You are on page 1of 7

METHOD STATEMENT FOR INSTALLATION OF Issued Date : 23-May-19

CONDUIT PIPE
Page 1 of 7
TANJUNG JATI B EXPANSION (JAWA-4)
COAL FIRED STEAM POWER PLANT 2 x 1,000MW

METHOD STATEMENT FOR EXCAVATION WORK IN


THE COAL YARD AREA

Doc Ref : NCISW-CS-019-18-MTD


METHOD STATEMENT FOR INSTALLATION OF Issued Date : 23-May-19
CONDUIT PIPE
Page 2 of 7
TANJUNG JATI B EXPANSION (JAWA-4)
COAL FIRED STEAM POWER PLANT 2 x 1,000MW

Contents
A. PURPOSE ................................................................................................................................. 3
B. SCOPE OF WORK .................................................................................................................. 3
C. REFERENCE DOCUMENT .................................................................................................... 3
D. PROCEDURE ........................................................................................................................... 3
E. EQUIPMENT ................................................................................................................................. 6
F. SAFETY ......................................................................................................................................... 7
G. ATTACHMENT ......................................................................................................................... 7

Doc Ref : NCISW-CS-019-18-MTD


METHOD STATEMENT FOR INSTALLATION OF Issued Date : 23-May-19
CONDUIT PIPE
Page 3 of 7
TANJUNG JATI B EXPANSION (JAWA-4)
COAL FIRED STEAM POWER PLANT 2 x 1,000MW

A. PURPOSE
This document is issued for guidance of Excavation Work for Cable Route of CCTV
and Communication System at Coal Yard in Tanjung Jati B Expansion (Java-4) Coal
Fired Steam Power Plant project.

B. SCOPE OF WORK
This method statement describes a proper work procedure shall be carried out during
the excavation stage as per specification drawings.

C. REFERENCE DOCUMENT
a. Drawing TJB56-L4-OFF-C-CSC-I-DRD-0303 Outdoor Cable Route for CCTV &
Communication System at Coal Yard Area

D. PROCEDURE
a. Material & Site Preparation
b. Excavation
c. Backfilling work
d. Installation Inspection

Doc Ref : NCISW-CS-019-18-MTD


METHOD STATEMENT FOR INSTALLATION OF Issued Date : 23-May-19
CONDUIT PIPE
Page 4 of 7
TANJUNG JATI B EXPANSION (JAWA-4)
COAL FIRED STEAM POWER PLANT 2 x 1,000MW

General Flow Chart

STEP 1.
PREPARATION
SITE ENGINEERING
- Check layout drawing
- Prepare the Material

STEP 2.
EXCAVATION

EXCAVATION
· MarkArea
· Digging
· Check the depth
NO

INSPECTION

YES

BACKFILLING
· 1st Layer of Sand
· HDPE Pipe
· 2nd Layer of Sand
· Concrete Tile
· Backfilling using excavation
material
· Warning Tape
· Backfilling using excavation
material

FINISH

Doc Ref : NCISW-CS-019-18-MTD


METHOD STATEMENT FOR INSTALLATION OF Issued Date : 23-May-19
CONDUIT PIPE
Page 5 of 7
TANJUNG JATI B EXPANSION (JAWA-4)
COAL FIRED STEAM POWER PLANT 2 x 1,000MW

WORK PROCEDURE

a. Material & Site Preparation


1. Preparation of engineering data such as :
1.1. Approved Shop drawing :
TJB56-L4-OFF-C-CSC-I-DRD-0303 Outdoor Cable Route for CCTV &
Communication System at Coal Yard Area
1.2. Preparation of equipment and tools required for Excavation
1.2.1. Equipment and tools needed :
1.2.1.1. Hoe, Fork Hoe
1.2.1.2. Meter Tape
1.2.1.3. Shovel
1.2.1.4. Generator
1.2.1.5. Safety Equipment like Safety Shoes and Gloves
1.2.2. Preparation of manpower :
1.2.2.1. Digger
1.2.2.2. Helper
1.2.2.3. Supervisor
b. Excavation
1. General
1.1. Tools & Raw Material
1.1.1. Tools/Equipment
Hoe, Fork Hoe, Shovel, Meter Tape, Generator and Safety
Equipment.
1.1.2. Materials
· Sand
· HDPE Corrugated Pipe
· Warning Tape
· Tile
2. Excavation
2.1. The area to be excavated shall be properly marked and clear before
starting the works
2.2. The digger starts digging the ground using tools and equipment
2.3. The depth of excavation shall be periodically checked to avoid over
excavation.

Doc Ref : NCISW-CS-019-18-MTD


METHOD STATEMENT FOR INSTALLATION OF Issued Date : 23-May-19
CONDUIT PIPE
Page 6 of 7
TANJUNG JATI B EXPANSION (JAWA-4)
COAL FIRED STEAM POWER PLANT 2 x 1,000MW

2.4. All excavated material shall be kept a minimum of 1.0 meter from the
edge of excavation
c. Backfilling Work
Backfilling shall commence using similar excavated material. Backfilling work
need to be done for the following:
1. A layer of sand will be introduced at bottom of trench
2. The direct buried cables pipe will be laid on the sand layer and shall be
separated based on the cable route classification
3. Appropriate concrete or tile covers will be provided between the ground
and buried cables along the direct burial cable route
4. The marking of cable routes with warning tapes or sign poles will be
provided for direct buried cables
5. Back filling using similar excavated material followed with compaction
shall continue till final level is achieved
d. Inspection
Inspection of Excavation Work should be accomplished & recorded by designer,
supervisor and owner. Acceptance of project should be processed step by step
and the quality of the process should meet the design requirement.
Inspection will be held during the activity until the end of Excavation Work. The
sequence for inspection is:
1. Visual check during installation and after finish installation
During pipe installation, visual check for installation should be held by QC
team and followed by Supervisor & Owner team.
Visual check item for this sequence such as:
a. Check for pipe Orientation and alignment
b. Coordinate & elevation

E. EQUIPMENT
Equipment for Excavation Work such as:

1. Hoe, Fork Hoe


2. Generator
3. Gloves
4. Safety Equipment like Safety Shoes and Helmet

Doc Ref : NCISW-CS-019-18-MTD


METHOD STATEMENT FOR INSTALLATION OF Issued Date : 23-May-19
CONDUIT PIPE
Page 7 of 7
TANJUNG JATI B EXPANSION (JAWA-4)
COAL FIRED STEAM POWER PLANT 2 x 1,000MW

F. SAFETY
 During a work sequence started, the safety sign should be apply include road
barricade
 Worker should be follow safety tool box meeting before to work
 Safety man and supervisor should be supervised all of time
 APD (Alat Pelindung Diri) :
o Safety Helmet
o Safety Glasses
o Safety Shoes
o Gloves

G. ATTACHMENT
1. Drawing TJB56-L4-OFF-C-CSC-I-DRD-0303 Outdoor Cable Route for CCTV &
Communication System at Coal Yard Area

Doc Ref : NCISW-CS-019-18-MTD