You are on page 1of 43

EXCAVATION WORKS

1. Excavation:

a. Column Footing

V1= (1m) (1m) (0.75 m + 0.325 m) V= (0.5 m) (0.5m) (0.5m)

=1.075 m3 x10column footings = 0.125 m3 x 5 catch basins

= 10.75m3 = 0.625 m3

V2= (0.8m) (0.8m) (0.75 m + 0.325 m)

= 0.688m3 x 2 column footings 2. BACKFILLING

= 1.376 m3
a. Column Footing
b. Wall Footing
V1 = 10.75m3-(10)[(1m x 1m)(0.325)-
P= 63.17 m (0.75)(0.25m x 0.25m)](10 C/F)

Depth= 0.4 + 0.2 = 0.6 m = 7.03 m3

Width= 0.4 m b. Wall Footing

V= 63.17 m (0.6 m) (0.4m V = 15.16 m3— [ (63.17m x 0.4m x


0.2m)-0.4(63.17m x 0.1m)]
= 15.16m3
= 7.58 m3
c. SEPTIC TANK

Depth = 0.2m + 1.7m= 1.9 m

Width = 1.10m

Length = 1.80m

V= (1.9m) (1.10m) (1.80m)

= 3.762 m3

d. CATCH BASIN

Depth = 0.50 m
Width = 0.50m

Length = 0.50m
Outside Wall Area 1 total :18.44 +19.19+31.79+31.71
Front: Area 1 total= 101.13m2
Area 1: [8m-0.25(3)m]*3.3m=23.95m2 Area 2 total: 2.9 + 2.9 + 4.8 + 4.5
Window: 1.63m*1.2m=1.956m2 Area 2 total= 15.1m2
Door: 1.68m*2.1m=3.528m2 Outside Wall Total: 101.13 + 15.1 =
116.23m2
Area 1=18.44m2
Area 2: [8m-0.25(3)m]*0.4m=2.9m2
Inner Wall
Rear: Area 1: [11.5m-
0.25(3)m]*3.3m=35.475m2
Area 1: [8m-0.25(3)m]*3.3m=23.95m2
Door: 0.78m*2.1m=1.638m2
Window: 1.63m*1.2m=1.956m2 0.68m*2.1m=1.42m2
1.63m*0.7m=1.141m2 Area 1=32.41m2
Door: 0.78m*2.1m=1.638m2 Area 2: [11.5m-0.25(3)m]*0.4m=4.3m2
Area 1=19.19m2
Area 2: [8m-0.25(3)m]*0.4m=2.9m2 Width: [4m-0.13(2)m]*3=11.22m
Area 1: 11.22m*3.3m=37.026m2
Left: Door: 0.78m*2.1m*2=3.276m2
Area 1: [13m-0.25(3)m]*3.3m=39.6 m2 Area 1= 33.75 m2
Window: 0.83m*1.2m=0.996 m2 Area 2: 11.22m*0.4m=4.488 m2
0.6m*0.7m*2=0.84 m2
1.63m*1.2m*2=3.912 m2 Toilet:
Door: 0.98m*2.1m=2.058 m2 Area 1: 2m(3.3m)+1.3m(3.3m)-
0.68m(2.1m)=9.426 m2
Area 1= 31.79 m2
Area 2: 2m(0.4m)+1.3m(0.4m)=1.32 m2
Area 2: [13m-0.25(3)m]*0.4m=4.8 m2
Area 1 Total: 32.41 + 33.75 + 9.426
Area 1 Total: 75.62 m2
Right:
Area 2 Total: 4.3 + 4.488 +1.32
Area 1: [12m-0.25(3)m]*3.3m=37.1 m2
Area 2 Total: 10.11 m2
Window: 2.4m*1.2m=2.88 m2
1.63m*1.2m=1.956 m2
Final Area of Wall: Area outside +
0.83m*0.7m=0.581 m2 Area inside
Area 1=31.71 m2 Area 1: 101.13m2+75.62m2= 176.75 m2
Area 2: [12m-0.25(3)m]*0.4m=4.5 m2 Area 2: 15.1m2+10.11m2= 25.21 m2
MASONRY WORKS

1. Walls
No. of CHB for Area 1: 176.75m2*12.5pcs/m2= 2209.38pcs
No. of CHB for Area 2: 25.21m2*12.5pcs/m2= 315.13pcs
Total # of CHB = 2524.51pcs say 2525pcs
@3% allowance
2525*1.03=2600.75pcs say 2601pcs

For 1 CHB: Use 0.10m x 0.2m x 0.4m


Vbl = 0.0125m*0.10m*0.4m = 0.0005 m3
Vf = 0.075m*0.05m*0.2m*4 = 0.003 m3
Vp = 0.0125m*0.2m*0.4m*2 = 0.002 m3
For Vbl + Vf :

0.0005m3 + 0.003m3 = 0.0035 m3

For Vbl + Vf + Vp :

0.0035m3 + 0.002m3 = 0.0055 m3

For Area 1:

V1: 2210pcs*0.0055 m3/pc = 12.16 m3

For Area 2:

V2: 315pcs*0.0035 m3/pc = 1.10 m3

Total Volume = 13.26 m3

Using Class “B’’ of (Table 2-1)

Cement: 13.26 m3*12bags/ m3= 159.12bags

C.Sand: 13.26 m3*1.0 = 13.26 m3


2. Septic Vault

Width: 1.1m
Length: 2.6m
Depth: 1.7m

Area = ( 1.1m + 2.6m ) * 1.7 = 6.29 m2

No. of CHB: 6.29 m2 *12.5pcs/m^2 = 78.63 pcs say 79 pcs

For 1 CHB: Use 0.10m x 0.2m x 0.4m


Vbl = 0.0125m*0.10m*0.4m = 0.0005m3
Vf = 0.075m*0.05m*0.2m*4 = 0.003 m3
Vp= 0.0125m*0.2m*0.4m*1 = 0.001 m3
For Vbl + Vf :

0.0005 m3 + 0.003 m3= 0.0035 m3

For Vbl + Vf + Vp :

0.0035 m3 + 0.001 m3 = 0.0045 m3

Volume: 79 pcs*0.0045/pc = 0.356 m3

Using Class “B’’ of (Table 2-1)

Cement: 0.356 m3*12bags/ m3 = 4.27 bags

C.Sand: 0.356m3*1.0 = 0.356 m3


FOR TILE MORTAR

GLAZED TILES:

