You are on page 1of 16

704

Measured performance of a 26 m deep top-down


excavation in downtown Shanghai
Yong Tan and Mingwen Li

Abstract: Via a long-term comprehensive instrumentation program, the performance of a 26 m deep metro station excava-
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13

tion constructed by the top-down method in downtown Shanghai was extensively examined. The measured excavation re-
sponses included diaphragm wall deflections, wall settlements, ground settlements, uplifts of interior steel columns, axial
forces of propping struts, groundwater table levels, and settlements of adjacent buildings and utility pipelines. Based on the
analyses of field data, the following major findings were obtained: (i) the concrete struts along with the floor slabs effec-
tively suppressed later wall movements and consequently reduced the chance that the maximum wall deflections would oc-
cur above the excavation surfaces, (ii) with the progress of excavation to a lower depth, the diaphragm walls underwent a
serrated settlement pattern over time, (iii) no significant post-excavation wall deflection occurred, (iv) the relationship be-
tween the interior column uplifts and the maximum wall deflections can be described by a linear equation, and (v) most sys-
tem loads due to soil removal were carried by the concrete struts along with the floor slabs. The struts sustained mainly the
released earth pressures due to the exposure of the adjacent portions of diaphragm walls, and the soil removal distant from
the struts imposed limited effects on the strut axial forces.
Key words: top-down excavation, soft clays, field data, buildings and utility pipelines.
Résumé : La performance d’une excavation d’une profondeur de 26 m pour une station de métro au centre-ville de Shan-
ghai, construite selon la méthode de construction descendante, a été étudiée de façon extensive à l’aide d’un programme
For personal use only.

d’instrumentation à long terme. Les comportements étudiés comprennent les déflections du mur à diaphragme, les tasse-
ments des murs et du sol, les soulèvements des colonnes d’acier intérieures, les niveaux de la nappe phréatique, les forces
axiales dans les supports verticaux, et les tassements des bâtiments adjacents et des canalisations. Selon les analyses des
données de terrain, les conclusions suivantes sont obtenues : (i) les supports de béton le long des dalles de plancher suppri-
ment de façon efficace les mouvements futurs des murs et ainsi réduisent les chances que la déflection maximale des murs
se produise au-dessus des surfaces de l’excavation, (ii) en raison de la progression en profondeur de l’excavation, les murs à
diaphragme ont subit, avec le temps, un modèle de tassement dentelé, (iii) aucune déflection significative des murs s’est
produite après l’excavation, (iv) la relation entre les soulèvements des colonnes intérieures et la déflection maximale du mur
peut être décrite par une équation linéaire et (v) la majorité des charges du système causées par l’enlèvement du sol ont été
portées par les supports de béton le long des dalles de plancher. Les supports ont principalement maintenu les pressions des
terres enlevées en raison de l’exposition aux portions adjacentes des murs à diaphragme, et l’enlèvement du sol loin des
supports a causé des effets limités sur les forces axiales des supports.
Mots‐clés : excavation descendante, argiles molles, données de terrain, bâtiments et canalisations.
[Traduit par la Rédaction]

Introduction or facilities will confront bigger risks of being damaged.


Due to limited space in densely populated urban environ- However, stress–strain behavior of soils, especially soft soils,
ments, underground structures such as basements and metro is highly nonlinear and is affected by many factors, e.g., ani-
lines have to go deeper today than in the past. As deeper ex- sotropy, creep, and destructuration (Hashash 1992; Fang and
cavations incur larger stress and strain fields, both the con- Yin 2006; Yin and Cheng 2006; de Lyra Nogueira et al.
structed underground structures and the adjacent structures 2009; Yildiz et al. 2009). It is difficult to predict the actual
development of stress–strain in soils under complex construc-
Received 24 June 2010. Accepted 8 November 2010. Published tion conditions via a numerical or analytical method. As a re-
at www.nrcresearchpress.com/cgj on 4 May 2011. sult, the design of an excavation today still relies heavily on
Y. Tan. Key Laboratory of Geotechnical and Underground empirical and semi-empirical approaches, some of which date
Engineering, Ministry of Education, Department of Geotechnical back several decades. By updating the current database, well-
Engineering, Tongji University, 1239 Siping Road, Shanghai documented field observation data regarding a deep excava-
200092, P.R. China. tion — especially in soft clays and (or) congested urban en-
M. Li. Shanghai Tunnel Engineering & Rail Transit Design and vironments — will be beneficial in a practical sense to
Research Institute, 200 West Tianmu Road, Shanghai 200070, P. designers, practitioners, and researchers. Another immediate
R. China. benefit of field observations is that they can provide timely
Corresponding author: Y. Tan (e-mail: feedback to both designers and contractors and consequently
tanyong21th@tongji.edu.cn). help lower the risk for design and construction.

Can. Geotech. J. 48: 704–719 (2011) doi:10.1139/T10-100 Published by NRC Research Press
Tan and Li 705

In the past few decades, performances of excavations have Ningbo Road to the north. The excavation pit was approxi-
been extensively investigated, and some empirical or semi- mately 25 m by 152 m in plan with an excavation depth of
empirical approaches for estimating the magnitudes of exca- 24 to 26 m. It was bounded by Metro Line 2 below East
vation-induced wall deflections and ground movements have Nanjing Road, Hongyi building under construction, and the
been developed on the basis of field measurements (e.g., four-story commercial building Laojiefu to the south; by a
Peck 1969; Mana and Clough 1981; O’Rourke 1981; Finno new development and the eight-story steel-reinforced con-
et al. 1989; Clough and O’Rourke 1990). However, most of crete Huadong Real Estate Group building to the west; by
these field data were obtained from excavations less than the four-story brick masonry “residential building 1” to the
15 m deep, supported by flexible retaining systems (e.g., northwest; by the four-story brick masonry “residential build-
sheet pile walls, soldier pile walls) or without lateral support ing 2” to the northeast; and by the four-story brick masonry
systems or with support systems lacking sufficient stiffness. “commercial building,” the four-story brick masonry “resi-
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13

More recently, the observed data (Ou et al. 1993, 1998; dential building 3,” and the five-story brick masonry Shang-
Hsieh and Ou 1998; Ng 1998; Long 2001; Moormann 2004; hai Gas Corporation building to the east. Except for the
Liu et al. 2005; Wang et al. 2005; Kung et al. 2007; Leung Hongyi building, all these adjacent buildings are relatively
and Ng 2007; Seo et al. 2010; Tan and Wei 2011) in deep old with histories of 50 to more than 100 years. Prior to ex-
excavations supported by stiff diaphragm walls proved that cavation, a 1 m thick concrete diaphragm wall with a depth
these empirical or semi-empirical approaches may overesti- of 30 m had been constructed between the new development
mate wall deflections and ground movements due to excava- and the planned excavation. All these buildings are supported
tion. Until now, most of these aforementioned studies focused by strip footings, except for Huadong Real Estate Group
on retaining wall deflections and ground settlements during building that was supported by pre-stressed high-strength
excavation. Few cases were known to document pre- and concrete (PHC) pipe piles (13 to 18 m in length, 300 mm in
post-excavation wall deflections and ground settlements, external diameter, and 70 mm in wall thickness). The mini-
long-term development of retaining wall settlements, axial mum distance was 7 m between the excavation and Huadong
forces of propping struts, and movements of interior steel Real Estate Group building and 9 m between the south shaft
columns. These parameters are important indicators of sup- and Metro Line 2 (in service). The excavation was also sur-
porting system stability, and the relevant field measurements rounded by numerous utility pipelines, including one con-
For personal use only.

