ANALISA HARGA SATUAN BOW 2010

PEKERJAAN KAYU
HARGA
KODE
INDEK SAT URAIAN HARGA SATUAN (Rp) BAHAN UPAH JUMLAH HARGA (Rp)
ANALISA
( Rp ) ( Rp )
A. PEKERJAAN PONDASI KAYU
A.1.BOW SEBUAH TONGKAT ULIN UK.10/10 CM TINGGI 2,00 M
DICINCIN, DILANCIP DAN DITUMBUK
0.0200 M3 Balok ulin @ 4,500,000.00 90,000.00
0.5100 OH tukang kayu @ 98,000.00 49,980.00
0.8750 OH pekerja @ 79,000.00 69,125.00
0.0510 OH kepala tukang @ 110,000.00 5,610.00
0.0440 OH mandor @ 110,000.00 4,840.00
JUMLAH 90,000.00 129,555.00 219,555.00
A.2 SEBUAH TONGKAT ULIN UK.12/12 CM TINGGI 8,00 M
2 SAMBUNGAN DGN PIPA GALVANIS
0.0800 M3 Balok ulin @ 4,500,000.00 360,000.00
0.5100 OH tukang kayu @ 98,000.00 49,980.00
0.8750 OH pekerja @ 79,000.00 69,125.00
0.0510 OH kepala tukang @ 110,000.00 5,610.00
0.0440 OH mandor @ 110,000.00 4,840.00
JUMLAH 360,000.00 129,555.00 489,555.00
A.3 SEBUAH TONGKAT ULIN UK.10/10 CM TINGGI 4,00 M'
0.0400 M3 Balok ulin @ 4,500,000.00 180,000.00
0.5100 OH tukang kayu @ 98,000.00 49,980.00
0.8750 OH pekerja @ 79,000.00 69,125.00
0.0510 OH kepala tukang @ 110,000.00 5,610.00
0.0440 OH mandor @ 110,000.00 4,840.00
JUMLAH 180,000.00 129,555.00 309,555.00
A. 4 1 M3 MENGERJAKAN PAPAN SIRING KAYU ULIN
1.1000 M3 papan siring kayu ulin @ 5,300,000.00 5,830,000.00
3.0000 kg paku ulin @ #REF! #REF!
15.0000 OH tukang kayu @ 98,000.00 1,470,000.00
4.0000 OH pekerja @ 79,000.00 316,000.00
1.5000 OH kepala tukang @ 110,000.00 165,000.00
0.2000 OH mandor @ 110,000.00 22,000.00
JUMLAH #REF! 1,973,000.00 #REF!
A. 5 1 M3 RANGKA BAWAH KAYU ULIN ( tiang + kalang, sunduk )
1.1000 M3 balok ky ulin @ 4,500,000.00 4,950,000.00
15.0000 OH tukang kayu @ 98,000.00 1,470,000.00
5.0000 OH pekerja @ 79,000.00 395,000.00
1.5000 OH kepala tukang @ 110,000.00 165,000.00
0.2500 OH mandor @ 110,000.00 27,500.00
JUMLAH 4,950,000.00 2,057,500.00 7,007,500.00
B. PEKERJAAN LANTAI KAYU
B. 1 1 M3 MENGERJAKAN SLOOF DAN GELAGAR KY ULIN
1.1000 M3 balok ky ulin @ 4,500,000.00 4,950,000.00
10.0000 Kg paku ulin @ #REF! #REF!
15.0000 OH tukang kayu @ 98,000.00 1,470,000.00
5.0000 OH pekerja @ 79,000.00 395,000.00
1.5000 OH kepala tukang @ 110,000.00 165,000.00
0.2500 OH mandor @ 110,000.00 27,500.00
JUMLAH #REF! 2,057,500.00 #REF!
B. 2 1 M2 LANTAI PAPAN KAYU ULIN DIKETAM
0.0254 M3 papan kayu ulin @ 5,300,000.00 134,620.00
0.2500 Kg paku ulin @ #REF! #REF!
0.8000 OH tukang kayu @ 98,000.00 78,400.00
0.2800 OH pekerja @ 79,000.00 22,120.00
0.0800 OH kepala tukang @ 110,000.00 8,800.00
0.0140 OH mandor @ 110,000.00 1,540.00
JUMLAH #REF! 110,860.00 #REF!
B. 3 1 M2 LANTAI PAPAN KAYU MERANTI DIKETAM
0.0254 M3 papan kayu meranti klas 1 @ 2,920,320.00 74,176.13
0.2500 Kg paku biasa @ 20,500.00 5,125.00
0.8000 OH tukang kayu @ 98,000.00 78,400.00
0.2800 OH pekerja @ 79,000.00 22,120.00
0.0800 OH kepala tukang @ 110,000.00 8,800.00
0.0140 OH mandor @ 110,000.00 1,540.00
JUMLAH 79,301.13 110,860.00 190,161.13
B. PEKERJAAN DINDING KAYU
B. 4 1 M3 MENGERJAKAN RANGKA RUMAH KAYU ULIN (termasuk kusen)
1.1000 M3 balok ky ulin @ 4,500,000.00 4,950,000.00
5.0000 Kg paku ulin @ #REF! #REF!
20.0000 OH tukang kayu @ 98,000.00 1,960,000.00
10.0000 OH pekerja @ 79,000.00 790,000.00
2.0000 OH kepala tukang @ 110,000.00 220,000.00
0.5000 OH mandor @ 110,000.00 55,000.00
JUMLAH #REF! 3,025,000.00 #REF!
B. 5 1 M3 MENGERJAKAN RANGKA RUMAH KAYU MERANTI (termasuk kusen)
1.1000 M3 balok ky meranti @ 2,650,000.00 2,915,000.00
5.0000 Kg paku biasa @ 20,500.00 102,500.00
20.0000 OH tukang kayu @ 98,000.00 1,960,000.00
10.0000 OH pekerja @ 79,000.00 790,000.00
2.0000 OH kepala tukang @ 110,000.00 220,000.00
0.5000 OH mandor @ 110,000.00 55,000.00
JUMLAH 3,017,500.00 3,025,000.00 6,042,500.00

B. 6 1 M2 DINDING PAPAN ULIN DIKETAM


0.0240 M3 papan kayu ulin @ 5,300,000.00 127,200.00
0.2000 Kg paku ulin @ #REF! #REF!
0.8000 OH tukang kayu @ 98,000.00 78,400.00
0.2800 OH pekerja @ 79,000.00 22,120.00
0.0800 OH kepala tukang @ 110,000.00 8,800.00
0.0100 OH mandor @ 110,000.00 1,100.00
JUMLAH #REF! 110,420.00 #REF!

B. 7 1 M2 DINDING PAPAN MERANTI DIKETAM


0.0240 M3 papan kayu meranti @ 2,920,320.00 70,087.68
0.2000 Kg paku biasa @ 20,500.00 4,100.00
0.8000 OH tukang kayu @ 98,000.00 78,400.00
0.2800 OH pekerja @ 79,000.00 22,120.00
0.0800 OH kepala tukang @ 110,000.00 8,800.00
0.0100 OH mandor @ 110,000.00 1,100.00
JUMLAH 74,187.68 110,420.00 184,607.68

B. 8 1 M2 DINDING SUSUN SIRIH PAPAN MERANTI


0.0250 M3 papan kayu meranti @ 2,920,320.00 73,008.00
0.1500 Kg paku biasa @ 20,500.00 3,075.00
0.4000 OH tukang kayu @ 98,000.00 39,200.00
0.1400 OH pekerja @ 79,000.00 11,060.00
0.0400 OH kepala tukang @ 110,000.00 4,400.00
0.0070 OH mandor @ 110,000.00 770.00
JUMLAH 76,083.00 55,430.00 131,513.00
B. 9 1 M2 DINDING PAPAN MERANTI SUSUN SIRIH DIKETAM
0.0250 M3 papan kayu meranti @ 2,920,320.00 73,008.00
0.2000 Kg paku biasa @ 20,500.00 4,100.00
0.8000 OH tukang kayu @ 98,000.00 78,400.00
0.2800 OH pekerja @ 79,000.00 22,120.00
0.0800 OH kepala tukang @ 110,000.00 8,800.00
0.0100 OH mandor @ 110,000.00 1,100.00
JUMLAH 77,108.00 110,420.00 187,528.00