* Wall for Kitchen Counter and Comfort Room:

From Table 7-1, 0.11bags/m2

Tile Adhesive:

x 0.11 bags
=
18.99 m2 1m2

= 2.09 bags, say 2.25 bags

* Flooring:

From Table 7-1, 0.086 bags/m2

Cement for Mortar:

x 0.086 bags
=
99. 21 m2 1m2

= 8.53 bags, say 9 bags

From Table 7-1, 0.50kg/m2

White Cement for Joint Filler:

x 0.50kg
=
123.44 m2 1m2

= 61.72 kg

61.72 kg
= 1.54 bags
40kg/bag

= 2 bags
CONCRETING WORKS

1. Wall Footing: Volume total: 0.572m^3*10=5.72m3

W=0.4m , t=0.2m C2/F2

Outside Length: V1: 0.15m*0.15m*4.35m= 0.10m3

L: 7.25m+7.25m+12m+11.25m = V2: 0.3m*0.8m*0.8m= 0.19 m3


37.75m
Volume total: 0.29 m3*2 = 0.58 m3
Inside Length:
Volume Total:
L: 10.75-0.78-0.68=9.29m
5.72 m3+ 0.58 m3= 6.28 m3
11.22-2(0.78) = 9.66m

2+1.3-0.68 = 2.62m
Using Class “B’’ of ( Table 1-2 )
=21.57m
Cement: 6.28m3*7.5bags/m3= 47.1bags
Total Length: 37.75m+21.57m = 59.32m
C .Sand: 6.28 m3 * 0.5= 3.14m3
V: 0.4m*0.2m*59.32m= 4.75 m3
Gravel: 6.28 m3 * 1.0= 6.28 m3

Using Class “B’’ of ( Table 1-2 )


Summary:
Cement: 4.75m3 *7.5bags/m3
Cement: -------------------------- 47.1 bags
= 35.63bags
C.Sand: --------------------------- 3.14 m3
C .Sand: 4.75 m3*0.5= 2.38m3
Gravel: ---------------------------- 6.28 m3
Gravel: 4.75m3*1.0= 4.75m3

3. Concrete Slab
Summary:
Area Left: 4m*11.5m = 46m2
Cement: ------------------------- 35.63 bags
Area Right: 4m*12m = 48 m2
C.Sand: -------------------------- 2.38m3
Area Laundry: 1m*1.2m = 1.2 m2
Gravel: --------------------------- 4.75 m3
Area = 95.2 m2

Column: 0.25m*0.25m*10 = 0.625 m2


2. For Column and Footing
Area Total = 94.58m2
C1/F1
Thickness 4” = 0.10m
V1: 0.25m*0.25m*4.35m= 0.272 m3
Volume: 94.58m^2*0.10m = 9.46 m3
V2: 0.3m*1m*1m= 0.3 m3
Gravel Base: Using Class “B’’ of ( Table 1-2 )

Thickness 1” = 0.025m Cement: 1.4m3 * 7.5bags/m3

Volume: 94.58 m2 * 0.025m = 2.36 m3 = 10.5bags

C .Sand: 1.4m3 * 0.5= 0.7m3

Using Class “B’’ of ( Table 1-2 ) Gravel: 1.4m3*1.0= 1.4 m3

Cement: 9.46m3*7.5bags/m3 Summary:

= 70.95bags Cement: ------------------------ 87.08 bags

C .Sand: 9.46m3*0.5 = 4.73m3 C.Sand: -------------------------- 5.8 m3

Gravel: 9.46m3 + 2.36m3*1.0 = 11.82m3 Gravel: -------------------------- 18.7 m3

Porch: 4. Septic Vault

Area: 2.5m*4m = 10 m2 Slab:

Column: 0.15m*0.15m*2 = 0.045 m2 Area = 2.6 m * 1.1 m = 2.86 m2

Area Total = 9.96 m2 Thickness: 0.10m

Thickness 4” = 0.075m Volume = 2.86m2 * 0.10m

Volume: 9.96 m2 * 0.075m = 0.75 m3 = 0.286 m3

Using Class “B’’ of ( Table 1-2 ) Using Class “B’’ of ( Table 1-2 )

Cement: 0.75m3*7.5bags/m3 = 5.63bags Cement: 0.286m3 * 7.5bags/m3

C .Sand: 0.75m3*0.5 = 0.37m3 = 2.15 bags

Gravel: 0.75 m3*1.0 = 0.75 m3 C .Sand: 0.286m3 *0.5= 0.143 m3

Gravel: 0.286m3 * 1.0= 0.286 m3

Garage Cover 1:

Area: 7m*4m = 28m2 Volume: 0.39m * 0.39m * 0.10m

Thickness: 0.05m = 0.015 m3

Volume: 28 m2 *0.05m = 1.4 m3

Using Class “B’’ of ( Table 1-2 )

Cement: 0.015 m3 * 7.5bags/m3

= 0.1125 bags

C .Sand: 0.015 m3 * 0.5= 0.0075 m3

Gravel: 0.015 m3 * 1.0= 0.015 m3


Cover 2: Using Class “B’’ of ( Table 1-2 )

Volume: 0.19m * 0.19m * 0.10m Cement: 0.125 m3 * 7.5bags/ m3

= 0.00361 m3 = 0.94 bags

Volume = 0.00361 m3 * 2 = 0.00722 m3 C .Sand: 0.125 m3 * 0.5= 0.0625 m3

Gravel: 0.125 m3 * 1.0= 0.125 m3

Using Class “B’’ of ( Table 1-2 )

Cement: 0.00722 m3 * 7.5bags/m3  Walls and Slab on Fill:

= 0.054 bags V = {(0.5m) (0.5m) (0.1m) + (0.4m)


(0.4m) (0.1m)} * 5 catch basins
C .Sand: 0.00722 m3 * 0.5= 0.00361 m3
V = 0.21m3
Gravel: 0.00722 m3 * 1.0= 0.00722 m3

Using Class “B’’ of ( Table 1-2 )


Summary:
Cement: 0.21 m3 * 7.5bags/ m3 = 1.58
Cement: ------------------------ 2.32 bags
bags
C.Sand: -------------------------- 0.154 m3
C .Sand: 0.21 m3*0.5= 0.11 m3
Gravel: -------------------------- 0.31 m3
Gravel: 0. 21m3*1.0= 0.21 m3

5. Catch Basin
Summary:

 Cover: Cement: ------------------------ 2.52 bags

V = 0.50m * 0.50m * 0.10m C.Sand: -------------------------- 0.17 m3

V = 0.025m3 x 5 catch basin Gravel: -------------------------- 0.34 m3

V = 0.125m3
METAL REINFORCEMENT WORKS

1. Wall Reinforcement: Stirrups

No. of CHB = 2601 pcs 0.35 – 2(0.075) + 2(0.1) = 0.4 m.


