................................xii 
4.8 Annex 4 the calculation of the anchoring forces ....................................................................................... xiv 
4.8.1 Topsides .......................................................................................................................................... xiv 
4.8.2 Jacket ............................................................................................................................................... xv 
 
 
 

   1  
 
1 Introduction
In connection with the project "environmentally sound recycling and decommissioning of 
offshore  platforms",  it  became  at  an  early  stage  clear,  the  choice  of  methods  for 
dismantling  of  platforms  will  be  a  strong  competition  parameter,  in  which  the 
transportation method must be in alignment with the disassembly method.  
  
This document describes the conditions related to the choice of an appropriate transport 
barge, as well as the design of a sea fastening principle, which aims to minimize offshore 
work as much as possible. The latter should be seen in the light of the facilities being at the 
open sea, when attachment to the barge is being performed.  
The  present  document  takes  as  its  starting  point  a  1000  tonnes  topsides  and  an  1800 
tonnes jacket.  
    

   2  
 
2 Conclusion
By using, a large and strong barge flexibility with, regard to transportation sea fastening, is 
achieved. By choosing a large barge, reduced the transportation loads significantly, as the 
barge will be calmer in the sea compared to smaller barges.  
  
”Giant 2 – Ocean‐Going Deck barge” is an example of a barge, which comply with the requirements 
with regard to the carrying capacity and size.  
  
However, the enclosed calculations are on the Noble Denton’s load criteria based, which 
normally provide conservative loading. A detailed analysis should be of the transportation 
carried out.  
  
The  structures  are  directly  on  mattresses  of  wood  placed,  which  in  stiffness  and  area  is 
sufficient to distribute the loads to the strong points of the barge. Two types of fastening 
devices – 1) air chain pulleys, 2) drag bars are highlighted, both possible solutions either 
separately or in combination.  
  
The topsides module will need only mattresses of wood and the devices mentioned, whereas 
the supports of jacket design must be by load distributing beams supplemented.  
 
3 Transportation
The  transport  is  analysed  according  to  the  Noble  Denton  ´  s  criterion  "General  guidelines  for 
Marine Transportations".  

However, in connection with a detailed project, it should be assessed whether the Noble Denton ´ s 
requirements can be reduced:  

1. As the structures are without any significant value damage due to poor fastening is in principle 
negligible. However, the safety should be at the highest level and no damage to the barge, 
should be seen.  

2. Normally a construction is transported in not quite tranquil weather conditions in order to 
frame a favourable weather window for installation a day or two later. Missing this weather 
window, you have the choice between staying on site, or to return to the safe haven until the 
next favourable weather window appears. The structures, during tranquil weather are lifted 
onto the barge, fastened and barged to port. This means a transportation time approximately 
11/2 day.  

3.1 Installation vessel


The  last  years  have  several  installation  vessels  been  built  with  focus  on  the  increasing  offshore 
wind  activities  mainly  in  Northern  European  waters.  Crane  lifting  capacity  up  to  1200  tons, 
Dynamic Positioning System 2,  cargo area of 4,300m2 with a deck loading of 15 ton/m2. Attached 
is the vessel’s technical specifications as well as the crane diagram. The vessel has recently proved 
its  ability  lifting  and  transporting  a  no  longer  useable  gas  platform  in  German  waters  to  a  shore 
facility.   

Advantages:  

   3  
 
The vessel can be close to the construction positioned. With the six sets of 3‐Chord truss type legs 
and the DP2 system as well as various thrusters ‐ a very steady operation is possible. The large and 
strong  cargo  area  mean  that  quite  some  heavy  volumes  of  cargo  can  be  loaded  and  transported 
with a strong and safe sea fastening equipment.  

MOB:  
PoE ‐ Remember that we MUST be able to pre‐load and jack up to the operating air gap in PoE, as it 
will ensure faster and safe operation when to be unloaded. PoE has procedure for permission to 
jack up ‐ but who probably know this can be a challenge. 
 
There must be some flexibility in sea fastening as it can be a challenge to cut e.g. jacket underwater 
accurately and therefore it must be possible to adjust slightly on site. All other equipment will be 
mobilised to have fixed space, remember to fill empty baskets and backloads on site so requires a 
good management and deck plane. There must bunkers Fuel so hot work shall be planned in the 
project.  
 
All ROV equipment must be "wet" tested in port. 
 
Transit:  
DEP. PoE to Site. 
Transit Plan for the site, weather criteria (Hs) compared to sailing, jacking, and sea fastening 
(especially back to PoE). 
 
 
SITE:  
The position should be calculated carefully compared lifting tasks and loading on deck, walkway 
with water flow from VIW must be installed. 
 
Location assessment must always be with penetration study, risks, etc. 
 
VIW arrive and set up DP approx. 500 meters from the location. Once permission from the owner is 
given, manoeuvred VIW in on location. The ship lowers the legs when it is close to the final position 
for approx. 1‐2 meters above the sea floor, according to the cables and pipelines. 
 
When the position is reached, within the tolerances (the smaller the tolerance the longer it takes), 
final position approved by the responsible. 
 
VIW preloaded and jacks‐up for surgery air gap. 
 
From here, it is many crane lifts in small and large pieces, small in baskets and backloads 
continuously, the large pieces loaded on deck and taken back to the PoE. 
The ship's deck is made clear to large lift either leg or between the legs, the easiest but not too 
time possible. Between the legs used bumpers, all lift out fed with tag lines and lifting supervisor. 
On deck are there painted safety routes (emergency), making a promise corridor where no work 
should be done on deck. Remember marine fouling on the jacket and hand ring / approvals shells 
mm. 
 
Demob:  
All components are unloaded in PoE, cooked‐level on the quay facility for which the large modules 
to be landed. 
 
General:  
Remember to handled environmental considerations on site and PoE, e.g. oil in pipes, asbestos. 
 
   4  
 
3.2 Selection of barge
A large barge to transport the different modules is for the following reasons selected:  

1. A large barge provides small movements and thus smaller forces from the structure.  

2. A strong barge (deck capacity 15 tons/m2) enables a fastening system, which the barge or the 
construction not be should tailored.  

The selected barge is the Giant 2. See barge information on the following two pages.  

   5  
 
  

   6  
 
  

   7  
 
4 Fastening of Structures
As the construction is situated in the open sea, it is important that the fastening system is designed 
to minimize offshore work (annex 1).  
  
In order to achieve a system that is independent of the choice of barge, the barge deck is 
with  a  100‐200  mm  thick  "mattresses  of  wood"  covered.  This  compensates  for 
unevenness in the deck and ensures a sufficient load distribution on the barge.  
  
For securing the jacket design, it will be necessary, however, to supplement with load distributing 
beams.  
  
The structure placed directly on mattresses of wood and attached by means of straps. There are 
two types of straps:  
  
1. Chain  hoists,  which  snaps  to  the  strong  points  of  the  barge  and  structure.  Chain 
hoists are tensioned one after another to all chain hoists are tense.  
  
2. HEB‐profiles  or  tubular  with  gusset  plates  or  equivalent  is  butt  welded  to  the 
structure and to the strong points of the barge.  Tension stays are fabricated with an 
over‐length  and  shortened  to  the  right  length  when  the  module  is  placed.  Welding 
inspection prior to transportation is carried out.  
 
4.1 Topsides
  
The modules shall be from all equipment released situated under the deck such that the main‐deck 
bars forming a frame on which the module can rest.  
  
4.1.1  Method 1‐Chain hoists  
  
When the module is set down on mattresses of wood, it is important that the loads are sufficiently 
distributed in order not to damage the barge.   
  
The following table specifies the required number of air chain hoists based on a topside weight 
of 1,000 tonnes and a total "mattresses of wood" ‐area equivalent to 210 m2. Accelerations are 
in annex 2 shown 
  
   Acceleration   Factual   Fcapacity   Chain     
        
hoists  
        
  
2
   m/s  x g   tons   ton/m tons   ton/m Number1)  
2  2 
  
                       
Heave   1,796      8,55      15,0        
Roll   0,592   600      640      12   (3+3)x2, top + bottom 
either side  
Pitch   0,375   380      426      8   (2+2)x2, top + bottom 
either side  
Total                  20     
1)
”75” t SWL Chain hoist with reduced safety, i.e. SWL 5/3x75=125 t.  
  
The above results have been analysed in annex 4.   

   8  
 
  
4.1.2  Method 2‐Tension stays   
  
The tension bars are with 4 rods in top and bottom arranged respectively under an angle of 
45o relative to the length direction of the barge. Top rods arranged further with a slope of 
45o in relation to the vertical.  
  
The horizontal force from the topside is 600 tonnes (roll), as described in method 1.  
  
   Factual    Tension bars  
  
  
   tons   Number   Dimension  
Bottom   212   4   HEB300/Ø508x9.5  
Top   300   4   HEB400/Ø508x12.7  
  
  
Forces from the pitch accelerations will also be taken by the same bars as above. The 
above results have been analysed in annex 4.  
  
  
4.2 Jacket
  
Its  construction  shall  be  released  from  all  obstacles,  so  that  the  legs  are  forming  2  runners,  on 
which the construction can rest.  
  
The jacket has a weight of approximately 1500 tons exclusive of fouling, piles bits, grout and the 
like. It is that the total weight of the jacket is 1800 tonnes assumed.  
  
Heave‐accelerations in ANNEX 3, is analysed to be 1,887. The load of the barge is consequently:   
 1800*1.9 tons = 3420 tons  
  
With a deck capacity of 15 t/m2 the following last distribution area is required:  
UAREA = 3420 / 15 M2 = 228 M2  
  
It means the load‐width under each leg should be:  
Uwidth = 228 / 2 * 51 m = 2.24 m  
  
However,  this  is  unrealistic,  as  the  mattresses  of  wood,  where  appropriate,  should  be  very 
thick.  
The  mattresses  of  wood  should  be  with  steel  beams  over  the  strong  points  of  the  barge 
supplemented.  
  
 
 
   

   9  
 
4.3 Method 1‐Chain hoist
  
   Acceleration   Factual    Fcapacity   Chain hoist    
     
  
  
   m/s2 x g   tons   tons   number1)  
  
              
  
Roll   0,735   1323   1493   28  
(7+7)x2, 
top+bottom in 
either side  
Pitch   0,465   837   854   16   (4+4)x2, 
top+bottom in 
either side  
Total            44     
1)
”75” t SWL chain hoist with reduced safety, ie. SWL 5/3x75=125 t.  
  
  
4.4 Metode 2‐Tension rods
  
The tension rods are arranged with an even number of rods in top and bottom respectively. Top 
rods are arranged with a slope of 45o in relation to the vertical.  
  
