1. Scope of Work
3. System Proposal
Description
MASTERPROTECT 1812 is a two-component solvent free pitch extended epoxy resin system
to provide high build protective coating that protects concrete and metal substrate from a wide
range of aggressive chemicals
Applications include:
Advantages
2. Application Procedure
a. Construction Joint Treatment –
• Installing hydro swelling waterbar MasterSeal 910 with MasterSeal 911 adhesive
while doing casting of concrete
• Packing and filling of construction joint with MasterEmaco S 348 and injection
grouting
b. Surface Preparation – Grinding the surface and cleaning the surface
e. Treating Leakages – Any leakages found must be treated with injection of MasterSeal
901 and observe for 12 hours for further leakages
f. Defects in the concrete surface – Defects treatment with MasterEmaco S 348 mortar
Construction joints at the retaining wall shall be installed with MASTERSEAL 910; 20mm x
10mm cross-sectional sized hydro-swelling water bar based on advance vinylacrylate
polymers. The waterbar shall be formulated to exhibit low pre-mature swelling (less then
50% with in 12 hours) and shall not be based on super absorbents. The water bar shall have
low swelling pressure; not exceeding 0.25 MPa at full swelling capacity. The waterbar shall
be installed with special adhesive.
1. MASTERSEAL 910 hydrophilic acrylate-based water bar shall be placed in all construction
joints.
2. The concrete substrate to which the MASTERSEAL 910 is to be fixed must be smooth and
sound.
3. Cut the MASTERSEAL 910 to the required length .
4. Fix the MASTERSEAL 910 to the concrete substrate using MASTERSEAL 911 Adhesive.
Apply light tension to the MASTERSEAL 910 as it is being fixed. Allow the adhesive on
the verticals to dry at least over night before concreting.
5. Protect the fixed MASTERSEAL 910 from mould release oil and dirt. Do not saturate the
water bar before concreting as this may cause it to swell. Protect is against rain and curing
water.
6. After placement of the MASTERSEAL 910, cast the next concrete pour.
NOTE: PLEASE REFER THE TECHNICAL DATA SHEET OF MASTERSEAL 910 FOR MORE
DETAILS
• PACKING AND FILLING OF CONSTRUCTION JOINT
➢ Grove Cutting – Construction Joint must be grove cut until the depth of 25mm
X 25mm and filled with MasterEmaco S 348 repair mortar and allow it to cure
for 7 days
• The concrete Substrate shall be free from oil, grease, mold release agent, curing
membrane, to do the application
2.c) Coving –
Providing coving of 75mm X 75mm at wall and slab joint with MasterEmaco S 348 thixotropic
repair mortar
2.d) Water Ponding – After coving with MasterEmaco S 348, fill the tank with water and
observe the leakages after 36 hour
2.e) Treating of Leakages –
Any leakages found after water ponding to be treated by injecting three component MasterSeal
901 (Vinyl Ester Methacrylate Resin) by installing packers in zigzag pattern using
MasterEmaco S 348 at 45 degrees and observe for 12 hours for any further leakages continue
the same procedure for the treatment of leakages.
Using a stiff brush, work the bonding slurry well into the damp surface (the surface
needs to be in SSD condition)
After application, cure the surface for minimum 3 days and then do application of
Master Protect 180
The above activity needs to be done after all the surface preparation works like removal
of loose particles, construction joint treatment and other preparatory works is complete
Providing and applying two component, solvent free, pitch extended epoxy resin system
MasterProtect 1812
Mixing
MasterProtect 1812 can be using short nap roller, shorthaired brush in two coats and each
at wet film thickness of 150 microns and the second coat applied after the first coat has dried
(4 to 6 hrs)