212 x 0.4m. = 84.8 m
Using ( Table 3-5 )
84.8m / 6m = 15 +1
*Vertical Reinforcement SP @ 80cm
= 16 pcs of 10 mm ɸ rebar
201.96 m2 * 1.6m/m2 = 323.136 m

*Horizontal Reinforcement every 3


layers Tie Wires
212 x 0.3m x 2 = 127.2 m.
201.96 m2 * 2.15m/m2 = 434.214 m
X/ 127.2 = 1kg/ 53
Total Length: 323.136m + 434.214m
X = 2.4 kg of tie wire
= 757.35 m

757.35m/6m = 126.225 pcs


Summary:
say 127 pcs of 10 mm ɸ x 6m long
rebars 12 mm ɸ x 6m rebars: -------- 23 pcs

Tie Wire for CHB: 10 mm ɸ x 6m rebars: -------- 16 pcs

Using Table 3-6: 0.60m spacing, 3 Tie wire: ------------------------- 2.4 kg


layers, 30 cm tie

Qty of tie wire:


3. Metal Reinforcement for
(201.96 m2)(0.032kg/m2) = 6.46kg Column and Footing (MAIN
BARS)
Summary:
C1/F1
10 mm ɸ x 6m rebars: -------- 127 pcs
1.Net Length
Tie wire : ------------------------- - 6.46 kg
Ln: 1.0m – 2(0.075) = 0.85m

2. Total number of cuts in one footing


2. Wall Footing
5 x 2 = 10pcs
Using 12 mm ɸ rebar for sides and 10
mm ɸ rebar for stirrups
Perimeter = 63.17m. 3. For 10 footings
(63.17m /6) x 2= 21.06 m. +1 = 22+1 10 x 10 = 100pcs
= 23 pcs. of 12 mm ɸ x 6m rebar 4. 6m/0.85m = 7.06 = 7pcs
(63.17m /0.3) = 211 +1
5. 100pcs/7 = 14.29 pcs
= 212 pcs. of stirrups
Tie Wires Length occupied by 2-2”, 3-3”, 4-4”

5 x 5 = 25 ties 2(0.05m) = 0.10m

25 x 10 x 0.3 = 75m 3(0.075m) = 0.225m

x/75m = 1kg/53m 4(0.10m) = 0.4m

x = 1.43kg 0.725m , 9 deformed lateral ties

Spacing calculations:

C2/F2 48 x 10mm ɸ = 480mm

1.Net Length 16 x 16mm ɸ = 256mm

Ln: 0.8m – 2(0.075) = 0.65m Least width = 200mm ----spaced after


4-4”
2. Total number of cuts in one footing
Spaced left of 0.2 m spacing:
3 x 2 = 6pcs
= 0.3m+3.3m+0.75m+0.3m-[0.075m-
3. For 2 footings 2(16/100)]-0.725
6 x 2 = 12 pcs = 3.882m/ 0.2 m = 19.14 say 20 + 1
4. 6m/0.65m = 9.23 = 10 pcs = 21
5. 12pcs/10 = 1.2 pcs Total Lateral Ties per column:
Tie Wires 21 + 10 = 31pcs
3 x 3 = 9 ties For 12 columns: 31 x 12 = 372 pcs
9 x 2 x 0.3 = 5.4m Length of 1 lateral tie:
X/5.4m = 1kg/53m Lt: (4)[0.25m-2(0.04)]+2(0.10m)=0.88m
X = 0.10 kg Lateral Ties in 6m length:
6m/0.88m = 6.82 pcs say 6 pcs
Summary:
No. of 6m bars for 372 pcs of lateral
16mm ɸ x 6m rebars: --------15.49 pcs ties:
Tie wire : ------------------------- -- 1.52 kg X/372 pcs = 1/ 6pcs
X= 62 pcs of 10 mm ɸ x 6m rebars for
lateral ties
4. COLUMNS

( FOR LATERAL TIES )


MAIN BARS
Column length:
221.136m/6 = 36.856 pcs
0.3m+3.3m+0.3m-[0.075m- say 37pcs of 16mm ɸ x 6m rebars
2(16/100)]+0.75m
Tie Wire for 12 columns:
= 4.607m x 4 corners x 12 columns
372 lateral ties (4 corners ) (0.3m)
= 221.36m = 446.4m
X/446.4m = 1kg/53m Tie Wires
X = 8.42 kg 8 x 26 = 208 ties
Summary: 208 x 2 x 0.3 = 124.8 m
10 mm ɸ x 6m rebars: -------- 62 pcs X/124.8 m = 1kg/53m
16mm ɸ x 6m rebars: -------- 37 pcs X = 2.35 kg
Tie wire : ------------------------- 8.42kg

Area Laundry: 1m * 1.2m


5. SLAB REBARS 1 / 0.6 = 1.67 say 2 + 1 = 3 pcs
@ 0.6m spacing 3 * 1.2 = 3.6 m
Area Left: 4m * 11.5m 3.6 m / 6m = 0.6 pcs
4 / 0.6 = 6.66 say 7 + 1 = 8pcs

8 * 11.5 = 92 m 1.2 / 0.6 = 2 + 1 = 3 pcs


92 m / 6m = 15.33 pcs 3*1=3m

3 m / 6m = 0.5 pcs

Tie Wires
11.5 / 0.6 = 19.17 say 20 + 1 = 21pcs 3 x 3 = 6 ties
21 * 4 = 84 m 6 x 2 x 0.3 = 3.6 m
84 m / 6m = 14 pcs X/3.6 m = 1kg/53m
Tie Wires X = 0.07 kg
8 x 21 = 168 ties

168 x 2 x 0.3 = 100.8 m Total number of 6m rebars :


X/100.8 m = 1kg/53m 15.33 + 14 + 20 + 17.33 + 0.6 + 0.5 =
X = 1.90 kg 67.76 say 68 pcs