B. 10 1 M2 MENGERJAKAN DINDING PARTISI KAYU


MERANTI DAN LAPISAN MULTIPLEK 9 MM
0.0210 M3 papan kayu meranti @ 2,920,320.00 61,326.72
0.7000 LBR Multiplek 9 mm @ #REF! #REF!
0.0400 KG Paku biasa @ 20,500.00 820.00
0.0400 KG Paku plywood @ #REF! #REF!
0.0150 OH Tukang kayu @ 98,000.00 1,470.00
0.8000 OH Pekerja @ 79,000.00 63,200.00
0.0150 OH kepala tukang @ 110,000.00 1,650.00
0.0400 OH Mandor @ 110,000.00 4,400.00
JUMLAH #REF! 70,720.00 #REF!
NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)
G. PEKERJAAN BETON
G.6.6.1 1 M3 BETON TUMBUK 1 pc ; 3 ps ; 5 kr #REF!
G.6.6.2 1 M3 BETON TUMBUK 1 pc ; 3 ps ; 6 kr #REF!
G.6.6.3 1 M3 BETON TUMBUK 1 pc ; 4 ps ; 6 kr #REF!
G.6.6.4 1 M3 MEMBUAT LANTAI KERJA BETON TUMBUK 1 pc ; 3 ps ; 5 kr #REF!
G.6.6.5. 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ; 3 kr) #REF!
G.6.6.6 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ; 4 kr) #REF!
G.6.6.7 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ;2,5 kr) #REF!
G.6.6.8 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1,5 ps ; 3 kr) #REF!
G.6.6.9 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1,5 ps ;2,5 kr) #REF!
G.6.6.10 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1 ps ; 2 kr) #REF!
G.6.6.11 1M3 MEMBUAT TIANG PANCANG PRESTRESSED BETON #REF!
G.6.6.12 1M3 MEMBUAT BETON DENGAN PUZZDITH - 100 XR #REF!
G.6.6.13 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ;3 kr) #REF!
G.6.6.14 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 2 ps ; 4 kr) #REF!
G.6.6.15 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1,5 ps ;3kr) #REF!
G.6.6.16 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1,5 ps ; 2,5 kr) #REF!
G.6.6.17 1 M3 MEMBUAT BETON BERTULANG (1 pc ; 1 ps ;1kr) #REF!
G.6.6.18 1M3 MEMBUAT BETON KEDAP AIR DENGAN STROROX - 100 #REF!
G.6.6.19 1M' MEMASANG PVC WATERSTOP LEBAR 150 MM #REF!
G.6.6.20 1M' MEMASANG PVC WATERSTOP LEBAR 200 MM #REF!
G.6.6.21 1M' MEMASANG PVC WATERSTOP LEBAR 230 MM #REF!
G.6.6.22 1M' MEMASANG PVC WATERSTOP LEBAR 250 MM #REF!
G.6.6.23 1M' MEMASANG PVC WATERSTOP LEBAR 300 MM #REF!
G.6.6.24 1M' MEMASANG PVC WATERSTOP LEBAR 320 MM #REF!
G.6.6.25 1 KG PEMBESIAN DG BESI POLOS #REF!
G.6.6.25 1 KG PEMBESIAN DG BESI ULIR #REF!
G.6.6.26 1 KG KABEL PRESSTRESSED POLOS/STRANDS #REF!
G.6.6.27 1 KG JARING KAWAT BAJA #REF!
G.6.6.28 1M2 PASANG BEKISTING UNTUK PONDASI #REF!
G. 6.6.29 1 M2 PASANG BEKISTING UNTUK SLOOF ( 2 x pakai ) #REF!
G. 6.6.30 1 M2 PASANG BEKISTING UNTUK KOLOM ( 2 x pakai ) #REF!
NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)
G. 6.6.31 1 M2 PASANG BEKISTING UNTUK BALOK ( 2 x pakai ) #REF!
G. 6.6.32 1 M2 PASANG BEKISTING UNTUK LANTAI ( 2 x pakai ) #REF!
G. 6.6.33 1 M2 PASANG BEKISTING UNTUK DINDING ( 2 x pakai ) #REF!
G. 6.6.34 1 M2 PASANG BEKISTING UNTUK TANGGA #REF!
G. 6.6.35 1M3 MEMBUAT BETON DENGAN MUTU K 225 #REF!
G. 6.6.36 1M3 MEMBUAT BETON DENGAN MUTU K 275 #REF!
G. 6.6.37 1 M2 PASANG JEMBATAN COR #REF!
G. 6.6.38 1M3 MEMBUAT PONDASI BETON BERTULANG (150KG BESI + BEKISTING) #REF!
G. 6.6.39 1M3 MEMBUAT SLOOF BETON BERTULANG (200KG BESI + BEKISTING) #REF!
G. 6.6.40 1M3 MEMBUAT KOLOM BETON BERTULANG (300KG BESI + BEKISTING) #REF!
G. 6.6.41 1M3 MEMBUAT BALOK BETON BERTULANG (200KG BESI + BEKISTING) #REF!
G. 6.6.42 1M3 MEMBUAT BALOK BETON BERTULANG (150KG BESI + BEKISTING) #REF!
G. 6.6.43 1M3 MEMBUAT DINDING BETON BERTULANG (150 KG BESI + BEKISTING) #REF!
G. 6.6.44 1M3 MEMBUAT TANGGA BETON BERTULANG (200KG BESI + BEKISTING) #REF!
G. 6.6.45 1M3 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11x11) CM #REF!
G. 6.6.46 1M' MEMBUAT RING BALOK BETON BERTULANG (10X15) CM #REF!
H. PEKERJAAN PENUTUP ATAP
H. 6.6.1 1M2 PASANG ATAP GENTENG PALENTONG KECIL #REF!
H. 6.6.2 1M2 PASANG ATAP GENTENG KODOK /GLAZZUR #REF!
H. 6.6.3 1M2 PASANG ATAP GENTENG PALENTONG SUPER / BESAR #REF!
H. 6.6.4 1M2 PASANG ATAP GENTENG BUBUNG PALENTONG #REF!
H. 6.6.5 1M' PASANG BUBUNG GENTENG KODOK #REF!
H. 6.6.6 1M2 PASANG BUBUNG GENTENG PALENTONG BESAR #REF!
H. 6.6.7 1M2 PASANG ROOFLIGHT FIBREGLASS (180X90) CM #REF!
H. 6.6.8 1m2 PASANG ATAP ASBES GELOMBANG (2,50X0,92)X5MM #REF!
H. 6.6.9 1m2 PASANG ATAP ASBES GELOMBANG (2,25X0,92)X5MM #REF!
H. 6.6.10 1m2 PASANG ATAP ASBES GELOMBANG (2,00X0,92)X5MM #REF!
H. 6.6.11 1m2 PASANG ATAP ASBES GELOMBANG (1,80X0,92)X5MM #REF!
H. 6.6.12 1m2 PASANG ATAP ASBES GELOMBANG (3,00X1,05)X4 MM #REF!
H. 6.6.13 1m2 PASANG ATAP ASBES GELOMBANG (2,70X1,05)X4 MM #REF!
H. 6.6.14 1m2 PASANG ATAP ASBES GELOMBANG (2,40X1,05)X4 MM #REF!
H. 6.6.15 1m2 PASANG ATAP ASBES GELOMBANG (2,10X1,05)X4 MM #REF!
H. 6.6.16 1m2 PASANG ATAP ASBES GELOMBANG (1,5X1,05)X4 MM #REF!
NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)
H. 6.6.17 1m2 PASANG ATAP ASBES GELOMBANG (3,00X1,08)X6 MM #REF!
H. 6.6.18 1m2 PASANG ATAP ASBES GELOMBANG (2,70X1,08)X6 MM #REF!
H. 6.6.19 1m2 PASANG ATAP ASBES GELOMBANG (2,40X1,08)X6 MM #REF!
H. 6.6.20 1m2 PASANG ATAP ASBES GELOMBANG (2,10X1,08)X6 MM #REF!
H. 6.6.21 1m2 PASANG ATAP ASBES GELOMBANG (1,80X1,08)X6 MM #REF!
H. 6.6.22 1M' PASANG BUBUNG STEL GELOMBANG 0,92 M #REF!
H. 6.6.23 1M' PASANG NOK STEL GELOMBANG 1,05 M #REF!
H. 6.6.24 1M' PASANG NOK STEL GELOMBANG 1,08 M #REF!
H. 6.6.25 1M' PASANG NOK paten 0,92 m #REF!
H. 6.6.26 1M' PASANG NOK PATEN 1,05 M #REF!
H. 6.6.27 1M' PASANG NOK PATEN 1,08 M #REF!
H. 6.6.28 1M' PASANG NOK STEL RATA 0,92 M #REF!
H. 6.6.29 1M' PASANG NOK STEL RATA 1,05 M #REF!
H. 6.6.30 1M2 PASANG ATAP GENTENG BETON #REF!
H. 6.6.31 1M2 PASANG ATAP GENTENG ASPAL #REF!
H. 6.6.32 1M2 PASANG ATAP GENTENG METAL #REF!
H. 6.6.33 1M' PASANG ATAP SIRAP #REF!
H. 6.6.34 1M' PASANG NOK GENTENG BETON #REF!
H. 6.6.35 1M' PASANG NOK GENTENG ASPAL #REF!
H. 6.6.36 1M' PASANG NOK GENTENG METAL #REF!
H. 6.6.37 1 M' MEMASANG BUBUNGAN ATAP SIRAP L 40 cm #REF!
H. 6.6.38 1 M2 MEMASANG ATAP SENG #REF!
H. 6.6.39 1 M2 MEMASANG BUBUNGAN ATAP SENG #REF!
H. 6.6.40 1 M2 PASANG ATAP ALUMUNIUM #REF!
H. 6.6.41 1 M2 PASANG NOK ALUMUNIUM #REF!
H. 6.6.42 1 M2 PASANG ALUMUNIUM FOIL /SISALATION #REF!
I. PEKERJAAN PLAFOND
I. 6.6.1 1 M2 PLAFOND ASBES (1,00 X 1,00) M, TEBAL 6 MM #REF!
I. 6.6.2 1 M2 PLAFOND ASBES (1,00 X 1,00) M, TEBAL 5 MM #REF!
I. 6.6.3 1 M2 PLAFOND ASBES (1,00 X 1,00) M, TEBAL 4 MM #REF!
I. 6.6.4 1 M2 PLAFOND ASBES (1,00 X 1,00) M, TEBAL 3,5 MM #REF!
I. 6.6.5 1 M2 PLAFOND AKUSTIK (30 X 30) CM #REF!
I. 6.6.6 1 M2 PLAFOND AKUSTIK (30 X 60) CM #REF!
NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)
I. 6.6.7 1 M2 PLAFOND AKUSTIK (60 X 120) CM #REF!
I. 6.6.8 1 M2 PLAFOND PLYWOOD ( 30 X 60 ) cm, TEBAL 4 MM #REF!
I. 6.6.9 1 M2 PLAFOND PLYWOOD ( 30 X 60 ) cm, TEBAL 6 MM #REF!
I. 6.6.10 1 M2 PLAFOND PLYWOOD ( 60 X 120 ) cm, TEBAL 2 MM #REF!
I. 6.6.11 1 M2 PLAFOND PLYWOOD ( 60 X 120 ) cm, TEBAL 6 MM #REF!
I. 6.6.12 1 M2 PLAFOND TEAKWOOD ( 30 x 60 ) cm, TEBAL 4 MM #REF!
I. 6.6.13 1 M2 PLAFOND TEAKWOOD ( 60 x 120 ) cm, TEBAL 4 MM #REF!
I. 6.6.14 1M2 PLAFOND LAT KAYU JATI #REF!
I. 6.6.15 1M2 PLAFOND LAT KAYU MERANTI #REF!
I. 6.6.16 1M2 PLAFOND LAT KAYU BENGKIRAI #REF!
I. 6.6.17 1M2 PLAFOND SOFTBOARD #REF!
I. 6.6.18 1M2 PLAFOND AKUSTIK 60 X 120 CM + RANGKA ALUMUNIUM #REF!
I. 6.6.19 1M2 PLAFOND KAYU PROFIL #REF!
I. 6.6.20 1M2 PLAFOND ASBES ( 1,00 X 1,00 ) M, TEBAL 3,2MM RANGKA MERANTI #REF!
I. 6.6.21 1M2 PLAFOND PLYWOOD 4 MM + RANGKA KAYU MERANTI #REF!
I. 6.6.22 1M2 PLAFOND AKUSTIK (30 X 60 ) CM + RANGKA KAYU MERANTI #REF!
I. 6.6.23 1M2 PLAFOND AKUSTIK (30 X 30 ) CM + RANGKA KAYU MERANTI #REF!
I. 6.6.24 1M2 PLAFOND GYPSUM BOARD, TEBAL 9 MM #REF!
J. PEKERJAAN SANITAIR
J. 6.6.1 MEMASANG 1 BH CLOSED DUDUK / MONOBLOK #REF!
J. 6.6.2 MEMASANG 1 BH CLOSED JONGKOK KERAMIK #REF!
J. 6.6.3 MEMASANG 1 BH CLOSED JONGKOK TERASO #REF!
J. 6.6.4 MEMASANG 1 BH URINOIR #REF!
J. 6.6.5 MEMASANG 1 BH WASTAFEL #REF!
J. 6.6.6 MEMASANG 1 BH BAK MANDI TERASO VOLUME 0.30 M3 #REF!
J. 6.6.7 MEMASANG 1 BH BAK MANDI FIBREGLASS VOLUME 0,30 M3 #REF!
J. 6.6.8 MEMASANG 1 BH BAK AIR BATU BATA VOLUME 0,3 M3 ( 60 x 60 ) #REF!
J. 6.6.9 MEMASANG 1 BH BADKIP PORSELEN #REF!
J. 6.6.10 MEMASANG 1 BH BAK BETON VOLUME 1 M3 AIR #REF!
J. 6.6.11 MEMASANG 1 BH BAK FIBERGLASS VOLUME 1 M3 AIR #REF!
J. 6.6.12 MEMASANG 1M' PIPA PENYALUR AIR LIMBAH JENIS PIPA TANAH, DIA.15 CM #REF!
J. 6.6.13 MEMASANG 1M' PIPA PENYALUR AIR LIMBAH JENIS PIPA TANAH, DIA.20 CM #REF!
J. 6.6.14 MEMASANG 1M' PIPA BETON, DIAMETER 15 - 20 CM #REF!
Hal : 520
NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)
J. 6.6.15 MEMASANG 1M' PIPA BETON, DIAMETER 30 - 100 CM #REF!
J. 6.6.16 MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (30X30)CM TINGGI 35 CM #REF!
J. 6.6.17 MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (45X45)CM TINGGI 50 CM #REF!
J. 6.6.18 MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (60 x 60)CM TINGGI 65 CM #REF!
J. 6.6.19 MEMASANG 1M' PIPA GALVANIS DIAMETER 1/2" #REF!
J. 6.6.20 MEMASANG 1M' PIPA GALVANIS DIAMETER 3/4" #REF!
J. 6.6.21 MEMASANG 1M' PIPA GALVANIS DIAMETER 1 " #REF!
J. 6.6.22 MEMASANG 1M' PIPA GALVANIS DIAMETER 1 1/2 " #REF!
J. 6.6.23 MEMASANG 1M' PIPA GALVANIS DIAMETER 3" #REF!
J. 6.6.24 MEMASANG 1M' PIPA GALVANIS DIAMETER 4 " #REF!
J. 6.6.25 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1/2 " #REF!
J. 6.6.26 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3/4" #REF!
J. 6.6.27 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1 " #REF!
J. 6.6.28 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1 1/2 " #REF!
J. 6.6.29 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 2" #REF!
J. 6.6.30 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 2 1/2" #REF!
J. 6.6.31 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3" #REF!
J. 6.6.32 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 4" #REF!
J. 6.6.33 MEMASANG 1BH BAK CUCI PIRING STAINLES STEEL #REF!
J. 6.6.34 MEMASANG 1 BH BAK CUCI PIRING TERASO #REF!
J. 6.6.35 MEMASANG 1BH KRAN DIAMETER 3/4" ATAU 1/2" #REF!
J. 6.6.36 MEMASANG 1BH FLOOR DRAIN #REF!
K. PEKERJAAN BESI
K. 6.6.1 1 KG PASANG RANGKA ATAP BAJA #REF!
K. 6.6.2 1 M2 PASANG PINTU BESI BAJA #REF!
K. 6.6.3 1 M2 PASANG JENDELA BESI #REF!
K. 6.6.4 1 M2 PASANG JENDELA BESI TAHAN API #REF!
K. 6.6.5 1 M2 PASANG PINTU GULUNG BESI #REF!
K. 6.6.6 1 M2 PASANG PINTU LIPAT #REF!
K. 6.6.7 1 M2 PASANG PINTU SUNSCREEN ALLUMUNIUM #REF!
K. 6.6.8 1 M2 PASANG ROLLING DOOR #REF!
K. 6.6.9 1 M2 PASANG PINTU ALLUMUNIUM #REF!
K. 6.6.10 1 M2 PASANG VENETIONS BLINDS #REF!
NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)
K. 6.6.11 1 M2 PASANG VERTIKALS BLINDS #REF!
K. 6.6.12 1 M2 PASANG TERALI BESI #REF!
K. 6.6.13 1 M2 PASANG KAWAT HARMONIKA #REF!
K. 6.6.14 1 M2 PASANG KAWAT NYAMUK #REF!
K. 6.6.15 1 M2 PASANG KAWAT KASSA #REF!
K. 6.6.16 1 M2 PASANG KAWAT BURUNG #REF!
K. 6.6.17 1 M2 PASANG JENDELA NAKO & TRALIS #REF!
K. 6.6.18 1 M' PASANG TALANG DATAR, SENG BLJS 28 #REF!
K. 6.6.19 1 M' PASANG TALANG MIRING, SENG BLJS 28 #REF!
K. 6.6.20 1 M' PASANG TALANG 1/2 LINGKARAN D-10 CM. SENG BJLS 28 #REF!
K. 6.6.21 1 M' PASANG TALANG 1/2 LINGKARAN D-10 CM. SENG BJLS 24 #REF!
L. PEKERJAAN KUNCI DAN KACA
L. 6.6.1 1 BUAH PASANG KUNCI TANAM ANTIK #REF!
L. 6.6.2 1 BUAH PASANG KUNCI TANAM BIASA #REF!
L. 6.6.3 1 BUAH PASANG KUNCI KAMAR MANDI #REF!
L. 6.6.4 1 BUAH PASANG KUNCI SILINDER #REF!
L. 6.6.5 1 BUAH PASANG ENGSEL PINTU #REF!
L. 6.6.6 1 BUAH PASANG ENGSEL JENDELA KUPU - KUPU #REF!
L. 6.6.7 1 BUAH PASANG ENGSEL ANGIN #REF!
L. 6.6.8 1 BUAH PASANG SPRING KNIP #REF!
L. 6.6.9 1 BUAH PASANG KAIT ANGIN #REF!
L. 6.6.10 1 BUAH PASANG DOOR CLOSER #REF!
L. 6.6.11 1 BUAH PASANG KUNCI SELOT #REF!
L. 6.6.12 1 BUAH PASANG PEGANGAN PINTU / DOOR HOLDER #REF!
L. 6.6.13 1 BUAH PASANG DOOR STOP #REF!
L. 6.6.14 1 BUAH PASANG REL PINTU DORONG #REF!
L. 6.6.15 1 BUAH PASANG KUNCI LEMARI #REF!
L. 6.6.16 1 M2 PASANG KACA, TEBAL 3 MM #REF!
L. 6.6.17 1 M2 PASANG KACA, TEBAL 5 MM #REF!
L. 6.6.18 1 M2 PASANG KACA, TEBAL 8 MM #REF!
L. 6.6.19 1 M2 PASANG KACA GELAP, TEBAL 5 MM #REF!
L. 6.6.20 1 M2 PASANG KACA CERMIN, TEBAL 5 MM #REF!
L. 6.6.21 1 M2 PASANG KACA CERMIN, TEBAL 6 MM #REF!
NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)
L. 6.6.22 1 M2 PASANG KACA CERMIN, TEBAL 8 MM #REF!
L. 6.6.23 1 M2 PASANG KACA " WIREGLASS", TEBAL 5 MM #REF!
L. 6.6.24 1 M2 PASANG KACA PATRI, TEBAL 5 MM #REF!
M. PEKERJAAN PENUTUP LANTAI & DINDING
M.6.6.1 1 M2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 40 X 40 CM #REF!
M.6.6.2 1 M2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 30 X 30 CM #REF!
M.6.6.3 1 M2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 20 X 20 CM #REF!
M.6.6.4 1 M2 PASANG LANTAI UBIN WARNA UKURAN 40 X 40 CM #REF!
M.6.6.5 1 M2 PASANG LANTAI UBIN WARNA UKURAN 30 x 30 CM #REF!
M.6.6.6 1 M2 PASANG LANTAI UBIN WARNA UKURAN 20 x 20 CM #REF!
M.6.6.7 1 M2 PASANG LANTAI UBIN TERASO UKURAN 40 x 40 CM #REF!
