ID Task Name

April 2019 Duration Start Finish May 2019


27 29 1 3 5 7 9 11 13 15
1 Proses Pemasangan BFP 2B 8 days Fri 5/3/19 Tue 5/14/19
2 Dismantiling Impeller (Prepare Assembly after 1 day Sun 5/5/19 Sun 5/5/19
dynamic balancing)
3 Perakitan pompa 7 days Sun 5/5/19 Tue 5/14/19
4 Prepare 1 day Sun 5/5/19 Mon 5/6/19
5 Runout Shaft (Setelah proses mobilisasi) 1 day Sun 5/5/19 Sun 5/5/19
6 Final Check Clearance Wear Ring + 1 day Sun 5/5/19 Sun 5/5/19
Impeller
7 Final Check Clearance diffuser + Impeller 1 day Mon 5/6/19 Mon 5/6/19

8 Proses Perakitan Awal (Workshop) 2 days Mon 5/6/19 Tue 5/7/19


9 Pemasangan Impeller Stage 1~12 2 days Mon 5/6/19 Tue 5/7/19
10 Pemasangan Diffuser Stage 1~12 2 days Mon 5/6/19 Tue 5/7/19
11 Proses Perakitan (On Site) 5 days Sun 5/5/19 Sun 5/12/19
12 Pengangkatan Rotor ke Site 1 day Tue 5/7/19 Tue 5/7/19
13 Persiapan Spesial Tools 2 days Sun 5/5/19 Mon 5/6/19
14 Pemasangan Sealing & C-Ring Suction & 1 day Wed 5/8/19 Wed 5/8/19
Discharge
15 Pemasangan Rotor ke Pompa Casing 3 days Wed 5/8/19 Fri 5/10/19
16 Pemasangan Lower Suction Case & Lower 1 day Fri 5/10/19 Fri 5/10/19
Discharge Case
17 Pemasangan Mechseal DE & NDE 1 day Fri 5/10/19 Fri 5/10/19
18 Pemasangan Bearing Housing DE dan NDE 1 day Fri 5/10/19 Fri 5/10/19

19 Setting Spigot & Centering 1 day Sat 5/11/19 Sat 5/11/19


Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Thu 5/2/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Name
April 2019 Duration Start Finish May 2019
27 29 1 3 5 7 9 11 13 15
20 Setting Total Endplay tanpa thrust bearing 1 day Sat 5/11/19 Sat 5/11/19
& dengan thrust bearing
21 Pemasangan Upper Line bearing (DE 1 day Sat 5/11/19 Sat 5/11/19
&NDE) Dan Thrust bearing
22 Pemasangan Upper Bearing Housing DE & 1 day Sat 5/11/19 Sat 5/11/19
NDE
23 Pemasangan Kopling Pompa 1 day Sun 5/12/19 Sun 5/12/19
24 Alignment Pompa 2 days Mon 5/13/19Tue 5/14/19
25 Alignment Pump ~ Fluid Coupling 2 days Mon 5/13/19Tue 5/14/19
26 Alignment Fluid Coupling ~ Motor 2 days Mon 5/13/19Tue 5/14/19
27 Assembly Aksesoris Part 1 day Tue 5/14/19 Tue 5/14/19
28 Perakitan Aksesoris Pipa 1 day Tue 5/14/19 Tue 5/14/19
29 Perakitan Aksesoris Instrument 1 day Tue 5/14/19 Tue 5/14/19
30 Pelepasan Blank Flanges + Connecting Piping 1 day Tue 5/14/19 Tue 5/14/19
BFP ke Sistem

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Thu 5/2/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2