Area Right: 4m * 15m Total number of Tie Wires:

4 / 0.6 = 6.66 say 7 + 1 = 8pcs 1.90 + 2.35 + 0.07 = 4.32kg

8 * 15 = 120 m

120 m / 6m = 20 pcs Summary:

10 mm ɸ x 6m rebars: -------- 68 pcs

15 / 0.6 = 25 + 1 = 26 pcs Tie wire : ------------------------- 4.32kg

26 * 4 = 104 m

104 m / 6m = 17.33 pcs


6. Septic Vault 1.1 / 0.3 = 3.67 +1 = 5pcs

Area = ( 1.1m + 2.6m ) * 1.7 5*1.7m = 8.5m


= 6.29 m2 8.5m / 6m = 1.42 pcs
Cover: Total Length: 1.28m+ 1.42m = 2.7 pcs
Area = 2.6m * 1.1m = 2.86 m2 say 3 pcs of 10 mm ɸ x 6m long
rebars

Using ( Table 3-5 )

*Vertical Reinforcement SP @ 40 cm Tie Wires:

9.15 m2 * 2.93m/m2 = 26.81 m 7 * 5 = 35 ties

*Horizontal Reinforcement every 2 35 x 2 x 0.3 = 21 m


layers
X/14.4m = 1kg/53m
9.15 m2* 3.30 m/ m2 = 30.2 m
X = 0.40 kg
Total Length: 26.81 m + 30.2 m
Summary:
= 57.01 m 10 mm ɸ x 6m rebars: -------- 13 pcs
57.01m/6m = 9.50 pcs Tie wire : ------------------------- - 0.64 kg
say 10 pcs of 10 mm ɸ x 6m long
rebars
7. Catch Basin

Awall = [(0.5m) (0.5m)](5)= 1.25 m2


Tie Wire for CHB:
Acover = [(0.5m) (0.5m)](5)= 1.25 m2
Using Table 3-6: 0.40m spacing, 2
layers, 30 cm tie Using ( Table 3-5 )
Qty of tie wire: Vertical Reinforcement SP @ 0.40m
( 9.15m2)(0.065kg/m2) = 0.59kg 2.5 m2 x 2.93/m2 = 7.33 m

*Horizontal Reinforcement @ every 2


Summary: layers:

10 mm ɸ x 6m rebars: -------- 10 pcs 2.5 m2 x 3.30/m2 = 8.25m

Tie wire : ------------------------- - 0.59 kg Total Length = 7.33 m + 8.25 m

 Slab: = 15.58 m

Area = 1.7m * 1.1m 15.58m/6m = 2.60 pcs

1.7 / 0.30 = 5.67 + 1 = 7 pcs say 3 pcs of 10 mm ɸ x 6m long


rebars
7*1.1m = 7.7 m

7.7m / 6m = 1.28 pcs


Tie Wire for CHB: Summary:

Using Table 3-6: 0.40m spacing, 2 10 mm ɸ x 6m rebars: -------- 9 pcs


layers, 30 cm tie
Tie wire : ------------------------- - 0. 26 kg
Qty of tie wire:

( 1.25 m2)(0.065kg/m2) = 0.08 kg

Slab:

Area = 0.5m * 0.5m

0.5 / 0.20 = 2.5 + 1 = 4 pcs

4*0.9m = 3.6 m * 5 = 18m

18 m / 6m = 3 pcs 10 mm ɸ x 6m

0.5 / 0.20 = 2.5 + 1 = 4 pcs

4*0.9m = 3.6 m * 5 = 18m

18m m / 6m = 3 pcs 10 mm ɸ x 6m

Tie Wires:

4 * 4 = 16 ties

16 x 2 x 0.3 = 9.6 m

X/14.4m = 1kg/53m

X = 0.18 kg
CARPENTRY WORKS

1. DOOR JAMB + DOOR 3. Formworks

2 sets PVC Doors a. Column:

5 sets Panel Doors For C1

2. SCAFFOLDS P = 2( a + b ) + 0.20

COLUMNS: P = 2( 0.25 + 0.25 ) + 0.20

Vertical Support: 2” x 4” P = 1.2m

Horizontal: 2” x 3” Area = 1.2m (3.3m) (10 )

Diagonal Support: 2” x 2 ” A = 39.6 m2

No of plywood = 39.6m2/ 2.88 m2

For C1 = 13.75 pcs say 14 pcs

3.3 * 10 = 33

Vertical Support: Using Table 5-1

33m * 9.35 = 308.55 BD.FT For 2x2 frame on 6mm (1/4”) marine
plywood:
Horizontal Support:
14 plywood * 29.67 = 415.38 say 415
33m * 31.67 = 1045.67 BD. FT board feet

Diagonal Braces: Order :

33m * 11.70 = 386.1 BD.FT 14 pcs. 1.20m x 2.40m ( 4’ x 8’ )


plywood
For C2
415 board feet 2” x 2” lumber
3.3 * 2 columns = 6.6m
For C2
Using Table 5-3
P = 2( a + b ) + 0.20
Vertical Support:
P = 2( 0.15 + 0.15 ) + 0.20
6.6m * 9.35 = 61.71 BD.FT
P = 0.8m
Horizontal Support:
Area = 0.8m (3.3m) (2 )
6.6m * 31.67 = 209.02 BD. FT
A = 5.28 m2
Diagonal Braces:

6.6m * 11.70 = 73. 06 BD.FT


No of plywood = 5.28m^2 / 2.88 m^2

= 1.83 pcs say 2 pcs


Using Table 5-1 No. of plywood = 23.73m2/2.88m2

For 2x2 frame on 6mm (1/4”) marine = 8.24 pcs say 9 pcs.
plywood:
Using Table 5-1
2 plywood * 29.67 = 59.43 say 59 board
feet For 2x2 frame on 6mm (1/4”) marine
plywood:
Order :
9 plywood * 29.67 = 267.03 say 268
2 pcs. 1.20m x 2.40m ( 4’ x 8’ ) board feet
plywood

59 pcs 2” x 2” lumber
d. Septic Tank:

Floor Slab:
b. Column Footing: Area = 2.6m * 1.1m = 2.86m2

For C1/F1: No. of plywood = 2.86m2/2.88m2

Area = 0.3m * 1.0 * 10 columns = 3m2 = 0.99 pcs say 1 pc.

