You are on page 1of 5

MALL OF SARGODHA

RCC PIPE DESIGN FOR DISPOSAL


FROM SITE 3 TO OUTLET

1- Design flow required 10 Cusecs


2- Use Manning’s formula =1.486/n*AR(2/3)S(1/2)
= C1* S(1/2)
3- Available Slope = 4.37 feet in 2300 rft
= 0.0019
(1/2)
S =0.04359 use Table A-1

Q=10=C1*0.04359
C1=10/0.04359=229
From Table 3 nearest value using n=0.012 is of 24 inch diameter
MALL OF SARGODHA
RCC PIPE DESIGN FOR DISPOSAL
FROM SITE 4 TO OUTLET

1- Design flow required 10 Cusecs


2- Use Manning’s formula =1.486/n*AR(2/3)S(1/2)
= C1* S(1/2)
3- Available Slope = 4.00 feet in 7600 rft
= 0.00053
(1/2)
S =0.02302 use Table A-1

Q=10=C1*0.02302
C1=10/0.02302=434
From Table 3 nearest value using n=0.012 is of 30 inch diameter
MALL OF SARGODHA
RCC PIPE DESIGN FOR DISPOSAL
FROM SITE 3 TO SAIM NULLAH

S No Description Unit Quantity Rate Amount


1 Excavation Cft 46300
2 Bed under RCC pipe 6” PCC 1:2:4 Cft 1400
3 RCC Pipe 24” diameter Rft 2300
4 Back Fill Cft 15500
5 Disposal of Surplus Earth Cft 30809
6 Sand Filling Cft 18028
MALL OF SARGODHA
RCC PIPE DESIGN FOR DISPOSAL
FROM SITE 4 TO SAIM NULLAH

S No Description Unit Quantity Rate Amount


1 Excavation Cft 173888
2 Bed under RCC pipe 6” PCC 1:2:4 Cft 4940
3 RCC Pipe 30” diameter Rft 7600
4 Back Fill Cft 42365
5 Disposal of Surplus Earth Cft 131523
6 Sand Filling Cft 71919
MALL OF SARGODHA
RCC PIPE DESIGN FOR DISPOSAL
FROM SITE 4 TO SAIM NULLAH (Open Drain 30”x30”)

S No Description Unit Quantity Rate Amount


1 Excavation (Please check at site ) Cft 122436
2 Bed under RCC pipe 3” PCC 1:4:8 Cft 8550
3 PCC 1:2:4 Cft 22800
4 Brick Work Cft 28500
5 Plaster 1:4 Sft 106400
6 Back Fill Cft 18000
7 Disposal of Surplus Earth Cft 104436
Details of culverts at crossing