CONDUIT PIPE
Page 1 of 7
TANJUNG JATI B EXPANSION (JAWA-4)
COAL FIRED STEAM POWER PLANT 2 x 1,000MW
Contents
A. PURPOSE ................................................................................................................................. 3
B. SCOPE OF WORK .................................................................................................................. 3
C. REFERENCE DOCUMENT .................................................................................................... 3
D. PROCEDURE ........................................................................................................................... 3
E. EQUIPMENT ................................................................................................................................. 6
F. SAFETY ......................................................................................................................................... 7
G. ATTACHMENT ......................................................................................................................... 7
A. PURPOSE
This document is issued for guidance of Excavation Work for Cable Route of CCTV
and Communication System at Coal Yard in Tanjung Jati B Expansion (Java-4) Coal
Fired Steam Power Plant project.
B. SCOPE OF WORK
This method statement describes a proper work procedure shall be carried out during
the excavation stage as per specification drawings.
C. REFERENCE DOCUMENT
a. Drawing TJB56-L4-OFF-C-CSC-I-DRD-0303 Outdoor Cable Route for CCTV &
Communication System at Coal Yard Area
D. PROCEDURE
a. Material & Site Preparation
b. Excavation
c. Backfilling work
d. Installation Inspection
STEP 1.
PREPARATION
SITE ENGINEERING
- Check layout drawing
- Prepare the Material
STEP 2.
EXCAVATION
EXCAVATION
· MarkArea
· Digging
· Check the depth
NO
INSPECTION
YES
BACKFILLING
· 1st Layer of Sand
· HDPE Pipe
· 2nd Layer of Sand
· Concrete Tile
· Backfilling using excavation
material
· Warning Tape
· Backfilling using excavation
material
FINISH
WORK PROCEDURE
2.4. All excavated material shall be kept a minimum of 1.0 meter from the
edge of excavation
c. Backfilling Work
Backfilling shall commence using similar excavated material. Backfilling work
need to be done for the following:
1. A layer of sand will be introduced at bottom of trench
2. The direct buried cables pipe will be laid on the sand layer and shall be
separated based on the cable route classification
3. Appropriate concrete or tile covers will be provided between the ground
and buried cables along the direct burial cable route
4. The marking of cable routes with warning tapes or sign poles will be
provided for direct buried cables
5. Back filling using similar excavated material followed with compaction
shall continue till final level is achieved
d. Inspection
Inspection of Excavation Work should be accomplished & recorded by designer,
supervisor and owner. Acceptance of project should be processed step by step
and the quality of the process should meet the design requirement.
Inspection will be held during the activity until the end of Excavation Work. The
sequence for inspection is:
1. Visual check during installation and after finish installation
During pipe installation, visual check for installation should be held by QC
team and followed by Supervisor & Owner team.
Visual check item for this sequence such as:
a. Check for pipe Orientation and alignment
b. Coordinate & elevation
E. EQUIPMENT
Equipment for Excavation Work such as:
F. SAFETY
During a work sequence started, the safety sign should be apply include road
barricade
Worker should be follow safety tool box meeting before to work
Safety man and supervisor should be supervised all of time
APD (Alat Pelindung Diri) :
o Safety Helmet
o Safety Glasses
o Safety Shoes
o Gloves
G. ATTACHMENT
1. Drawing TJB56-L4-OFF-C-CSC-I-DRD-0303 Outdoor Cable Route for CCTV &
Communication System at Coal Yard Area