No. of plywood = 3m2/2.88m2 Using Table 5-1

= 1.04pcs. say 2 pcs For 2x2 frame on 6mm (1/4”) marine


plywood:
Using Table 5-1
1 plywood * 29.67 = 29.67 say 30 board
For 2x2 frame on 6mm (1/4”) marine feet
plywood:

2 plywood * 29.67 = 59.34 say 60 board


feet e. Catch Basin:

For C2/F2: Floor Slab:

Area = 0.3m * 0.8m* 2columns = 0.48m2 Area = 0.5m * 0.5m = 0.25m2

No. of plywood = 0.48m2/2.88m2 No. of plywood = 0.25m2/2.88m2

= 0.17 pcs say 2 pcs. = 0.09 pcs say 1 pc.

Using Table 5-1 Using Table 5-1

For 2x2 frame on 6mm (1/4”) marine For 2x2 frame on 6mm (1/4”) marine
plywood: plywood:

2 plywood * 29.67 = 59.34 say 60 board 1 plywood * 29.67 = 29.67 say 30 board
feet feet

c. Wall Footing:

L = 59.32m

A = 59.32m * 0.20 m * 2 sides= 23.73m2


4. CEILING JOIST AND CEILING
BOARD

a. Ceiling Joist:
Area = 8m * 15.6m = 124.8m2
4m * 4.1m = 16. 4 m2
4m * 0.6m = 2.4 m2
Total Area = 106 m2

Using Table 4-3

Using 2” x 2”lumber sp @ 0.40 x 0.40 m

106m2 x 6.379 bd. Ft/m2

= 676.174 bd. Ft, say 677 bd. Ft.

b. Ceiling Board

A INSIDE CEILING = 106 m2

Using Table 4-4: use 2” x 2” lumber

No. of plywood = 106m2/2.88m2

= 36.81pcs.

Say 38 pcs ¼ “x 4” x 8” Plywood

A OUTSIDE CEILING:

P = 42.9m

WEaves = 0.9m

Aoutside = 38.61m2

No. of plywood = 38.61m2/2.88m2

= 13.41pcs.

say 14 pcs ¼ “x 4” x 8” plywood


HARDWARES

1. Tiles: Area Total = 1.55m2


Main Floor: No. of tiles:
Using 60cm x 60cm glazed tiles 1.55m2/ 0.16m2= 9.69 pcs say 10 pcs
Area = 0.60m * 0.60m = 0.36m2 @ 3% allowance:
4m*11.5m = 46m2 10 * 1.03 = 10.3 pcs say 11 pcs
4m*15m = 60m2 T & B:
Total = 106m2 Using 40cm x 40cm unglazed tiles
Kitchen: Area = 0.40m * 0.40m = 0.16m2
0.5m * 1.5m = 0.75m2 1.2m * 2.2m = 2.64m2
0.5m * 1.6 m = 0.8 m2 1.3m * 2.10m = 2.6m2
T & B: Area Total = 5.24m2
1.2m * 2.2m = 2.64m2 No. of tiles:
1.3m * 2.10m = 2.6m2 5.24m^2 / 0.16m^2 = 32.75pcs
Area Total = 99.21m2 @ 3% allowance:
No of tiles: 32.75*1.03=33.73 pcs say 34 pcs
99.21m2/ 0.36m2= 275.86pcs say Using 40cm x 40cm glazed tiles
276pcs
Area = 0.40m * 0.40m = 0.16m2
@ 3% allowance:
1.2m * 1.6m = 1.92m2
276 * 1.03 = 284.28pcs say
285pcs 2.2m * 1.6m *2 = 7.04 m2

Kitchen Counter: 1.3m * 1.6m = 2.08m2

Using 40cm x 40cm glazed tiles 2m * 1.6m *2 = 6.4m2

Area = 0.40m * 0.40m = 0.16 m2 Area Total = 17.44m2

0.5m * 1.5m = 0.75m2 No. of tiles:

0.5m * 1.6 m = 0.8 m2 17.44m^2 / 0.16m^2 = 109 pcs


@ 3% allowance:

109 * 1.03 = 112.27 pcs say 113 pcs

Summary:

60cmx60cm glazed tiles: -------- 285 pcs

40cmx40cm glazed tiles: ---------124 pcs

40cmx40cm unglazed tiles:------ 34 pcs

2. DOORS • W-2
• D-1
Window Type: Sliding Glass
Door Type: PVC Door Window
Dimension: 0.6m x 2.1m
2 sets of D-1 Dimension: 1.63m x 1.2m

• D-2 4 sets of W-2

Door Type: Panel Door • W-3


Dimension: 0.88m x 2.1m Window Type: Sliding Glass
4 sets of D-2 Window
• D-3 Dimension: 1.63m x 0.7m
Door Type: Sliding Glass 1 set of W-3
Door • W-4
Dimension: 1.6m x 2.1m
1 set of D-3 Window Type: Sliding Glass
Window
• D-4
Dimension: 0.83m x 0.7m
Door Type: Panel Door
Dimension: 0.98m x 2.1m 1 set of W-4
1 set of D-4 • W-5

Window Type: Jalousie Glass


3. WINDOWS Window
• W-1
Dimension: 0.6m x 0.7m
Window Type: Sliding Glass
2 sets of W-5
Window
• W-6
Dimension: 2.4m x 1.2m
Window Type: Sliding Glass
1 set of W-1 Window

Dimension: 1.2m x 0.83m

2 sets of W-6
4. HARDWARE:

• Door Hinge:

21 pcs (3 sets per door)

• Door Lock

- 7 sets

• Door Knob

- 7 pcs.

