Activity ID Activity Name Original Performance % BL Project Start BL Project Finish Actual Start Actual Finish Qtr 2, 2019 Qtr 3, 2019
Duration Complete
Jun Jul
29d 0% May-29-19 Jul-03-19 May-01-19 Holcim Catch Up Plan Rev 1.2, 21.23%
Holcim Catch Up Plan Rev 1.2
Warehouse Overall 29d 0% May-29-19 Jul-03-19 May-29-19 Warehouse Overall, 21.23%
IMPORTANT NOTES
Actual Level of Effort Summary Page 1
Actual Work Uncontrolled Factors that may cause delays:
Remaining Work
Critical Remaining Work 1. Climate Change (Rainy Season)
Milestone
2. Safety
% Complete
Holcim Catch Up Plan Rev 1.2
Activity ID Activity Name Original Performance % BL Project Start BL Project Finish Actual Start Actual Finish Qtr 2, 2019 Qtr 3, 2019
Duration Complete
Jun Jul
A1410 Dwarf Wall: 2nd Coat Application 2d 0% Jun-03-19 Jun-04-19
A1480 Flooring: Epoxy Paint Application 2d 0% Jun-05-19 Jun-06-19
Hardwares & Accesories 6d 0% Jun-07-19 Jun-14-19 Hardwares & Accesories, 0%
A1490 Sliding Doors Installation 6d 0% Jun-07-19 Jun-14-19
MCC ROOM 3d 0% May-29-19 May-31-19 May-29-19 MCC ROOM, 70%
A1740 CHB Perimeter Laying 3d 70% May-29-19 May-31-19 May-29-19 70%
CONVEYOR GALLERY 9d 0% May-29-19 Jun-08-19 May-01-19 CONVEYOR GALLERY, 0%
IMPORTANT NOTES
Actual Level of Effort Summary Page 2
Actual Work Uncontrolled Factors that may cause delays:
Remaining Work
Critical Remaining Work 1. Climate Change (Rainy Season)
Milestone
2. Safety
% Complete