   Factual    Tension rods  
  
  
   tons   Number   Dimension  
Roll   1323   16   HEB300/Ø508x9.5  
Pitch   837   8   HEB300/Ø508x9.5  
Total      24   HEB300/Ø508x9.5  
  
  
  
  
   
  
  
  
  
  
  
  
  
  
    

   10  
 
4.5 Annex 1 Transport arrangement drawings
1700‐01‐01   Jacket hoist fixation  
1700‐01‐02   Topside hoist fixation 
1700‐01‐03   Jacket drawbar hoist fixation 
1700‐01‐04   Topside drawbar hoist fixation 
   

  xi  
 
4.6 BILAG 2 Accelerations of barge and topside

SEATRANSPORT ACCELERATIONS  
  It is assumed that the Roll and Pitch axes passes through the centre of floatation (C.O.F.)  
  Roll  cyclical angular motion of barge/ship about a longitudinal axis  
  Pitch:  Cyclical angular motion of barge/ship about a transverse axis  
  Heave:  Cyclical vertical motion of barge/ship  
  DESCRIPTION:     
    Topside Transportation  
  POINT:    (C.O.F. BARGE (0,0,0))    
  X_0      50.00  [m] Distance to C.O.F. (longitudinal) 
  Y_0      1.00  [m] Distance to C.O.F. (transverse) 
  Z_0      9.00  [m] Height above C.O.F. (vertical) 
  ROLL:     
  THETA_R      20.00  [deg] Roll angle (+/‐)
  T_R      10.00  [sec] Roll period (full cycle)
  PITCH:     
  THETA_P      12.50  [deg] Pitch angle (+/‐)
  T_P      10.00  [sec] Pitch period (full cycle)
  HEAVE:            
  X_G      0.20  [g] Heave acceleration (+/‐)   
  PARTIAL COEFFICIENT:      
  Wave load         1.30 
 
 
Help formulas:              

  G   9.81  GRAVITY    [m/sec^2]  


RR   9.055    ARM‐ROLL  [m]  
RP   50.804    ARM‐PITCH  [m]  
AR   3.097    AMPLITUDE‐ROLL  [m]  
AP   10.996    AMPLITUDE‐PITCH  [m]  
ATR   1.223    ACC‐TOTAL‐ROLL  [m/sec^2]  
ATP   4.341    ACC‐TOTAL‐PITCH  [m/sec^2]  
ALPHA‐R   1.460    ALPHA‐ROLL  [RAD]  
ALPHA‐P   0.178    ALPHA‐PITCH  [RAD]  
AVR   0.135    ACC‐VER‐ROLL  [m/sec^2]  
AVP   4.272    ACC‐VER‐PITCH  [m/sec^2]  
  AHR   1.215    ACC‐HOR‐ROLL  [m/sec^2]  
AHP   0.769    ACC‐HOR‐PITCH  [m/sec^2]  
AVR / G   0.014   ACC‐VER‐ROLL / G  [g]  
AVP / G   0.436   ACC‐VER‐PITCH / G  [g]  
AHR / G   0.124   ACC‐HOR‐ROLL / G  [g]  
AHP / G   0.078   ACC‐HOR‐PITCH / G  [g]  
HEAVE   AVH _R/ G   0.188   ACC‐VER‐HEAVE_ROLL/ G  [g]  
AVH _P/ G   0.195   ACC‐VER‐HEAVE_PITCH/ G  [g]  
AHH _R/ G   0.068   ACC‐HOR‐HEAVE_ROLL/ G  [g]  
AHH _P/ G   0.043   ACC‐HOR‐HEAVE_PITCH/ G  [g]  
GRAVITY   AVH _R/ G   0.940   ACC‐VER‐GRAVITY_ROLL/ G  [g]  
AVH _P/ G   0.976   ACC‐VER‐GRAVITY_PITCH/ G  [g]  
AHH _R/ G   0.342   ACC‐HOR‐GRAVITY_ROLL/ G  [g]  
AHH _P/ G   0.216   ACC‐HOR‐GRAVITY_PITCH/ G  [g]  
 
 
 
 
 
  xii  
 
 
 
 
 
TOTAL ACCELERATIONS WITHOUT AND WITH PARTIAL COEFFICIENTS:  
ACTION COMBINATION  
1.0 x DEAD + 1.0 x WAVE 1.0 x DEAD + 1.3 x WAVE
HORIZONTAL VERTICAL HORIZONTAL   VERTICAL

[g] [g] [g]   [g]


+ ROLL + HEAVE + GRAVITY   0.534 1.141 0.592   1.202
+ ROLL - HEAVE + GRAVITY   0.397 0.766 0.414   0.713
- ROLL + HEAVE + GRAVITY   0.287 1.114 0.270   1.166
- ROLL - HEAVE + GRAVITY   0.150 0.738 0.092   0.677
       
+ PITCH + HEAVE + GRAVITY 0.338   1.607   0.375   1.796  
+ PITCH - HEAVE + GRAVITY   0.252 1.217 0.262   1.289
- PITCH + HEAVE + GRAVITY   0.181 0.736 0.171   0.664
- PITCH - HEAVE + GRAVITY   0.095 0.346 0.058   0.156
  
 
4.7 Annex 3 Accelerations of barge and jacket

SEATRANSPORT ACCELERATIONS  
  It is assumed that the Roll and Pitch axes passes through the centre of floatation (C.O.F.)  
  Roll  cyclical angular motion of barge/ship about a longitudinal axis  
  Pitch:  Cyclical angular motion of barge/ship about a transverse axis  
  Heave:  Cyclical vertical motion of barge/ship  
  DESCRIPTION:     
    Topside Transportation  
  POINT:    (C.O.F. BARGE (0,0,0))    
  X_0      58.00  [m] Distance to C.O.F. (longitudinal) 
  Y_0      1.00  [m] Distance to C.O.F. (transverse) 
  Z_0      17.00  [m] Height above C.O.F. (vertical) 
  ROLL:     
  THETA_R      20.00  [deg] Roll angle (+/‐)
  T_R      10.00  [sec] Roll period (full cycle)
  PITCH:     
  THETA_P      12.50  [deg] Pitch angle (+/‐)
  T_P      10.00  [sec] Pitch period (full cycle)
  HEAVE:            
  X_G      0.20  [g] Heave acceleration (+/‐)   
  PARTIAL COEFFICIENT:      
  Wave load         1.30 
   

  xiii  
 
 Help formulas:              
   G   9.81   GRAVITY      [m/sec^2]  
RR RP   17.029    ARM‐ROLL    ARM‐PITCH  [m]  
60.440         [m]  

AR AP   5.824    AMPLITUDE‐ROLL AMPLITUDE‐ [m]  


13.082    PITCH   [m]  
ATR ATP   2.299    ACC‐TOTAL‐ROLL ACC‐TOTAL‐ [m/sec^2]  
5.164    PITCH   [m/sec^2]  

ALPHA‐R  1.512    ALPHA‐ROLL ALPHA‐PITCH   [RAD]  


ALPHA‐P   0.285    [RAD]  

AVR AVP   0.135    ACC‐VER‐ROLL ACC‐VER‐PITCH   [m/sec^2]  


4.956    [m/sec^2]  

  AHR   2.295    ACC‐HOR‐ROLL   [m/sec^2]  


  AHP   1.453    ACC‐HOR‐PITCH   [m/sec^2]  
AVR / G   0.014   ACC‐VER‐ROLL / G   [g]  
  AVP / G   0.505   ACC‐VER‐PITCH / G   [g]  

AHR / G   0.234   ACC‐HOR‐ROLL / G   [g]  


  AHP / G   0.148   ACC‐HOR‐PITCH / G   [g]  
HEAVE   AVH _R/ G   0.188   ACC‐VER‐HEAVE_ROLL/ G   [g]  
  AVH _P/ G   0.195   ACC‐VER‐HEAVE_PITCH/ G   [g]  

AHH _R/ G   0.068   ACC‐HOR‐HEAVE_ROLL/ G   [g]  


  AHH _P/ G   0.043   ACC‐HOR‐HEAVE_PITCH/ G   [g]  
GRAVITY   AVH _R/ G   0.940   ACC‐VER‐GRAVITY_ROLL/ G   [g]  
  AVH _P/ G   0.976   ACC‐VER‐GRAVITY_PITCH/ G   [g]  

AHH _R/ G   0.342   ACC‐HOR‐GRAVITY_ROLL/ G   [g]  


  AHH _P/ G   0.216   ACC‐HOR‐GRAVITY_PITCH/ G   [g]  
 
 
TOTAL ACCELERATIONS WITHOUT AND WITH PARTIAL COEFFICIENTS:  
  ACTION COMBINATION  
1.0 x DEAD + 1.0 x WAVE 1.0 x DEAD + 1.3 x WAVE
  HORIZONTAL VERTICAL HORIZONTAL   VERTICAL
 
  [g] [g] [g]   [g]
+ ROLL + HEAVE + GRAVITY   0.644 1.141 0.735  1.202
+ ROLL - HEAVE + GRAVITY   0.508 0.766 0.557   0.713
- ROLL + HEAVE + GRAVITY   0.176 1.114 0.127   1.166
- ROLL - HEAVE + GRAVITY   0.040 0.738 -0.051   0.677
           
+ PITCH + HEAVE + GRAVITY   0.408   1.677   0.465   1.887  
+ PITCH - HEAVE + GRAVITY   0.321 1.286 0.353   1.379
- PITCH + HEAVE + GRAVITY   0.112 0.666 0.080   0.573
- PITCH - HEAVE + GRAVITY   0.025 0.276 -0.032   0.066

  xiv  
 
 
4.8 Annex 4 the calculation of the anchoring forces
4.8.1 Topsides  
  
When the module is set down on the barge, it should be fastened:  
  
Method 1‐Chain hoists  
  
The module is approximately 10 high, assuming that C.O.G. is approximately 5 meters above the barge deck. 
Also assuming that both the crane and the de‐aerator have been from the module removed.  
  
The accelerations of the barge, along with the topsides are over estimated in annex 2, and the horizontal roll‐
acceleration for the topsides is calculated to 0.6 * g.  
  
The horizontal force from the topsides is 600 tonnes.  
  
The 6 x 75 tonnes SWL chain hoists with three chain hoists connected to at the top of the topsides and three 
chain hoists connected to the bottom of the topsides, are the following:  
  
The  Chain  hoists  have  a  safety  factor  of  five,  used  during  the  lift,  whereas  a  safety  factor  of  three  is 
acceptable  in  the  current  situation.  This  means  a  75  tonnes  hoist  can  be  to  maintain  used  a  force  of  125 
tonnes. It is assumed that the three chain hoists connected to the top of the topsides, have an inclination of 
45 degrees, the following capacity is calculated:  
  
         PMAX = 3*125 + 3*125*COS.(45) TONS = 640 Tons > 600 Tons  
  
This indicates that the roll‐movement requires 12 sets of 75 tonnes SWL chain hoists.  
  
The horizontal pitch‐acceleration for the topsides is calculated to 0.31 * g.  
  
The horizontal force from the topsides is thus 380 tonnes.  
  
If 4 x 75 tonnes SWL chain hoists are with two chain hoists used connected to at the top of the topsides and 
two chain hoists connected to the bottom of the topsides, we have the following:  
  
It is assumed that the two chain hoists connected to the top of the top side have an inclination of 45 degrees, 
the following capacity is calculated:  
  
         PMAX = 2*125 + 2*125*COS.(45) TONS = 426 Tons > 380 Tons  
  
That is to say, that the pitch movement requires 8 x 75 tonnes SWL chain hoists.  
  
A total of 20 required 75 tonnes SWL air chain hoists.  
  
Method 2‐Tension rods  
   
The horizontal force from the topsides is 600 tonnes as above.  
  
Used four tension rods with 2 rods linked to at the top of the topsides and 2 rods connected to the bottom of 
the topsides.  

  xv  
 
It is assumed that the 2 rods connected to the top of the topside have an inclination of 45 degrees with the 
horizontal,  and  that  all  4  bars  have  an  inclination  of  45  degrees  in  the  barge  longitudinal  direction,    the 
following capacity can be calculated:  
  
Lower rod:  
         300 Tons = 2 * cos. (45) * x => x = 212 Tons or 2120 kN  
  
Upper rod  
         300 Tons = 2 * cos2 (45) * y => y = 300 Tons or 3000 kN  
  
  
For  the  roll‐movement  the  lower  supports  a  drawbar  corresponding  to  a  HEB300  or  a  tube  Ø508  x  9.5  is 
required, in which the shear force connection is a 2.9 m long 5 mm fillet weld on both ends of the drag bar.  
  
For the upper supports a drawbar corresponding to a HEB400 or a tube Ø508 x 12.7 is required, in which the 
shear force connection is a 4 m long 5 mm fillet weld on both ends of the drag bar.  
  
Forces from the pitch accelerations will also be taken by the same bars as above.  
  
4.8.2 Jacket  
  
Check of barge deck  
  
When  the  jacket  is  resting  in  a  horizontal  position  on  the  mattresses  of  wood,  it  is  important  that  the 
load on the barge is evenly distributed in order not to damage the barge.   
  
The jacket weighs approximately 1500 tons of exclusive of marine fouling, pile pieces, grout and similar. 
We assume a total weight of 1800 tonnes. Due to the movements of the barge, the jacket will cause a 
loading  on  the  barge  with  substantial  horizontal  and  vertical  forces.  According  to  Noble  Denton,  the 
loads will be as shown in the table in annex 3. The vertical load from jacket will increase according to the 
table by a factor of 1.9. Therefore the load on the barge is:  
                    
1800*1.9 Tons = 3420 Tons  
  
The total support area of the barge must be:  
  
            UAREA = 3420 / 15 M2 = 228 M2  
  
It means the effective load width under each leg must be:  
  
            Uwidth = 228 / 2 * 51 m = 2.24 m  
  
, which is unrealistic, since the mattresses of wood, where appropriate, should be very thick.  
  
