Construction of Sewage Treatmeny Plant of Capacity 37 MLD on DBO Basis for

Project
UGSS in Tiruchirappalli City Corporation

Document Prepared Checked Approved Rev


Number RKK VJ GM 0
Structural Design Calculation of "Chlorine Contact Tank,Chlorine & Tonner
Title
Room,Overflow Tank .

3.1 Hydrodynamic Calculation

Unit Weights

Unit Weight of Reinforced Cement Concrete =25.0 kN/m3


Unit Weight of Plain Cement Concrete =24.0 kN/m3
Unit Weight of Cement Plaster =21.0 kN/m3
Floor Finish =24.0 kN/m3
Foam Concrete =10.0 kN/m3

Level Details

Future Ground Level =3.5 m


Top of Wall =3.5 m
Top of Raft =0.0 m
Maximum water Level =3.5 m

Dimension Details
Base Slab Projection
Length of the Wall =27.0 m L B
Breadth of the Wall =11.0 m =0.75 =1.40
Height of the Wall =3.5 m
Height of the Water =3.5 m
Thickness of the Base slab =0.30 m Varying Height (m)
Thickness of Wall Height 1 =0.45 m h1 =1.00
Thickness of Wall Height 2 =0.35 m h2 =1.00
Thickness of Wall Height 3 =0.35 m h3 =1.50
Average Wall Thickness =0.38 OK

Material Properties

Grade of the Concrete =30.00 N/mm2


Grade of the Steel =500.00 N/mm2
Youngs Modulus of the Concrete 27386.13 N/mm2
Youngs Modulus of the Steel 200000.00 N/mm2
Construction of Sewage Treatmeny Plant of Capacity 37 MLD on DBO Basis for
Project
UGSS in Tiruchirappalli City Corporation

Document Prepared Checked Approved Rev


Number RKK VJ GM 0
Structural Design Calculation of "Chlorine Contact Tank,Chlorine & Tonner
Title
Room,Overflow Tank .

3.2 Weight Calculation & Mass Calculation


Length Breadth Depth Unit Weight Weight Mass
S.No Details Nos
(m) (m) (m) kN/m3 kN Kg
1 Long Wall 27 0.383333 3.5 2 25 1811.25 184633
2 Short Wall 11 0.383333 3.5 2 25 737.9167 75220.86
3 Base Slab 28.5 12.5 0.3 1 25 2671.875 272362.4
4 Water 27 11 4 1 10 11880 1211009

Total Seismic Wight of the tank 17101.04 k N

a) Weight of tank wallwwall = 2549.167 kN


b) Mass of tank wall mwall = 2.6E+05 kg
c) Weight of Base Slabwbase = 2671.875 kN
d) Mass of Base Slab mbase = 272362 kg
e) Weight of the waterwwater = 11880 kN
f) Mass of Water mwater = 1211009 kg
Construction of Sewage Treatmeny Plant of Capacity 37 MLD on DBO Basis for
Project
UGSS in Tiruchirappalli City Corporation

Document Prepared Checked Approved Rev


Number RKK VJ GM 0
Structural Design Calculation of "Chlorine Contact Tank,Chlorine & Tonner
Title
Room,Overflow Tank .
Along "X" direction
3.30 Parametric Spring Model
h/L = 0.13 L/h 7.714286
mi / m = tanh((0.866*L/h)/(0.866*L/h))
mc / m = 0.264*tanh((3.16*h/L)/(h/L))
hi / h = 0.375 For h/L<= 0.75
hi / h = 0.5-(0.09375)/(h/L) For h/L> 0.75
= -0.22321
h* i / h = 0.866*(L/h)/(2*tanh*(0.866)*(L/h) For h/L<= 1.33
= 0.619159
h* i / h = 0.45 For h/L> 1.33
hc / h = 1-((cosh(3.16*h/L)-1.0)/(3.16*h/L*sinh(3.16*h/L))
hc / h = 0.507
h* c / h = 1-((cosh(3.16*h/L)-2.01)/(3.16*h/L*sinh(3.16*h/L))
h* c / h = 6.361
Therefore,
hi / h = 0.375 hi 1.32 m
h* i / h = 0.619159 h* i 2.17 m
mi / m = 0.149687 mi 181272.7 Kg
mc / m = 0.790512 mc 957317.1 Kg
hc / h = 0.507 hc 1.7745 m
h* c / h = 6.361 h* c 22.2635 m
Construction of Sewage Treatmeny Plant of Capacity 37 MLD on DBO Basis for
Project
UGSS in Tiruchirappalli City Corporation

