GROUP No.

: 2
Activity: Painting Works of Interior Walls for Three Classroom School Building
Workshop Output: RESPIRATORY PROTECTION
IDENTIFIED HAZARDS CONTROL MEASURES
ENGINEERING ADMINISTRATIVE

All doors and windows Maintain perimeter baricades to the


Exposure of Laborers, visitors should be open to
People and other students to paint avoid suphocation to construction site to prohibit unauthorized
fumes and dust persons from entering the site.
the painters

Possibility of exposure of Orientation and information desimination


hands and other parts of the n/a during tool box meeting.
body to toxic solvents

Equipment n/a

Impose no smoking/ policy while at work


and inform and train workers on the
proper use of fire extinguishers. Also
Provide fire orient or instruct laborers to read first the
extinguisher at job Materials Safety Data Sheet prior to using
Materials Possible source of fire site. the chemicals.

Impose proper
Possible damage to labelling and Orient and impose policy on proper waste
Environment environment due to segregation of disposal of materials used.
improper use and disposal. materials for use and
disposal.

Method
S
PPE

Provide air purifying


half face mask
respirators to laborers
and visitors entering
the jobsite

Provide leather gloves


to laborers doing the
sanding works and
vinyl and neoprene
gloves for laborers
doing painting works.

n/a
SAFETY AND HEALTH ACTIVITIES

A. DAILY ACTIVITIES
Check Safety Signages
Conduct of Tool Box Meeting
Conduct of House Keeping
Physical Exercise
Inventory of Tools and Equipment
Security Check
Manpower Check
Rest

B. WEEKLY ACTIVITIES
Inspection of Materials and Equipment condition at Site
Staff /BSPMC Meeting
Inventory of First Aid Kit
C. MONTHLY
Safety Audit