It may be necessary to combine the mattresses of wood with steel beams over the strong points of the 
barge, in order to get a combination of evenly distributed loads and point loads.  
  
Method 1‐Chain hoists  
  
Roll‐accelerations are 0,735 g according to Annex 3. Thus the current force is 1800x0.735=1323 tons.  
  
  xvi  
 
PMAX = 7*125 + 7*125*COS. (45) TONS = 1493 tons > 1323 tons  
  
Pitch‐accelerations are 0,465 g. Thus, the current force is 1800 x 0,465=837 tons.  
  
PMAX = 4*125 + 4*125*COS. (45) TONS = 854 tons > 837 tons  
  
Method 2‐Tension rods  
  
Roll‐accelerations are 0,735 g  
  
PMAX= 1493 tons  
  
Selected a total of 8 bars with 4 rods in top and bottom respectively.  
  
1493 = 4*x +4* cos. (45) * x => x = 219 tons  
  
Selected HEB300 or tubular Ø508x 9.5.  
  
Pitch‐accelerations are 0,465  
  
PMAX= 837 tons   
  
Selected a total of 4 rods with 2 rods in top and bottom respectively.  
  
837 = 2*x +2* cos. (45) * x => x = 245 tons  
  
Selected HEB300 or tubular Ø508x 9.5.  

  xvii  
 
Appendix A
A4

 
Environmentally sound recycling and scrapping of offshore
platforms

 
 
 

Onshore decommissioning of installations


 
 
 
 
 
 
 
 
 
June 2013 
Table of contents 
1   Introduction ‐ onshore recycling in Denmark ....................................................................... 3 
1.2  Introduction – purpose ......................................................................................................... 3 
1.3  Harbour facilities for decommissioning of offshore installations in Denmark ........................ 3 

2  Environment and safety onshore in Denmark ................................................................... 4 
2.1  General regulations pertaining to waste in Denmark ............................................................ 4 
2.1.1  Challenges when handling  decommissioning waste ............................................................................... 4 
2.1.2  Hazardous materials on offshore installations ........................................................................................ 5 
2.1.3  Handling of hazardous materials onshore ............................................................................................... 6 


1 Introduction ‐ onshore recycling in Denmark
1.2 Introduction – purpose

The purpose of this description is to determine if final processing of decommissioned parts of 
offshore installations from the Danish sector could take place in Denmark. 

There is no legislative requirement that a country must decommission materials that stem from 
that country’s own sector. Denmark is subject to EU regulations and a range of international 
agreements that regulate trade and entrepreneurial assignments. 

1.3 Harbour facilities for decommissioning of offshore installations in


Denmark
Decommissioning  will involve legislative authorities and it will attract special attention from 
public authorities, not least in terms of environmental requirements when installations are 
handled. 

Entrepreneurs in the field of waste will be responsible for the onshore treatment, and they 
might perform tasks through the establishment of consortiums, if necessary.  

So far, the Danish harbor in Esbjerg has been mentioned in connection with decommissioning 
assignments.  Furthermore, Frederikshavn, Grenaa and Odense/the Lindø terminal in 
combination with Lindø dock 3 have expressed interest.  These 5 harbours already function as 
ship scrapping locations.  

Historically, the renovation of rigs has been performed in Esbjerg. 

 
2 Environment and safety onshore in Denmark
2.1 General regulations pertaining to waste in Denmark
Decommissioning of offshore structures on site must be performed in a safe and responsible 
manner and under circumstances that are fully satisfactory in terms of protecting the 
environment.  

Especially chemical waste materials that may be contained in individual, dismantled parts should 
be handled very carefully. This should only be handled by companies that possess the required 
resources and knowhow. An example of such a company in Denmark is Nordgroup in Nyborg. 

The most significant piece of legislation in Denmark in this field is the most recent executive 
order on waste from 2012, no. 1309. This executive order is exhaustive in that it applies to all 
areas that are not regulated by other legislation. Definitions and classifications of waste are 
described in the executive order. 

One of the most important elements is the fact that the Danish municipalities are responsible 
for waste treatment. The responsibility includes determining if a substance or an object is to be 
regarded as waste and ensuring that all waste handling takes place in accordance with the legal 
requirements of the executive order. The Danish municipalities must also respect the intentions 
to minimize the amount of waste. The waste hierarchy is the fundamental idea behind and a 
prerequisite of this minimization. 

The executive order contains the ‘List of Waste’ ‐ the so‐called EAK codes that are based on the 
European Council’s directives. In English, the list is called ‘The European Waste Catalogue’ (EAK). 

The section that classifies and regulates the treatment of substances from the oil and gas sector 
plus all classifications of environmentally hazardous waste is particularly interesting. In section 
2.2, it is described how this is handled in practice through quality control systems that identify 
and determine how all types of environmentally hazardous waste should be treated. 

2.1.1 Challenges when handling decommissioning waste


It should be stressed that there are no types of waste resulting from decommissioning of 
offshore constructions which are not already being handled in Denmark. Section 2.2 contains an 
example of how the classification may be built up and how it may be controlled by a quality 
control system that identifies all types of environmentally hazardous waste and determine how 
they should be treated.  

In the Danish sector, most of the waste from the North Sea sector is handled via the harbour in 
Esbjerg. The individual types of waste are therefore already known, including environmentally 
hazardous waste. However, we are talking about small amounts of manageable sizes, which can 
usually be collected in special, closed containers and transported from a rig to the end receiver.  
The challenge lies in the amount of waste and the conditions under which it exists. From a HSE 
perspective, it is essential that the risk is transferred from offshore locations to onshore 
locations as quickly as possible. 

This is described in section on dismantling and transport in the main report. Apart from the 
engineering interest in handling as large units as possible, these activities also involve a 
significant element of risk: it is necessary to make sure that environmentally hazardous 
substances do not end in the sea or are released at the onshore location. 

2.1.2 Hazardous materials on offshore installations


The following hazardous materials are either present or potentially present on the platform 
topside and require appropriate handling. 

Table 5.2.1/hazardous materials in the Dan Field (ref. the “old” Dan Field Platforms and Pipelines 
Decommissioning Programs, p. 26) 

Currently, it is not possible to estimate the total cost of the above as the amount is not known. 
This should not be seen as a problem because specific tender documents and surveys prior to 
bidding will answer this question. 

 
2.1.3 Handling of hazardous materials onshore
In connection with handling and transportation of hazardous materials onshore, the onshore 
scrapping company will ensure that all parties, both the environment as well as personnel, will 
not be contaminated. The scrapping company will also ensure that hazardous material is 
handled in accordance with local regulations, thus to ensure safe and proper handling. The 
above mentioned materials are, and expected quantified as: 
Table 4.3 Selected group of organic compounds in produced water per year (ref. Environmental 
Challenges – Decommissioning B0‐01ER0, p. 25) 
 

Organic  Norwegian shelf (kg)/10/ The Danish field (kg)


Compounds  2003 2011 2003 2011
BTEX  861,160 1,675,059 45.9  144
Alkyl phenols C1‐C3  281,116 289,324 15.0  24.9
Alkyl phenols C4‐C5  10,104 14,360 0.54  1.24
Alkyl phenols C6‐C9  401 219 0.02  0.02
Phenols  184,168 179,546 9.82  15.4
Oil in water  1,698,382 1,23,608 90.5  106
Organic acids  33,576,880 22,251,835 1,790  1.914
APA‐PAH  45,176 1,863 2.41  0.16
Sum PAH  99,456 155,915 5.30  13.4
 
Table 4.4 Amount (kg) heavy metals within produced water per year (ref. Environmental 
Challenges – Decommissioning B0‐01ER0, p. 26

 
 
 

 
 
ENVIRONMENTAL 
CHALLENGES ASSOCIATED 
WITH DECOMMISSIONING 

September 2012 
  

 
  
  
  

  

  

  

  

 
 

   
 
     

 
 
 

Table of contents 
1  INTRODUCTION ............................................................................................................................... 3 
1.1  Abbreviations ....................................................................................................................................... 3 
2  REGULATIONS ................................................................................................................................. 4 
3  ENVIRONMENTAL CONCERNS ......................................................................................................... 7 
3.1  Major decommissioning activities ....................................................................................................... 7 
3.1.1  Working steps .................................................................................................................................. 8 
3.1.2  Activities offshore ............................................................................................................................ 9 
3.1.3  Waste handling .............................................................................................................................. 10 
3.2  Typical waste residues ....................................................................................................................... 11 
3.2.1  Production chemicals ..................................................................................................................... 13 
3.2.2  Residual oil materials ..................................................................................................................... 14 
3.2.3  Heavy metals .................................................................................................................................. 16 
3.2.4  NORM ............................................................................................................................................. 18 
3.2.5  Asbestos ......................................................................................................................................... 20 
3.2.6  Paints and other coatings .............................................................................................................. 21 
3.3  Other considerations ......................................................................................................................... 21 
3.3.1  Hydrogen sulphide (H2S) ................................................................................................................ 21 
4  DANISH SECTOR TEST CASE ............................................................................................................ 23 
4.1  Chemicals ........................................................................................................................................... 24 
4.2  Organic compounds ........................................................................................................................... 25 
4.3  Heavy metals ...................................................................................................................................... 26 
4.4  NORM ................................................................................................................................................. 27 
5  SUMMARY AND CONLUSIONS ........................................................................................................ 29 
6  REFERENCE .................................................................................................................................... 32 
 
  
  
  
 

  
  
  
  
  
  
  
  

 
 
1 INTRODUCTION
Offshore oil and gas installations that have reached end of production (EoP) have to be 
decommissioned. Disused installations must normally be removed and disposed on land according 
to the OSPAR Decision 98/3. The OSPAR Decision requires, with few exceptions, completely 
removal of any offshore oil and gas installation, when they are no longer in use.   
  
The focus of this report is to establish an overview of typical environmental concerns in relation to 
decommissioning projects. Focus will be on decommissioning of production facilities, and in 
particular the typical waste of concern generated during these operations. Conditions concerning 
well plugging and abandonment as well as energy consumption and emissions to air during 
decommissioning operations are not part of the scope for the report and will not be included. 
However, since well plugging and abandonment is considered a relative large issue with respect to 
decommissioning, the topic will briefly be described.  
  
The environmental challenges may vary markedly between different installations as offshore oil 
and gas production units are varying. Therefore, the validity of generalising environmental 
concerns connected to decommissioning is questionable. However, some similarities are found 
between decommissioning projects and the purpose of this report is to give a general overview of 
typical environmental challenges.   
  
Public available information from completed decommissioning projects is relatively limited. Some 
general descriptions of topics of environmental concerns are however; in the UK, 
decommissioning programmes described /33/. In addition, some Norwegian decommissioning 
programmes are available, e.g. Huldra from April 2012 /27/ and the Norwegian OLF 
environmental reports /10/, /11/, /12/.   
  
No relevant information has been from the Danish oil and gas sector found. Nevertheless, the 
Field at the Danish continental shelf is as a test case used in this report. The environmental 
concerns in relation to the decommissioning of the Field are thus described based on available 
information (primarily from the Norwegian sector) correlated to the sizes of production at the 
Field. It is important to stress that the actual environmental concerns related to the Field 
cessation is not known.   
  
     
1.1 Abbreviations
  
ALARP   As Low As Reasonably Practicable  
CoP   Cease of production  
DEPA   Danish Environmental Protection Agency   
HOCNF   Harmonised Offshore Chemical Notification Format   
IMO   International maritime organization  
Kd   Distribution coefficient  
Klif   Norwegian Climate and Pollution Agency  
LSA   Low specific activity  
MEG    Monoethylene glycol  
NPD   Norwegian Petroleum Directorate   

3   
 
 
  
NPD   Naphthalene, phenatrene, antracene and benzothiophene and their 
C1‐, C2‐ and C3 alkyl substituted derivates  
OLF   Oil Industry Association  
OSPAR   Oslo and Paris commission for the protection of the marine environment of the 
north East Atlantic  
P&A   Plug and abandonment  
PAHs    polycyclic aromatic hydrocarbons  
PCB   Polychlorinated biphenyl  
PPE   Personal protective equipment   
PFOS    Perfluorooctyl sulphonate  
PVC    Polyvinyl chloride  
SIS   National Institute of Radiation Protection  
SRB   Sulphate reducing bacteria   
TBT   Tributyltin   
WEEE   Waste electrical and electronic equipment  
     
2 REGULATIONS
There are international, regional and national legislation intended to conserve the marine 
environment and safeguard human health with respect to the process of decommissioning. Both 
the removal process of installation (primarily concerned with safety of navigation and other users 
of the sea) and the disposal process (primarily aimed at pollution prevention) are by these 
legislations regulated.       
  