can help designers, practitioners, and researchers further crete storm sewer with a diameter of 1000 mm and thickness
understand the behavior of deep excavations. For excavation- of 100 mm; two cast-iron water-supply pipelines with diame-
induced building settlements, there were only limited field ters of 300 and 1000 mm and thicknesses of 5 and 10 mm,
data available in the literature (e.g., O’Rourke et al. 1976; respectively; two cast-iron gas-supply pipelines with diame-
Boscardin et al. 1978; Finno and Bryson 2002). For excavation- ters of 300 and 700 mm and thicknesses of 5 and 10 mm,
induced settlements of nearby utility pipelines, few case his- respectively; one cast-iron communication-cable pipeline
tories can be found in the literature. with a diameter of 1000 mm and thickness of 10 mm; three
This study investigated the performance of a 26 m deep cast-iron power-cable pipelines with diameters of 300 and
excavation at East Nanjing Road Station of Metro Line 10, 1000 mm and thicknesses of 5 and 10 mm, respectively; and
which was constructed by the top-down method in soft clays several electricity pipelines. These utility pipelines were
in the commercial district of downtown Shanghai, China. buried at depths of 0.5 to 1.0 m below ground surface (BGS).
Field measurements of lateral deflections and vertical move-
ments of diaphragm walls, ground settlements, axial forces of Subsurface conditions and soil properties
struts, vertical movements of interior steel columns, ground-
water table levels outside the excavation, and settlements of Prior to excavation, soil conditions at the site were ex-
adjacent buildings and utility pipelines were reported, ana- plored by a series of field exploration programs (e.g., bore-
lyzed, and discussed. This project and the relevant field data holes, standard penetration tests, and cone penetration tests).
not only provide a good case history to calibrate and verify The field exploration encountered a thin layer of fill (layer I)
numerical tools, but also to facilitate thorough understanding in the upper 2 m BGS, followed by a layer of firm silty clay
of the general behavior of deep excavations constructed by (layer II) to a depth of 7 m BGS. Below layer II, there ex-
the top-down method in soft clays within congested urban isted a layer of very soft clay (layer III) to a depth of 18 m
environments. BGS. The next layer was soft to firm silty clay (layer IV) ex-
tending to a depth of 39 m BGS, underlain by a stiff silty
clay (layer V) to a depth of 43 m BGS. Beneath layer V was
Project information very dense silty fine sand interbedded with sandy silt (layer
The investigated excavation is located in the commercial VI) to the termination depth of 70 m BGS. The observed
district of downtown Shanghai, China. As the largest city long-term groundwater table at the site was around 0.5 to
and the commercial and financial center of China, Shanghai 0.7 m BGS.
is located at the estuary of Yangtze River on China’s east The soil properties along the depth were characterized by
coast. The city sits on the flat alluvial plain known as the both in situ field vane shear tests and a series of laboratory
Yangtze River Delta featuring high groundwater tables and tests including oedometer tests (confined compression tests),
thick layers of soft clays. Figure 1 presents the site plan of triaxial tests, and unconfined compression tests. The effective
the project along with the instrumentation layout for field cohesion, c′, and the effective friction angle, f0 , were deter-
monitoring. The investigated excavation was parallel to Mid- mined by consolidated undrained triaxial tests; the coefficient
dle Henan Road with East Nanjing Road to the south and of compressibility, av(0.1–0.2), and the constrained modulus,

Published by NRC Research Press


706 Can. Geotech. J. Vol. 48, 2011

Fig. 1. Site plan of the project along with the instrumentation layout.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13
For personal use only.

E0.1–0.2, were obtained by oedometer tests at stress ranges of commercial activities nearby during construction, the top-
100 to 200 kPa; the undrained shear strength, Su, along the down method supported by braced concrete diaphragm
depth was measured by consolidated–undrained quick shear walls was adopted for this deep excavation.
tests; the specific penetration resistance, Ps, was obtained Figure 3 briefly illustrates the top-down excavation se-
from in situ static cone penetration tests, which accounts for quence at the site. It started with construction of 1 m thick
both cone resistance and sleeve friction. It is calculated by perimeter retaining walls and then the load-bearing elements
(LBE) that would carry the future metro station structures.
4l
½1 Ps ¼ qc þ fs The diaphragm walls were toed through the soft clay layers
D into the underlying very dense silty fine sand stratum to pro-
where qc is cone resistance in MPa, l is length of the cone vide lateral stability and effective cutoff of groundwater. The
rod in metres, D is diameter of the cone rod in metres, and load-bearing elements consisted of ACIP piles, which pene-
fs is sleeve friction in MPa. Both the laboratory and field test- trated into the very dense silty fine sand and sandy silt layers.
ing results indicated that the soft soils in the upper layers fea- The interior H-section steel columns (460 mm × 460 mm)
ture relatively high water content, high void ratio, high were constructed on the deep-seated ACIP piles to sustain
compressibility, and low strength. The in situ vane shear test construction loads as well as function as permanent struc-
results showed that the soft soils in the upper 20 m BGS ex- tures for later use. Then, the ground floors, which also
hibited medium sensitivity, St, of around 2 to 4, which im- worked as struts for supporting the diaphragm walls, were
plies that the strength and stiffness of the soft clays would cast. As excavation proceeded to a lower level, new struts or
degrade substantially once subjected to disturbances arising floor slabs were propped or cast. This process was repeated
from construction activities. The soil profiles along with ba- down to the final excavation levels. The construction was
sic soil properties are presented in Fig. 2. conducted from the two end shafts toward the central stand-
ard segments. Excavation at the south shaft started on 29 No-
vember 2007 and ended on 8 April 2008; excavation at the
Construction sequence and procedure north shaft started on 2 March 2008 and ended on 14 July
The investigated excavation consisted of three sections (i.e., 2008; excavation at the central standard segments started on
the south shaft, the central standard segments, and the north 26 August 2008 and ended on 25 October 2008. Tables 1
shaft). To mitigate potentially adverse impact induced by and 2 summarize the detailed construction activities at the
excavation on the adjacent historic Huadong Real Estate north shaft and the central standard segments.
Group building, a row of auger cast-in-place (ACIP) piles Figure 4 presents the typical cross sections of the north
were installed between the building and the planned metro shaft and central standard segments. The cross section of the
station prior to excavation. The ACIP piles were 31 m in south shaft is similar to that of the north shaft except for
length and 550 mm in diameter, and were spaced at 0.6 m. some minor details. The excavation depths were 26.1 m at
Considering (i) limited construction space, (ii) mitigation of the south shaft, 25.8 m at the north shaft, and 24.24 m at
potentially adverse effects on adjacent buildings and facili- the central standard segments. The depths of the diaphragm
ties as much as possible, and (iii) maintenance of normal walls were 53 m at the south shaft, 46 m at the north shaft,

Published by NRC Research Press


Tan and Li 707

Fig. 2. Soil profiles and material properties.


Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13
For personal use only.

and 44 m at the standard segments. The use of a deeper dia- of the south and north shafts and the struts at levels 1, 3, and
phragm wall at the south shaft was to minimize the excava- 6 of the standard segments were steel-reinforced concrete,
tion-induced impact on Metro Line 2 (in service), which is and the struts at other levels were steel pipes 609 mm in ex-
only 9 m away from the south shaft. The ACIP piles func- ternal diameter and 16 mm in wall thickness. To enable max-
tioning as the load-bearing elements were 0.8 m in diameter imum working space inside the excavation, diagonal strutting
and 30 m in length at the south shaft, 1.0 m in diameter and was used at the corners. The concrete struts were horizontally
40 m in length at the standard segments, and 1.0 m in diam- spaced at 6 m and the steel pipe struts were horizontally
eter and 30 m in length at the north shaft. Prior to excava- spaced at 2 to 3 m along the longitudinal direction of the ex-
tion, layers of soils at different depths on the excavation side cavation. The vertical distance from the centers of the struts
were reinforced by jet-grouting to restrain wall movements. to the nearest excavation surface directly below was around
The reinforced soils were located at depths of 9.95 to 0.5 m.
12.45 m BGS, 16.90 to 19.10 m BGS, and 26.10 to 29.10 m Because of tight construction schedule, the curing period
BGS at the south shaft; at depths of 16.67 to 18.47 m BGS of the concrete struts and floor slabs was 14 days (concrete
and 24.24 to 27.24 m BGS at the standard segments; and at reached 80%∼90% of the design strength) at the two end
depths of 16.60 to 18.77 m BGS and 25.80 to 28.08 m BGS shafts and was only 6 to 7 days (concrete strength < 70% of
at the north shaft. The measured unconfined compression the design value) at the standard segments. The Young’s
strength of these reinforced soils 28 days after completion of moduli, E, of the concrete and steel used at this site were
grouting was more than 1.2 MPa. It is common engineering 3 × 107 and 2 × 108 kPa, respectively.
practice in Shanghai excavations to reinforce the soils at
some depths on the excavation sides by grouting. The main
Instrumentation
purposes of grouting are to: (i) restrict wall movements dur-
ing excavation (unloading) by reinforcing the soils on the ex- To verify design assumptions and monitor the performance
cavation side, (ii) mitigate potential basal heave during of the deep excavation for securing the safety of this project,
excavation, and (iii) cut off seepage of waterflow below the a long-term comprehensive instrumentation program was
excavation surface. Via laboratory tests, Fang and Yin conducted in situ. Figure 1 presents the instrumentation
(2007) found that the deep cemented soft soils consolidate layout used to monitor the performance of the excavation.
faster than the pure soft ground. The struts at levels 1 and 6 The deflections of the diaphragm walls were monitored by

