OPT PROB PES EST START FINISH

Layout/Staking/Fabrication of Batterboard 1 3 3 3 1-Aug 1-Aug


Excavation (Col Ftg, Wall Ftg, Septic Tank) 3 5 7 5 2-Aug 4-Aug
Fabrication of Rebars -Col Ftg & Col 2 4 6 4 2-Aug 3-Aug
Fabrication of Rebars for Beams 2 4 6 4 2-Aug 3-Aug
Fabrication of Rebars - 2F Col 2 4 6 4 2-Aug 3-Aug
Fabrication of Rebars - Roof Beam 2 4 6 4 2-Aug 3-Aug
Fabrication of Rebars - Ext Col 2 4 6 4 2-Aug 3-Aug
Installation of Rebars - Col ftg & Col 1 3 5 3 4-Aug 4-Aug
Pouring of Concrete for Col Ftg 1 3 5 3 5-Aug 5-Aug
Fab & Inst of Formworks for Col 3 5 7 5 6-Aug 8-Aug
Trimming of Wall Footing 3 5 7 5 9-Aug 11-Aug
Pouring of Concrete for Col 1 3 5 3 9-Aug 9-Aug
Dismantling of Column Formworks 1 3 5 3 10-Aug 10-Aug
Fabrication & Installation of Wall Ftg Rebars 2 4 6 4 11-Aug 12-Aug
Pouring of Concrete for wall ftg 1 3 5 3 13-Aug 13-Aug
CHB Laying - GF 6 8 10 8 14-Aug 19-Aug
CHB Laying - GF (Interior) 3 5 7 5 14-Aug 16-Aug
Installation of Scaffoldings 6 8 10 8 17-Aug 22-Aug
Installation of Rebars - Beam 2 4 6 4 23-Aug 24-Aug
Electrical Layout/Plumbing Layout 6 8 10 8 23-Aug 28-Aug
Fab & Inst of Formworks for Beam 4 6 8 6 23-Aug 26-Aug
Installation of Steel Decking 2 4 6 4 27-Aug 28-Aug
Fab & Inst of Rebars - Slab 2 4 6 4 29-Aug 30-Aug
Pouring of Concrete - Slab (Ready Mix) 1 3 5 3 31-Aug 31-Aug
Installation of Rebars - 2F Col 4 6 8 6 31-Aug 3-Sep
Fab & Inst of Formworks - 2F Col 3 5 7 5 4-Sep 6-Sep
Pouring of Concrete - 2F Col 1 3 5 3 7-Sep 7-Sep
Dismantling of Formworks - Beam/Scaffoldings 1 3 5 3 8-Sep 8-Sep
Dismantling of Formworks - 2F Col 1 3 5 3 8-Sep 8-Sep
Layout of Stairs 1 3 5 3 9-Sep 9-Sep
CHB Laying - 2F (EXTERIOR) 6 8 10 8 9-Sep 14-Sep
CHB Laying - 2F (INTERIOR) 3 5 7 5 9-Sep 11-Sep
Installation of Rebars - Roof Beam 2 4 6 4 12-Sep 13-Sep
Fab & Inst of Formworks for Stairs 3 5 7 5 14-Sep 16-Sep
Fab & Inst of Formworks - Roof Beam 4 6 8 6 14-Sep 17-Sep
Fabrication/Installation of Rebars for Stairs 2 4 6 4 14-Sep 15-Sep
Pouring of Concrete - Roof Beam 1 3 5 3 18-Sep 18-Sep
Pouring of Concrete - Stairs 1 3 5 3 18-Sep 18-Sep
Installation of Rebars - Ext Col 1 3 5 3 19-Sep 19-Sep
Dismantling of Formworks - Roof Beam 1 3 5 3 19-Sep 19-Sep
Fab & Inst of Formworks - Ext Col 2 4 6 4 19-Sep 20-Sep
Pouring of Concrete - Ext Col 1 3 5 3 21-Sep 21-Sep
Dismantling of Formworks - Ext Col 1 3 5 3 22-Sep 22-Sep
CHB Laying - Parapet 3 5 7 5 23-Sep 25-Sep
Plastering of Parapet 3 5 7 5 26-Sep 28-Sep
Fab & Inst of Roof Framing 4 6 8 6 29-Sep 2-Oct
Inst of Roof & Roofing Materials 2 4 6 4 3-Oct 4-Oct
Fab & Inst of Ceiling Framing 5 7 9 7 5-Oct 9-Oct
Plastering Exterior 18 20 22 20 5-Oct 22-Oct
CR Floor - Waterproofing 1 3 5 3 5-Oct 5-Oct
Installation of FiberCem Board 3 5 7 5 10-Oct 12-Oct
Installation of Door Jamb 3 5 7 5 10-Oct 12-Oct
Plastering Interior 18 20 22 20 13-Oct 30-Oct
Dismantling of Formworks - Stairs 1 3 5 3 23-Oct 23-Oct
Backfilling & Compaction 5 7 9 7 13-Oct 17-Oct
Application of Paint for Ceiling 3 5 7 5 13-Oct 15-Oct
Fab & Inst of Slab-on-fill rebars 1 3 5 3 18-Oct 18-Oct
Installation of Electrical Devices/Plumbing Fixtures 2 4 6 4 18-Oct 19-Oct
Application of Epoxy for metal decking 3 5 7 5 18-Oct 20-Oct
Pouring of Concrete - Slab-on-fill 1 3 5 3 19-Oct 19-Oct
Fab & Inst of Laundry Sink 3 5 7 5 20-Oct 22-Oct
Installation of Aluminum Glass Door & Window 1 3 5 3
Fab & Inst of Kitchen Counter 4 6 8 6 20-Oct 23-Oct
Skimcoating - Grey 12 14 16 14 20-Oct 31-Oct
Skimcoating - White 12 14 16 14 1-Nov 12-Nov
Tile Works - 2nd Floor (40x40) 6 8 10 8 13-Nov 18-Nov