The requirements of disposal of disused offshore installation are regulated by the Offshore Safety  
Act /1/ in the Danish sector. The central international framework is by the OSPAR Convention 
covered /7/. The international treaty Guidelines of 1989 are by the International Maritime 
Organization (IMO) established /6/. All briefly described in the following.  
  
The OSPAR Decision 98/3, which came into force in February 1999, gives the criteria for 
acceptable disposal alternatives with respect to various kinds of installations /7/. The decision 
combines and updates the 1972 Oslo Convention on dumping waste at sea, and the 1974 Paris 
Convention on land‐based sources of marine pollution. The provisions of disposal of disused 
offshore installation given in the OSPAR conversion require description of the installation, the 
proposed disposal site and the proposed disposal method /8/. The OSPAR Decision 98/3 includes 
the following key requirements:    
  
• The topside off all installations, irrespective of size, should be removed to shore  
  
• All sub‐structures or jackets weighing less than 10,000 tonnes should be to shore removed 
for reuse, recycle or disposal on land.   
  
If removal of structures involves high safety risks or is technically not feasible, it is possible to seek 
exemption to the OSPAR Decision 98/3 requirement. Based on a case‐by‐case basis, exemption is 
by the national government given if an international consultation process has assessed that 
leaving the structures in place is justifiable. The decision for granting derogation of leaving 
offshore structures wholly or partly in place in the marine sea ultimately lies with the Danish 
4   
 
 
 
 

 
 

Government, following justification and consultation with other OSPAR Contracting Parties. The 
exceptions can be for the whole or part given of the installation and according to OSPAR includes 
the following:  
  
• The footings of large steel platforms weighing over 10,000 tonnes put in place before 
February 1999  
  
• The concrete gravity‐based platform sub‐structures  
  
• Floating concrete installations  
  
• Concrete anchor bases  
  
• Structures with significant damage or deterioration where there may be practical 
difficulties in removing installations  
  
The derogations do however only apply to installations installed prior to nine of February 1999, 
meaning that all installations put in place must be after this date removed completely.   
  
The OSPAR Decision includes complete removal of any redundant offshore installation and state 
that "no disused offshore installation or disused offshore pipeline shall be dumped and no 
disused offshore installation shall be left wholly or partly in place in the marine sea". However, 
the decision does not comprise the following:  
  
• Facilities placed under the seabed   
• Concrete anchor bases  
• Drill cuttings  
• Pipelines  
  
As OSPAR Decision 98/3 does not address the above categories of installations these are currently 
by national requirements controlled. This, together with a generally low level of experience to 
date causes the standards required difficult to predict. In Denmark specific requirements for 
pipeline decommissioning are not formulated. However, decommissioning of pipelines typically 
involves pigging, flushing, filling and plugging of lines, followed by removal or in‐situ 
abandonment. In UK the pipeline decommissioning is relatively well described in their guidance 
note from 2009 /3/. According to the UK Guideline, pipeline decommissioning will have to 
consider:  
  
• Decisions will be considering the individual circumstances taken. All feasible 
decommissioning options should be considered and compared. Pipelines can be placed on 
top of the seabed, trenched or buried and this may also influence the required 
decommissioning programme. In general, if the pipeline is of a small diameter (less than 
12”) it is likely that it will have to be removed or fully buried. This applies to all in‐field 
flow‐lines and control bundles.   
  

5   
 
 
  
Other framework worth mentioned with respect to decommissioning is The Petroleum Act in 
Norway, /4/ The Petroleum Act 1998 (UK) /5/ and the international treaty Guidelines of 1989 
established by IMO /6/. The IMO international standards and guidelines are not formally binding, 
but used as advisory for removal of offshore installations. Some of the ones not superseded by the 
OSPAR 98/3 are the following:  
  
• All abandoned or disused installations or structures standing in less than 75 m of water 
and weighing less than 4,000 tonnes in air, excluding the deck and superstructure, should 
be entirely removed.  
  
• In cases of partial removal referred an unobstructed water column sufficient to ensure 
safety of navigation, but not less than 55 m, should be provided above any partially 
removed installation or structure which does not project above the surface of the sea.  
  
• The position, surveyed depth and dimensions of any installation not entirely removed 
should be indicated on nautical charts and any remains, where necessary, properly 
marked with aids to navigation.  
  
• The person responsible for maintaining the aids to navigation and for monitoring the 
condition of any remaining material should be identified.  
  

Internationally Denmark has signed the "IMO convention on the Prevention of Marine Pollution by  
Dumping of Wastes and Other Matter 1972" the "London Convention" and 1996 Protocol Thereto 
"London Protocol". Nationally, the most important legislative act in Denmark with respect to 
decommissioning is currently the Offshore Safety Act which requires the following /1/:  
  
• § 56 Abandonment of a fixed offshore installation shall be planned and executed in a way 
that the health and safety risks at work are identified, assessed and reduced as much as is 
reasonably practicable.  

• § 57 The Minister of Transport and Energy may lay down rules on decommissioning of 
fixed offshore installations.  
  
Finally, the Marine Environmental Law (Havmiljøloven /2/) which regulates the general waste 
handling in the Danish sector is mentioned. The Marine Environmental Law has the purpose of 
preventing marine pollution from dumping of wastes and other matter. The main wording of the 
law in respect to the subject of this report is the following:     
  
• Dumping § 25: "Discharges of substances or materials shall not take place, apart from the 
dumping of seabed material included".  
 
In summary, the principal terms for the decommissioning and disposal of disused offshore 
installations follows international agreements and conventions. Nevertheless, the regional 
authority is in many cases in a better position than a national one to make overall, crosssectional 
assessments. Regulating decommissioning projects requires special expertise and close 
coordination between international, national and regional legislation.   
       
6  
 
 
 
 

 
 

3 ENVIRONMENTAL CONCERNS
The focus in this chapter is to establish an overview of typical environmental concerns within 
decommissioning projects no matter the type of installation and decommissioning solution 
selected.   
  
A major challenge of decommissioning is the limited information available. In general, the oil and 
gas companies prefer to keep detailed data regarding the specific decommissioning project on a 
certain level of confidentiality. In the public available decommissioning programmes and in the 
few available cessation closeout reports information of major waste issues are described in a very 
general level.   
  
The environmental concerns of decommissioning of a specific installation are largely by the design 
affected of the installation, the production history and operation. Therefore, planning, 
engineering and method selection require case‐by‐case studies where chemicals and waste must 
be identified, documented and mapped. Furthermore, the specific decommissioning project needs 
to assess design and production history for the specific installation.   
  
Identifying environmental and safety risks is vital for selecting the decommissioning solution.  
During cessation of an installation the focus should be on minimising environmental impacts.   
  
An overview of the environmental challenges in general is given, with the following descriptions:  
  
 Major decommissioning activities:  
o the working steps, section 3.1.1 
o activities offshore, section 3.1.2  
o  waste handling, section 3.1.3  
 The typical waste residues:  
o Production chemicals, section 3.2.1 
o Residual oil materials, section 3.2.2  
o Heavy metals, section 3.2.3 
o NORM, section 3.2.4 
o Asbestos, section 3.2.5 
o Paint and other coatings, section 3.2.6  
 Other considerations:  
o Hydrogen sulphide, section 3.3.1    
  
  
 
3.1 Major decommissioning activities
  
The issues of relevance vary between the different offshore fields and the environmental concerns 
have to be assessed as an individual matter. However, the major principle of preparations and 

 

 
 
  
working flow involve the same key areas. In the two following sections, these elements 
considered of utmost importance within the scope of this report are briefly descried.     
  
  
3.1.1 Working steps
  
Decommissioning of an installation is a complex process that involve environmental and safety 
challenges. Identification of possible environmental and safety risks involve inspection, sampling 
programmes, laboratory testing and even in some cases pilot scale testing. Expertise guidance is 
needed to be able to deal with and assess associated environmental and safety risks, which will 
constitute the basis for the decision making process. Furthermore, the complex process of 
decommissioning should be assessed thoroughly to ensure that the large number of uncertainties 
is addressed. The phases of decommissioning can roughly be described by the steps in Figure 3.1.  
 
Inspection

Decommissioning  programme and studies

Authority Management

Survey/safety inspection

Environmental and Risk Assessment

Engineering Design

Securing module

Offshore work before removal:
‐  Cleaning topside and flushing of process units
‐  Making the facilities hydrocarbon ‐ free
‐  Removal of residual hydrocarbons
‐  Prepare installation for removal/lift operation 

Plugging and abandoment of wells

Documentation

Dismantling and disposal

 
Figure 3.1 Work steps in a decommissioning project /25/ 
  
A solid multidisciplinary planning of the working steps illustrated in Figure 3.1 is necessary to 
address the safety and environmental challenges. Furthermore, thorough and detailed 
operational planning based on in‐depth knowledge and understanding of all technical and 

 

 
 
 
 

 
 

operational aspects of the structure and its history is a key success factor for safe and controlled 
decommissioning.   
  
  
3.1.2 Activities offshore
  
The major activities offshore besides the preparation activities are the following:  
  
• P&A  
• Removal  
  
After CoP a water injection well and water producer can beneficial be kept operational. The water 
injector may be needed during P&A work for the injection of flushing water. Water will be used 
for  the  internal  flushing  operations  of  topside  equipment  after  oil  production  has  ended.  The 
water injector may in some occasions also be used as waste well.  
  
After  CoP  internal  flushing  of  flow  lines,  process  module  equipment  and  export  risers  will  be 
executed as well as vessel entries for manual cleaning and inspections. All separators, coalescers 
etc. will typically be cleaned manually after flushing to remove residual fractions of bottom sludge 
and potential scale residues. Waste from the cleaning can be collected in slop tanks and brought 
to shore for disposal.   
  
Minor waste masses generated by the activities performed offshore during decommissioning 
activities may be discharged offshore, as long it is within the levels specified in the discharge 
permit. Minimising the emissions in general should be of high priority for protecting the 
environment and human health with respect to the process of decommissioning. Emissions to sea 
could be minimised by the following means:   
  
o All water used for deck and wellhead cleaning should be collected via drains.  

o All water used for flushing of topside should be exported to neighbouring active 
installation, in vessels or slop tanks. The water should be cleaned according to the 
required legislative regulated levels.   o Sludge and P&A related waste should be 
collected in slop tanks or similar and transported to shore for required treatment.  

o Chemical usage:  

• For topside cessation the focus should be on only using environmental friendly 
degreasing agents and soap. All wash water should be collected via drains.  

• In some cases biocides or MEG (Monoethylene glycol) may be added to the oil and 
gas riser/pipelines. Environmental impact should in such cases be assessed.  

  
Decommissioning involve permanent abandonment of the platform wells, isolation and limiting 
the possible release of pollution. The cessation activities at the specific installation may often be 
controlled by the plans and procedures for P&A execution, as the P&A activity is a very costly and 

 

 
 
  
time consuming element of decommissioning oil and gas installations. The P&A activities generally 
include plugging and securing of wells and subsequent preparation for abandonment of the wells.  
  
The offshore installations must be dismantled and removed to shore, if they are not abandoned 
and left in place. The offshore dismantling is normally performed by cutting the platform into 
small sections or by removing whole modules in the reverse of the installation. Another option is 
to remove the topsides and/or jacket in one piece, but this is rarely performed. Many factors can 
influence the removal of offshore installations, e.g. availability of heavy lift vessels, development 
and use of new technology for removing installations, capacity of decommissioning yards, and 
weather conditions. The complexity of the removing process could cause the facilities to be left in 
place to long after cease of production. Over time the installation will deteriorate and the 
cessation project will become more costly as unmaintained installations require substantial 
modifications to fulfil safety requirements /15/.  
  