Document Prepared Checked Approved Rev


Number RKK VJ GM 0
Structural Design Calculation of "Chlorine Contact Tank,Chlorine & Tonner
Title
Room,Overflow Tank .

3.4 Time Period of Impulsive Mode


Time period of Impulsive Ti = 2*Pi()*sqrt((d/g))
d-deflection of tank wall on the vertical centre line at a height ℎ  
q-Unifromly distributed Pressure
Where ℎ  =  (�_�/2 
ℎ_�+�  _�  ℎ/2)/
(�_�/2+�  _� )

�  _� =mass of one tank wall perpendiculat to direction of loading

= b*t*25*1000 / 9.81

= 3761.043 kg

ℎ   = 1.338 m
q=  (�_�/2+�  _� )�/𝐵ℎ

q = 24.05 kN/m2
Deflection per unit width of strip:
Considered as cantilever and subjected to concentrated force P= qxhx1 84.175 kN
With the length of cantilever =ℎ  

Iw = 0.00469 m4
d= Ph^3/3EIw d = 0.001 m
Ti = 0.046 sec
Time Period of Convective Mode
Tc = Cc*Sqrt(L/g)

Cc 2*PI()
=
Sqrt(3.16*tanh(3.16*(h/L))

Cc = 5.68

Tc = 9.43 sec
Construction of Sewage Treatmeny Plant of Capacity 37 MLD on DBO Basis
Project
for UGSS in Tiruchirappalli City Corporation

Document PrepareChecked Approved Rev


Number RKK VJ GM 0
Structural Design Calculation of "Chlorine Contact Tank,Chlorine & Tonner
Title
Room,Overflow Tank .
5.1 Design Horizontal Seismic Co-efficient
Impulsive Mode Convective Mode
Ahi = (Z*I / 2R) * (Sa/g) Ahc = (Z*I / 2R) * (Sa/g)
Z = 0.16 Zone 3 Z = 0.16 Zone 3
I = 1.5 I = 1.5
R = 2 Ref.,Table 2 IS 1893 R = 2 Ref.,as per Cl.4.5.1
Soil type = Hard Soil type = Hard
Damping = 5% Damping = 5%
Ti = 0.05 secs Tc = 9.43 secs
Sa/g = 1.75 secs Sa/g = 0.19 secs
Therefore Therefore
Ahi = 0.42 Ahc = 0.0456
Base Shear
Impulsive Case
Vi = Ahi*(mi+mw+mt)g
Vi = 1817.53 kN
Convective Case
Vc = Ahc*mc*g
Vc = 428.25 kN
Total base shear at the bottom of wall(v) = Sqrt(Vi^2+Vc^2)
= 1867.301 kN
Percentage weight of lateral base shear = 12.95 %
Moment at bottom of wall
Impulsive Case
Mi = Ahi*(mi*hi+mw*hw+mt*ht)g
Mi = 3494.367 kNm
Convective Case
Mc = Ahc*mc*hc*g
Mc = 759.9161 kNm
Total bending moment at the base of the wall (M) = Sqrt(Mi^2+Mc^2)
= 3576.041 kNm
Overturning Moment at the base of base slab
Impulsive Case
Mi* = (Ah)i [mi(hi*+tb) + mw(hw+tb) + mt(ht+tb) + mbtb/2] g
Mi* = kNm
Convective Case
Mc* = Ahc*mc*hc*+tb*g
Mc* = kNm
Total bending moment at the base of the wall (M) = Sqrt(Mi^2+Mc^2)
= 0 kNm