5. Roofing Material

Corrugated G.I. Sheet

Using table 6-2: using 2 ½ corrugations

Length of rafters = 4m

Using Table 6-5, 4m or 4.10m rafter requires a combination of 2.4m and 1.8m
G.I. sheets

13.3 17.8
= 22.17pcs = 29.6pcs ≈ 30 pcs
0.6 0.6
≈ 23 pcs 30 pcs @ 1.8m long
23 pcs @ 1.8m long 30 pcs @ 2.4m long

23 pcs @ 2.4m long

Roofing Nails

Using Table 6-2:

For a 2.4m sheet: 53 x 18= 974 pcs

For a 1.8m sheet: 53 x 14= 742 pcs

Total= 974+ 742

= 1716 pcs of Roof Nails

Using Table 6-3:


1716
G.I. Roof Nails: =14.3 kg
120
= 15 kg of G.I. Roof Nails
1716
G.I. Washers: = 13.62 kg
126
= 14 kg of G.I. Washers
1716
Lead Washers: = 22.88 kg
75
= 23 kg of G.I. Lead Washers

Gutter

Using table 6-2:

Total Length of Gutter = 31.1m

31.1m
= 13.23 pcs
2.35
= 14 pcs

Total width of Gutter = 45 cm

0.90
= 2 pcs
0.45

14
= 7 pcs Plain G.I. Sheets
2

Flashing

Total Length= 2(3.44m)= 6.88m

6.88m
= 2.99 pcs
2.30
= 3 pcs

Total Width of Flashing = 45cm


0.90
= 2 pcs
0.45
3
= 1.5 pcs
2
= 2 pcs of Plain G.I. Sheets

Flashing

Total Length = 2(5.68m) = 11.36m

11.36m
=4.94 pcs
2.30
= 5 pcs
Total Width of Flashing = 45cm

0.90
= 2 pcs
0.45

5
= 2.5 pcs
2
= 2 pcs of Plain G.I. Sheets

Flashing

Total Length= 7.92m

7.92m
= 3.44pcs
2.30
= 4 pcs

Total Width of Flashing= 45cm

0.90 = 2 pcs

0.45
4
= 2 pcs of Plain G.I. Sheets
2

Ridge Roll

Total Length = 13.3m


13.3m
= 6.05 pcs
2.20
= 7 pcs

7pcs
= 3.5 pcs of Plain G.I. Sheets
2

Ridge Roll

Total Length = 2.60m

2.60m
= 1.18 pcs
2.20
= 2 pcs
2 pcs
=1 pc of Plain G.I. Sheets
2
SUMMARY:

Corrugated G.I. Sheets= 53 pcs @ 2.4m long

= 53 pcs @ 1.8m long

Plain G.I. Sheets = 17.5 pcs Plain G.I. Sheets

Roofing Nails = 15 kg of G.I. Roof Nails

G.I. Washers = 14 kg of G.I. Washers

Lead Washers = 23 kg of G.I. Lead Washers


PLUMBING WORKS

I. Sewer Line
2” Ø, P-Trap PVC Pipe 3
2” Ø, 90° Bend PVC Pipe 4
2” Ø, Plug PVC Pipe 1
3” Ø, 45° Bend PVC Pipe 2
3” Ø, 90° Elbow PVC Pipe 15
3” Ø, P-Trap PVC Pipe 2
4” Ø, 45° Bend PVC Pipe 9
4” Ø, 90° Elbow PVC Pipe 3
4” Ø, Wye PVC Pipe 6
2” Ø, Plug PVC Pipe 2
2”x4” Ø, Wye Reducer PVC Pipe 3
2”x4” Ø, Tee Reducer PVC Pipe 1
3”x4” Ø, Wye Reducer PVC Pipe 2
2” Ø, 4m PVC Pipe 2
3” Ø, 4m PVC Pipe 7
4” Ø, 4m PVC Pipe 13
Solvent Cement

2” Ø PVC Pipes = 2(0.7)m+0.8m+3.5m+0.5m+2(0.3m) = 6.8m

No. of 2” Ø, 4m PVC Pipes = 6.8m/4m = 1.7 pcs, say 2 pcs 2” Ø, 4m PVC Pipes

3” Ø PVC Pipes = 4.7m (5 downspouts) + 2(0.3m) = 24.1m

No. of 3” Ø, 4m PVC Pipes = 24.1m/4m = 6.03 pcs, say 7 pcs 3” Ø, 4m PVC Pipes

4” Ø PVC Pipes
=2(0.5m)+1.75m+1.96m+2.66m+5.85m+2.13m+8.48m+1.73m+11.81m+2.10m+2.96
m+7.3m

= 49.73m

No. of 4” Ø, 4m PVC Pipes = 49.73m/4m = 12.43 pcs, say 13 pcs 4” Ø, 4m PVC


Pipes
II. Water Line
Gate Valve 1
Water Meter 1
½” Ø
½” Ø, Tee G.I. Pipe 10
½” Ø, 90° Elbow G.I. Pipe 18
½” Ø, 6m G.I. Pipe
Teflon Tape

½” Ø G.I. Pipes

=
17.9m+8.3m+0.8m+2(0.1m)+5(0.6m)+0.4m+2(1.7m)+2(0.3m)+1.95m+1.3m+1.0m

= 38.85m

No. of ½” Ø, 6m G.I. Pipes = 38.85m/6m = 6.48 pcs, say 7 pcs. ½” Ø, 6m G.I.


Pipes

III. Fixtures
Faucet 5
3”x3” Floor Drain Strainer 2
Water Closet 2
Lavatory 2
Kitchen Sink 1
2”x2” Kitchen Drain Strainer 1
Shower 2
PAINTING WORKS

1. Interior and Exterior Walls

Area Total = 176.75m2 x 2 sides


Area = 353.5 m2
1gal 1quartz
Neutralizer = 353.5 m2 x x = 4.71 gal, say 5 gal
30m3 2.5 gal(water)

353.5 m2
Surface Primer = = 11.78 gal, say 12 gal
30m2/gal

353.5m2
Acrylic latex paint = = 12 gal.
30m2/gal
353.5m2
Acrylic gloss latex paint = = 12 gal.
30m2/gal

2. Ceiling

ATOTAL = 144.61 m2
144.61m2
Interior Primer and Sealer = = 5.78 gal, say 6 gal
25m2/gal

144.61 m2
Flat wall Enamel = = 3.62 gal, say 4 gal
40m2/gal

3. Roof

Ar = (5.68)(11.5+1.8) +(5.68(16+1.8))

Area Total = 176.65 m2

Roof Paint = 176.65 m = 5.89 gal, say 6 gallons


2

30m2/gal
4. Plyboard ( Triangles )