The removal method chosen can influence the types of waste transported to land. Offshore 
installations removed to shore are typically delivered to approved demolition and waste 
treatment plant or reused directly (e.g. signal buoys, wind turbines). Although reuse of 
installations and equipment is desirable, experiences have shown that the reuse of offshore 
installations or part of equipment is difficult, primarily due to strict requirements in this business 
sector. The reuse is in general environmental friendly, but it is more economic to purchase new 
rather than repair old equipment. There are however some examples of successful reuse of 
installations e.g. the steel column from the Frigg platform re‐used as a breakwater at Tau, the 
topside has been used as a training centre for offshore personnel and the Brent Spar concrete 
substructure that is used as material for building a pier in Stavanger /15/, /34/.  
  
  
  
3.1.3 Waste handling
  
Waste  generated  during  decommissioning  has  to  be  identified  and  handled  in  accordance  with 
international and national legislation, in addition to following company requirements and criteria. 
Precautions concerning oil residues, heavy metals, NORM etc. have to be taken into consideration. 
Furthermore, decommissioning facilities need to be designed to allow safe handling of identified 
waste,  including  hazardous  substances,  e.g.  have  an  effective  collection  system  and  an  on‐site 
treatment plant. The waste handling involves a large number of steps and a simplified illustration 
of the recommended waste handling in general is given in Figure 3.2.   
  
  
Hazardous 
Safety   Securing   Material 
waste  Saleable  Metal reuse
Inspection  module  inspection
removal  
  
Figure 3.2 Principles of work flow  
  
Each step in Figure 3.2 is briefly described in the following:  
  
• Safety Inspection: The installation is inspected by expert teams that secure the 
module for later work.  

10   
 
 
 
 

 
 

  
• Securing: Based on safety inspection observations, all acute issues, in relation to 
contamination and general risk of personnel, are taken care in this phase.   
  
• Material inspection: Establish overview of hazardous waste.   
  
• Hazardous waste removal: Removal of hazardous waste including further handling 
of waste.   
  
• Saleable: The most valuable equipment such as cranes, process unit etc. are removed and 
this equipment could be sold for direct reuse.   
  
• Metal reuse: The different modules at the installation can be handed for metal scraping 
after the hazardous waste is removed.  
  
3.2 Typical waste residues
  
Waste from the petroleum industry may be present in many physical and chemical forms. For 
example as produced water, sludge deposits in the process system removed during maintenance, 
drill cuttings, chemicals used during production, or scale/sludge removed at routine maintenance 
of valves and tubular. Waste from offshore activities include many different types of waste and 
some examples, ranging from ordinary household waste to various hazardous waste fractions, 
generated from oil and gas activities are given below:    
  
• Asbestos   
• Zinc anodes   
• Batteries   
• Flame retardants, for example brominated flame retardants   
• Diesel   
• Waste electrical and electronic equipment (WEEE)   
• Phthalates (plasticisers in flooring and cables)   
• Hydraulic oil, grease and lubricants   
• Isocyanates from polyurethane paints   
• CFC and HCFC gases released from cooling agents   
• Chloroparaffins   
• Mercury   
• Low specific activity (LSA) material   
• PCBs (polychlorinated biphenyls)   
• PFOS (perfluorooctyl sulphonate)   
• PVC (polyvinyl chloride)   
• Organotin compounds from anti‐fouling systems   
• Heavy metals  
• Various other chemicals   
  
11   
 
 
  
The possible release of pollutants and generation of waste of possible environmental concern 
generated by the decommissioning of the specific facility, needs to be described in the 
decommissioning programmes and in the environmental impact assessment. Based on this 
documentation individual permits for the planned cessation project is given /15/.   
  
Both amounts and treatment of hazardous and industrial waste is typically reported by the 
offshore sector. From offshore activities at the Norwegian sector about 315,772 tons of hazardous 
waste and 27,070 tons of non‐hazardous waste was taken ashore in 2011. The major fraction of 
the hazardous waste was drilling waste, as illustrated in Table 3.1 /12/.  
  

Table 3.1 Hazardous waste from offshore activities on Norwegian shelf in 2010 /12/  

Hazardous waste   2003   2011  


Rock cuttings and other   70,664   308,456  
Batteries   77   50.3  
Blasting sand   47.4   72.5  
Chemical mix w/halogen   6,661   5,084  
Chemical mix w/metal   10.1   0.3  
Chemical mix w.o./halogen ‐ 
139   30  
w.o./heavy metals  
Lightbulbs   36.9   5.6  
Paint   350   83  
Oil‐contaminated waste   1,673   1,966  
Pure chemicals w/halogen   0.6   0  
Pure chemicals w/heavy metals   1.3   2.8  
Pure chemicals w.o./halogen ‐ 
94.8   17  
w.o./heavy metals  
Spray cans   5.5   5.2  
  
Offshore petroleum operation is known to include usage of hazardous materials and production of 
residues of chemicals, oil and other substances. These materials are expected to be found at the 
installation to be decommissioned. Based on this, information regarding operational waste 
handled offshore can give indication of challenges that could be of environmental concern and 
constitute a safety issue. The main parts of pollutants are removed as part of closing down the 
installation offshore. Cleaning will be executed by high‐pressure water jetting and mechanical 
scraping or scrubbing, while in some cases chemical cleaning methods or sandblasting may be 
used. Even though the installation is cleaned, it is expected to be polluted to some extent due to 
the long term contact with oil or other chemicals. Possible residues of concern are presented in 
Table 3.2  
     
Table 3.2 Possible residues materials of environmental concern. Input from ref. /18/  

Waste   Location  

Residual hydrocarbon sludge   Separators, piping, pipelines, oil storage  
LSA/NORM scale   Piping, valves, tanks  
Heavy metals   Within oil residues, scale or bound to metal surfaces  

12   
 
 
 
 

 
 

Inorganic scale   Piping, valves, tanks  
Production and drilling chemicals    Tanks/pumps  
Hydraulic oil   Compressor etc.  
Attic oil   Oil storage  
Sediment   Oil storage  
H2S    Enclosed tanks/compartments  
  
The table shows that residues of various substances should be expected. All of which require 
appropriate handling, typical collected and delivered to approved waste treatment plant. Large 
uncertainty exists however regarding the properties and the amount of possible residues of 
concern, particular in the subsea structures due to the difficulty of access to carry out 
investigations. The properties of the residues can partly depend on the age of the installation, e.g. 
old installation (30‐40 years) can contain more hazardous substances and materials with 
undesirable properties than the recently built installations which must meet other requirements. 
An example on this could be the previous widely usage of asbestos.  
  
Discharged or accidental leaks/spills of residual substances during decommissioning will have 
consequences for the surrounding environment. Any possible impact depends on the properties 
and amount of the residue substance in question. The typical residues of concern that can remain 
in offshore facilities are briefly described in the following sections.   
  
  
3.2.1 Production chemicals
  
The offshore sector is in generally obligated to perform yearly reports of the usage and release of 
hazardous waste. The use of chemicals offshore is regulated based on the environmental 
properties of the chemical in question. As Denmark constitute one of the contracting parties with 
respect to the OSPAR commission, the oil and gas activity on Danish shelf have to follow the 
OSPAR regulations. The oil and gas companies operating on the Danish shelf have to apply to the 
Danish Environmental Protection Agency (DEPA) for permission for use and discharge of offshore 
chemicals. Pre‐screenings have to be done by the operators and every single product has to be 
included in the application, which is controlled against the information in the Product Register by  
DEPA. This information is treated confidentially in Denmark. The Harmonised Offshore Chemical 
Notification Format (HOCNF), given in Table 3.3, forms the basis for the information in the Product 
Register.   
     
Table 3.3 The requirements under the HOCNF /26/  
  
Classification   Category Description  
Water    Considered to pose Little or No 
Green   Risk to the Environment  
Chemicals on the PLONOR List  
(PLONOR list)  
Hormone‐disruptive substances   Black   No discharge is basically 

13   
 
 
  
Chemicals on the priority list in White Paper No.      permitted, but in special cases 
permits are given  
Biodegradability < 20% and low Pow ≥ 5  
Biodegradability <20% and toxicity EC50 or  
LC50≤10 mg/l  
Two of three categories: biodegradability < 60%, log  Pose an environmental hazard 
Pow≥3, EC50 or LC50≤10 mg/l   and should be replaced. 
Inorganic and EC50 or LC50≤1 mg/l   Permits can be given, but the 
Red   chemical is normally placed on 
a phase‐out plan, which 
Biodegradability<20%  
means that alternatives must 
be identified.  
Chemicals not included in any 
of the other categories. 
Other chemicals   Yellow  
Normally permitted without 
specific conditions  
  
Based on the properties, chemicals are divided into four OSPAR categories; green, yellow, red and 
black, as illustrated in Table 3.3. The form is used to regulate the chemicals used by the offshore 
industry in the OSPAR sector.  
   
The use of chemicals will vary from one platform to another and during the fields' life time. Hence, 
the environmental evaluation regarding the chemicals has to be assessed as an individual matter. 
The increased focus directed to the use of environmental friendly chemicals can increase the 
fraction in the water phase as these chemicals are often water‐soluble. From this, it can be 
implied that the amount of chemical residues present at offshore platforms might have been 
reduced.   
  
Possible chemical residues present after CoP may to some degree be reflected by the chemicals 
used during production. Nevertheless, the majority of the chemicals used follows the production 
streams or will be removed offshore by flushing and cleaning of the system during cessation of the 
installation. From this, the chemicals is primary an environmental concern during production 
rather than decommissioning.   
  
  
3.2.2 Residual oil materials
  
Crude oil is a very complex mixture of thousands of chemical components with different toxicity 
and the composition of the hydrocarbon residues depend on the composition of the specific crude 
oil.   
  
The PAHs (polycyclic aromatic hydrocarbons) commonly found in heavy oil fractions are among 
the most persistent pollutants in the environment /20/. NPD is a PAH subgroup and consists of 
Naphthalene, phenanthrene, dibenzothiophene and theirs alkylated derivates. These compounds 
are of concern because they have potential to bioaccumulate and some of them are carcinogenic, 
therefore an issue for human health /21/.  In general, the toxicity of the PAH's increases with 
increasing molecular weight and substitution.   

14   
 
 
 
 

 
 

  
It should be pointed out that transformation of some compounds can give origin to more 
bioavailable and toxic metabolites. For example benzene is transformed to phenol which again is 
further degraded /19/.   
  
Oil residues together with a water phase remaining in e.g. separators or storage compartments 
could result in biological activity where bacteria are using hydrocarbons as substrate. The 
bacterial growth based on the bioavailable hydrocarbon can cause H2S challenges for the 
decommissioning project, as explained in section 3.3.1. Bioavailability and degradability varies 
between the different hydrocarbons. In general, substances with higher water solubility are more 
bioavailable and hence relatively rapidly degraded. Compounds with high number of carbons are 
less water soluble and hence biodegrades more slowly. An increased fraction of heavier 
hydrocarbons, which are difficult to degrade, are thus expected with time.   
  
The oil compounds with relatively low water solubility including higher paraffins and olefins, 
asphalthenes, waxes and PAH compounds. The low solubility of these compounds continues to 
decrease with increasing chain length. A limited concentration of these compounds is expected in 
the water phase of the flushed enclosed systems as these compounds have a high tendency to 
absorb to particulate material. The adsorption to particles results in precipitation at the internal 
walls and the bottom where they will accumulate.  
  
Residuals of hydrocarbon sludge that is not removed by the flushing/cleaning process, is assumed 
to be the main contamination in the installations to be removed. As previous described, the 
process system is typical flushed and cleaned offshore prior to the removal of the installations.   
  
Topside units can be opened and manual cleaned offshore before transported to land, but 
nonaccessible units such as subsea storages might be difficult to clean properly. Units and 
structures containing residues not possible to remove offshore are normally removed onshore by 
additional cleaning during dismantling. Any structures left in place may to a certain extent contain 
hydrocarbon residues. Pipes can contain scale and hard deposits which is not feasible to remove 
offshore. These deposits can be both inorganic and hydrocarbon based. In storage facilities 
hydrocarbons can also be present as bottom sludge or as floating oil emulsion material with a 
nature as illustrated in Figure 3.3. The emulsion could be of environmental concern for facility 
units such as storage cells which are typical difficult to clean. Removal of oil and other residues 
from storage facilities may be difficult to accomplish as the installation typical is not designed with 
the purpose of supporting a cleaning operation.   
  