Tile Works - 1st Floor (60x60) 6 8 10 8 13-Nov 18-Nov
Tile Works - 2nd Floor CR 12 14 16 14 19-Nov 30-Nov
Tile Works - 1st Floor CR 12 14 16 14 19-Nov 30-Nov
Application of Primer (1st Coating) 2 4 6 4 19-Nov 20-Nov
Tile Works - Balcony & Stairs 12 14 16 14 1-Dec 12-Dec
Firewall Waterproofing 2 4 6 4 13-Dec 14-Dec
Varnishing 6 8 10 8 15-Dec 20-Dec
Application of Final Coating 2 4 6 4 21-Dec 22-Dec
Preparation of Ground/Garage 2 4 6 4 15-Dec 16-Dec
Meter Banking - Fabrication and Wiring 2 4 6 4 17-Dec 18-Dec
Tileworks - Countertop 3 5 7 5 19-Dec 21-Dec
Application of Tile Grout 1 3 5 3 22-Dec 22-Dec
Punchlisting & Cleaning 2 4 6 4 23-Dec 24-Dec
PROJECT: DEVV - FSTN 1ST: PROJECT: Dulalia Executive Village - Valenzuela Civil / Structural 75.00%
LOCATION: 2ND: LOCATION: Finishing Works 25.00%
CONTRACT AMOUNT PER SQ.M. PHP 4,400.00 3RD: CONTRACT AMOUNT PER SQ.M.: 4,400.00 Total Percentage 100.00%
AREA: 70.00 SQ.M. 4TH: AREA: 70.00
TOTAL CONTRACT AMOUNT: PHP 308,000.00 TOTAL PREV PAYMEN TOTAL CONTRACT AMOUNT: 308,000.00
Sir, pa check po kung
DESCRIPTION % EARTHWORKS ok to kasi po mas 2.00%
simple po, at para
EARTHWORKS Trimming of Wall Footing maintindihan din kung 0.50%
3 Trimming of Wall Footing 0.50% sino man po ang mag
Backfilling and Compaction 0.50%
bibilling,
4 Backfilling & Compaction 0.50% Septic Tank Fabrication 1.00%
PHP 3,080.00 1.00% STRUCTURAL 39.75%
REBARS Column Footing
5 Fabrication of Rebars -Col Ftg & Col 1.00% Rebars (Fabrication/Installation) 0.50%
6 Fabrication of Rebars for Beams 1.00% Concrete Works 1.00%
7 Fabrication of Rebars - 2F Col 1.00% Wall Footing
8 Fabrication of Rebars - Roof Beam 1.00% Rebars (Fabrication/Installation) 0.50%
9 Fabrication of Rebars - Ext Col 1.00% Concrete Works 1.00%
10 Fabrication & Installation of Wall Ftg Rebars 1.00% Column ( Ftg to 2F)
11 Installation of Rebars - Col ftg & Col 0.50% Rebars (Fabrication/Installation) 1.00%
12 Installation of Rebars - Beam 1.00% Formworks (Fabrication / Installation /Dismantling) 1.00%
13 Installation of Steel Decking 1.00% Concrete Works 1.50%
14 Fab & Inst of Rebars - Slab 1.00% Beam
15 Installation of Rebars - 2F Col 1.00% Rebars (Fabrication/Installation) 1.50%
16 Installation of Rebars - Roof Beam 1.00% Formworks (Fabrication / Installation /Dismantling) 1.00%
17 Fabrication/Installation of Rebars for Stairs 0.75% Concrete Works 1.50%
18 Installation of Rebars - Ext Col 1.00% Column ( 2F to Roof Beam)
19 Fab & Inst of Slab-on-fill rebars 0.75% Rebars (Fabrication/Installation) 2.00%
PHP 43,154.54 14.01% Formworks (Fabrication / Installation /Dismantling) 1.50%
CONCRETE Concrete Works 1.50%
20 Pouring of Concrete for Col Ftg 1.50% Roof Beam
21 Pouring of Concrete for Col 1.50% Rebars (Fabrication/Installation) 2.00%
22 Pouring of Concrete for wall ftg 1.50% Formworks (Fabrication / Installation /Dismantling) 1.50%
23 Pouring of Concrete - Slab (Ready Mix) 3.00% Concrete Works 2.00%
24 Pouring of Concrete - 2F Col 1.50% Column ( Roof Beam to Parapet)
25 Pouring of Concrete - Roof Beam 2.00% Rebars (Fabrication/Installation) 2.00%
26 Pouring of Concrete - Stairs 1.50% Formworks (Fabrication / Installation /Dismantling) 1.50%
27 Pouring of Concrete - Ext Col 1.50% Concrete Works 1.50%
28 Pouring of Concrete - Slab-on-fill 1.50% Second Floor Slab
29 Fab & Inst of Laundry Sink 0.50% Rebars (Fabrication/Installation) - One-way Slab 1.00%
30 Fab & Inst of Kitchen Counter 1.00% Formworks (Fabrication / Installation /Dismantling) 0.25%
PHP 52,360.00 17.00% Steel Decking Installation 0.75%
SCAFFOLDINGS & FORMWORKS Concrete Works 2.50%
