You are on page 1of 3

2ND FLOOR SENIOR HIGH SCHOOL

ST. JOSEPH COMMUNITY HIGH


SAPAD, LANAO DEL NORTE

BILL OFMATERIALS AND ESTIMATE

I. CONCRETE WORKS: Php 232, 250.00

65 m3 Gravel ₱ 1,000.00 ₱ 65,000.00


650 bags Cement 225.00 146,250.00
35 m3 Sand 600.00 21,000.00

II. MASONRY WORKS: Php 124, 385.00

2,775 pc 4” CHB ₱ 14.00 ₱ 38,850.00


120 bags Cement 225.00 27,000.00
17 m3 Sand 600.00 10,200.00
320 pc 10mmɸ DSB 148.00 47,360.00
15 kls #16 Tie wire 65.00 975.00

III. FINISHES: Php 83, 925.00

293 bags Cement ₱ 225.00 ₱ 65,925.00


30 m3 Sand 600.00 18,000.00

IV. REBARS: Php 345, 383.00

595 pc 9mmɸ RSB ₱ 95.00 ₱ 56,525.00


516 pc 10mmɸ RSB 148.00 76,368.00
15 pc 12mmɸ RSB 190.00 2,850.00
260 pc 16mmɸ RSB 385.00 100,100.00
53 pc 20mmɸ RSB 680.00 36,040.00
75 pc 25mmɸ RSB 980.00 73,500.00

V. FORMWORKS: Php 322, 040.00

300 pc 2 x 4 x 12 – 2,400 BF
750 pc 2 X 3 X 12 – 4,500 ₱ 18.00 ₱ 210,600.00
1,200 pc 2 X 2 X 12 – 4,800
11,700 BF

128 pc ½ x 4 x 8 plywood 580.00 74,240.00


12 box’s 4” CWNails 1,000.00 12,000.00
5 box’s 3” CWNails 1,000.00 5,000.00
4 box’x 2 ½ ” CWNails 1,000.00 4,000.00
2 box’s 1 ½ ” CWNails 1,000.00 3,000.00
8 rolls # 16 Tie wire 1,650.00 13,200.00

VI. DOORS: Php 15, 840.00

6 sets (2.10 x 0.90) panel door ₱ 2,100.00 ₱ 12,600.00


9 pairs 3 ½ x 3 ½ loose pin hinges 150.00 1,350.00
6 sets Hapslock master 250.00 1,500.00
6 pc Door handle 6” 65.00 390.00

VII. WINDOWS: Php 23, 520.00

504 pc ¼ x 4 x 26” glass blade ₱ 35.00 ₱ 17,640.00


42 pairs Alum. Frame x 1.10 140.00 5,880.00

VIII. ELECTRICAL WORKS: Php 30, 000.00


IX. PAINTING WORKS: Php 50, 000.00

X. STAIRWELL; HANDRAIL Php 129, 010.00

2 pc 4” ɸ 6.1 pipe ₱ 5,200.00 ₱ 10,400.00


7 pc ¼x2x2x6L 780.00 5,460.00
16 pc 3/16 x 2 x 2 x 6 L 720.00 11,520.00
4 pc 3/16 x 1 x 1 x 6 L 380.00 1,520.00
5 pc Steel mating 600.00 3,000.00
16 pc 3” ɸ x 20’ stainless 2,500.00 40,000.00
40 pc 1” ɸ x 20’ stainless 1,300.00 52,000.00
12 pc 3” ɸ elbow 130.00 1,560.00
10 bags Cement 225.00 2,250.00
1 m3 Gravel 1,000.00 1,000.00
½ m3 Sand 600.00 300.00

XI. STEEL TRUSS (9 SETS) Php 144, 980.00

54 pc 3/16 x 1 ½ x 1½ x 6m Top ₱ 560.00 ₱ 30,240.00


31 pc 3/16 x 1½ x 1½ x 6m Bot 560.00 17,360.00
8 pc 3/16 x 1½ x 1½ x 6m S-Post 560.00 4,480.00
29 pc 3/16 x 2 x 2 x 6m S Post, Web 720.00 20,880.00
20 pc 3/16 x 1½ x 1½ x 6m cross C-Purlins 560.00 11,200.00
108 pc 1.2 x 2 x 3 x 6 C-Purlins 420.00 45,360.00
10 pc 10mmɸ bracing 148.00 1,480.00
30 pc 1/8 x 1 x 1 x 6m L 320.00 9,600.00
15 pc 10mmɸ RSB 148.00 2,220.00
18 pc 12mmɸ turnbuckle 120.00 2,160.00

XII. ROOF SHEATING: Php 69, 559.00

29 L 0.35 x 1.00 x 6.70 prepainted ₱ 1,541.00 ₱ 44,689.00


1000 pc 2 ½ tekscrew 2.00 2,000.00
25 pc Box gutter x 24” 380.00 9,500.00
12 pc Gutter fuush x 24” 380.00 4,560.00
4 box’s ½ x 1/8 blind rivets 250.00 1,000.00
2 Ltrs Vulca seal 380.00 760.00
6 pc 9/64 drill bit 65.00 390.00
37 pc Fascia cap 12” x 2.40 180.00 6,660.00

XIII. REFLECTED CEILING: Php 104, 534.00


1. INSIDE

95 pc 3/16 x 4 x 8 HardiLight ₱ 320.00 ₱ 30,400.00


450 pc 1 x 2 x 17 metal faring 95.00 42,750.00
15 box’s 1/8 x ½ b.rivets 250.00 3,750.00
2. OUTSIDE

80 pc 1 x 2 x 17 metal faring ₱ 95.00 ₱ 7,600.00


57 pc 0.3mm x 1.00 x 1.00 mini ribs 210.00 11,970.00
2 pc 0.3mm x 1.00 x 6.70 mini ribs 1,407.00 2,814.00
10 pc 0.3mm x 2.5 x 1.00 mini ribs 525.00 5,250.00

SUMMARY

A. MATERIALS Php 1, 675, 426.00


B. LABOR 753, 941.00
2, 429, 367.00
C. CONTENGENCIES 320, 633.00
GRAND TOTAL Php 2, 750, 000.00