M.6.6.8 1 M2 PASANG LANTAI UBIN TERASO UKURAN 30 x 30 CM #REF!
M.6.6.9 1 M2 PASANG LANTAI UBIN GRANITO UKURAN 40 X 40 CM #REF!
M.6.6.10 1 M2 PASANG LANTAI UBIN GRANITO UKURAN 30 X 30 CM #REF!
M.6.6.11 1 M2 PASANG LANTAI UBIN TERALUX TERANG UKURAN 40 X 40 CM #REF!
M.6.6.12 1 M2 PASANG LANTAI UBIN TERALUX TERANG UKURAN 30 X 30 CM #REF!
M.6.6.13 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 60 X 60 CM #REF!
M.6.6.14 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 40 X 40 CM #REF!
M.6.6.15 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 30 X 30 CM #REF!
M.6.6.16 1 M' PASANG PLINT UBIN PC ABU-ABU UKURAN 15 X 20 CM #REF!
M.6.6.17 1 M' PASANG PLINT UBIN PC ABU-ABU UKURAN 10 X 30 CM #REF!
M.6.6.18 1 M' PASANG PLINT UBIN PC ABU-ABU UKURAN 10 X 40 CM #REF!
M.6.6.19 1 M' PASANG PLINT UBIN PC WARNA UKURAN 10 X 20 CM #REF!
M.6.6.20 1 M' PASANG PLINT UBIN PC WARNA UKURAN 10 X 30 CM #REF!
M.6.6.21 1 M' PASANG PLINT UBIN PC WARNA UKURAN 10 X 40 CM #REF!
M.6.6.22 1 M' PASANG PLINT UBIN TERASO UKURAN 10 X 30 CM #REF!
M.6.6.23 1 M' PASANG PLINT UBIN TERASO UKURAN 10 X 40 CM #REF!
M.6.6.24 1 M' PASANG PLINT UBIN GRANITO UKURAN 10 X 40 CM #REF!
M.6.6.25 1 M' PASANG PLINT UBIN GRANITO UKURAN 10 X 30 CM #REF!
M.6.6.26 1 M' PASANG PLINT UBIN TERALUX KERANG UKURAN 10 X 40 CM #REF!
M.6.6.27 1 M' PASANG PLINT UBIN TERALUX KERANG UKURAN 10 X 30 CM #REF!
M.6.6.28 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 X 60 CM #REF!
M.6.6.29 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 X 40 CM #REF!
NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)
M.6.6.30 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 X 30 CM #REF!
M.6.6.31 1 M2 PASANG TERASO COR DITEMPAT #REF!
M.6.6.32 1 M2 PASANG TERALUC COR DITEMPAT, TEBAL 3 CM #REF!
M.6.6.33 1 M2 PASANG UBIN TAHAN ASAM #REF!
M.6.6.34 1 M2 PASANG LANTAI KERAMIK ARTISTIK 10 X 20 CM #REF!
M.6.6.35 1 M2 PASANG LANTAI KERAMIK ARTISTIK 10 X 10 CM #REF!
M.6.6.36 1 M2 PASANG LANTAI KERAMIK ARTISTIK 5 X 20 CM #REF!
M.6.6.37 1 M2 PASANG PLINT KERAMIK ARTISTIK 10 X 20 CM #REF!
M.6.6.38 1 M2 PASANG PLINT KERAMIK ARTISTIK 10 X 10 CM #REF!
M.6.6.39 1 M2 PASANG PLINT KERAMIK ARTISTIK 5 X 20 CM #REF!
M.6.6.40 1 M' INTERNAL COVE ARTISTIK ( 5 X 5 X 20 ) CM #REF!
M.6.6.41 1 M' PASANG PLINT VINYL TANPA ADUKAN #REF!
M.6.6.42 1 M2 PASANG LANTAI KERAMIK 10 X 20 CM #REF!
M.6.6.43 1 M2 PASANG LANTAI KERAMIK 15 X 15 CM #REF!
M.6.6.44 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM #REF!
M.6.6.45 1 M2 PASANG LANTAI KERAMIK 25 X 25 CM #REF!
M.6.6.46 1 M2 PASANG LANTAI KERAMIK 15 X 20 CM #REF!
M.6.6.47 1 M2 PASANG LANTAI KERAMIK 30 x 30 CM #REF!
M.6.6.48 1 M2 PASANG LANTAI KERAMIK 30 x 30 CM ANTI SLIP #REF!
M.6.6.49 1 M2 PASANG LANTAI KERAMIK 10 x 33 CM #REF!
M.6.6.50 1 M2 PASANG LANTAI MOSAIK 30 X 30 CM, EX. LOKAL #REF!
M.6.6.51 1 M2 PASANG LANTAI MARMER #REF!
M.6.6.52 1 M2 PASANG LANTAI KARPET 100 % WOOL #REF!
M.6.6.53 1 M2 PASANG LANTAI KARPET 80 % WOOL, 20% NYLON #REF!
M.6.6.54 1 M2 PASANG UNDRLYER, TEBAL 6 MM #REF!
M.6.6.55 1 M2 PASANG LANTAI KARPET #REF!
M.6.6.56 1 M2 PASANG LANTAI PARQUET JATI #REF!
M.6.6.57 1 M2 PASANG GYMFLOOR #REF!
M.6.6.58 1 M2 PASANG DINDING PORSELIN 11 X 11 CM, PUTIH #REF!
M.6.6.59 1 M2 PASANG DINDING PORSELIN 11 X 11 CM, WARNA #REF!
M.6.6.60 1 M2 PASANG DINDING PORSELIN 15 X 15 CM, PUTIH #REF!
M.6.6.61 1 M2 PASANG DINDING PORSELIN 15 X 15 CM, WARNA #REF!
M.6.6.62 1 M2 PASANG DINDING PORSELIN 10 X 20 CM, WARNA #REF!
NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)
M.6.6.63 1 M2 PASANG DINDING PORSELIN 20 X 20 CM, WARNA #REF!
M.6.6.64 1 M2 PASANG DINDING KERAMIK ARTISTIK 10 X 20 CM #REF!
M.6.6.65 1 M2 PASANG DINDING KERAMIK ARTISTIK 5 X 20 CM #REF!
M.6.6.66 1 M2 PASANG DINDING KERAMIK 10 X 20 CM #REF!
M.6.6.67 1 M2 PASANG DINDING KERAMIK 15 x 15 CM #REF!
M.6.6.68 1 M2 PASANG DINDING KERAMIK 20 x 20 CM #REF!
M.6.6.69 1 M2 PASANG DINDING KERAMIK 10 x 20 CM #REF!
M.6.6.70 1 M2 PASANG DINDING MARMER #REF!
M.6.6.71 1 M2 PASANG DINDING BATA PELAPIS 7 X 3 X 24 CM #REF!
M.6.6.72 1 M2 PASANG DINDING BATA KLINKER 5 X 5 X 24 CM #REF!
M.6.6.73 1 M2 PASANG DINDING BATU PAROS #REF!
M.6.6.74 1 M2 PASANG DINDING BATU TEMPEL HITAM #REF!
M.6.6.75 1 M2 PASANG LANTAI VINYL KARET 30 X 30 CM KL I #REF!
M.6.6.76 1 M2 PASANG LANTAI VINYL KARET 30 X 30 CM KL II #REF!
M.6.6.77 1 M2 PASANG LANTAI VINYL ASBES 30 X 30 CM #REF!
M.6.6.78 1 M2 PASANG LANTAI VINYL MOTIF KEMBANG 30 X 30 CM #REF!
M.6.6.79 1 M2 PASANG WALL COVERING LEBAR 50 CM #REF!
M.6.6.80 1 M2 FLOOR HARDENER FERROVAX #REF!
M.6.6.81 1 M2 FLOOR HARDENER MASTERCRON #REF!
M.6.6.82 1 M2 PLINT KAYU 2 X 10 CM #REF!
N. PEKERJAAN CAT - CATAN
N. 6.6.1 1 M2 MENGIKIS/MENGEROK PERMUKAAN CAT TEMBOK LAMA #REF!
N. 6.6.2 1 M2 MENCUCI BIDANG PERMUKAAN TEMBOK YANG PERNAH DICAT #REF!
N. 6.6.3 1 M2 MENGEROK KARAT CAT LAMA PERMUKAAN BAJA DENGAN CARA MANUAL #REF!
N. 6.6.4 1 M2 MENYABUN PERMUKAAN TEMBOK LAMA #REF!
N. 6.6.5 1 M2 MENGEROK KARAT ATAU CAT LAMA PERMUKAAN BAJA DENGAN PANCAR #REF!
N. 6.6.6 1 M2 MENDEMPUL DAN MENGGOSOK KAYU #REF!
N. 6.6.7 1 M2 PENGECATAN BIDANG KAYU LAMA #REF!
N. 6.6.8 1 M2 PENGECATAN BIDANG KAYU BARU ( 1 LAPIS PLAMIR ), 1 LAPIS CAT DASAR, #REF!
N. 6.6.9 1 M2 PENGECATAN BIDANG KAYU BARU ( 1 LAPIS PLAMIR ) #REF!
N. 6.6.10 1 M2 PELABURAN BIDANG KAYU DENGAN TEAK OIL #REF!
N. 6.6.11 1 M2 PELABURAN BIDANG KAYU DENGAN POLITUR #REF!
N. 6.6.12 1 M2 PELABURAN BIDANG KAYU DENGAN CAT RESIDU DAN TER #REF!
NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)
N. 6.6.13 1 M2 PELABURAN BIDANG KAYU DENGAN VERNIS #REF!
N. 6.6.14 1 M2 PENGECATAN TEMBOK BARU ( 1 lapis plamir, #REF!
N. 6.6.15 1 M2 PENGECATAN TEMBOK LAMA #REF!
N. 6.6.16 1 M2 MELABUR TEMBOK DENGAN KALKARIUM #REF!
N. 6.6.17 1 M2 MELABUR TEMBOK DENGAN KAPUR SIRIH #REF!
N. 6.6.18 1 M2 MELABUR TEMBOK LAMA DENGAN KAPUR SIRIH ( UNTUK PEMELILHARAAN ) #REF!
N. 6.6.19 1 M2 PEMASANGAN WALL PAPER #REF!
N. 6.6.20 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI #REF!
N. 6.6.21 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI DAN PERANCAH #REF!
N. 6.6.22 1 M2 PENGECATAN PERMUKAAN BAJA LAPIS SENG ( GALBANI ) SECARA MANUAL #REF!
N. 6.6.23 1 M2 PENGECATAN PERMUKAAN BAJA LAPIS SENG ( GALBANI ) SECARA MANUAL #REF!
N. 6.6.24 1 M2 PENGECATAN PERMUKAAN BAJA LAPIS SENG ( GALBANI ) SECARA MANUAL #REF!
N. 6.6.25 1 M2 PENGECATAN PERMUKAAN BAJA LAPIS SENG ( GALBANI ) SECARA SEMPROT #REF!
DAFTAR ONGKOS ANGKUT MATERIAL