Atotal = 5.8 + 16.17 + 10.37 = 32.34m2

32.34m2
Interior Primer and Sealer = = 1.29 gal, say 2 gal
25m2/gal

32.34 m2
Flat wall Enamel = = 0.81 gal, say 1 gal
40m2/gal

5. Door

D-1: ((2.1+0.05)(0.88)(4) = 7.57m2


D-2: ((2.1+0.05)(0.98)(1) = 2.11 m2

Total Area = 9.68 m2 x 2 = 19.36 m2

19.36 m2
Interior Primer and Sealer = = 0.77 gal, say 1 gal
25m2/gal

19.36 m2
Flat wall Enamel = = 0.48 gal, say 1 gal
40m2/gal
STEEL WORKS

1. Main Truss

Item 1: Top Chord 2” x 2” x 3/16”

L1 = √(5.1𝑚)2 + (2.5𝑚)2 = 5.68 m

= 5.68 x 2 x 3

= 34.08 m

Item 2: Web Angle Bar 1-1/2” x 1½” x 3/16”

L2 = (0.2m + 0.5m + 1.2m + 1.2m + 2m + 3m + 3.8m)(2)(0.5) + 4.6m(0.5)

= 14.2m x 3

= 42.6 m

Item 3: Web Angle Bar 1-1/2” x 1½” x 3/16”

L3 = (1m + 1.2m + 1.6m + 2m + 2.5m + 3.5m + 4m)(2)(0.5)

= 15.8m x 3

= 47.4 m

Item 4: Bottom Chord 2” x 2” x 3/16”

=10.2m x 3

= 30.6m

Total Length for 2” x 2” x 3/16” Angle Bar for Top Chord and Bottom Chord

= 34.08m + 30.6m

= 64.68m

64.68m
=
6m
= 10.78 pcs, say 11 pcs

Total Length for 1-1/2” x 1½” x 3/16” Angle Bar for Web

= 47.4m + 30.6m

= 78m

78m
= = 13 pcs
6m
2. Truss ( Porch )

Item 1: Top Chord 2” x 2” x 3/16”

L1 = √(1.5𝑚)2 + (3.1𝑚)2 = 3.44 m

= 3.44 x 2 x 2

= 13.78m

Item 2: Web Angle Bar 1-1/2” x 1½” x 3/16”

L2 = (0.2m + 0.7m + 1.2m + 1.2m + 2m)(2)(0.5) + 2.6m(0.5)

= 6.6m x 2

= 13.2m

Item 3: Web Angle Bar 1-1/2” x 1½” x 3/16”

L3 = (0.8m + 1.2m + 1.5m + 1.8m + 2.5m)(2)(0.5)

= 7.8m x 2

= 15.6 m

Item 4: Bottom Chord 2” x 2” x 3/16”

= 6.2m x 2

= 12.4 m

Total Length for 2” x 2” x 3/16” Angle Bar for Top Chord and Bottom Chord

= 13.78m + 12.4m

= 26.18m

26.18m
=
6m
= 4.36 pcs, say 5 pcs

Total Length for 1-1/2” x 1½” x 3/16” Angle Bar for Web

= 13.2m + 15.6m

= 28.8m

28.8m
= = 4.8 pcs say 5 pcs.
6m
3. Purlins

L = (8m) (1/0.70m) = 11.43 pcs say 12 pcs

LTOTAl= (12) (13.3m) + 5.8(1/0.70m)(3.4) = 187.77 m

187.77m
= 31.3 pcs, say 32 pcs
6m

CEE Purlins = 32 pcs @ 6.00 m 2” x 4” Ga #16 CEE Purlins


X. LABOR ESTIMATES
EARTHWORKS:

 SITE CLEARING, GRUBBING AND GRADING

3 Laborers for 2 days

 EXCAVATION

VFOOTING = 10.75 + 1.376 = 12.126 m3

VWALLFOOTING = 15.16 m3

VSEPTIC TANK = 3.762 m3

VCATCH BASIN = 0.625 m3

Volume Total = 31.673 m3


1 md 10.56md
31.673 m3 x 3 m3 = = 3.52  4 days
3m

3 laborers for 4 days

 BACKFILL

Volume Total:

7.03 m3 + 7.58 m3 = 14.61 m3


1 mh 1d 1.99 md
14.61 m3 x x = 1m = 1.99 2 days
1.22 m3 6h

1 laborer for 2 days

REINFORCED CONCRETE WORKS:

 WALL FOOTING :

Volume Total = 4.75 m3


8.54 mh 1d 6.76 md
4.75 m3 x x = = 2.25 days  3 days
1 m3 6h 3m

1 steel man, 1 laborer, 1 mason for 3 days

 COLUMNS:

Volume Total: 5.72 + 0.58 = 6.28 m3


2 md 25.12md
6.28 m3 x = = 4.19  5 days
0.50 m3 6m

1 steel man, 4 laborer, 1 mason for 5 days


 SLAB

Volume Total: 9.42 + 0.75 + 1.4 = 11.57 m3


2 md 27.55md
11.57m3 x = = 4.59  5 days
0.84 m3 6m

1 steel man, 4 laborer, 1 mason for 5 days

MASONRY:

 WALLS:
2 md 50.5 md
2,525pcs. of CHB x = = 16.83  17 days
100 pcs of CHB 3m

1 laborer, 1 mason for 18 days

 Septic Tank:
2 md 1.58md
79 pcs. of CHB x = = 0.79  1 day
100 pcs of CHB 2m

1 laborer, 1 mason for 1 days

 PLASTERING:

Area = (176.75+6.29) X 2 = 366.08 m2


2 md 91.52md
366.08 m2 x = = 15.25  16 days
8 m2 6m

3 mason for 16 days

TILE WORKS:

Total Area: 99.21 m2 +1.55 +5.24 +17.44 = 123.44 m2

1 ft2 1 md 17.7 md
123.44 m2 x = 1327.31 ft2 x = = 4.43  5 days
0.093 m2 75 ft2 4m

2 masons, 2 laborers for 5 days

METAL WORKS:

 TRUSS AND PURLINS:

Total Number of Truss and Purlins: 32 +5 = 37 pcs

1 md 3.7 md
37 pcs. x = = 1.23  2 days
10 pcs 3m

1 welder, 2 laborers for 2 days


ROOFING:

 ROOFING SHEETS:

Total Number of GI Sheet: 53 + 18 = 71 sheets

2 md 12.91 md
71 sheets x = = 3.23  4days
11 sheets 4m

4 laborers for 4 days

DOOR INSTALLATION:
1 md 4 md
8 doors x = = 2 days
2 doors 2m

2 laborers for 2 days

WINDOW INSTALLATION:
1 md 5.5md
11 windows x = = 2.75 days
2 pcs 2m

2 laborers for 3 days

CARPENTRY WORKS:

 FORMWORKS:

Total Area: 39.6 +5.28 +3 + 0.48 + 23.73 + 2.86 + 0.25 = 75.2 m2

2.5 mh 1d 31.33 md
75.2 m2 x x = = 6.27  7 days
1 m2 6 hr 5m

3 carpenters, 2 laborers for 7 days

 CEILING:

Total Area: 106 m2 + 38.61 = 144.61 m2


2.5 mh 1d 60.25 md
144.61 m2 x x = = 12.05  13 days
1 m2 6 hr 5m

3 carpenters, 2 laborers for 13 days


PAINTING:

AreaWALL = 353.5 m2

AreaLUMBER = 144.61 m2

AreaROOF = 176.75 m2

AreaPLYBOARD = 32.34 m2

AreaDOORS = 19.36 m2

Total Area: 726.56 m2

1 md 72.66 md
726.56 m2 x = = 24.22  25 days
10 m2 3m

3 painters for 25 days

PLUMBING:

 WATER CLOSET

2 md 4 md
2 water closet x = = 2 days
1 water closet 2m

1 laborer, 1 plumber for 2 days (including installation and layout)

 LAVATORY

2 md 6 md
3 lavatory x = = 3 days
1 lavatory 2m

1 laborer, 1 plumber for 3 days (including installation and layout)

 INSTALLATION OF G.I PIPES

2 md 0.7md
7 lengths x = = 0.35  1 day
20 lenghts 2m

1 laborer, 1 plumber for 1 day


TABLES

TABLE 1-2 CONCRETE PROPORTION

Mixture Cement in Bag


Proportion Sand cu. M. Gravel cu. m.
Class 40 kg. 50 kg.
AA 1: 1 ½ : 3 12.0 9.5 0.50 1.0
A 1: 2 : 4 9.0 7.0 0.50 1.0
B 1: 2 ½ : 5 7.5 6.0 0.50 1.0
C 1: 3 : 6 6.0 5.0 0.50 1.0

TABLE 2-1 QUANTITY OF CEMENT ND SAND FOR MORTAR AND PLASTER


MIXTURE PER CUBIC METER

Cement in Bag
Class Mixture Sand cu. M.
40 kg. 50 kg.
A 1: 2 18.0 14.5 1.0
B 1: 3 12.0 9.5 1.0
C 1: 4 9.0 7.0 1.0

TABLE 3-5 LENGTH OF REINFORCEMENT BARS FOR CHB IN METERS

Vertical Reinforcement Horizontal Reinforcement


Spacing Spacing
Length of Bars in meter Length of Bars in meter
Layer
cm. Per Block Per sq. m. Per Block Per sq. m.
40 0.235 2.93 2 0.264 3.30
60 0.171 2.13 3 0.172 2.15
80 0.128 1.60 4 0.138 1.72

TABLE 3-6 NO. 16 G.I. TIE WIRE FOR CHB REINFORCEMENT PER SQUARE
METER

Vertical Horizontal Kilograms per Square Meter


Spacing Layer Spacing 25 cm. tie 30 cm. tie 40 cm. tie
40 2 0.054 0.065 0.086
40 3 0.039 0.047 0.063
40 4 0.024 0.029 0.039
60 2 0.036 0.044 0.057
60 3 0.026 0.032 0.042
60 4 0.020 0.024 0.032
80 2 0.027 0.033 0.044
80 3 0.020 0.024 0.032
80 4 0.015 0.018 0.024
TABLE 5-1 BOARD FOOT OF WOOD FRAME FOR COLUMN AND BEAM PER
PLYWOOD FORM

THICKNESS OF PLYWOOD FORM


SIZE OF WOOD POST BEAM
FRAME 12 mm
6 mm (1/4”) 12 mm (1/2”) 6 mm (1/4”)
(1/2”)
2” x 2” 29.67 20.33 25.06 18.66
2” x 3” 44.50 30.50 37.60 28.00

TABLE 5-3 QUANTITY OF LUMBER FOR SCAFFOLDING OR STAGING

THICKNESS OF PLYWOOD FORM


SIZE OF POST BEAM
WOOD FRAME
6 mm (1/4”) 12 mm (1/2”) 6 mm (1/4”) 12 mm (1/2”)

2” x 2” 29.67 20.33 25.06 18.66


2” x 3” 44.50 30.50 37.60 28.00
TABLE 6-2 EFFECTIVE COVERING OF G.I. ROOFING SHEETS

Effective Covering Side Lapping Number of


Length Purlins Spacing
Nails or Rivets
Ft. - Meter 1 1/2 2 1/2 in Meter
per Sheet
5’ – 1.50 0.70 0.60 0.60 14
6’ – 1.80 0.70 0.60 0.75 14
7’ – 2.10 0.70 0.60 0.60 18
8’ – 2.40 0.70 0.60 0.70 18
9’ – 2.70 0.70 0.60 0.60 22
10’ – 3.00 0.70 0.60 0.67 22
12’ – 3.60 0.70 0.60 0.66 26

TABLE 6-3 QUANTITY OF ROOF ACCESSORIES IN KILOGRAMS

Materials Number in Kilogram


G.I. Roof Nails 120
G.I. Rivets 180
G.I. Washers 126
Lead Washers 75
Umbrella Nails 120

TABLE 6-4 SIZE AND QUANTITY OF STRAPS IN ONE PLAIN G.I. SHEET

Number of Strap in
Size of Purlins in Inches Size of G.I. Strap in Inches
One Plain Sheet
2” x 3” 1” x 9” 384
2” x 4” 1” x 10” 342
2” x 5” 1” x 11” 312
2” x 6” 1” x 12” 288
TABLE 7-2 QUANTITY OF MARBLE TILES AND MORTAR PE SQUARE METER

Number Cement Bags Mixture Sand


Size (cm)
per sq. m. A B C cu.m.
15 x 30 22.3 .45 .30 .225 .025
20 x 20 25.0 .45 .30 .225 .025
20 x 40 12.5 .45 .30 .225 .025
30 x 30 11.1 .45 .30 .225 .025
30 x 60 5.6 .45 .30 .225 .025
40 x 40 6.3 .45 .30 .225 .025
60 x 60 2.8 .45 .30 .225 .025

PAINTING

CHART 1

CHART 2
CHART 3

You might also like