  

15   
 
 
  

  
Figure 3.3 Oil/water emulsion materials /25/  
  
In general, it is expected that the remaining oil residues consists mainly of heavy oil components 
as the lighter water soluble hydrocarbons are most likely removed by flushing, normally 
performed after CoP.    
  
Both the properties and the amount of hydrocarbons will affect any possible impact of oil 
residues. High concentration of oil compounds can promote toxic effects. Heavy oil compounds 
can have chronic impact due the persistency in the environment while light hydrocarbons 
normally have acute effect as this fraction is relatively soluble, dissolve easily and can be quite 
volatile. Discharged or accidental leaks/spills of the heavy oil residues can have long term effects 
on the environment due to the relative low degradability caused by the low solubility and thereby 
low bioavailability.   
  
  
3.2.3 Heavy metals
  
Heavy metals include both essential and toxic elements and the concentration of these elements 
is decisive for an environmental evaluation. In environmental science the primary heavy metals of 
note are considered to be Arsenic (As), Lead (Pb), Cadmium (Cd), Cobalt (Co), Copper (Cu), 
Chromium (Cr), Mercury (Hg), Nickel (Ni), Tin (Sn), Vanadium (V) and Zinc (Zn).   
  
Many metals are common elements in offshore installations, e.g. Cr, Zn, Al, Mg and Ni are used in 
alloys while Mn and Fe are common elements in steel. From this, the design of the modules and 
equipment used is of environmental relevance in the process of decommissioning. The metals 
used in installations vary between the different components and installations. In general, new 
installations contain less material with undesirable properties due to stricter requirements /15/.  

Whole modules or smaller sections of the installation are transported to land, where the waste is 
registered and weighted. During dismantling of offshore structures the steel waste flow could be 
as in Figure 3.4. Steel of which is 98 % recyclable is a major component in offshore installations 
today /15/.  

  
  

 
16 

 
 
 
 

 
 

 
Figure 3.4 Metal flow at decommissioning facilities /15/   
  
In addition to the presence of common elements in offshore structure materials, metals are also 
natural occurring elements that can be transported from the reservoir to the topside with the 
production fluids. Furthermore, experience has shown that production liquid is also contaminated 
with various metals originated from the installation, e.g. Fe, Mn, Cr and Ni. Throughout the 
production life, scale and deposits are accumulated in separators, storages, pipes, valves etc.  
These deposits can partly be removed during shutdown operations and entirely during  
dismantling of the installations. The deposits include a complex mixture of calcium (carbonate, 
oxalate, sulphate, silicates), aluminium (silicates, hydroxides, phosphates), barium sulphate, 
mercury etc.  
  
Mercury is present in many gas fields in varying concentrations, as the vaporised mercury follows 
the gas stream. In some cases the mercury is even found as elementary liquid in e.g. dewpoint 
units. Mercury is a metal that have been identified to be of particular concern and the toxic metal 
can be present as scale deposits in pipelines and other equipment, where it is mainly present as 
mercury disulphide. Mercury is of high environmental interest as heavy metal pollutant because 
of its toxicity. Furthermore, its effect can be chronic even in low concentrations. Nevertheless, the 
toxic effects of metals, including mercury, depend on its chemical form. The organic form of 
mercury is generally considered to be of larger environmental concern because of its resistance to 
degradation and higher toxicity compared to the inorganic forms. In water the major form of 
mercury is elemental‐, organic‐ (particular methyl mercury) and ionic mercury (bound to chloride, 
sulphide or organic acids) /22/. Materials containing mercury are handled as hazardous waste and 
due to its toxicity it should be identified before the demolition of the platform /15/.  
  
The properties of mercury are challenging the waste handling as it absorbs to steel surfaces and 
may form mercury amalgams. The amount of mercury adsorbed to the steel varies as the 
mechanism is a function of metallurgical and physical/chemical factors. The mechanism is not 
currently completely understood, but it is important to point out that the process is reversible. 
Therefore, mercury adsorbed by the steel components can re‐dissolved into liquids or 
reevaporated into gas, which can cause exposure of workers and leaches to the surrounding 
environment during decommissioning projects /15/, /28/.   
 
17 

 
 
  
  
In summary, the heavy metals present will vary from one platform to another depending on the 
reservoir properties and the condition in the process system. The toxicity and features of a 
specific metal in question varies with its speciation, defined as the physical and chemical form in 
which an element exists in. The toxic forms of the elements are the primary of interest in 
environmental chemistry. Both the abundance and the biological availability of an element are 
controlling the toxic affect. The dissolved fraction contains the majority of bioavailable species 
and this fraction of metals is therefore considered as greater importance. Quantification and 
identification of species present by speciation studies is necessary for an understanding of the 
toxicity, bioavailability, bioaccumulation and transport of a particular metal /30/   
  
  
3.2.4 NORM
  
NORM – Naturally Occurring Radioactive Material originates from the reservoir and is transported 
to the surface, mainly dissolved or suspended in the water produced together with the oil. In the 
context of decommissioning the radioactive substances of primary relevance are radium isotope 
(Ra‐226 and Ra‐228), lead isotope (Pb‐210) and polonium isotope Po‐210. These radionuclides are 
accompanied with produced water and form radioactive scale during the oil and gas operations 
/14/,/15/ /23/.   
  
During production NORM can deposit in pipe work and tanks due to pressure and temperature 
drops and/or due to mixing of different types of water /13/. Radioactive scale is often deposited 
together with barium sulphate originating from seawater that precipitates out from produced 
water. Therefore, larger quantities of NORM material in installations from oil fields is expected 
compared to those from gas fields.   
  
The activity level of the NORM deposits produced in the various steps in the oil and gas 
production differs within different types of activities. A broad ranking of the activity level in 
NORM, of which occur in different types of activities, is illustrated in Figure 3.5.    
  

 
Figure 3.5 Ranking of radioactivity level in NORM from different types of activities /17/  
The environmental concern of NORM is the ionizing radiation that can cause radiation damage, 
primarily if inhaled/swallowed or in direct contact with the surface of organisms. This is also an 
important aspect regarding safe working environment during decommissioning. Workers can be 
exposed by external and internal radiation through NORM dust if swallowed or inhaled. When 
assessing the environmental fate and impact of NORM it is important to take the affinity towards 
particulate matter into consideration, see Table 3.4 below.     
  
 
18 

 
 
 
 

 
 

Table 3.4 Open ocean distribution coefficients between particulate phase and water phase /24/  

Element   Distribution coefficient, Kd  

Radium (Ra)   4 x103  
Lead (Pb)   1x107  
Polonium (Po)   2x107  
  
The table shows that Pb and Po is very strongly associated to particulate matter, whereas Ra has a 
smaller affinity to particulate matter. High distribution coefficient illustrates high degree of 
association to organic or inorganic particulate matter and will typically accumulate in the seabed 
/23/, /24/.   
  
NORM is classified as hazardous waste and must be handled thereafter by approved facilities. 
Radioactive waste is controlled by national requirements, and in Denmark the requirements is 
established by the National Institute of Radiation Protection (SIS) /16/. Environmental impacts of 
the various disposal methods are shown in Table 3.5.  
     
 
 
 
Table 3.5 NORM disposal options, ranked relative to health and safety risks (part of table in 
/17/)  
  
Occupational Hazard to
Technology   Comment  
hazard   public  
Exposure risk for:  
Sea disposal • offshore workers  
discharge Low (acceptable)   Minimum   • fishermen (fishing)  
(offshore)   • public through consumption 
of fish/seafood  
Exposure risk for:  
Sea disposal • workers  
Low (acceptable)   Low (acceptable)  
near shore   • public (near shore 
environment)  
Exposure risk for offshore 
Re-injection   Low (acceptable)   Minimum   workers  
NORM encapsulated   
In situ Isolation in subsurface (minimum 
downhole Minimum   Minimum   exposure)  
abandonment
Encapsulation Exposure risk for offshore 
and Low (acceptable)   Minimum   workers  
downhole Isolation in subsurface (minimum 
19   
 
 
  
disposal   exposure to public)  

Exposure risk for:  
Onshore built • offshore workers  
disposal Low (acceptable)   Low (acceptable)   • onshore workers  
facility   Exposure risk for public  
(transport/leakage)  
Exposure risk for:  
Onshore • offshore workers  
Low (acceptable)   Low (acceptable)  
landfill   • onshore workers  
• public (transport/leakage)  
  
The disposal method relevant for the Danish sector includes re‐injection, which has to be 
permitted by the national authority SIS. Disposal in an onshore built disposal facility is also a 
Danish disposal optioning, but such a facility does not currently exist and NORM waste is 
therefore stored temporary in Esbjerg. Work is however ongoing with respect to establishing an 
onshore disposal facility, where three alternative places are assessed as possible storage 
locations.   
  
There is no data available on the content of radioactive substances in waste from 
decommissioning projects at the Danish shelf. In a Norwegian publications the experience is 
stated as: "about four tonnes of radioactive waste (scale, sludge and sediments) with an activity 
concentration of 10 Bq/g or more has been found in each offshore installation decommissioned" 
/15/. Based on this, some NORM waste is expected present and need to be handle in most 
decommissioning projects. The NORM handling is assessed mostly as a waste handling issue 
during dismantling and cleaning of pipes etc.   
  
  
3.2.5 Asbestos
  
The largest challenge associated with asbestos is the working environment during removal. There 
are very high demands to make the removal safe for the personnel involved. This includes 
establishment of sanitation zones and use of special personal protective equipment (PPE).   
  
Asbestos can be present in many parts of the offshore structure, e.g. insulation, gaskets, cables for 
emergency systems and hard wall plates. Asbestos have been widely used because of its unique 
properties: it is hard‐wearing and chemically inert (resistant to corrosion by acids and bases), and 
stable at high temperatures. Documentation and materials inventories from the construction 
period of the installation in question contain information on the use of asbestos.  
  
Health risks are associated with asbestos and the use has been prohibited in Denmark since 1986 
/32/. The issue is restricted to decommissioning of old facilities. Inhalation is the main way that 
asbestos enters the body and even small amounts of certain types of asbestos inhaled can cause 
serious health problems such as asbestosis and cancer.  
  

20   
 
 
 
 

 
 

During the demolition works materials that contain asbestos is removed and handled as other 
materials classified as hazardous, including packaging and labeling in accordance with the 
asbestos regulations and delivered to an approved landfill /15/.   
  
  
3.2.6 Paints and other coatings
  
A wide variety of paint and coatings is used on the structures of offshore facilities for inhibition of 
corrosion and preventing marine fouling. Different types of toxic components can be present in 
the paint and coatings, e.g. PCBs, tributyltin (TBT), heavy metals (for example lead, barium, 
cadmium, chromium, copper, zinc) and pesticides. These compounds can have properties that 
require precautions during decommissioning. It can be necessary to remove paint and coatings in 
cutting zones to secure safe working environment, as paint can release toxic gases during heating 
or combustion. Toxic components are typical dealt with at smelting facilities as paint on large 
metal surfaces is not normally removed before the metal is delivered for remelting /15/.    
  
  
3.3 Other considerations
 
Decommissioning facilities must be equipped to deal with many different types of challenges. In 
addition to waste handling, a decommissioning plan must include other issues such as:   
 
• Interference with neighbours  
• Noise  
• Light  
• Air emission   
• Emission to sea  
• Dust   
• Hydrogen sulphide (H2S)  
  
Among the issues above listed, Hydrogen sulphide (H2S) is considered of utmost importance 
within the scope of this report and is therefore described in the following.   
 
 
3.3.1 Hydrogen sulphide (H2S)
  
H2S can accumulate in systems that are enclosed after CoP. These systems include in particular the 
top side separator tanks and the substructure storage cells. It is important to specify that H2S is a 
concern with respect to the working environment and is not an environmental issue. H2S is 
however included in this report as the very toxic H2S gas can be an overlooked challenge in 
decommissioning projects. The toxic gas may escape to the working environment during 
decommission and it can result in immediate deaths offshore when it reaches high concentrations 
(>700 ppm) /25/.  
  

