Professional Documents
Culture Documents
Transmission System which shall include, but not limited to, the following:
Proposed new grid substations and substation augmentations
Proposed transmission line/cable additions and reinforcements
Network expansion and reconfigurations
Reactive power compensation
Any other improvements
(v) A comprehensive list of proposed large and small capital expenditure to be incurred in each
year, and the specific impacts expected by each investment.
Small capital expenditure shall be defined as expenditure, either on a line, a
substation or associated transmission equipment, not exceeding LKR 500
million including all project-related expenditure, customs duty and taxes.
(vi) Unit block basis costs of transmission system components.
(vii) Costs of the proposed investments, and the annual investment requirements, with clear
indications of
investment requirements in each year
taxes and other expenses expected
system components
(viii) Analysis of the status of ancillary services, especially reactive power balance and spinning
reserve, black start, line charging and the plan to address the related issues.
The main objective of these studies is to identify the under-rated switchgear, to carry out the
necessary protection studies and to formulate action plans to remedy the situation. The Transmission
Licensee shall keep the relevant system users informed of the fault level details.
Based on the above studies, the Transmission Licensee shall prepare a report explaining the effect of
fault levels on system equipment and the remedial action proposed to ensure that all equipment used
in the Transmission System are within the design limits.
Three phase and single phase design fault levels of the Transmission System and also of the
Distribution system are given in the Table PC -1.
It is planned to limit the maximum three phase circuit currents at the 33 kV and 11 kV bus bars of
any grid substation, in order to protect the elements in the downstream distribution network