31 Installation of Scaffoldings 1.00% Stairs
32 Layout of Stairs 0.50% Rebars (Fabrication/Installation) 0.75%
33 Fab & Inst of Formworks for Col 1.00% Formworks (Fabrication / Installation /Dismantling) 1.50%
34 Dismantling of Column Formworks 0.50% Concrete Works 1.50%
35 Fab & Inst of Formworks for Beam 1.00% Slab-on-Fill / Slab-on-Grade
36 Dismantling of Formworks - Beam/Scaffoldings 0.50% Preparation (Backfilling / Gravel Bedding) 0.25%
37 Fab & Inst of Formworks - 2F Col 1.00% Rebar Works 0.75%
38 Dismantling of Formworks - 2F Col 0.50% Concrete Works 1.50%
39 Fab & Inst of Formworks for Stairs 1.00% Kitchen Counter Top
40 Dismantling of Formworks - Stairs 0.50% Rebars (Fabrication/Installation) 0.25%
41 Fab & Inst of Formworks - Roof Beam 1.00% Formworks (Fabrication / Installation /Dismantling) 0.10%
42 Dismantling of Formworks - Roof Beam 0.50% Concrete Works 1.00%
43 Fab & Inst of Formworks - Ext Col 1.00% Laundry Countertop
44 Dismantling of Formworks - Ext Col 0.50% Rebars (Fabrication/Installation) 0.10%
PHP 32,340.00 10.50% Formworks (Fabrication / Installation /Dismantling) 0.05%
MASONRY Concrete Works 0.50%
45 CHB Laying - GF 1.50% Erection of Scaffoldings 1.00%
46 CHB Laying - GF (Interior) 0.75% MASONRY WORKS 14.75%
47 CHB Laying - 2F (EXTERIOR) 2.00% Wall Footing Concrete Hollow Blocks
48 CHB Laying - 2F (INTERIOR) 1.50% Reinforcement 0.20%
49 CHB Laying - Parapet 1.50% 6.36% Installation 0.50%
50 Plastering of Parapet 1.50% GF Concrete Hollow Blocks
51 Plastering Exterior 5.00% Reinforcement 0.20%
52 Plastering Interior 3.00% 9.50% Installation 1.00%
PHP 51,590.00 16.75% contractor 57,950.70 2F Concrete Hollow Blocks
ELECTRICAL & PLUMBING Reinforcement 0.20%
53 Electrical Layout/Plumbing Layout 1.50% Installation 1.00%
54 Installation of Electrical Devices/Plumbing Fixtures 2.00% Parapet Concrete Hollow Blocks
PHP 10,780.00 3.50% Reinforcement 0.20%
ROOFING Installation 0.75%
55 Fab & Inst of Roof Framing 1.75% Partition Concrete Hollow Blocks
56 Inst of Roof & Roofing Materials 2.25% Reinforcement 0.20%
PHP 12,320.00 4.00% contractor 7,500.00 Installation 1.00%
WOODWORKS Plastering (Exterior) 5.00%
57 Fab & Inst of Ceiling Framing 1.25% Plastering (Interior) 3.00%
58 Installation of FiberCem Board 1.50% Plastering (Parapet/Firewall) 1.50%
59 Installation of Door Jamb 1.50% ELECTRICAL WORKS 3.25%
PHP 13,090.00 4.25% contractor 10,489.34 Rough-ins
PAINTING Installation of Electrical Pipes 1.00%
60 CR Floor - Waterproofing 0.50% Installation of Electrical Wires & Cables 0.50%
61 Application of Paint for Ceiling 2.00% Electrical Fixtures and Equipment
62 Application of Epoxy for metal decking 1.00% Installation of Panel Box & Circuit Breaker 0.75%
63 Skimcoating - Grey 2.00% Installation of Convenience Outlet & Switches 1.00%
64 Skimcoating - White 2.50% PLUMBING & SANITARY WORKS 2.35%
65 Application of Primer (1st Coating) 1.50% Rough-ins
66 Firewall Waterproofing 2.00% Installation of Sanitary Pipes and Fittings 1.25%
67 Varnishing 2.50% Installation of Water Pipes and Fittings 0.75%
68 Application of Final Coating 2.00% Plumbing Fixtures
PHP 49,286.91 16.00% Installation of Water Closets 0.10%
TILE WORKS Installation of Lavatories 0.10%
69 Tile Works - 2nd Floor (40x40) 1.00% Installation of Floor Drains 0.05%
70 Tile Works - 1st Floor (60x60) 1.00% Installation of Shower Heads 0.10%
71 Tile Works - 2nd Floor CR 1.00% WOOD WORKS 7.85%
72 Tile Works - 1st Floor CR 1.00% Ceiling
73 Tile Works - Balcony & Stairs 0.50% Ceiling Framing (Installation) 1.25%