BIDANG : CIPTA KARYA


TAHUN : September 2008
JARAK ANGKUT
RATA-RATA 46 - 70
NO MATERIAL SAT
ONGKOS
ANGKUT
JUMLAH
1 Balok Klas I Bangkirai m3 - #REF!
2 Balok Klas I Ulin m3 - 4,500,000.00
3 Balok Kayu Meranti m3 - 2,650,000.00
4 Batu Gunung m3 - 220,000.00
5 Kayu Klas 2 m3 - 1,230,000.00
6 Kayu galam dia 10 - 12 cm btg - 9,500.00
7 Kerikil Beton / Split ( 2-3 cm ) m3 - #REF!
8 Koral m3 - 425,000.00
9 Papan Kayu Bangkirai m3 - 6,500,000.00
10 Papan Kayu Ulin m3 - 5,300,000.00
11 Papan Kayu kelas 2 m3 - 2,920,320.00
12 Papan Kayu Meranti m3 - 2,920,320.00
13 Pasir Beton m3 - 365,000.00
14 Pasir Pasang sungai m3 - 365,000.00
15 Pasir pasang putih m3 - 87,000.00
16 Pasir Urug m3 - 87,000.00
17 Sirtu m3 - #REF!
18 Tanah Urug m3 - 87,000.00
DAFTAR HARGA SATUAN UPAH DAN BAHAN
ZONA WARU
BIDANG : Cipta Karya
TAHUN ANGGARAN : 2014
HARGA DASAR
NO URAIAN SAT SUN BIAYA ANGKUT SATUAN KETERANGAN
1 2 3 4 5 6 7
A UPAH KERJA
1 Pekerja ( Buruh semi terlatih ) Hari 79,000.00 - 79,000.00
2 Tukang Batu Hari 98,000.00 - 98,000.00
3 Tukang Kayu Hari 98,000.00 - 98,000.00
4 Tukang Besi Hari 98,000.00 - 98,000.00
5 Tukang Cat Hari 98,000.00 - 98,000.00
6 Kepala Tukang Hari 110,000.00 - 110,000.00
7 Mandor Hari 110,000.00 - 110,000.00
8 Sopir Hari 95,000.00 - 95,000.00
9 Pembantu Sopir Hari 79,000.00 - 79,000.00