21   
 
 
  
Sources of residue hydrocarbons will act as substrate for microorganisms in the production fluids, 
where both water from the reservoir and seawater containing bacterial fauna enters the system. 
Experience shows that it takes a long time to restore a good decommissioning solution and 
therefore the systems might be closed for a long time after CoP. The environment within the 
closed system will with time shift to anaerobic, which is favourable for sulphate reducing bacteria  
(SRB). The SRB’s will take over as the major driver in the anaerobic environment and H2S is 
produced by reduction of sulphate as shown below:  
  
SO42‐ + organic matter → CO2 + H2O + H2S  
  
From this, it is assessed that inhibition of H2S is important to ensure safe working environment 
during decommissioning work. Inhibition of H2S can be executed by the use of H2S scavengers 
which is commonly used by the industry for pH increase during production. The chemical 
treatment can however be toxic and will produce residues that may require further treatment or 
handling. Based on this, H2S scavengers is of environmental concern and requires appropriate 
handling as it could have hazard impact by killing microorganisms present in the surrounding 
environment if discharged to sea.   
       

22   
 
 
 
 

 
 

4 DANISH SECTOR TEST CASE


All producing fields in Denmark are located offshore in the North Sea. In 2011, total 19 fields were 
producing from 278 active production wells of which 199 were oil wells and 79 were gas wells. 
The production that began in 1972 has been increasing until 2004, while it has been declining 
from 2004 until 2011  . The decline is assessed to primary be due to many old facilities that have 
produced the bulk of the anticipated recordable oil. The oldest field from which the first Danish oil 
was produced is called Dan. The Field is in this chapter as test case used and is to as the Danish 
field referred. The Field is only used as reference with respect to production data, thus the 
possible environmental and waste issues described is not direct valid for the Dan field itself /9/.   
  
Oil and gas production results in some impact to the surrounding environment. Drill cuttings may 
be left at the seabed from drilling operations, chemicals used during production and produced 
water will be discharged to the sea. Produced water originates from the reservoirs and from the 
water injected to enhance the oil production. Produced water is in process system separated from 
the well fluid, and is finally discharged to the surrounding sea. Challenges associated with drill 
cutting will not be in this report covered.   
  
The activities on the Danish shelf are to the authorities reported. With the exception of amount of 
produced oil and gas, the data on production chemical usage and waste handling is confidentially 
in Denmark treated. Hence, it is not possible to neither assess the environmental trends nor 
appoint components of environmental concern. Since no Danish environmental data are available, 
published data from the Norwegian sector is as basis used for describing the environmental 
challenges as part of production and decommissioning in the Danish sector.   
  
Activities on the Norwegian continental shelf are compiled in the so called EnvironmentWeb, 
which is a joint database for the Norwegian Climate and Pollution Agency (Klif), and the  
Norwegian Petroleum Directorate (NPD). Based on these data obtained, the Norwegian Oil 
Industry Association (OLF) provides yearly a public environmental report that includes discharges 
to sea and waste produced in connection with the activities on the Norwegian Continental Shelf. 
The reviewed Norwegian data reported by OLF in 2011 are to the sizes correlated of production at 
the Field /9/, /10/, /12/. Based on this, an overview of possible environmental concerns 
associated with a typical Danish field is in this chapter given. Composition of the produced water 
discharged in the Norwegian sector is the basis given for environmental evaluations and mapping 
of trends. This can provide some indication of the environmental challenges with respect to 
decommissioning of the installations.  
  
The volume of produced water discharged on the Norwegian shelf and from the Field is in Table 
4.1 presented. Data from the year 2011 and 2003 is included in this report. The latest reported 
data available is from 2011, while 2003 is the oldest data found covering all parameters described 
in the following.  
  

23   
 
 
  
Table 4.1 Discharged volume (m3) of produced water per year  

Norwegian shelf   The field /9/  


Parameters  
2003 /11/   2011 2003   2011  
/10/  
Produced water (m3)   134,729,541   128,550,571   7,183   11,059  
  
Seen from the table the trend of Dan is opposite compared to the Norwegian shelf. The decreased 
amount of produced water is primarily due to an overall reduced production on the Norwegian 
shelf /10/. The increase of produced water at the Field installation is due to increased water 
content of total liquid production. This trend is normally seen in the late life of oil and gas fields as 
the reservoir pressure decreases and injection of water increases. In general, the production of 
produced water is typical increasing over the field lifespan and normally constitutes a very high 
fraction of the production liquid during the last phase of the oil production.   
4.1 Chemicals
  
The use of chemicals during production varies between different installations, as highlighted in 
section 3.2.1. Nevertheless, the amount of consumption and discharged in Norway is correlated to 
the produced water at the Danish field, which is given in Table 4.2. It is important to highlight that 
the validity of this correlation involves major uncertainties, however it provides some indication 
on levels of consumption based on the large Norwegian data basis.   
 
Table 4.2Consumption and discharge og chemicals per year  

  

The table shows that the amount consumed is larger than the amount discharged. The reason for 
this is that not all chemicals used will be released, as some of the chemicals follow the water 
injected into reservoirs and/or the oil exported.  
  
Seen from Table 4.2 the consumption of red chemicals decreases, while both the green and yellow 
chemicals increase. The decrease in the use of red chemicals is assumed due to efforts in avoiding 
the usage and especial discharge of the most harmful chemicals. The usage of black chemicals has 
increased in the period, however the discharge has at the same time been significant lowered. The 
increase in use of green and yellow chemicals may be due to the reason that these chemicals are 
less effective than the red and black ones.   
24   
 
 
 
 

 
 

  
Based on the trend illustrated in the table, a smaller risk of finding harmful chemical residue at the 
installation to be decommissioned is expected. The increase in usage of black chemicals is 
expected to be a temporary situation as large effort is done to phase out this category of 
chemicals.   
  
The red and black chemicals with hazardous properties require waste handling thereafter. In 
relevance to decommissioning less use of red and black chemicals will cause less accumulation of 
problematic residues in the process system and finally requires less need of specialised waste 
treatment.  
  
  
4.2 Organic compounds
  
Produced water contains different inorganic salts and organic substances as it has been in contact 
with geological formation for millions of years. Furthermore, various chemicals and oil compounds 
is present within the water. Selected organic compounds discharged to sea are given in Table 4.3, 
which also include the correlated amount discharged from the Danish field.  
     
Table 4.3 Selected group of organic compounds in produced water per year  

Organic Norwegian shelf (kg)/10/ The Danish field (kg)  


compounds  
2003 2011 2003 2011
BTEX   861,160  1,675,059  45.9  144 
Alkyl phenols C1‐C3   281,116  289,324  15.0  24.9 
Alkyl phenols C4‐C5   10,104  14,360  0.54  1.24 
Alkyl phenols C6‐C9   401  219  0.02  0.02 
Phenols   184,168  179,546  9.82  15.4 
Oil in water   1,698,382  1,235,608  90.5  106 
Organic acids   33,576,880  22,251,835  1,790  1,914 
EPA‐PAH   45,176  1,863  2.41  0.16 
sum PAH   99,456  155,915  5.30  13.4 
  
The overall trend at the Danish Field is an increased amount of organic compounds, where 7 of 
the 9 compounds have been increasing from 2003 to 2011. This trend is as expected, based on the 
increased amount of produced water. The amount of some compounds has also increased on the 
Norwegian shelf, meaning that the concentration of these compounds in produced water has 
been increased, as the water production has simultaneously been slightly decreasing. These 
compounds found in increased concentrations includes BTEX, alkyl phenols (C1‐C3 and C4‐C5) and 
sum PAH.   
  
The oil compounds BTEX and PAH both increased some. However, as mentioned in chapter 3.2.2 
the majority of the lighter organic compounds such as BTEX and C1‐C8 are expected to be 
removed by the offshore cleaning process performed during the decommissioning projects. The 
25   
 
 
  
increase of PAH is an important trend with respect to parameters of environmental concern; 
however the amount estimated for the Danish field is relative low. This group of organic 
compound have showed to constitute to a large fraction of the persistent oil residues remaining in 
the installations. PAH is of environmental interest because they have potential to bioaccumulate 
and some are known to have toxic effects, and is therefore an issue regarding environmental 
evaluation.  
  
  
4.3 Heavy metals
  
A range of metals can be found in deposits and water phases in the installation to be removed. As 
explained in section 3.2.3 the pronounced metals various from platform to platform. Table 4.4 
presents the amount of metals found in produced water discharged on the Norwegian shelf and 
then correlated amount from the Danish field.     

Table 4.4 Amount (kg) heavy metals within produced water per year  

Norwegian shelf   The Dani  sh field  


Parameters  
2003 2011 2003 2011
Arsenic   471  656  0.03  0.06 
Barium   1,925,471  7,639,584  103  657 
Lead   527  428  0.03  0.04 
Iron    714,214  959,698  38.1  82.6 
Cadmium   32  32  0.003  0.002 
Copper   3,991  162  0.21  0.01 
   
Chrome   117  221  0.01  0.02 
Mercury   7  15  0.001  0.0004 
Nickel   407  223  0.02  0.02 
Zinc   11,211  10,108  0.60  0.87 
  

26   
 
 
  

There is no clear trend to appoint on the Norwegian shelf, except for the increased amount of 
barium. The amount of metals in general increased from 2003 to 2011 at the Danish field, as the 
amount of produced water is increasing. Barium is the dominant metal followed by iron and zinc. 
In general, barium and iron are metals most often found in increased concentrations compared to 
seawater. Barium occur naturally in reservoirs and the concentrations of the metal in produced 
water are commonly found to exceed those in seawater by a factor of 1,000. The metal is a 
common problem in the offshore industry, as it accumulates as scale deposits when it forms 
complexes with sulphate (barite). Although barium has the potential to accumulate in aquatic 
organisms, the metal pose in general little environmental risk as its forms insoluble salts, of which 
has limited bioavailability /29/. The relative high amount of iron and zinc is assumed to be primary 
caused by contamination from the process system. It is important to highlight that the 
concentration in the water phase indicates relative low levels of the most problematic metals, 
such as Mercury and Cadmium. These components are typical strong bound to deposits and 
therefore water phase concentrations does not well describe the challenges possible arising from 
residues of these components.  
  
  
4.4 NORM
  
The oil and gas companies should report the total discharge of radioactive substances to both SIS 
and OSPAR. The OSPAR convention requires that radioactive substances estimated discharged 
with produced water, and in the context of the activities of descaling and decommissioning 
operations, and from tracer experiments is reported. For all installations discharging should report 
the total amount. The radioactive discharge from installations located at Danish sector is 
presented in Table 4.5.  
  

Table 4.5 Discharges from the offshore oil and gas industry in Denmark in 2009, terabecquerel 
(TBq) /31/  

Offshore oil and gas activities   Pb-210   Ra-226   Ra-228  


Discharged with produced         
water      1.17E‐02  1.02E‐02   6.40E‐03 

Radioactivity in suspended solids 
arising from water‐jet descaling   N.D   N.D   N.D  
Descaling operations, both offshore 
and onshore, from normal 
production that leads to discharges   Radioactivity in solution as a result 
of using acids or scale dissolvers   9.75E‐08   2.37E‐07   7.83E‐08  

Radioactivity in suspended solids 
arising from water‐jet descaling     N.D   N.D   N.D  
Descaling operations, both offshore 
and onshore, from 
decommissioning of oil and gas  Radioactivity in solution as a result 
installations that leads to discharges   of descaling using acids or scale 
        
dissolvers   

27   
 
 
 

Table 4.5 shows that produced water is the major contributor to radioactive substance 
discharged. Pb‐210 is the dominant substance in produced water followed by Ra‐226 and Ra‐228 
respectively. Discharge during descaling operations under normal production is significant lower, 
and contain Ra‐226 as the dominant substance followed by Pb‐210 and Ra‐228.   
  
Currently there have been no decommissioning projects at the Danish shelf and hence there are 
no data regarding radioactive waste discharged during these operations. In general, the trend is 
that high concentration of NORM present in produced water causes larger quantity of NORM 
material in scale and residue deposits present within the process system of offshore facilities. The 
content and amount of radioactive waste discharged during decommissioning varies between the 
different offshore facilities. From this, it is not possible to neither generalize nor appoint any trend 
of radioactive waste at the Danish sector.  
       