Published by NRC Research Press


708 Can. Geotech. J. Vol. 48, 2011

Fig. 3. Top-down construction sequence at the site. To address the safety concerns regarding the buildings and
utility pipelines in the proximity of the excavation, the settle-
ments of the buildings and pipelines were also surveyed dur-
ing excavation. Thirty-six settlement points (designated as J1
to J36), established on the exterior walls of seven adjacent
buildings, were surveyed by a level instrument. As to the
utilities, a total of 93 settlement points were surveyed by a
level instrument, and they are designated as Y1 to Y16 for
the concrete storm sewer, S1 to S25 for two cast-iron water-
supply pipelines, M1 to M24 for two cast-iron gas pipelines,
T1 to T13 for the cast-iron communication-cable pipeline,
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13

and DL1 to DL15 for three cast-iron power-cable pipelines


(some of the surveying points are marked in Fig. 1).
All the instrumentations equipment was zeroed before any
construction activities started. Field readings were obtained
every 2 days during stages 1(a) and 1(b), every day between
stages 2(a) and 9, and every 2 days during casting of the base
slabs and the following 30 days. Thereafter, instrument read-
ings were retrieved every 7 days.

Observed performance of the excavation


Prior to the commencement of major work, all the existing
buildings and utility pipelines within the predefined influence
zones were surveyed to establish benchmarks for monitoring
the impact from excavation. As it is not feasible to present all
For personal use only.

the field observation data due to limited paper length, only


typical field measurements are presented and discussed in
this study.

Deflections of diaphragm walls


Figure 5 presents the typical lateral deflections of dia-
phragm walls measured at Q3 of the south shaft, Q23 of the
north shaft, and Q9 of the central standard segments follow-
ing the completion of each excavation stage. It was noticed
that as excavation went down to level 2, wall movements in
the upper part were restrained by the cast ground floors and
24 inclinometer tubes (designated as Q1 to Q24); the settle- then the walls began to develop deep-seated movements
ments of the diaphragm walls were surveyed by a level in- (bulging profiles) towards the excavation side. During the
strument with an accuracy of 0.01 mm. These surveyed subsequent excavation stages, the walls continuously devel-
points were at the same locations as the inclinometer tubes oped deep-seated movements towards the excavation side
(Q1 to Q24). For the struts at Z2 and Z3 (designated as and the locations of maximum wall deflections moved down-
Z2-1 to Z2-7 and Z3-1 to Z3-6, respectively), the develop- ward as excavation went deeper. Compared with Q3 and
ment of the strut axial forces was monitored by the vibrating Q23, the diaphragm wall at Q9 experienced significantly
wire stress meters for the concrete struts and by the vibrating larger deflections at the completion of excavation at each
wire strain gauges for the steel pipe struts. The vertical level. This discrepancy may be attributed to these two fac-
movements of the interior steel columns (designated as L1 to tors: (i) corner effects at the end shafts and (ii) insufficient
L25) were monitored by an electronic total station instru- curing time for the poured concrete struts and floor slabs at
ment. The groundwater tables outside the excavation were the central standard segments. Because of arching effects (e.g.,
monitored by six standpipe piezometers (designated as SW1 Singh et al. 2010), wall deflections at the excavation cor-
to SW6), which were buried to a depth of 15 m BGS. The ners (end shafts) may be smaller than those at the central
ground settlements at locations D1 to D18, around 1 to 5 m sections, where plane-strain conditions can be assumed (e.g.,
behind the diaphragm walls, were surveyed by a level instru- Ou and Chiou 1993; Ou and Shiau 1998). To catch up
ment. To monitor the ground settlements close to the adja- with the tight construction schedule, the curing time for the
cent buildings, two critical sections (designated as D10 to cast concrete struts and floors at the standard segments was
D10-5 close to the Huadong Real Estate Group building and only 7 days. This means that excavation to a lower level
D11 to D11-5 close to the Shanghai Gas Company building) was carried out before the cast concrete struts or floor slabs
were selected. The settlement points at both sections were gained sufficient strength. As a result, the struts and floor
spaced at 5 m. The settlement points D10 to D10-5 were 5 slabs may not have provided sufficient strength to suppress
to 30 m away and the points D11 to D11-5 were 0.5 to the wall deflections during excavation.
25 m away from the diaphragm walls. Figure 6a shows the relationship between the measured

Published by NRC Research Press


Tan and Li 709

Table 1. Main stages of excavation at the north shaft. Ø, external diameter.

Stage Event Date Days spent


1(a) Construction of diaphragm wall, ACIP bored piles as load-bearing 5 Jan. 2007 ∼ 7 Dec. 2007 336
elements, and ACIP isolation piles
1(b) Construction of H-section steel columns resting on the ACIP piles, 13 Dec. 2007 ∼ 6 Jan. 2008 24
and performance of jet-grouting
2(a) Excavation to 1.5 m BGS (level 1) 2 Mar. 2008 1
2(b) Casting of level 1 reinforced concrete struts (1.5 m × 0.4 m) 3 Mar. 2008 ∼ 4 Mar. 2008 2
2(c) Curing of level 1 struts 4 Mar. 2008 ∼ 17 Mar. 2008 14
3(a) Excavation to 6.42 m BGS (level 2) 18 Mar. 2008 ∼ 22 Mar. 2008 5
3(b) Installation of level 2 steel pipe struts (Ø609 mm) 22 Mar. 2008 1
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13

3(c) Construction of roof slab (0.8 m thick) 23 Mar. 2008 ∼ 24 Mar. 2008 2
3(d) Curing of roof slab 25 Mar. 2008 ∼ 8 Apr. 2008 14
4(a) Excavation to 10.15 m BGS (level 3) 9 Apr. 2008 ∼ 13 Apr. 2008 5
4(b) Installation of level 3 steel pipe struts (Ø609 mm) 13 Apr. 2008 1
4(c) Construction of middle slab 1 (0.8 m thick) 14 Apr. 2008 ∼ 17 Apr. 2008 4
4(d) Curing of middle slab 1 18 Apr. 2008 ∼ 2 May 2008 14
5(a) Excavation to 13.05 m BGS (level 4) 3 May 2008 ∼ 9 May 2008 7
5(b) Moving level 3 struts to level 4 9 May 2008 1
6(a) Excavation to 17.10 m (level 5) 10 May 2008 ∼ 17 May 2008 8
6(b) Installation of level 5 steel pipe struts (Ø609 mm) 15 May 2008 1
6(c) Construction of middle slab 2 (0.8 m thick) 16 May 2008 ∼ 22 May 2008 7
6(d) Curing of middle slab 2 23 May 2008 ∼ 6 June 2008 14
7(a) Excavation to 20.12 m BGS (level 7) 7 June 2008 ∼ 14 June 2008 8
7(b) Moving level 5 struts to level 7 14 June 2008 1
7(c) Casting of level 6 reinforced concrete struts (1.5 m × 1.0 m) 15 June 2008 ∼ 17 June 2008 3
For personal use only.