B Harga Bahan
1
2 Ampelas Lbr 3,000.00 - 3,000.00
5 Atap Metal Berkualitas ( 2 ssn, 8 daun ) Lbr 87,000.00 - 87,000.00
25 Balok Klas I Ulin M3 4,500,000.00 - 4,500,000.00
26 Balok Kayu Meranti M3 2,650,000.00 - 2,650,000.00
29 Batu Bata Bh 1,000.00 - 1,000.00
30 Batu apung Kg 950.00 - 950.00
31 Batu Gunung M3 220,000.00 - 220,000
35 Besi Beton Polos Kg 10,500.00 - 10,500.00
47 Cat Air / tembok Kg 75,000.00 - 75,000.00
48 Cat Air / tembok ex.setara ICI,dulux,mowilex Kg 110,000.00 110,000.00
50 Cat Dasar / plamir Kg 21,000.00 - 21,000.00
51 Cat Kilap / Kayu Kg 37,800.00 - 37,800.00
52 Cat Menie kayu Kg 21,600.00 - 21,600.00
57 Daun Jendela Uk. Besar (Fabrikasi) Kc 5 mm Bh 337,500.00 - 337,500.00
58 Daun Jendela Uk. Kecil (Fabrikasi) Kc 5 mm Bh 298,600.00 - 298,600.00
61 Dempul Halus ( INFRA ) Kg 45,000.00 - 45,000.00
62 Dempul kayu Kg 27,500.00 - 27,500.00
63 Dempul Politur Kg 32,500.00 - 32,500.00
64 Engsel Jendela Lokal 3 " Bh 28,500.00 - 28,500.00
65 Engsel Pintu Lokal 5 " Bh 38,750.00 - 38,750.00
NO URAIAN SAT SUN BIAYA ANGKUT HARGA DASAR KETERANGAN
SATUAN
1 2 3 4 5 6 7
71 Grendel Jendela Bh 27,500.00 - 27,500.00
72 Grendel Pintu Bh 23,400.00 - 23,400.00
73 Grendel tanam Pintu Bh 65,000.00 - 65,000.00
75 Hak Angin Bh 18,750.00 - 18,750.00
76 Handle Jendela putih Bh 23,500.00 - 23,500.00
77 Handle Pintu Bh 27,500.00 - 27,500.00
78 Jalusi Atap Bh 365,000.00 - 365,000.00
85 Kaca polos 5 mm M2 35,000.00 - 35,000.00
88 Kawat Bendrat / Beton Kg 22,000.00 - 22,000.00
94 Kayu Klas 2 M3 2,900,000.00 - 2,900,000.00
95 Kayu galam dia 10 - 12 cm Btg 25,000.00 - 25,000.00
98 Keramik 20 x 20 cm M2 65,000.00 - 65,000.00
99 Keramik 40 x 40 cm Halus M2 72,300.00 - 72,300.00
100 Keramik 40 x 40 cm Kasar M2 72,300.00 - 72,300.00
104 Batu Split ( ukuran 2-3 cm/1-2 )Ex. Krayan M3 425,000.00 - 425,000.00
106 Koral (ex.Lokal) M3 425,000.00 - 425,000.00
109 Kuas 3 " Bh 23,500.00 - 23,500.00
110 Kunci Pintu 2 Slag berkualitas Bh 145,000.00 - 145,000.00
111 Kunci Pintu Double Ex Cisa Bh 165,000.00 - 165,000.00
116 Kuda-kuda baja ringan modern trus m2 187,000.00 - 187,000.00
123 Lampu Pijar 18 Wat Bh 47,500.00 - 47,500.00
138 List Plafond Plywood M' 33,500.00 - 33,500.00
149 Minyak cat Ltr 9,500.00 - 9,500.00
150 Minyak bekisting Ltr 10,800.00 - 10,800.00
159 Nok Model U ukuran 110 x 5 x 6 cm M' 33,750.00 - 33,750.00
168 Paku Genteng metal Kg 27,500.00 - 27,500.00
169 Paku Kayu / biasa Kg 20,500.00 - 20,500.00
174 Paku Sekrup Kg 3,000.00 - 3,000.00
175 Papan Kayu Bangkirai M3 6,500,000.00 - 6,500,000.00
176 Papan Kayu Ulin M3 5,300,000.00 - 5,300,000.00
177 Papan Kayu kelas 2 M3 2,920,320.00 - 2,920,320.00
178 Papan Kayu Meranti M3 2,920,320.00 - 2,920,320.00
179 Papan Nama Proyek Bh 550,000.00 - 550,000.00
183 Pasir Beton Ex. Lokal samuntai M3 365,000.00 - 365,000.00
184 Pasir Beton (sepaku) M3 477,000.00 - 477,000.00
185 Pasir Pasang sungai ex. Kandilo M3 365,000.00 - 365,000.00
186 Pasir pasang putih M3 87,000.00 - 87,000.00
188 Pasir Urug M3 87,000.00 - 87,000.00
190 Pasangan Jendela rangka alumunium + kaca 5 mm Bh 345,000.00 - 345,000.00
191 Pasangan Kusen Almunium Jendela m' 120,000.00 - 120,000.00
196 Pintu Panel kayu Ulin Ukuran Besar L 80 cm Bh 620,000.00 - 620,000.00
212 Plamir Kg 16,650.00 - 16,650.00
213 Plitur Kg 17,500.00 - 17,500.00
219 Plywood 9 mm Lbr 185,000.00 - 185,000.00
224 Rangka besi hollow M' 23,500.00 - 23,500.00
227 Roster beton 20 x 20 cm Bh 19,000.00 - 19,000.00
231 Saklar Ganda Bh 27,500.00 - 27,500.00
232 Saklar Tunggal Bh 19,500.00 - 19,500.00
233 Sekering Kas 3 Group + Instalasi Unit 245,000.00 - 245,000.00
234 Semen Abu - Abu / PC ( 50 kg/Zak ) Zak 66,000.00 - 66,000.00
235 Semen Warna Kg 9,000.00 - 9,000.00
236 Semen putih Kg 1,600.00 - 1,600.00
246 Stop Kontak Bh 22,500.00 - 22,500.00
249 Tanah Urug M3 87,000 - 87,000.00
266 Titik Mata Lampu Ttk 160,000.00 - 160,000.00
272 Pasir beton Exs. Palu m3 490,000.00 490,000.00
275 Kalsiboard 4 mm Lbr 85,000.00 85,000.00
276 Washtafel Unit - -

Catatan :
1. Harga diatas adalah harga disumber material ( disungai, dilokasi penggalian) khusus utk bahan lokal
2. Untuk bahan-bahan non lokal harga tersebut adalah harga toko / harga yang berlaku dipasaran
3. Harga sudah terrmasuk keuntungan kontraktor dan ongkos angkut
4 Harga belum termasuk PPn
Daftar Analisa Satuan Pekerjaan ( SNI )

Harga Satuan Upah Bahan Jumlah Harga


No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)

A Pekerjaan Persiapan
3 1 m' Pengukuran dan pemasangan bouwplank
0.0120 m3 Kayu meranti 2,650,000.00 31,800.00
0.0200 kg Paku kayu 20,500.00 410.00
0.0070 m3 Papan kayu meranti 3/20 2,920,320.00 20,442.24
0.1000 Tukang kayu 98,000.00 9,800.00
0.1000 Pekerja 79,000.00 7,900.00
0.0100 Kepala Tukang 110,000.00 1,100.00
0.0050 Mandor 110,000.00 550.00
Jumlah 19,350.00 52,652.24 72,002.24
B Pekerjaan Tanah
1 1 m3 Galian tanah biasa sedalam 1 meter
0.4000 Pekerja 79,000.00 31,600.00
0.0400 Mandor 110,000.00 4,400.00
Jumlah 36,000.00 36,000.00
9 1 m3 Pemadatan tanah
0.5000 Pekerja 79,000.00 39,500.00
0.0500 Mandor 110,000.00 5,500.00
Jumlah 45,000.00 - 45,000.00
10 1 m3 Urugan tanah
1.2000 m3 Tanah 87,000.00 104,400.00
0.2500 Pekerja 79,000.00 19,750.00
0.0250 Mandor 110,000.00 2,750.00
1.0000 ls Biaya pemadatan 45,000.00 45,000.00
Jumlah 67,500.00 104,400.00 171,900.00
11 1 m3 Mengurug tanah kembali
0.1920 Pekerja 79,000.00 15,168.00
0.0190 Mandor 110,000.00 2,090.00
Jumlah 17,258.00 17,258.00
12 1 m3 Urugan pasir
1.2000 m3 Pasir urug 87,000.00 104,400.00
0.3000 Pekerja 79,000.00 23,700.00
0.0100 Mandor 110,000.00 1,100.00
1.0000 ls Biaya pemadatan 45,000.00 45,000.00
Jumlah 69,800.00 104,400.00 174,200.00
C Pekerjaan Pondasi
1 1 m3 Pasang pondasi batu kosong/Aanstamping
1.2000 m3 Batu gunung 220,000.00 264,000.00
0.3000 m3 Pasir urug 87,000.00 26,100.00
0.7800 Pekerja 79,000.00 61,620.00
0.3900 Tukang Batu 98,000.00 38,220.00
0.0390 Kepala Tukang 110,000.00 4,290.00
0.0390 Mandor 110,000.00 4,290.00
Jumlah 108,420.00 290,100.00 398,520.00
3 1 m3 Pasang pondasi batu gunung 1 : 4
1.1000 m3 Batu gunung 220,000.00 242,000.00
3.2600 zak Semen PC 50 kg 66,000.00 215,160.00
0.5200 m3 Pasir pasang 87,000.00 45,240.00
1.5000 Pekerja 79,000.00 118,500.00
0.6000 Tukang batu 98,000.00 58,800.00
0.0600 Kepala Tukang 110,000.00 6,600.00
0.0750 Mandor 110,000.00 8,250.00
Jumlah 192,150.00 502,400.00 694,550.00
Harga Satuan Upah Bahan Jumlah Harga
No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)
D Pekerjaan Struktur
1 1 m2 pasang bekisting untuk pondasi
0.0400 m3 Papan kayu kelas 2 2,920,320.00 116,812.80
0.3000 kg Paku kayu 20,500.00 6,150.00
0.1000 lt minyak bekisting 10,800.00 1,080.00
0.3000 Pekerja 79,000.00 23,700.00
0.2600 Tukang kayu 98,000.00 25,480.00
0.0260 Kepala Tukang 110,000.00 2,860.00
0.0050 Mandor 110,000.00 550.00
Jumlah 52,590.00 124,042.80 176,632.80
2 1 m2 pasang bekisting untuk sloof
0.0450 m3 Papan kayu kelas 2 2,920,320.00 131,414.40
0.3000 kg Paku kayu 20,500.00 6,150.00
0.1000 lt minyak bekisting 10,800.00 1,080.00
0.3000 Pekerja 79,000.00 23,700.00
0.2600 Tukang kayu 98,000.00 25,480.00
0.0260 Kepala Tukang 110,000.00 2,860.00
0.0050 Mandor 110,000.00 550.00
Jumlah 52,590.00 138,644.40 191,234.40
3 1 m2 pasang bekisting untuk kolom
0.0400 m3 Papan kayu kelas 2 2,920,320.00 116,812.80
0.4000 kg Paku kayu 20,500.00 8,200.00
0.2000 lt minyak bekisting 10,800.00 2,160.00
0.0150 m3 Balok kayu meranti 2,650,000.00 39,750.00
0.3500 lbr plywood tebal 9 mm 185,000.00 64,750.00
2.0000 btg kayu galam 25,000.00 50,000.00
0.3000 Pekerja 79,000.00 23,700.00
0.3300 Tukang kayu 98,000.00 32,340.00
0.0330 Kepala Tukang 110,000.00 3,630.00
0.0060 Mandor 110,000.00 660.00
Jumlah 60,330.00 281,672.80 342,002.80