74 Tileworks - Countertop 0.50% Ceiling Boards (Installation) 1.50%
75 Application of Tile Grout 0.75% Doors and Door Jambs
PHP 17,710.00 5.75% contractor 11,165 Door (Installation) 1.00%
FINISHING Door Jamb (Installation) 1.50%
76 Preparation of Ground/Garage 1.50% Cabinet Door (Installation) 1.00%
77 Meter Banking - Fabrication and Wiring 1.75% Cabinet Door Jamb (Installation / Fabrication) 0.75%
78 Punchlisting & Cleaning 1.00% Door Knob / Cabinet Handle (Installation) 0.10%
4.25% PVC Door and Jamb (Installation) 0.50%
Stair Railings (Wood-Installation) 0.25%
97.01% TILE WORKS 10.25%
TOTAL PERCENTAGE OF ACCOMPLISHMENT PHP 0.00 Waterproofing (CR Second Floor) 0.50%
ADMIN DONE #REF! Floor Tiles
TOTAL ACCOMPLISHMENT #REF! Ground Floor 1.00%
LESS 10% RETENTION #REF! Second Floor 1.00%
NET AMOUNT #REF! CR - Ground Floor 1.00%
LESS : PREVIOUS #REF! CR - Second Floor 1.00%
TOTAL AMOUNT TO BE PAID #REF! Balcony 0.50%
Stair 0.50%
Wall Tiles
CR - Ground Floor 1.50%
CR - Second Floor 1.50%
Kitchen Counter Top ( Granite / Tiles ) 1.00%
RAILINGS 1.30%
Stair Railings
Fabrication 0.25%
Installation 0.75%
Balcony
Fabrication 0.10%
Installation 0.20%
ROOFING WORKS 3.75%
Roof Framing
Fabrication/Installation 1.75%
Roof Sheet and Accessories
Gutter (Fabrication/Installation) 1.00%
Roof Sheet (Installation) 0.25%
Roofing Accessories (Installation) 0.75%
PAINTING WORKS 13.65%
Exterior Paint
Skimcoating White 1.25%
Sanding 1.00%
Primer 0.75%
Final Painting 1.00%
Interior Paint
Skimcoating Grey 1.40%
Skimcoating White 1.25%
Sanding 0.75%
Primer 0.75%
Final Painting 1.00%
Doors , Jambs, Cabinet Doors & Stair Railings Varnishing
Preparation 2.00%
Final Coating 0.50%
Ceiling
Preparation 1.50%
Final Coating 0.50%
FINISHING WORKS 1.10%
Ground Preparation
Garage
Preparation 0.10%
Rebar Works 0.20%
Concrete Works 0.20%
Laundry
Preparation 0.05%
Rebar Works 0.05%
Concrete Works 0.20%
Punchlisting 0.30%

100.00%
MODEL : BELLIS AZALEA EDELWEISS DAFFODIL CATTLEYA
AREA : 56.00 SQ.M. 66.00 SQ.M. 64.00 SQ.M. 70.00 SQ.M. 84.00 SQ.M.
CONTRACT AMOUNT PER SQ.M. : PHP 5,900.00 PHP 5,900.00 PHP 5,900.00 PHP 5,900.00 PHP 5,900.00
TOTAL CONTRACT AMOUNT : PHP 330,400.00 PHP 389,400.00 PHP 377,600.00 PHP 413,000.00 PHP 495,600.00
CONTRACT DURATION : 3.00 month/s 3.50 month/s 4.00 month/s 4.50 month/s 5.00 month/s
AVERAGE NO. OF MANPOWER : 8 8 8 8 8
AVERAGE RATE : PHP 529.49 PHP 534.89 PHP 453.85 PHP 441.24 PHP 476.54

MODEL : BELLIS AZALEA EDELWEISS DAFFODIL CATTLEYA


AREA : 56.00 SQ.M. 66.00 SQ.M. 64.00 SQ.M. 70.00 SQ.M. 84.00 SQ.M.
CONTRACT AMOUNT PER SQ.M. : PHP 5,700.00 PHP 5,700.00 PHP 5,700.00 PHP 5,700.00 PHP 5,700.00
TOTAL CONTRACT AMOUNT : PHP 319,200.00 PHP 376,200.00 PHP 364,800.00 PHP 399,000.00 PHP 478,800.00
CONTRACT DURATION : 3.00 month/s 3.50 month/s 4.00 month/s 4.50 month/s 5.00 month/s
AVERAGE NO. OF MANPOWER : 8 8 8 8 8
AVERAGE RATE : PHP 511.54 PHP 516.76 PHP 438.46 PHP 426.28 PHP 460.38

MODEL : BELLIS AZALEA EDELWEISS DAFFODIL CATTLEYA


AREA : 56.00 SQ.M. 66.00 SQ.M. 64.00 SQ.M. 70.00 SQ.M. 84.00 SQ.M.
CONTRACT AMOUNT PER SQ.M. : PHP 5,400.00 PHP 5,400.00 PHP 5,400.00 PHP 5,400.00 PHP 5,400.00
TOTAL CONTRACT AMOUNT : PHP 302,400.00 PHP 356,400.00 PHP 345,600.00 PHP 378,000.00 PHP 453,600.00
CONTRACT DURATION : 3.00 month/s 3.50 month/s 4.00 month/s 4.50 month/s 5.00 month/s
AVERAGE NO. OF MANPOWER : 8 8 8 8 8
AVERAGE RATE : PHP 484.62 PHP 489.56 PHP 415.38 PHP 403.85 PHP 436.15
FLORA
87.00 SQ.M.
PHP 5,900.00
PHP 513,300.00
6.00 month/s
8
PHP 411.30

FLORA
87.00 SQ.M.
PHP 5,700.00
PHP 495,900.00
6.00 month/s
8
PHP 397.36