7(d) Curing of level 6 struts 17 June 2008 ∼ 1 July 2008 14


8(a) Excavation to 23.32 m BGS (level 8) 2 July 2008 ∼ 8 July 2008 7
8(b) Moving level 7 struts to level 8 8 July 2008 2
9 Excavation to 25.80 m BGS (final level) 10 July 2008 ∼ 14 July 2008 6
10(a) Construction of base slab (1.4 m thick) 15 July 2008 ∼ 19 July 2008 5
10(b) Curing of base slab 20 July 2008 ∼ 15 Oct. 2008 86

maximum wall deflection, dhm, and the excavation depth, H, Chicago, Boston (1977), and San Francisco were between
at the site. For a better understanding of this excavation, 0.6%H and 2.2%H, which were above the range of dhm =
some published case histories of excavations in soft to me- 0.1%H to 0.6%H measured in Taipei, Boston (1993), and
dium clays, including 35 cases in Taipei (Ou et al. 1993, this excavation in Shanghai. This phenomenon is due to the
1998; Hsieh and Ou 1998; Kung et al. 2007), four cases in fact that the excavations in Taipei, Shanghai, and Boston
Singapore (Nicholson 1987; Hulme et al. 1989; Wallace et (1993) were supported by stiff diaphragm walls, while the
al. 1992; Lim et al. 2003), four cases in Oslo (NGI 1962; excavations in Oslo, Chicago, Boston (1977), and San Fran-
Murphy et al. 1975; Mitchell 1976), two cases in Boston cisco were supported by flexible sheet piles and (or) soldier
(Ladd et al. 1977; Whittle et al. 1993), two cases in Chicago piles. Although the excavations in Singapore were also sup-
(O’Rourke et al. 1976; Finno and Harahap 1991), and four ported by stiff diaphragm walls, the measured dhm values
cases in San Francisco (Tait and Taylor 1974; Reed 1980; ranged from 0.1%H to 1.0%H, which was above those meas-
Mana and Clough 1981), were also plotted in this figure for ured in Taipei and Shanghai. This may be attributed to the
comparison. The excavations in Taipei, Singapore, and Bos- weaker soil conditions in Singapore in comparison with the
ton (1993) were supported by stiff diaphragm walls, and the soil conditions in Taipei and Shanghai (see Table 3). The
excavations in Oslo, Chicago, Boston (1977), and San Fran- comparison in Fig. 6a indicates that although the excavations
cisco were supported by sheet piles or soldier piles. For ease in Taipei and Shanghai were much deeper than those in Oslo,
of comparison, typical soil properties of the clays at various Chicago, Boston, San Francisco, and the cases reported by
sites are summarized in Table 3. Peck (1969), the use of a braced stiff diaphragm wall can
From Fig. 6a, it was observed that except for Q20, dhm val- substantially reduce the wall deflections caused by excava-
ues at the south and north shafts in this study were greater tion.
than 0.1%H, but less than 0.275%H. Except for Q10, dhm val- Based on 10 excavations in Taipei soft clays, Ou et al.
ues at the standard segments were between 0.275%H and (1993) found that the ratio Hm/H is approximately equal to
0.5%H. The data points of dhm lay far below the limiting 1.0, where Hm is the location of the maximum wall deflec-
line, dhm = 1%H, proposed by Peck (1969) based on the ob- tion. Figure 6b shows the relationship between Hm and H at
served excavations in soft clays supported by sheet piles and this site. It was noticed that the ratios of Hm/H fell between
(or) soldier piles. By comparing excavations at various sites, Hm = H and H + 7 m (i.e., dhm occurred within 7 m below
it was noticed that most of the measured dhm values in Oslo, the excavation surface) when H ≤ 16 m, which were in

Published by NRC Research Press


710 Can. Geotech. J. Vol. 48, 2011

Table 2. Main stages of excavation at the central standard segments.

Stage Event Date Days spent


1(a) Construction of diaphragm wall, ACIP bored piles as load-bearing 18 Dec. 2006 ∼ 4 Oct. 2007 290
elements, and H-section steel columns
1(b) Performing jet-grouting 31 July 2008 ∼ 16 Aug. 2008 17
2(a) Excavation to 1.5 m BGS (level 1) 26 Aug. 2008 1
2(b) Casting of level 1 reinforced concrete struts (1.5 m × 0.4 m) 27 Aug. 2008 ∼ 28 Aug. 2008 2
2(c) Curing of level 1 struts 29 Aug. 2008 ∼ 5 Sep. 2008 7
3(a) Excavation to 6.22 m BGS (level 2) 11 Sep. 2008 ∼ 13 Sep. 2008 3
3(b) Installation of level 2 steel pipe struts (Ø609 mm) 13 Sep. 2008 1
3(c) Construction of roof slab (0.8 m thick) 14 Sep. 2008 ∼ 15 Sep. 2008 2
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13

3(d) Curing of roof slab 16 Sep. 2008 ∼ 23 Sep. 2008 8


4(a) Excavation to 10.22 m BGS (level 4) 24 Sep. 2008 ∼ 26 Sep. 2008 3
4(b) Installation of level 4 steel pipe struts (Ø609 mm) 26 Sep. 2008 1
4(c) Casting of level 3 reinforced concrete struts (1.0 m × 0.8 m) and 27 Sep. 2008 ∼ 29 Sep. 2008 3
middle slab 1 (0.4 m thick)
4(d) Curing of level 3 struts and middle slab 1 30 Sep. 2008 ∼ 6 Oct. 2008 7
5(a) Excavation to 12.82 m BGS (level 5) 7 Oct. 2008 ∼ 9 Oct. 2008 3
5(b) Moving level 4 struts to level 5 9 Oct. 2008 1
6(a) Excavation to 17.17 m (level 7) 10 Oct. 2008 ∼ 12 Oct. 2008 3
6(b) Installation of level 7 steel pipe struts (Ø609 mm) 12 Oct. 2008 1
6(c) Casting of level 6 reinforced concrete struts (1.2 m × 0.8 m) and 13 Oct. 2008 ∼ 14 Oct. 2008 2
middle slab 2 (0.4 m thick)
6(d) Curing of level 6 struts and middle slab 2 15 Oct. 2008 ∼ 21 Oct. 2008 7
7(a) Excavation to 18.97 m BGS (level 8) 21 Oct. 2008 1
7(b) Moving level 7 struts to level 8 21 Oct. 2008 1
For personal use only.

8(a) Excavation to 21.77 m BGS (level 9) 22 Oct. 2008 1


8(b) Installation of level 9 steel pipe struts (Ø609 mm) 22 Oct. 2008 1
9 Excavation to 24.24 m BGS (final level) 23 Oct. 2008 ∼ 25 Oct. 2008 3
10(a) Construction of base slab (1.3 m thick) 26 Oct. 2008 ∼ 29 Oct. 2008 4
10(b) Curing of base slab 29 Oct. 2008 ∼ 19 Dec. 2008 52

agreement with those observations of five excavations less forces and consequently the maximum wall deflections oc-
than 20 m deep in Shanghai soft clays by Wang et al. curred above the excavation surfaces.
(2005). However, the ratios of Hm/H tended to fall between It has been widely acknowledged that consolidation and
Hm = H – 7 and H + 7 m (i.e., some dhm occurred within creep of soft clays could result in significant wall deflections
7 m above the excavation surface and some within 7 m be- and ground movements. To examine this, the maximum post-
low) when H > 16 m. This phenomenon could be explained excavation deflections of the diaphragm wall at each moni-
by examining the measured strut axial forces (refer to the tored location were plotted against the elapsed time in
section titled “Axial forces of struts”). When excavation to Fig. 7. Time coordinate starts from the completion of excava-
each level was executed, the earth pressures released due to tion to the final level on 9 April 2008 at the south shaft, 15
soil removal were basically retained by the level of struts July 2008 at the north shaft, and 26 October 2008 at the
just above (e.g., earth pressure released by excavation to level central standard segments. The monitored results showed
2 would be retained by level 1 struts). If the struts could pro- that the maximum wall deflections increased 1 to 10 mm in
vide enough axial forces, they would suppress further wall the first 4 to 10 days (i.e., during the construction of base
deflections above them. Consequently, the retaining wall de- slabs) and then stabilized quickly over time. No long-term
flection due to soil removal would basically occur below the post-construction wall deflection was observed. It can be
struts and the maximum deflection would stay below the ex- concluded that in this top-down excavation, most of the wall
cavation surface. Otherwise, the retaining wall portion above deflections arose from stress relief related to excavation,
the struts would be mobilized and deflected toward the upper while creep of the soft clays did not induce apparent post-
struts that could provide enough axial forces. When excavat- construction (time-dependent) wall movements.
ing in the upper 16 m, the steel and concrete struts in combi- Figure 8 plots the relationship between the normalized
nation with the cast floor slabs managed to withstand the maximum wall deflections, dhm /He, and the factors of safety
released earth pressures, and hence the maximum wall de- (FOS) against basal heave, in which FOS was calculated us-
flections occurred below the excavation surfaces. When exca- ing the method of Bjerrum and Eide (1956), He is the final
vation proceeded to the lower 10 m, the earth pressures excavation depth, and the two boundary curves shown were
released by each level of excavation increased with depth so proposed by Mana and Clough (1981). The reported data of
that the steel pipe struts at levels 7 and 8 could not fully sus- the top-down excavations in Shanghai soft clays (Liu et al.
tain them. As a result, the wall deflections developed up- 2005; Xu 2007) were also included in this figure for compar-
wards until the concrete struts at level 6 offered extra axial ison. It was noticed that except for a few scattering data, most