4 1 m2 pasang bekisting untuk balok


0.0400 m3 Papan kayu kelas 2 2,920,320.00 116,812.80
0.4000 kg Paku kayu 20,500.00 8,200.00
0.2000 lt minyak bekisting 10,800.00 2,160.00
0.0180 m3 Balok kayu meranti 2,650,000.00 47,700.00
0.3500 lbr plywood tebal 9 mm 185,000.00 64,750.00
2.0000 btg kayu galam 25,000.00 50,000.00
0.3200 Pekerja 79,000.00 25,280.00
0.3300 Tukang kayu 98,000.00 32,340.00
0.0330 Kepala Tukang 110,000.00 3,630.00
0.0060 Mandor 110,000.00 660.00
Jumlah 61,910.00 289,622.80 351,532.80

7 1 m3 Pek. beton bertulang 1 : 2 : 3


6.7200 zak Semen PC 50 kg 66,000.00 443,520.00
0.5400 m3 Pasir beton 365,000.00 197,100.00
0.8100 m3 Koral 425,000.00 344,250.00
2.0000 Pekerja 79,000.00 158,000.00
0.3500 Tukang batu 98,000.00 34,300.00
0.0350 Kepala Tukang 110,000.00 3,850.00
1.0000 Mandor 110,000.00 110,000.00
Jumlah 306,150.00 984,870.00 1,291,020.00
1.0000 m3 Pek. Beton + Bekisting u/ sloof 1,482,254.40
( contoh )

8 1 m3 Pek. beton tumbuk 1 : 3 : 5


4.3600 zak Semen PC 50 kg 66,000.00 287,760.00
0.5200 m3 Pasir beton 365,000.00 189,800.00
0.8700 m3 Koral 425,000.00 369,750.00
1.6500 Pekerja 79,000.00 130,350.00
0.2500 Tukang batu 98,000.00 24,500.00
0.0250 Kepala Tukang 110,000.00 2,750.00
0.0800 Mandor 110,000.00 8,800.00
Harga Satuan Upah Bahan Jumlah Harga
No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)
Jumlah 166,400.00 847,310.00 1,013,710.00
Harga Satuan Upah Bahan Jumlah Harga
No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)

9 1 Kg Pembesian dengan besi polos / besi ulir


1.0500 kg Besi beton 10,500.00 11,025.00
0.0150 kg Kawat beton 22,000.00 330.00
0.0070 Pekerja 79,000.00 553.00
0.0070 Tukang besi 98,000.00 686.00
0.0007 Kepala Tukang 110,000.00 77.00
0.0003 Mandor 110,000.00 33.00
Jumlah 1,349.00 11,355.00 12,704.00
11 1 m2 Rabat beton tebal 5 cm
campuran 1 : 3 : 5
0.2000 zak Semen PC 50 kg 66,000.00 13,200.00
0.0260 m3 Pasir beton 365,000.00 9,490.00
0.0440 m3 Koral 425,000.00 18,700.00
1.1500 Pekerja 79,000.00 90,850.00
0.0200 Tukang batu 98,000.00 1,960.00
0.0020 Kepala Tukang 110,000.00 220.00
0.0060 Mandor 110,000.00 660.00
Jumlah 93,690.00 41,390.00 135,080.00

E Pekerjaan Dinding
1 1 m2 Pasangan batu bata tebal 1/2 bata 1 : 2
60.0000 bh Batu bata 1,000.00 60,000.00
0.3790 zak Semen PC 50 kg 66,000.00 25,014.00
0.0380 m3 Pasir pasang putih 87,000.00 3,306.00
0.3200 Pekerja 79,000.00 25,280.00
0.1000 Tukang batu 98,000.00 9,800.00
0.0100 Kepala Tukang 110,000.00 1,100.00
0.0150 Mandor 110,000.00 1,650.00
Jumlah 37,830.00 88,320.00 126,150.00
2 1 m2 Pasangan batu bata tebal 1 bata 1 : 2
### bh Batu bata 1,000.00 120,000.00
0.8700 zak Semen PC 50 kg 66,000.00 57,420.00
0.0800 m3 Pasir pasang putih 87,000.00 6,960.00
0.6500 Pekerja 79,000.00 51,350.00
0.2000 Tukang batu 98,000.00 19,600.00
0.0200 Kepala Tukang 110,000.00 2,200.00
0.0300 Mandor 110,000.00 3,300.00
Jumlah 76,450.00 184,380.00 260,830.00
3 1 m2 Pasangan batu bata tebal 1/2 bata 1 : 4
60.0000 bh Batu bata 1,000.00 60,000.00
0.2300 zak Semen PC 50 kg 66,000.00 15,180.00
0.0430 m3 Pasir pasang putih 87,000.00 3,741.00
0.3200 Pekerja 79,000.00 25,280.00
0.1000 Tukang batu 98,000.00 9,800.00
0.0100 Kepala Tukang 110,000.00 1,100.00
0.0150 Mandor 110,000.00 1,650.00
Jumlah 37,830.00 78,921.00 116,751.00
4 1 m2 Pasang dinding roster 20 x 20
26.0000 bh Roster 19,000.00 494,000.00
0.2560 zak Semen PC 50 kg 66,000.00 16,896.00
0.0350 m3 Pasir pasang putih 87,000.00 3,045.00
0.3000 Pekerja 79,000.00 23,700.00
0.1000 Tukang batu 98,000.00 9,800.00
0.0150 Kepala Tukang 110,000.00 1,650.00
0.0150 Mandor 110,000.00 1,650.00
Jumlah 36,800.00 513,941.00 550,741.00
Harga Satuan Upah Bahan Jumlah Harga
No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)
F Pekerjaan Plesteran
2 1 m2 Plesteran tebal 15 mm dengan 1 : 2
0.1704 zak Semen PC 50 kg 66,000.00 11,246.40
0.0170 m3 Pasir pasang putih 87,000.00 1,479.00
0.2000 Pekerja 79,000.00 15,800.00
0.1500 Tukang batu 98,000.00 14,700.00
0.0150 Kepala Tukang 110,000.00 1,650.00
0.0100 Mandor 110,000.00 1,100.00
Jumlah 33,250.00 12,725.40 45,975.40