FLORA
87.00 SQ.M.
PHP 5,400.00
PHP 469,800.00
6.00 month/s
8
PHP 376.44
PROJECT: DEVV - FSTN PROJECT:
LOCATION: LOCATION
AMOUNT PER SQ.M.: 4,400.00 AMOUNT
AREA: 70.00 AREA:
TCP: 308,000.00 TCP:

EARTHWORKS 2.30% WT
Trimming of Wall Footing 0.50%
Backfilling and Compaction 0.80%
Septic Tank Fabrication 1.00%
STRUCTURAL 42.00%
Column Footing
Rebars (Fabrication/Installation) 0.50%
Concrete Works 1.00%
Wall Footing
Rebars (Fabrication/Installation) 0.50%
Concrete Works 1.00%
Column ( Ftg to 2F)
Rebars (Fabrication/Installation) 1.00%
Formworks (Fabrication / Installation /Dismantling) 1.00%
Concrete Works 1.50%
Beam
Rebars (Fabrication/Installation) 1.50%
Formworks (Fabrication / Installation /Dismantling) 1.00%
Concrete Works 1.50%
Column ( 2F to Roof Beam)
Rebars (Fabrication/Installation) 2.00%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 1.50%
Roof Beam
Rebars (Fabrication/Installation) 2.00%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 2.00%
Column ( Roof Beam to Parapet)
Rebars (Fabrication/Installation) 2.00%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 1.50%
Second Floor Slab
Rebars (Fabrication/Installation) - One-way Slab 1.00%
Formworks (Fabrication / Installation /Dismantling) 0.25%
Steel Decking Installation 1.00%
Concrete Works 2.50%
Stairs
Rebars (Fabrication/Installation) 0.75%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 1.50%
Slab-on-Fill / Slab-on-Grade
Preparation (Backfilling / Gravel Bedding) 0.25%
Rebar Works 0.75%
Concrete Works 1.50%
Kitchen Counter Top
Rebars (Fabrication/Installation) 0.25%
Formworks (Fabrication / Installation /Dismantling) 0.10%
Concrete Works 1.00%
Laundry Countertop
Rebars (Fabrication/Installation) 0.10%
Formworks (Fabrication / Installation /Dismantling) 0.05%
Concrete Works 0.50%
Erection of Scaffoldings 3.00%
MASONRY WORKS 14.75%
Wall Footing Concrete Hollow Blocks
Reinforcement 0.20%
Installation 0.50%
GF Concrete Hollow Blocks
Reinforcement 0.20%
Installation 1.00%
2F Concrete Hollow Blocks
Reinforcement 0.20%
Installation 1.00%
Parapet Concrete Hollow Blocks
Reinforcement 0.20%
Installation 0.75%
Partition Concrete Hollow Blocks
Reinforcement 0.20%
Installation 1.00%
Plastering (Exterior) 5.00%
Plastering (Interior) 3.00%
Plastering (Parapet/Firewall) 1.50%
ELECTRICAL WORKS 3.25%
Rough-ins
Installation of Electrical Pipes 1.00%
Installation of Electrical Wires & Cables 0.50%
Electrical Fixtures and Equipment
Installation of Panel Box & Circuit Breaker 0.75%
Installation of Convenience Outlet & Switches 1.00%
PLUMBING & SANITARY WORKS 2.35%
Rough-ins
Installation of Sanitary Pipes and Fittings 1.25%
Installation of Water Pipes and Fittings 0.75%
Plumbing Fixtures
Installation of Water Closets 0.10%
Installation of Lavatories 0.10%
Installation of Floor Drains 0.05%
Installation of Shower Heads 0.10%
WOOD WORKS 7.85%
Ceiling
Ceiling Framing (Installation) 1.25%
Ceiling Boards (Installation) 1.50%
Doors and Door Jambs
Door (Installation) 1.00%
Door Jamb (Installation) 1.50%
Cabinet Door (Installation) 1.00%
Cabinet Door Jamb (Installation / Fabrication) 0.75%
Door Knob / Cabinet Handle (Installation) 0.10%
PVC Door and Jamb (Installation) 0.50%
Stair Railings (Wood-Installation) 0.25%
TILE WORKS 5.90%
Waterproofing (CR Second Floor) 0.50%
Floor Tiles
Ground Floor 0.50%
Second Floor 0.50%
CR - Ground Floor 0.25%
CR - Second Floor 0.25%
Balcony 0.20%
Stair 0.20%
Wall Tiles
CR - Ground Floor 1.00%
CR - Second Floor 1.00%
Kitchen Counter Top ( Granite / Tiles ) 0.75%
Wall Cladding 0.75%
RAILINGS 0.85%
Stair Railings
Fabrication 0.35%
Installation 0.50%
Balcony 0.80%
Fabrication 0.58%
Installation 0.22%
ROOFING WORKS
Roof Framing 1.00%
Fabrication/Installation 1.00%
Roof Sheet and Accessories 1.30%
Gutter (Fabrication/Installation) 0.60%
Roof Sheet (Installation) 0.25%
Roofing Accessories (Installation) 0.45%
PAINTING WORKS 14.75%
Exterior Paint
Skimcoating White 1.60%
Sanding 1.30%
Primer 0.70%
Final Painting 0.75%
Interior Paint
Skimcoating Grey 1.25%
Skimcoating White 1.40%
Sanding 1.30%
Primer 0.70%
Final Painting 0.75%
Doors , Jambs, Cabinet Doors & Stair Railings Varnishing
Preparation 2.50%
Final Coating 0.50%
Ceiling
Preparation 1.50%
Final Coating 0.50%
FINISHING WORKS 2.90%
Ground Preparation
Garage
Preparation 0.30%
Rebar Works 0.50%
Concrete Works 0.50%
Laundry
Preparation 0.30%
Rebar Works 0.50%
Concrete Works 0.50%
Punchlisting 0.30%