Published by NRC Research Press


Tan and Li 711

Fig. 4. Cross sections of the north shaft and the central standard segments.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13
For personal use only.

of the Shanghai cases were around the lower boundary of plied a different settling pattern for the diaphragm walls than
Mana and Clough (1981). This could be attributed to the use expected. Such a phenomenon can probably be explained by
of the top-down technique along with reinforcement of the the different soil movements that took place at different time
soils below the excavation bases by grouting. intervals. When a layer of soils was removed, the soils inside
the excavation pit moved upwards immediately due to stress
Wall settlements relief and consequently pulled the wall up by upward skin
When designing a retaining wall, it is common to assume friction. As time went by, the soils outside the pit started to
that the wall itself will not settle significantly. If the soil con- be mobilized and pulled the wall down by larger downward
ditions below the toe of the wall were complex and (or) the skin friction. The observed wall settlements at the north shaft
wall did not rest on hard bearing stratum, wall settlements were on average greater than those measured at the south shaft
could take place and cause racking or even failure of relevant and the standard segments. This was likely caused mainly by
bracing systems. Hence, it is necessary to monitor the wall the buildings nearby, which imposed additional surcharges to
settlements during excavation to ensure the safety of projects. the ground against the diaphragm walls once their sensitive
Figure 9 presents the development of wall settlements during foundation soils were disturbed by construction activities.
construction of the north shaft. The diaphragm walls initially The field measurements in Figs. 7 and 9 show that both
moved upwards up to 4 mm after completion of the concrete the lateral wall deflections and the vertical wall settlements
struts at level 1. As excavation proceeded to lower levels, the stabilized quickly following casting of the concrete base
diaphragm wall began to settle and the wall settlements in- slabs. This implies that the construction of the rigid base
creased continuously when excavation proceeded. Following slabs imposed immediate effects on suppression of the devel-
the completion of the base slabs, the wall settlements tended opment of wall movements.
to stabilize around 4.5 to 7.5 mm. When taking a close look
at Fig. 9, it can be noticed that during excavation at different Ground settlements
levels, the diaphragm walls underwent serrated settlement pat- Figure 10a presents the relationship between the ground
terns (i.e., the walls moved up first and then down). This im- settlements, dv, and the distance from the diaphragm wall, d,

Published by NRC Research Press


712 Can. Geotech. J. Vol. 48, 2011

Fig. 5. Typical wall deflections measured at the south shaft, north shaft, and central standard segments. dh, wall deflection.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13

Fig. 6. Relationships between (a) dhm and H; (b) Hm and H. for the final excavation stage, in which both dv and d are nor-
For personal use only.

malized by the final excavation depth, He. The empirical ap-


proach for the excavation-induced ground settlements, which
was developed by Peck (1969) from excavations propped by
sheet piles or soldier piles, was included in this figure for
comparison. Different from those reported in Peck (1969),
most of the field data in this case fell within zone I, far
away from zone III for very soft to soft clays. This indicates
that the use of a braced stiff concrete diaphragm wall can
substantially reduce excavation-induced ground settlements.
Figure 10b presents the relationship between the normal-
ized settlements, dv/dvm, along sections D10 to D10-5 and
D11 to D11-5 and the normalized distance, d/H, from dia-
phragm walls, where dv is the ground settlement at various
distances behind the diaphragm walls and dvm is the maxi-
mum ground settlement along one section. The empirical ap-
proaches recommended by Clough and O’Rourke (1990) and
Hsieh and Ou (1998) were also included for comparison.
This figure shows that most of the field data falls within the
envelope proposed by Clough and O’Rourke (1990) and the
primary influence zone defined by Hsieh and Ou (1998).

Uplifts of interior steel columns


In top-down excavation, the magnitude of the interior col-
umn uplifts is an important criterion for quality assurance
and quality control. Following the deep-seated deflection of
diaphragm walls, base upheavals, and ground movements to-
wards the excavation sides, the interior columns will be lifted
up continuously during excavation. Intolerable column uplifts
will cause racking or collapse of the strutting systems, which
could lead to detrimental results. Figure 11 presents the
measured column uplifts at L3 to L16 during construction of
the north shaft. As shown in this figure, the columns kept
being lifted up as excavation proceeded. Following the con-
struction of the base slabs, the column uplifts were reduced
and then stabilized quickly as the concrete cured with time.

Published by NRC Research Press


Tan and Li 713

Table 3. Typical soil properties of soft to medium clays at various sites.

Undrained shear Water content, Plasticity index, Soil sensitivity,


Sites strength, Su (kPa) w (%) PI (%) St References
San Francisco 23 to 34 45 to 60 15 to 60 4 to 8 Mana and Clough (1981)
Boston 65 30 11 3 to 6 Ladd et al. (1977)
Chicago 18 to 80 20 to 40 10 to 20 — O’Rourke et al. (1976)
Oslo 24 to 29 20 to 45 10 to 35 2 to 6 NGI (1962)
Singapore 20 to 30 50 to 90 30 to 70 3 to 10 Hulme et al. (1989)
Taipei 25 to 75 45 to 60 10 to 20 — Ou et al. (1993)
Shanghai 20 to 60 20 to 60 10 to 25 2 to 4 This study
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13

Fig. 7. Development of the maximum post-excavation wall move- Fig. 9. Development of wall settlements during construction.
ments.
For personal use only.

Fig. 8. Normalized maximum wall deflections versus FOS against Fig. 10. Observed ground settlement profiles versus those predicted
basal heave. by empirical methods: (a) relationship between normalized ground
settlements and normalized distance from the wall for the final ex-
cavation stage; (b) relationship between relative settlements and nor-
malized distance from wall at different excavation stages.

