DAVAO INTERNATIONAL CONTAINER TERMINAL

Bo. San Pedro Panabo City, Davao Del Norte, 8105

TO: Capt. Maung Myint


MV BARRY TRADER

FROM: ENGINEERING & MAINTENANCE DEPARTMENT

SUBJECT: ACCOMPLISHMENT REPORT

DATE: APRIL 13, 2019

Dear Sir,

Good Day!

This is to formally inform you that the damage cell guide of Bay 30, Row 10, Row 08 and Row 06 forward
part has been repaired by our maintenance team.

Dates of Repaired Activity:

March 16, 2019: 1300hrs-2200hrs


March 30, 2019: 0030hrs-1700hrs
April 13, 2019: 2100hrs-1730hrs

Prepared by:
Glenn Alderite
Maintenance Engineer

Noted by:
V. Tan
Engg. & Maint. - Mech. Foreman

W. Narciso
Engg. & Maint – Mech Supervisor MV BARRY TRADER REPRESENTATIVE