Total % per week 100.00%
To Date %
PROJECT: DEVV - FSTN PROJECT:
LOCATION: LOCATION:
AMOUNT PER SQ.M.: 4,000.00 AMOUNT PER
AREA: 64.00 AREA:
TCP: 256,000.00 TCP:

EARTHWORKS 2.30% WT EARTHW


Trimming of Wall Footing 0.50%
Backfilling and Compaction 0.80%
Septic Tank Fabrication 1.00%
STRUCTURAL 42.00% STRUCTU
Column Footing
Rebars (Fabrication/Installation) 0.50%
Concrete Works 1.00%
Wall Footing
Rebars (Fabrication/Installation) 0.50%
Concrete Works 1.00%
Column ( Ftg to 2F)
Rebars (Fabrication/Installation) 1.00%
Formworks (Fabrication / Installation /Dismantling) 1.00%
Concrete Works 1.50%
Beam
Rebars (Fabrication/Installation) 1.50%
Formworks (Fabrication / Installation /Dismantling) 1.00%
Concrete Works 1.50%
Column ( 2F to Roof Beam)
Rebars (Fabrication/Installation) 2.00%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 1.50%
Roof Beam
Rebars (Fabrication/Installation) 2.00%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 2.00%
Column ( Roof Beam to Parapet)
Rebars (Fabrication/Installation) 2.00%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 1.50%
Second Floor Slab
Rebars (Fabrication/Installation) - One-way Slab 1.00%
Formworks (Fabrication / Installation /Dismantling) 0.25%
Steel Decking Installation 1.00%
Concrete Works 2.50%
Stairs
Rebars (Fabrication/Installation) 0.75%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 1.50%
Slab-on-Fill / Slab-on-Grade
Preparation (Backfilling / Gravel Bedding) 0.25%
Rebar Works 0.75%
Concrete Works 1.50%
Kitchen Counter Top
Rebars (Fabrication/Installation) 0.25%
Formworks (Fabrication / Installation /Dismantling) 0.10%
Concrete Works 1.00%
Laundry Countertop
Rebars (Fabrication/Installation) 0.10%
Formworks (Fabrication / Installation /Dismantling) 0.05%
Concrete Works 0.50%
Erection of Scaffoldings 3.00%
MASONRY WORKS 14.75% MASONR
Wall Footing Concrete Hollow Blocks
Reinforcement 0.20%
Installation 0.50%
GF Concrete Hollow Blocks
Reinforcement 0.20%
Installation 1.00%
2F Concrete Hollow Blocks
Reinforcement 0.20%
Installation 1.00%
Parapet Concrete Hollow Blocks
Reinforcement 0.20%
Installation 0.75%
Partition Concrete Hollow Blocks
Reinforcement 0.20%
Installation 1.00%
Plastering (Exterior) 5.00%
Plastering (Interior) 3.00%
Plastering (Parapet/Firewall) 1.50%
ELECTRICAL WORKS 3.25% ELECTRIC
Rough-ins
Installation of Electrical Pipes 1.00%
Installation of Electrical Wires & Cables 0.50%
Electrical Fixtures and Equipment
Installation of Panel Box & Circuit Breaker 0.75%
Installation of Convenience Outlet & Switches 1.00%
PLUMBING & SANITARY WORKS 2.35% PLUMBIN
Rough-ins
Installation of Sanitary Pipes and Fittings 1.25%
Installation of Water Pipes and Fittings 0.75%
Plumbing Fixtures
Installation of Water Closets 0.10%
Installation of Lavatories 0.10%
Installation of Floor Drains 0.05%
Installation of Shower Heads 0.10%
WOOD WORKS 7.85% WOOD W
Ceiling
Ceiling Framing (Installation) 1.25%
Ceiling Boards (Installation) 1.50%
Doors and Door Jambs
Door (Installation) 1.00%
Door Jamb (Installation) 1.50%
Cabinet Door (Installation) 1.00%
Cabinet Door Jamb (Installation / Fabrication) 0.75%
Door Knob / Cabinet Handle (Installation) 0.10%
PVC Door and Jamb (Installation) 0.50%
Stair Railings (Wood-Installation) 0.25%
TILE WORKS 5.90% TILE WOR
Waterproofing (CR Second Floor) 0.50%
Floor Tiles
Ground Floor 0.50%
Second Floor 0.50%
CR - Ground Floor 0.25%
CR - Second Floor 0.25%
Balcony 0.20%
Stair 0.20%
Wall Tiles
CR - Ground Floor 1.00%
CR - Second Floor 1.00%
Kitchen Counter Top ( Granite / Tiles ) 0.75%
Wall Cladding 0.75%
RAILINGS 0.85% RAILINGS
Stair Railings
Fabrication 0.35%
Installation 0.50%
Balcony 0.80%
Fabrication 0.58%
Installation 0.22%
ROOFING WORKS ROOFING
Roof Framing 1.00%
Fabrication/Installation 1.00%
Roof Sheet and Accessories 1.30%
Gutter (Fabrication/Installation) 0.60%
Roof Sheet (Installation) 0.25%
Roofing Accessories (Installation) 0.45%
PAINTING WORKS 14.75% PAINTING
Exterior Paint
Skimcoating White 1.60%
Sanding 1.30%
Primer 0.70%
Final Painting 0.75%
Interior Paint
Skimcoating Grey 1.25%
Skimcoating White 1.40%
Sanding 1.30%
Primer 0.70%
Final Painting 0.75%
Doors , Jambs, Cabinet Doors & Stair Railings Varnishing
Preparation 2.50%
Final Coating 0.50%
Ceiling
Preparation 1.50%
Final Coating 0.50%
FINISHING WORKS 2.90% FINISHIN
Ground Preparation
Garage
Preparation 0.30%
Rebar Works 0.50%
Concrete Works 0.50%
Laundry