The columns at the south shaft and the standard segments du-
plicated similar uplifting patterns as those at the north shaft.
As uplifts of the interior columns are closely related to the
excavation depths and the associated wall movements to-
wards the excavation side, the measured column uplifts were
plotted against the excavation depths in Fig. 12a and against
the measured maximum wall deflections at different excava-
tion depths in Fig. 12b. In these two figures, the column up-
lifts and the maximum wall deflections are averaged for the
south shaft, standard segments, and north shaft. As shown in
Fig. 12a, the column uplifts, Lh(avg.), increased with the exca-
vation depth, H. Similar to the observed wall deflections in 0.15%H. From Fig. 12b, it was noticed that the column up-
Fig. 6a, Lh(avg.) values at the central standard segments rang- lifts increased almost linearly with the maximum wall deflec-
ing between 0.15%H and 0.22%H were above those observed tions and their relationship can be approximated by a linear
at the north and south shafts ranging between 0.06%H and equation

Published by NRC Research Press


714 Can. Geotech. J. Vol. 48, 2011

Fig. 11. Development of the vertical movements of interior steel sign loads were calculated using the beam-on-elastic-foundation
columns. method, where the beam is simulated as a one-dimensional fi-
nite element. To continuously monitor the development of
the axial forces, the steel struts at levels 4 and 7 were not
moved to levels 5 and 8 once excavation at levels 5 and 8
was completed.
As shown in Fig. 13 and Table 4, the system loads due to
excavation were carried mainly by the rigid concrete struts
Z2-1 and Z2-5. The measured maximum axial forces at the
concrete struts Z2-1 and Z2-5 were up to 1.1 and 1.5 times
their design loads, respectively, and the final stabilized axial
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13

forces were around 0.8 and 1.3 times, respectively. In con-


trast, most of the measured maximum axial forces of the steel
struts were just around 50% of their design loads and the fi-
nal stabilized axial forces were 28%–51% of their design
loads. Compared with the measured axial force at concrete
strut Z2-1, the smaller magnitude at Z2-3 could be attributed
Fig. 12. Relationships between (a) Lh(avg.) and H; (b) Lh(avg.) and dhm(avg.). to the following two coupled factors: (i) the cast middle slab
1 below Z2-3 carried the excavation-induced loads jointly
with Z2-3 and (ii) the steel strut Z2-4 was not removed as
initially planned (i.e., according to the design, when excava-
tion proceeded to level 5, Z2-4 should have been relocated to
level 5). Therefore, Z2-4 shared the loads supposed to be car-
ried by Z2-3.
By further examination of the field observations at struts
Z2, it was found that the axial forces of most struts reached
For personal use only.

their maximum readings in 1 to 2 weeks after being propped


or cast. Thereafter, the axial forces kept almost steady over
time. This finding indicates that during excavation, transfer-
ring of the excavation-induced loads to the struts was com-
plete in 1 to 2 weeks after strut popping or casting. The
lateral earth pressures released due to wall exposure were
sustained mainly by the struts and the floor slabs above the
excavation surfaces and deeper excavation hardly affected the
axial forces of the distant struts.

Groundwater table
Figure 14 presents the development of the measured
groundwater table levels over time at SW5 and SW6 outside
the excavation pit. During the entire construction at the north
shaft, the measured groundwater table levels at SW5 and
SW6 fluctuated slightly between 0 and 0.5 m BGS according
to seasonal changes, which were within the long-term
groundwater table levels in Shanghai areas. The measured
groundwater table levels at SW1 to SW4 around the south
shaft and the central standard segments duplicated similar de-
velopment patterns as those monitored at SW5 and SW6.
This proved that the impervious concrete diaphragm walls
along with the jet-grouting reinforcement layers below the fi-
nal excavation surfaces functioned well as waterproof cur-
½2 Lhðavg:Þ ¼ 0:6dhmðavg:Þ tains, which successfully cut off seepage of the waterflow
during excavation.
where Lh(avg.) is the averaged column uplift at each excavation
section and dhm(avg.) is the averaged maximum wall deflection Building settlements
at each excavation section. Figure 15 shows the settlements of the eight-story concrete
Huadong Real Estate Group building supported by PHC pipe
Axial forces of struts piles during construction. Prior to excavation, the maximum
Figure 13 presents the measured axial forces of the struts building settlements developed were around 5 to 35 mm.
at different propping levels at location Z2 of the central The surveyed points close to the excavation, J1, J2, J9, J10, and
standard segments. The design axial loads of struts Z2-1 J11, experienced settlements around 15 to 35 mm, and those
(level 1) to Z2-7 (level 9) are summarized in Table 4. The de- away from the excavation, J3 to J8, experienced settlements

Published by NRC Research Press


Tan and Li 715

Fig. 13. Development of the axial forces of struts at Z2 during excavation.


Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13

Table 4. Axial forces, N, of the struts at Z2.

Measured Measured N
Design load, maximum N at stable
Location Strut material N (kN) (kN) state (kN)
Z2-1 (level 1) Concrete 4781 5215 3825
Z2-2 (level 2) Steel pipe 2000 1025 1025
Z2-3 (level 3) Concrete 2500 2370 2370
For personal use only.

Z2-4 (level 4) Steel pipe 2500 1267 1064


Z2-5 (level 6) Concrete 5000 7370 6560
Z2-6 (level 7) Steel pipe 2300 2400 1942
Z2-7 (level 9) Steel pipe 2300 1172 633

Fig. 14. Variation of groundwater table levels during excavation.

around 5 to 10 mm. These significant pre-excavation settle- the pit. The building developed an apparent inclination to-
ments were possibly due to the combined effects of the fol- wards the excavation. Following the completion of the con-
lowing three factors: (i) lack of support from the foundation crete base slab at stage 10(a), the settlements at all the
soils during diaphragm walling, (ii) additional settlements surveyed points continued to increase with time ,but at
under the building’s own weight, and (iii) possible creep ef- smaller rates, until 15 October 2008. Thereafter, the settle-
fects of the soft clays. As the diaphragm wall moved con- ments at J4 to J11 and J10-1 almost stopped, while J1, J2,
tinuously towards the excavation side while soil removal and J3 continued settling over time. The post-excavation
proceeded, the building kept settling over time. Immediately settlements at J1 to J3 and J9 to J11 between 15 July and
after excavation to the final level was completed, the maxi- 15 October 2008 were from to 13 up to 34 mm. As the
mum building settlements of 60 to 95 mm occurred at J1, diaphragm wall did not develop substantial post-excavation
J2, J3, J9, J10, and J11 on the southeast corner closest to deflections, these significant post-excavation building settle-
the pit, and the minimum settlements of 10 to 30 mm oc- ments may have resulted from the following factors: (i) ex-
curred at J6 to J8 on the northwest corner furthest from cavation at the adjacent standard segments close to the wall

Published by NRC Research Press


716 Can. Geotech. J. Vol. 48, 2011

Fig. 15. Settlement developments at Huadong Real Estate Group building.


Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13

J1 to J3 between 26 August and 25 October 2008 and (ii) the sensitive foundation soils around the buildings closer to
For personal use only.

additional building settlements under its own weight due to the excavation would be disturbed more during construction
disturbance of its sensitive foundation soils by construction and therefore the soil strength would degrade more. As a re-
activities. For survey points J1 to J3, at which the building sult, they would experience relatively longer and larger post-
settlements did not stop even after construction at the stand- construction settlements under their own weights. At the
ard segments was completed, factors other than the afore- Shanghai Gas Company building, apparent cracks were ob-
mentioned ones contributed to the observed settlements. served on the south wall along J28 to J30-1 and the north
One possible explanation is that the structural integrity of wall along J27 to J27-1, where the maximum differential set-
the building had been severely damaged by construction-in- tlements were up to 47 mm between J28 and J30-1 and
duced impact, and thus the side along J1 to J3 settled inde- 55 mm between J27 and J27-1.
pendently from the res of the building. This assumption was Different from Huadong Real Estate Group building and
proved by the fact that: (i) during construction, apparent Shanghai Gas Company building, the other five four-story
cracks were observed on the south wall along J2 to J3, the brick masonry buildings (i.e., residential buildings 1 to 3,
west wall along J3 to J4, and the interior wall along J4 to the commercial building, and the Laojiefu building) resting
J10 in an extra survey program, which is data that was not on shallow foundations experienced only very limited settle-
available for the current study; and (ii) the other building ments up to 7 mm throughout the excavation. Similar to the
walls (e.g., J9 to J11, J4 to J7, J7 to J9) completely stopped Shanghai Gas company building, these five buildings stopped
settling since the completion of excavation at the standard settling quickly as the concrete base slab was cast. Because
segments on 25 October 2008. These cracks should be the building settlements were greatly affected by many
caused by the excessive differential settlements, which were factors (e.g., foundation types, structural types, structural
up to 25 mm between J2 and J3, 34 mm between J3 and integrity, distances from excavations, and pre-construction
J4, and 55 mm between J4 and J10. The observed building conditions of the structures), it is difficult to give general
settlements indicated that although a row of isolation piles had explanations about the building settlements. A much more
been installed between the Huadong Real Estate Group build- detailed building survey program and structural analysis are
ing and the excavation pit, this concrete building still under- required for further investigation.
went significant settlements up to 115 mm at J1 and J2 and
differential settlements up to 105 mm between J2 and J7. Settlements of utility pipelines
The way the five-story brick masonry Shanghai Gas Com- Figure 16 presents the typical settlements of the utility
pany building settled was similar to that of Huadong Real pipeline — a 1.0 m diameter concrete storm sewer — during
Estate Group building, while the maximum settlement it ex- construction of the south shaft. The sewer is centered 0.7 m
perienced was only half that of Huadong Real Estate Group below the ground surface. The settlements of the other pipe-
building and no long-term post-excavation settlement was ob- lines duplicated similar settlement patterns, but with different
served after the construction of the base slabs. Such distinc- magnitudes. Prior to excavation, the pipelines settled slightly
tive settling behavior could be partially attributed to thae fact and then moved upwards. The initial settlements were likely
that theHuadong Real Estate Group building was closer to induced by ground settlements resulting from diaphragm
the excavation and much heavier. As explained previously, walling, and the later upheaval was likely caused mainly by

Published by NRC Research Press


Tan and Li 717

Fig. 16. Typical settlements of utility pipelines during excavation.


Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13

reinforcement of the soils on the excavation side using jet- sociated wall deflections. The measured column uplifts
grouting. Following excavation to deeper levels, the utility were between Lh(avg.) = 0.06%H and 0.22%H. The rela-
pipelines began to settle again and the settlements increased tionship between the column uplifts and the wall deflections
over time. After the base slab was cast, the pipelines almost can be fit by a linear equation, Lh(avg.) = 0.6dhm(avg.)%H.
stopped settling by 26 August 2008, when excavation at the 5. During excavation, the diaphragm walls underwent serrated
standard segments started. settlement patterns. This is likely due to the fact that the
As the settlements of utility pipelines are affected by soils on the two sides of the diaphragm walls were not
many factors (e.g., stiffness and length of the pipelines, pre- mobilized at the same time.
construction conditions of the pipelines, geometrical shapes 6. During top-down excavation, most of the system loads due
For personal use only.

of the excavations, embedment depths of the utilities, soil to soil removal were carried by the rigid concrete struts
conditions, distances relative to the excavations, and types and floor slabs. When each layer of soil was removed,
of adjacent facilities and structures), it is difficult to give a the earth pressures released due to wall exposure were
general interpretation for the observed pipeline behavior basically retained by the level of struts just above the
during excavation. excavation surface. If the struts could provide enough
axial forces, they were able to sustain retaining wall de-
Conclusions flections. Otherwise, the retaining wall would tend to
deflect towards the nearest struts that could provide
Via a long-term comprehensive instrumentation program, greater axial forces to resist the earth pressures. The pro-
the performance of a 26 m deep metro station excavation cess of transferring the excavation-induced loads to the
constructed by the top-down method in soft clays within braced struts was almost completed within 1 to 2 weeks
downtown Shanghai was extensively investigated. Based on after installation of the struts.
the analyses of the field data, the following major findings 7. The impervious concrete diaphragm walls along with the
were obtained: jet-grouting reinforcement layers below the excavation
1. Using the top-down excavation method with braced dia- bases can successfully cut off the seepage of waterflow
phragm walls along with jet-grouting reinforcement, con- during excavation. Therefore, additional settlements due
struction activities of this 26 m deep metro station did to consolidation of soft clays, which would result from
not induce a significantly adverse impact on the urban changing of the water head, can be prevented.
environment.
2. The diaphragm walls developed typical deep-seated inward Acknowledgements
movements (bulging profiles) during excavation. The Many people and organizations contributed to the success of
measured maximum wall deflections were between dhm this project and special thanks are due to Mr. Hong-liang Lan
= 0.1%H and 0.5%H. The ratios of Hm/H were between of Shanghai Geotechnical Investigations & Design Institute
Hm = H and H + 7 m when H ≤ 16 m, and between Co., Ltd. for providing the detailed information for soil condi-
Hm = H – 7 m and H + 7 m when H > 16 m. tions at the project site, Shanghai Jing-Hai Engineering Tech-
3. No significant long-term post-excavation wall movement was nology Company for field instrumentation and field data
observed. Most wall deflections and ground settlements collection, and Dr. Ye Lu of Shanghai University for her sub-
during excavation arose from stress relief incurred by stantial contribution to improve the quality of this manuscript.
soil removal instead of consolidation and (or) creep of The financial support from the National Natural Science Foun-
the soft clays. The immediate casting of the concrete base dation of China (NSFC Grant No. 50908172), Kwang-hua
slabs following the completion of excavation helped stabi- funds for the College of Civil Engineering of Tongji University,
lize the movements of the retaining walls and the ground and Shanghai Leading Academic Discipline Project (No. B308)
as well as the adjacent buildings and utility pipelines. are gratefully acknowledged. Finally, the great comments from
4. The uplifts of the interior steel columns due to excavation the three anonymous reviewers, the Associate Editor, and the
were closely related to the excavation depths and the as- Editor are sincerely appreciated.

Published by NRC Research Press


718 Can. Geotech. J. Vol. 48, 2011

References and EXCAV97. In Proceedings of Underground Singapore,


Singapore, 27–28 November 2003. Nanyang Technological
Bjerrum, L., and Eide, O. 1956. Stability of strutted excavations in
University, Singapore. pp. 83–94.
clay. Géotechnique, 6(1): 32–47. doi:10.1680/geot.1956.6.1.32.
Liu, G.B., Ng, C.W.W., and Wang, Z.W. 2005. Observed performance
Boscardin, M.D., Cording, E.J., and O’Rourke, T.D. 1978. Case
of a deep multistrutted excavation in Shanghai soft clays. Journal of
studies of building behavior in response to adjacent excavation.
Geotechnical and Geoenvironmental Engineering, 131(8): 1004–
Final report prepared by the University of Illinois at Urbana-
1013. doi:10.1061/(ASCE)1090-0241(2005)131:8(1004).
Champaign for the U.S. Department of Transportation, Washing-
Long, M. 2001. Database for retaining wall and ground movements
ton, D.C. Report No. UMTA-IL-06-0043-78-2.
due to deep excavations. Journal of Geotechnical and Geoenvir-
Clough, G.W., and O’Rourke, T.D. 1990. Construction induced
onmental Engineering, 127(3): 203–224. doi:10.1061/(ASCE)
movements of in-situ walls. In Design and Performance of Earth
1090-0241(2001)127:3(203).
Retaining Structures, Proceedings of a Specialty Conference,
Mana, A.I., and Clough, G.W. 1981. Prediction of movements for
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13

Ithaca, N.Y., 18–21 June 1990. GSP 25. Edited by P. Lambe and L.
braced cuts in clay. Journal of the Geotechnical Engineering
A. Hansen. American Society of Civil Engineers (ASCE), New
York. pp. 439–470. Division, ASCE, 107(6): 759–777.
de Lyra Nogueira, C., de Azevedo, R.F., and Zornberg, J.G. 2009. Mitchell, J.K. 1976. Fundamentals of soil behavior. John Wiley &
Coupled analyses of excavations in saturated soil. International Sons, Inc., New York.
Journal of Geomechanics, 9(2): 73–81. doi:10.1061/(ASCE)1532- Moormann, C. 2004. Analysis of wall and ground movements due to
3641(2009)9:2(73). deep excavation in soft soils based on a new worldwide database.
Fang, Z., and Yin, J.-H. 2006. Physical modelling of consolidation of Soils and Foundations, 44(1): 87–98.
Hong Kong marine clay with prefabricated vertical drains. Murphy, D.J., Clough, G.W., and Woolworth, R.S. 1975. Temporary
Canadian Geotechnical Journal, 43(6): 638–652. doi:10.1139/ excavations in varved clay. Journal of the Geotechnical Division,
T06-021. ASCE, 101(GT3): 279–295.
Fang, Z., and Yin, J.H. 2007. Response of excess pore water pressure Ng, C.W.W. 1998. Observed performance of multipropped excavation
in soft marine clay around a soil-cement column. International in stiff clay. Journal of Geotechnical and Geoenvironmental
Journal of Geomechanics, 7(3): 167–175. doi:10.1061/(ASCE) Engineering, 124(9): 889–905. doi:10.1061/(ASCE)1090-0241
1532-3641(2007)7:3(167). (1998)124:9(889).
Finno, R.J., and Bryson, L.S. 2002. Response of building adjacent to NGI. 1962. Measurements at a strutted excavation, Oslo Subway,
For personal use only.