 
28 

 
 
  

5 SUMMARY AND CONLUSIONS


  
The purpose of this report is to provide an overview of possible issues of environmental concern 
involved in future decommissioning projects in the Danish oil and gas sector.      
  
The decommissioning processes and extent of activities differ widely from installation to 
installation as the complexity of the installations is very variable. In all cases the decommissioning 
project needs to follow international, regional and national legislation. As part of the obligation 
before starting of removal, the plans for handling of the installation and the environmental 
impacts needs to be described in detail. The authorities shall approve the decommissioning 
programme and the environmental impact assessment report prior to the decommissioning. The 
decommissioning method selected and approved will often be the one involving the lowest 
possible environmental impacts.  
  
There are many environmental concerns to be taken into account throughout the process of 
decommissioning, e.g. planning, shutdown of operations, cleaning and preparation offshore, 
removal from offshore and waste handling onshore. It is important to establish routines that 
ensure satisfactory and appropriate waste handling, in addition to follow‐up environmental 
inspections to ensure that the environmental and safety risks are as low as reasonably practicable. 
The activities should be incorporated in a permanent plan for procedures relating to 
decommissioning assignments.   
  
Identifying the waste generated in the process of decommissioning is considered to be of utmost 
importance. Although it is assumed that the majority of residues are removed offshore by 
cleaning, it is highly likely that some residues will remain as sludge or scale in the facilities. As 
both residues and offshore structures typically are transported ashore, the waste is primary an 
onshore challenge with respect to environmental concerns. The main offshore environmental 
concern during decommissioning projects is assessed to be the substructures possible left in 
place. A proper cleaning of these structures can reduce any possible future environmental impact 
significantly. However, selecting the proper cleaning method can be difficult as identification of 
the possible residues is considered to be the major challenge due to often very difficult access. In 
most cases all parts of the structure will be removed and in such cases the major offshore 
environmental risks are assessed to be risk of spillage or leakage during the cleaning of the 
installations. It should also be mentioned that removal of substructures can cause physical 
disturbance of the seabed, which pose a risk of resuspension and spreading of contaminated 
sediment.    
  
At present no decommissioning projects have been executed in the Danish sector. In addition no 
approved reception facilities for handling of offshore installations is established in Denmark, 
hence there is no experiences that can directly appoint specific environmental concerns at the 
Danish sector. To examine possible environmental issues related to decommissioning the 
following topics have been reviewed:  
  
• Hazardous waste generated during production   

29   
 
 
 

• Hazardous waste described in decommissioning programmes   
• Usage of production chemicals  
  
During installation and production the largest fraction of hazardous wastes is from rock cuttings, 
followed in amount by waste categories as “chemicals with halogen” and “oil‐contaminated”. 
However based on the information reviewed in this study, hazardous waste of major challenges 
for the decommissioning project is assessed to be:   
 
• Residual hydrocarbon sludge: Separators, piping, pipelines, compressors, oil storage  
  
• Scale/Residues with content of NORM and Heavy metals: Piping, valves, tanks, metals 
surfaces  
  
• Production and drilling chemicals: Tanks, pumps  
• Asbestos: Insulation, fire protected cables  
  
To obtain more detailed information on the specific chemical components of concern, the usage 
of production chemicals and the discharge of components with produced water have been 
reviewed. Published data from the Norwegian sector have been towards the sizes correlated of 
production at the Field. Although the correlations between the Norwegian shelf and a typical 
platform at the Danish sector provide some indication of the environmental challenges, it includes 
large uncertainties. The environmental challenges are specific for the individual decommissioning 
project and a generalization of environmental issues based on the correlation is questionable.   
  
In summary, the more specific chemical component of concern will vary between the different 
offshore installations, however based on data from production at the Norwegian shelf the 
following have been with implication concluded for decommissioning of facilities:  
  
• Production chemical residues: In the period from 2003 to 2011, the combined used of the 
most harmful chemicals have declined and the trend is to continue expected. Therefore, 
there is as part of decommissioning project expected to be relative small amount found of 
problematic chemical residues.   
  
• Heavy oil compounds: The component of special environmental interest is assessed being: 
PAH and NPD components.  
  
• Heavy metals: Cadmium, lead, mercury and nickel are assessed being of largest concern.  
  
Safe working environment is a very important aspect regarding decommissioning, as workers can 
be exposed to various hazards. The following issues should be of high priority to ensure safe 
working environment:  
  

30   
 
 
  

• NORM. The low‐radioactive scale is containing typical the isotopes: Ra‐226, Ra‐228, Pb210 
and Po‐210.  NORM is mainly a waste issue; however prevention against dust inhalation 
shall be taken.  
  
• Paint and coatings. The possible hazard depends on the types of toxic components 
present in the different paint and coatings. Especially cutting operation can results in 
release of toxic gasses.  
  
• Asbestos. This can be very challenging issue on old facilities, having sever impact on the 
execution of demolition. Removal of asbestos needs to well planned with high level of PPE 
protection.   
  
• H2S. The toxic gas shall also be taken into account, before entering enclosed systems. Use 
of personnel H2S monitors and PPE can be needed in some occasions.   
  
  
For each decommissioning project thoroughly studies and mapping surveys is required to describe 
the possible environmental impacts.  For evaluation of the possible environmental impacts it is of 
outmost importance to collect representative samples. However, collecting representative 
samples can be a major challenge in decommissioning projects due to the very difficult access, 
particular to substructures e.g. pipes, storage cells etc. The transport and fate of the residues is 
also considered to be a key issue. The transport pathways in the physical environment, and the 
possible uptake of organisms, bioaccumulation and fate in the food web should be taken in 
consideration. Overall, this depends on the property of the specific residue in question which will 
vary between the different installations.   
     
 

 
31 

 
 
 

6 REFERENCE
  
/1/   Lov om sikkerhed m.v. for offshoreanlæg til efterforskning, produktion og transport af 
kulbrinter (offshoresikkerhedslov), LOV nr 1424 af 21/12/2005.  
/2/   Marine Environmental Law (2009), LBK 929, 24‐9‐2009 (erstatter tidligere LBK 1073, 20‐ 
10‐2008), Havmiljøloven: https://www.retsinformation.dk/Forms/R0710.aspx?id=127090  
/3/   DECC (2009) Guidance Notes, Decommissioning of Offshore Oil and Gas Installations and  
Pipelines under the Petroleum Act 1998, Version 4, August 2009, 
https://www.og.decc.gov.uk/regulation/guidance/decommission.htm  
/4/   LOV 1996‐11‐29 nr 72: Lov om petroleumsvirksomhet 
http://www.lovdata.no/cgihttp://www.lovdata.no/cgi‐wift/ldles?doc=/all/nl‐19961129‐
072.html ‐ map005wift/ldles?doc=/all/nl‐19961129‐072.html#map005  
/5/   The petroleum act 1998  
http://www.england‐legislation.hmso.gov.uk/acts/acts1998/ukpga_19980017_en_1  
/6/   IMO (1989), Guidelines and standards for the removal of offshore installations and structures 
on the continental shelf and in the exclusive economic zone. Guideline from the International 
Maritime Organization (IMO), 19. October 1989.  
http://www.imo.org/Newsroom/contents.asp?doc_id=628&topic_id=227  
/7/   OSPAR Decision 98/3 on the Disposal of Disused Offshore Installations, 
http://www.ospar.org. Last updated 17.08 2012.  
/8/   Offshore centre Denmark, 39 Danish sustainable offshore decommissioning project  
/9/   Danish energy agency, 2011, Oil and Gas Production – and Subsoil Use, oil and gas production 
in Denmark,  
 

 
32 

 
 
  

/10/ OLF, 2011, Environmental report   
/11/ OLF, 2004, Environmental report   
/12/ OLF, 2012, Environmental report  
/13/ Institute for energy technology (IFE), 2008, The new Norwegian repository for LSA scale from 
the petroleum industry  
/14/ Radioaktivt avfall fra petroleumsindustrien (Radioactive waste from the petroleum industry), 
May 2010, draft report from a working group headed by the Ministry of the Environment  
/15/ Climate and pollution agency, 2011, decommissioning of offshore installations, TA‐2761  
/16/ Sundhedsstyrelsen Statens institut for strålehygiejne 2005, Vejledning om håndtering af 
NORM fra olje og gas industrien, accessed from 
http://www.sst.dk/publ/Publ2005/SIS/Vejl_NORM/Vejl_NORM_2udg_SIS.pdf on 26/6/20102  
/17/ Sniffer (2004), Phase I, Technical report, Identification and assessment of alternative disposal 
options for radioactive oilfield wastes UKRSR07, Dated September 2004.  
/18/ British Petroleum (BP), 2006, North west Hutton decommissioning programme  
/19/ Skadsheim, A., et al. (2002). Konsekvenser av regulære utslipp til sjø‐ RKU Norskehavet 
Rogalandsforskning, SINTEF.  
/20/ Seo, J.‐S., et al. (2009). "Bacterial Degradation of Aromatic Compounds." International Journal 
of Environmental Research and Public Health 6(1): 278‐309.  
/21/ Kanaly, R. A. and S. Harayama (2000). "Biodegradation of High‐Molecular‐Weight Polycyclic 
Aromatic Hydrocarbons by Bacteria." J. Bacteriol. 182(8): 2059‐2067.  
/22/ Morel, F.M.M., (2001), Redox transformation and bioavailability of mercury, 
http://www.envirofacs.org/Preprints/Vol%2041%20No%201/Award%203/p138.PDF, 
retrieved 20.1.2012  
/23/ NORSEDECOM, 2003. Naturlige radionuklider i det marine miljø – en oversikt over 
eksisterende kunnskap med vekt på Nordsjø‐området. Report No. ND/E‐17/03 for Norges  
Forskningsråd. Strålberg, E., Varskog, A.T.S, Raaum, A. & Varskog, P., 27 November 2003.
/24/ OSPAR, 2006. Report on the relationship between Pb‐210 and Po‐210 concentrations in  
produced water discharges and in the environment – proposals regarding future monitoring 
and assessment. OSPAR RSC 06/3/2‐E. By IFE / Institute for Energy Technology:  
Discharges of Naturally Occurring Radioactive Materials (NORM) to Sea – Considerations in 
relation to the OSPAR Convention’s objective of reduced discharges (Elisabeth Strålberg,  
Rajdeep S. Sidhu, 1 June 2006)  
/25/ Søren Knudsen. 2011, Decommissioning concrete structures‐environmental and safety 
challenges, SPE international 140866.  
/26/ HELCOM Baltic Sea Action Plan, Helsinki commission, Baltic Marine Environment Protection 
Commission 29th Meeting, Helcom 29/2008.  
/27/ Statoil, 2012, Avslutning av virksomheten og disponering av innretninger på Huldra‐feltet 
Konsekvensutredning,   
/28/ Mercury Technology Services, 2008, mercury in steel  
/29/ Lee K. and Neff J., 2011, produced water, environmental risks and advances in mitigation 
technologies, springer , ISBN‐10: 1461400457  

33   
 
 
 

/30/ Stumm, W. and Morgan, J.J. ,1997, Aquatic Chemistry, chemical equilibria and rates in natural 
waters (3th edn., New York: John Wiley & Sons, Inc) 1022  
/31/ OSPAR commission, 2011,  Discharges of radioactive substances from the non‐nuclear sectors 
in 2009, Radioactive Substances Series, 
http://www.ospar.org/documents/dbase/publications/p00544_discharges%20from%20non 
%20nuclear%20sectors%202009.pdf  
/32/ The Danish Confederation of Trade Unions, 2005, Asbestos in Denmark and the global level, 
The international health & safety day on 28 April 2005, "Safe and healthy work for all – 
prevention and responsibility"  
/33/ Department of energy and climate change, Table of decommissioning programmes, 
http://og.decc.gov.uk/en/olgs/cms/explorationpro/decommissionin/table_decomm/table_d 
ecomm.aspx  
/34/ Rice T. and Owen P., 1999, Decommissioning the Brent Spar, ISBN 0‐419‐24090‐x  
  

34   
 
 

You might also like