Preparation 0.30%
Rebar Works 0.50%
Concrete Works 0.50%
Punchlisting 0.30%
Total % per week 100.00%
To Date %
ECT: DEVV - FSTN
ATION:
UNT PER SQ.M.: 4,400.00
84.00
369,600.00

ARTHWORKS 2.30% WT
Trimming of Wall Footing 0.50%
Backfilling and Compaction 0.80%
Septic Tank Fabrication 1.00%
TRUCTURAL 42.00%
Column Footing
Rebars (Fabrication/Installation) 0.50%
Concrete Works 1.00%
Wall Footing
Rebars (Fabrication/Installation) 0.50%
Concrete Works 1.00%
Column ( Ftg to 2F)
Rebars (Fabrication/Installation) 1.00%
Formworks (Fabrication / Installation /Dismantling) 1.00%
Concrete Works 1.50%
Beam
Rebars (Fabrication/Installation) 1.50%
Formworks (Fabrication / Installation /Dismantling) 1.00%
Concrete Works 1.50%
Column ( 2F to Roof Beam)
Rebars (Fabrication/Installation) 2.00%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 1.50%
Roof Beam
Rebars (Fabrication/Installation) 2.00%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 2.00%
Column ( Roof Beam to Parapet)
Rebars (Fabrication/Installation) 2.00%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 1.50%
Second Floor Slab
Rebars (Fabrication/Installation) - One-way Slab 1.00%
Formworks (Fabrication / Installation /Dismantling) 0.25%
Steel Decking Installation 1.00%
Concrete Works 2.50%
Stairs
Rebars (Fabrication/Installation) 0.75%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 1.50%
Slab-on-Fill / Slab-on-Grade
Preparation (Backfilling / Gravel Bedding) 0.25%
Rebar Works 0.75%
Concrete Works 1.50%
Kitchen Counter Top
Rebars (Fabrication/Installation) 0.25%
Formworks (Fabrication / Installation /Dismantling) 0.10%
Concrete Works 1.00%
Laundry Countertop
Rebars (Fabrication/Installation) 0.10%
Formworks (Fabrication / Installation /Dismantling) 0.05%
Concrete Works 0.50%
Erection of Scaffoldings 3.00%
MASONRY WORKS 14.75%
Wall Footing Concrete Hollow Blocks
Reinforcement 0.20%
Installation 0.50%
GF Concrete Hollow Blocks
Reinforcement 0.20%
Installation 1.00%
2F Concrete Hollow Blocks
Reinforcement 0.20%
Installation 1.00%
Parapet Concrete Hollow Blocks
Reinforcement 0.20%
Installation 0.75%
Partition Concrete Hollow Blocks
Reinforcement 0.20%
Installation 1.00%
Plastering (Exterior) 5.00%
Plastering (Interior) 3.00%
Plastering (Parapet/Firewall) 1.50%
LECTRICAL WORKS 3.25%
Rough-ins
Installation of Electrical Pipes 1.00%
Installation of Electrical Wires & Cables 0.50%
Electrical Fixtures and Equipment
Installation of Panel Box & Circuit Breaker 0.75%
Installation of Convenience Outlet & Switches 1.00%
LUMBING & SANITARY WORKS 2.35%
Rough-ins
Installation of Sanitary Pipes and Fittings 1.25%
Installation of Water Pipes and Fittings 0.75%
Plumbing Fixtures
Installation of Water Closets 0.10%
Installation of Lavatories 0.10%
Installation of Floor Drains 0.05%
Installation of Shower Heads 0.10%
WOOD WORKS 7.85%
Ceiling
Ceiling Framing (Installation) 1.25%
Ceiling Boards (Installation) 1.50%
Doors and Door Jambs
Door (Installation) 1.00%
Door Jamb (Installation) 1.50%
Cabinet Door (Installation) 1.00%
Cabinet Door Jamb (Installation / Fabrication) 0.75%
Door Knob / Cabinet Handle (Installation) 0.10%
PVC Door and Jamb (Installation) 0.50%
Stair Railings (Wood-Installation) 0.25%
LE WORKS 5.90%
Waterproofing (CR Second Floor) 0.50%
Floor Tiles
Ground Floor 0.50%
Second Floor 0.50%
CR - Ground Floor 0.25%
CR - Second Floor 0.25%
Balcony 0.20%
Stair 0.20%
Wall Tiles
CR - Ground Floor 1.00%
CR - Second Floor 1.00%
Kitchen Counter Top ( Granite / Tiles ) 0.75%
Wall Cladding 0.75%
AILINGS 0.85%
Stair Railings
Fabrication 0.35%
Installation 0.50%
Balcony 0.80%
Fabrication 0.58%
Installation 0.22%
OOFING WORKS
Roof Framing 1.00%
Fabrication/Installation 1.00%
Roof Sheet and Accessories 1.30%
Gutter (Fabrication/Installation) 0.60%
Roof Sheet (Installation) 0.25%
Roofing Accessories (Installation) 0.45%
AINTING WORKS 14.75%
Exterior Paint
Skimcoating White 1.60%
Sanding 1.30%
Primer 0.70%
Final Painting 0.75%
Interior Paint
Skimcoating Grey 1.25%
Skimcoating White 1.40%
Sanding 1.30%
Primer 0.70%
Final Painting 0.75%
Doors , Jambs, Cabinet Doors & Stair Railings Varnishing
Preparation 2.50%
Final Coating 0.50%
Ceiling
Preparation 1.50%
Final Coating 0.50%
NISHING WORKS 2.90%
Ground Preparation
Garage
Preparation 0.30%
Rebar Works 0.50%
Concrete Works 0.50%
Laundry
Preparation 0.30%
Rebar Works 0.50%
Concrete Works 0.50%
Punchlisting 0.30%
Total % per week 100.00%