stiff excavation support system in soft clay. Journal of Performance Vaterland 1. Norwegian Geotechnical Institute (NGI), Oslo,
of Constructed Facilities, 16(1): 10–20. doi:10.1061/(ASCE)0887- Norway. Technical Report 6.
3828(2002)16:1(10). Nicholson, D.P. 1987. The design and performance of the retaining
Finno, R.J., and Harahap, I.S. 1991. Finite element analysis of HDR-4 walls at Newton station. In Proceedings of the Singapore Mass
excavation. Journal of Geotechnical Engineering, 117(10): 1590– Rapid Transit Conference, Singapore, 6–9 April 1987. Singapore
1609. doi:10.1061/(ASCE)0733-9410(1991)117:10(1590). Mass Rapit Transit. pp. 147–154.
Finno, R.J., Atmatzidis, D.K., and Perkins, S.B. 1989. Observed O’Rourke, T.D. 1981. Ground movements caused by braced
performance of a deep excavation in clay. Journal of Geotechnical excavations. Journal of the Geotechnical Engineering Division,
Engineering, 115(8): 1045–1064. doi:10.1061/(ASCE)0733-9410 ASCE, 107(9): 1159–1178.
(1989)115:8(1045). O’Rourke, T.D., Cording, E.J., and Boscardin, M. 1976. The ground
Hashash, Y.M.A. 1992. Analysis of deep excavations in clay. Ph.D. movements related to braced excavation and their influence on
thesis, Department of Civil Engineering, Massachusetts Institute adjacent structures. University of Illinois report for U.S. Depart-
of Technology (MIT), Cambridge, Mass. ment of Transportation, Washington, D.C. Report No. DOT-TST-
Hsieh, P.-G., and Ou, C.-Y. 1998. Shape of ground surface settlement 76T-22.
profiles caused by excavation. Canadian Geotechnical Journal, 35 Ou, C.Y., and Chiou, D.C. 1993. Three-dimensional finite element
(6): 1004–1017. doi:10.1139/cgj-35-6-1004. analysis of deep excavation. In Proceedings of 11th Southeast Asia
Hulme, T.W., Potter, J., and Shirlaw, N. 1989. Singapore MRT Geotechnical Conference, Singapore, 4–8 May 1993. The Institu-
system: construction. Proceedings – Institution of Civil Engineers, tion of Engineers, Malaysia, Kuala Lumpur, Malaysia. pp. 769–
86: 709–770. 774.
Kung, G.T.C., Juang, C.H., Hsiao, E.C.L., and Hashash, Y.M.A. Ou, C.-Y., and Shiau, B.-Y. 1998. Analysis of the corner effect on
2007. Simplified model for wall deflection and ground-surface excavation behaviors. Canadian Geotechnical Journal, 35(3): 532–
settlement caused by braced excavation in clays. Journal of 540. doi:10.1139/t98-013.
Geotechnical and Geoenvironmental Engineering, 133(6): 731– Ou, C.-Y., Hsieh, P.-G., and Chiou, D.-C. 1993. Characteristics of
747. doi:10.1061/(ASCE)1090-0241(2007)133:6(731). ground surface settlement during excavation. Canadian Geotech-
Ladd, C.C., Foott, R., Ishihara, K., Schlosser, F., and Poulos, H.G. nical Journal, 30(5): 758–767. doi:10.1139/t93-068.
1977. Stress-deformation and strength characteristics. In Proceed- Ou, C.Y., Liao, J.T., and Lin, H.D. 1998. Performance of diaphragm
ings of the 9th International Conference on Soil Mechanics and wall constructed using the top-down method. Journal of
Foundation Engineering, Tokyo, 10–15 July 1977. Japanese Geotechnical and Geoenvironmental Engineering, 124(9): 798–
Society of Soil Mechanics and Foundation Engineering, Tokyo. 808. doi:10.1061/(ASCE)1090-0241(1998)124:9(798).
Vol. 2, pp. 421–494. Peck, R.B. 1969. Deep excavation and tunneling in soft ground. In
Leung, E.H.Y., and Ng, C.W.W. 2007. Wall and ground movements Proceedings of 7th International Conference on Soil Mechanics
associated with deep excavations supported by cast-in-situ wall in and Foundation Engineering, Mexico City, Mexico, 25–29 August
mixed ground condition. Journal of Geotechnical and Geoenvir- 1969. A.A. Balkema, Rotterdam, the Netherlands. State-of-the-art
onmental Engineering, 133(2): 129–143. doi:10.1061/(ASCE) volume, pp. 225–281.
1090-0241(2007)133:2(129). Reed, M.W. 1980. Observed behaviors of an excavation in an
Lim, K.W., Wong, K.S., Orihara, K., and Ng, P.B. 1977. Comparison unusually soft San Francisco Bay Mud deposit. Doctoral thesis,
of results of excavation analysis using WALLUP, SAGE CRISP Stanford University, Stanford, Calif.

Published by NRC Research Press


Tan and Li 719

Seo, M.W., Olson, S.M., Yang, K.S., and Kim, M.M. 2010. International Conference on Retaining Structures, Cambridge, UK,
Sequential analysis of ground movements at three deep excavation July 1992. Thomas Telford, London. pp. 195–204.
sites with mixed soil conditions. Journal of Geotechnical and Wang, Z.W., Ng, C.W.W., and Liu, G.B. 2005. Characteristics of wall
Geoenvironmental Engineering, 136(5): 656–668. doi:10.1061/ deflections and ground surface settlements in Shanghai. Canadian
(ASCE)GT.1943-5606.0000257. Geotechnical Journal, 42(5): 1243–1254. doi:10.1139/t05-056.
Singh, S., Sivakugan, N., and Shukla, S.K. 2010. Can soil arching be Whittle, A.J., Hashash, Y.M.A., and Whitman, R.V. 1993. Analysis
insensitive to f? International Journal of Geomechanics, 10(3): of deep excavation in Boston. Journal of Geotechnical Engineering,
124–128. doi:10.1061/(ASCE)GM.1943-5622.0000047. 119(1): 69–90. doi:10.1061/(ASCE)0733-9410(1993)119:1(69).
Tait, R.G., and Taylor, H.T. 1974. Design construction and Xu, Z.H. 2007. Deformation behavior of deep excavations supported
performance of rigid and flexible bracing systems for deep by permanent structures in Shanghai soft deposit. Doctoral thesis,
excavations in San Francisco Bay Mud. In Proceedings of the Shanghai Jiao Tong University, Shanghai, China. [In Chinese.]
ASCE National Meeting, Los Angeles, Calif. American Society of Yildiz, A., Karstunen, M., and Krenn, H. 2009. Effects of anisotropy
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Tennessee on 05/15/13

Civil Engineers (ASCE), New York. pp. 1403–1405. and destructuration on behavior of Haarajoki test embankment.
Tan, Y., and Wei, B. 2011. Observed behaviors of a long and deep International Journal of Geomechanics, 9(4): 153–168. doi:10.
excavation constructed by cut-and-cover technique in Shanghai 1061/(ASCE)1532-3641(2009)9:4(153).
soft clay. Journal of Geotechnical and Geoenvironmental En- Yin, J.-H., and Cheng, C.-M. 2006. Comparison of strain-rate
gineering. (Posted online ahead of print 14 April 2011.) doi:10. dependent stress–strain behavior from Ko-consolidated compres-
1061/(ASCE)GT.1943-5606.0000553. sion and extension tests on natural Hong Kong marine deposits.
Wallace, J.C., Ho, C.E., and Long, M. 1992. Retaining wall behaviour Marine Georesources and Geotechnology, 24(2): 119–147. doi:10.
for a deep basement in Singapore clay. In Proceedings of the 1080/10641190600704780.
For personal use only.

Published by NRC Research Press

You might also like