To Date %
PROJECT: DEVV - FSTN
LOCATION:
Foreman Assigned:
Date Started:
Turn-over Date:

EARTHWORKS 1.25% WT
Clearing / Layouting 0.05%
Excavation 1.00%
Trimming of Wall Footing 0.15%
Backfilling and Compaction 0.50%
Septic Tank Fabrication 0.60%
STRUCTURAL 42.00%
Column Footing
Rebars (Fabrication/Installation) 0.50%
Concrete Works 1.00%
Wall Footing
Rebars (Fabrication/Installation) 0.50%
Concrete Works 1.00%
Column ( Ftg to 2F)
Rebars (Fabrication/Installation) 1.00%
Formworks (Fabrication / Installation /Dismantling) 1.00%
Concrete Works 1.50%
Beam
Rebars (Fabrication/Installation) 1.50%
Formworks (Fabrication / Installation /Dismantling) 1.00%
Concrete Works 1.50%
Column ( 2F to Roof Beam)
Rebars (Fabrication/Installation) 2.00%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 1.50%
Roof Beam
Rebars (Fabrication/Installation) 2.00%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 2.00%
Column ( Roof Beam to Parapet)
Rebars (Fabrication/Installation) 2.00%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 1.50%
Second Floor Slab
Rebars (Fabrication/Installation) - One-way Slab 1.00%
Formworks (Fabrication / Installation /Dismantling) 0.25%
Steel Decking Installation 1.00%
Concrete Works 2.50%
Stairs
Rebars (Fabrication/Installation) 0.75%
Formworks (Fabrication / Installation /Dismantling) 1.50%
Concrete Works 1.50%
Slab-on-Fill / Slab-on-Grade
Preparation (Backfilling / Gravel Bedding) 0.25%
Rebar Works 0.75%
Concrete Works 1.50%
Kitchen Counter Top
Rebars (Fabrication/Installation) 0.25%
Formworks (Fabrication / Installation /Dismantling) 0.10%
Concrete Works 1.00%
Laundry Countertop
Rebars (Fabrication/Installation) 0.10%
Formworks (Fabrication / Installation /Dismantling) 0.05%
Concrete Works 0.50%
Erection of Scaffoldings 3.00%
MASONRY WORKS 14.75%
Wall Footing Concrete Hollow Blocks
Reinforcement 0.20%
Installation 0.50%
GF Concrete Hollow Blocks
Reinforcement 0.20%
Installation 1.00%
2F Concrete Hollow Blocks
Reinforcement 0.20%
Installation 1.00%
Parapet Concrete Hollow Blocks
Reinforcement 0.20%
Installation 0.75%
Partition Concrete Hollow Blocks
Reinforcement 0.20%
Installation 1.00%
Plastering (Exterior) 5.00%
Plastering (Interior) 3.00%
Plastering (Parapet/Firewall) 1.50%
ELECTRICAL WORKS 3.25%
Rough-ins
Installation of Electrical Pipes 1.00%
Installation of Electrical Wires & Cables 0.50%
Electrical Fixtures and Equipment
Installation of Panel Box & Circuit Breaker 0.75%
Installation of Convenience Outlet & Switches 1.00%
PLUMBING & SANITARY WORKS 2.35%
Rough-ins
Installation of Sanitary Pipes and Fittings 1.25%
Installation of Water Pipes and Fittings 0.75%
Plumbing Fixtures
Installation of Water Closets 0.10%
Installation of Lavatories 0.10%
Installation of Floor Drains 0.05%
Installation of Shower Heads 0.10%
WOOD WORKS 7.85%
Ceiling
Ceiling Framing (Installation) 1.25%
Ceiling Boards (Installation) 1.50%
Doors and Door Jambs
Door (Installation) 1.00%
Door Jamb (Installation) 1.50%
Cabinet Door (Installation) 1.00%
Cabinet Door Jamb (Installation / Fabrication) 0.75%
Door Knob / Cabinet Handle (Installation) 0.10%
PVC Door and Jamb (Installation) 0.50%
Stair Railings (Wood-Installation) 0.25%
TILE WORKS 5.90%
Waterproofing (CR Second Floor) 0.50%
Floor Tiles
Ground Floor 0.50%
Second Floor 0.50%
CR - Ground Floor 0.25%
CR - Second Floor 0.25%
Balcony 0.20%
Stair 0.20%
Wall Tiles
CR - Ground Floor 1.00%
CR - Second Floor 1.00%
Kitchen Counter Top ( Granite / Tiles ) 0.75%
Wall Cladding 0.75%
RAILINGS 0.85%
Stair Railings
Fabrication 0.35%
Installation 0.50%
Balcony 0.80%
Fabrication 0.58%
Installation 0.22%
ROOFING WORKS
Roof Framing 1.00%
Fabrication/Installation 1.00%
Roof Sheet and Accessories 1.30%
Gutter (Fabrication/Installation) 0.60%
Roof Sheet (Installation) 0.25%
Roofing Accessories (Installation) 0.45%
PAINTING WORKS 14.75%
Exterior Paint
Skimcoating White 1.60%
Sanding 1.30%
Primer 0.70%
Final Painting 0.75%
Interior Paint
Skimcoating Grey 1.25%
Skimcoating White 1.40%
Sanding 1.30%
Primer 0.70%
Final Painting 0.75%
Doors , Jambs, Cabinet Doors & Stair Railings Varnishing
Preparation 2.50%
Final Coating 0.50%
Ceiling
Preparation 1.50%
Final Coating 0.50%
FINISHING WORKS 2.90%
Ground Preparation
Garage
Preparation 0.30%
Rebar Works 0.50%
Concrete Works 0.50%
Laundry
Preparation 0.30%
Rebar Works 0.50%
Concrete Works 0.50%
Punchlisting 0.30%
Total % per week 100.00%