4 1 m2 Plesteran tebal 15 mm dengan 1 : 4


0.1040 zak Semen PC 50 kg 66,000.00 6,864.00
0.0200 m3 Pasir pasang putih 87,000.00 1,740.00
0.2000 Pekerja 79,000.00 15,800.00
0.1500 Tukang batu 98,000.00 14,700.00
0.0150 Kepala Tukang 110,000.00 1,650.00
0.0100 Mandor 110,000.00 1,100.00
Jumlah 33,250.00 8,604.00 41,854.00
6 1 m2 Plesteran ciprat 1 : 2
0.0864 zak Semen PC 50 kg 66,000.00 5,702.40
0.0160 m3 Pasir pasang putih 87,000.00 1,392.00
0.2500 Pekerja 79,000.00 19,750.00
0.1000 Tukang batu 98,000.00 9,800.00
0.0100 Kepala Tukang 110,000.00 1,100.00
0.0150 Mandor 110,000.00 1,650.00
Jumlah 32,300.00 7,094.40 39,394.40
G Pekerjaan Lantai & Dinding
3 1 m2 Pasang lantai keramik 20 x 20 type kasar
1.1000 m2 Keramik 20 x 20 65,000.00 71,500.00
0.2276 zak Semen PC 50 kg 66,000.00 15,021.60
0.0420 m3 Pasir pasang putih 87,000.00 3,654.00
1.5000 kg Semen warna 9,000.00 13,500.00
0.6200 Pekerja 79,000.00 48,980.00
0.3500 Tukang batu 98,000.00 34,300.00
0.0350 Kepala Tukang 110,000.00 3,850.00
0.0300 Mandor 110,000.00 3,300.00
Jumlah 90,430.00 103,675.60 194,105.60
4 1 m2 Pasang lantai keramik 40 x 40 type halus
1.1000 m2 Keramik 40 x 40 72,300.00 79,530.00
0.2276 zak Semen PC 50 kg 66,000.00 15,021.60
0.0420 m3 Pasir pasang putih 87,000.00 3,654.00
1.5000 kg Semen warna 9,000.00 13,500.00
0.6200 Pekerja 79,000.00 48,980.00
0.3500 Tukang batu 98,000.00 34,300.00
0.0350 Kepala Tukang 110,000.00 3,850.00
0.0300 Mandor 110,000.00 3,300.00
Jumlah 90,430.00 111,705.60 202,135.60
5 1 m2 Pasang lantai keramik 40 x 40 type kasar
1.1000 m2 Keramik 40 x 40 72,300.00 79,530.00
0.2276 zak Semen PC 50 kg 66,000.00 15,021.60
0.0420 m3 Pasir pasang putih 87,000.00 3,654.00
1.5000 kg Semen warna 9,000.00 13,500.00
0.6200 Pekerja 79,000.00 48,980.00
0.3500 Tukang batu 98,000.00 34,300.00
0.0350 Kepala Tukang 110,000.00 3,850.00
0.0300 Mandor 110,000.00 3,300.00
Jumlah 90,430.00 111,705.60 202,135.60
H Pekerjaan Plafond
5 1 m2 Plafond kalsiboard 3 mm + rangka
4.0000 m' Rangka Besi Hollow 23,500.00 94,000.00
0.3900 lbr Kalsiboard 3 mm 85,000.00 33,150.00
8.0000 bh Skrup 3,000.00 24,000.00
0.4000 Tukang kayu 98,000.00 39,200.00
0.2700 Pekerja 79,000.00 21,330.00
0.0400 Kepala Tukang 110,000.00 4,400.00
Harga Satuan Upah Bahan Jumlah Harga
No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)
0.0135 Mandor 110,000.00 1,485.00
Jumlah 66,415.00 151,150.00 217,565.00
Harga Satuan Upah Bahan Jumlah Harga
No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)
I Pekerjaan Kusen
1 1 m3 Kusen pintu, jendela, ventilasi kayu ulin
1.1000 m3 Kayu ulin 4,500,000.00 ###
6.0000 Pekerja 79,000.00 474,000.00
20.0000 Tukang kayu 98,000.00 ###
2.0000 Kepala Tukang 110,000.00 220,000.00
0.3000 Mandor 110,000.00 33,000.00
Jumlah ### ### 7,637,000.00
2 1 m3 Kusen pintu, jendela, ventilasi (bangkirai)
1.2000 m3 Kayu bangkirai 4,500,000.00 ###
6.0000 Pekerja 79,000.00 474,000.00
18.0000 Tukang kayu 98,000.00 ###
2.0000 Kepala Tukang 110,000.00 220,000.00
0.3000 Mandor 110,000.00 33,000.00
Jumlah ### ### 7,891,000.00
J Pekerjaan Atap
3 1 m2 Atap genteng metal
1.6660 lbr Genteng metal 87,000.00 144,942.00
0.2000 kg Paku genteng metal 27,500.00 5,500.00
0.2000 Pekerja 79,000.00 15,800.00
0.1000 Tukang kayu 98,000.00 9,800.00
0.0100 Kepala Tukang 110,000.00 1,100.00
0.0010 Mandor 110,000.00 110.00
Jumlah 26,810.00 150,442.00 177,252.00
6 1 m' Nok genteng metal
1.1000 bh Nok model U 33,750.00 37,125.00
0.0500 kg Paku genteng metal 27,500.00 1,375.00
0.2500 Pekerja 79,000.00 19,750.00
0.1500 Tukang kayu 98,000.00 14,700.00
0.0150 Kepala Tukang 110,000.00 1,650.00
0.0130 Mandor 110,000.00 1,430.00
Jumlah 37,530.00 38,500.00 76,030.00
9 1 m' List plank kayu klas I (1 x 2/20)
0.0086 m3 Papan kayu klas I 6,500,000.00 55,900.00
0.0600 kg Paku kayu 20,500.00 1,230.00
0.1000 Pekerja 79,000.00 7,900.00
0.1000 Tukang kayu 98,000.00 9,800.00
0.0100 Kepala Tukang 110,000.00 1,100.00
0.0500 Mandor 110,000.00 5,500.00
Jumlah 24,300.00 57,130.00 81,430.00

L Pekerjaan Cat-catan
1 1 m2 Mendempul
0.0800 kg Dempul 27,500.00 2,200.00
0.0200 liter Minyak cat 9,500.00 190.00
0.0100 Kg Batu apung 950.00 9.50
0.0400 Pekerja 79,000.00 3,160.00
0.0400 Tukang cat 98,000.00 3,920.00
0.0040 Kepala Tukang 110,000.00 440.00
0.0025 Mandor 110,000.00 275.00
Jumlah 7,795.00 2,399.50 10,194.50
2 1 m2 Mengecat tembok yang baru
( 1 lapis plamir, 1 lapis cat dasar, dan
2 lapis cat penutup )
0.1000 kg Plamir 16,650.00 1,665.00
0.1000 kg Cat dasar 21,000.00 2,100.00
0.2600 kg Cat tembok ( Cat Penutup ) 2x 110,000.00 28,600.00
0.0200 Pekerja 79,000.00 1,580.00
0.0630 Tukang cat 98,000.00 6,174.00
0.0063 Kepala Tukang 110,000.00 693.00
0.0025 Mandor 110,000.00 275.00
Jumlah 8,722.00 32,365.00 41,087.00
Harga Satuan Upah Bahan Jumlah Harga
No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)
3 1 m2 Pekerjaan cat kilap ( 1 lapis plamir ;
1 lapis cat dasar ; 2 lapis cat penutup )
0.2000 kg Cat meni 21,600.00 4,320.00
0.1500 kg Plamir 16,650.00 2,497.50
0.1700 kg Cat dasar 21,000.00 3,570.00
0.2600 kg Cat penutup 2 kali 110,000.00 28,600.00
0.0700 Pekerja 79,000.00 5,530.00
0.0090 Tukang cat 98,000.00 882.00
0.0060 Kepala Tukang 110,000.00 660.00
0.0025 Mandor 110,000.00 275.00
Jumlah 7,347.00 38,987.50 46,334.50
4 1 m2 Pekerjaan cat kilap ( 1 lapis plamir ;
1 lapis cat dasar ; 3 lapis cat penutup )
0.2000 kg Cat meni 21,600.00 4,320.00
0.1500 kg Plamir 16,650.00 2,497.50
0.1700 kg Cat dasar 21,000.00 3,570.00
0.3500 kg Cat penutup 3 kali 110,000.00 38,500.00
0.0700 Pekerja 79,000.00 5,530.00
0.1050 Tukang cat 98,000.00 10,290.00
0.0040 Kepala Tukang 110,000.00 440.00
0.0025 Mandor 110,000.00 275.00
Jumlah 16,535.00 48,887.50 65,422.50
5 1 m2 Plituran
0.5220 kg Politur 17,500.00 9,135.00
2.0000 lbr Ampelas 3,000.00 6,000.00
0.0600 Tukang cat 98,000.00 5,880.00
0.0160 Kepala Tukang 110,000.00 1,760.00
0.0025 Mandor 110,000.00 275.00
Jumlah 7,915.00 15,135.00 23,050.00

6 1 m2 Mengecat dasar / meni


0.1000 kg Cat dasar / meni 21,000.00 2,100.00
0.0100 Bh Kuas 23,500.00 235.00
0.2000 Tukang cat 98,000.00 19,600.00
0.0200 Pekerja 79,000.00 1,580.00
0.0200 Kepala Tukang 110,000.00 2,200.00
0.0100 Mandor 110,000.00 1,100.00
Jumlah 24,480.00 2,335.00 26,815.00
O Pekerjaan Pengunci penggantung & Kaca
1 1 bh.Pasang kunci tanam berkualitas
1.0000 bh kunci tanam antik 145,000.00 145,000.00
0.6000 Tukang kayu 98,000.00 58,800.00
0.0600 Pekerja 79,000.00 4,740.00
0.0600 Kepala tukang 110,000.00 6,600.00
0.0030 Mandor 110,000.00 330.00
Jumlah 70,470.00 145,000.00 215,470.00
2 1 bh.Pasang kunci tanam biasa
1.0000 bh kunci tanam biasa 165,000.00 165,000.00
0.5000 Tukang kayu 98,000.00 49,000.00
0.0100 Pekerja 79,000.00 790.00
0.0100 Kepala tukang 110,000.00 1,100.00
0.0050 Mandor 110,000.00 550.00
Jumlah 51,440.00 165,000.00 216,440.00
5 1 bh.Pasang engsel pintu
1.0000 bh engsel pintu 38,750.00 38,750.00
0.1500 Tukang kayu 98,000.00 14,700.00
0.0150 Pekerja 79,000.00 1,185.00
0.0150 Kepala tukang 110,000.00 1,650.00
0.0008 Mandor 110,000.00 82.50
Jumlah 17,617.50 38,750.00 56,367.50
Harga Satuan Upah Bahan Jumlah Harga
No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)
6 1 bh.Pasang engsel jendela kupu-kupu
1.0000 bh engsel kupu-kupu 28,500.00 28,500.00
0.1000 Tukang kayu 98,000.00 9,800.00
0.0100 Pekerja 79,000.00 790.00
0.0100 Kepala tukang 110,000.00 1,100.00
0.0005 Mandor 110,000.00 55.00
Jumlah 11,745.00 28,500.00 40,245.00
7 1 bh.Pasang engsel angin
1.0000 bh engsel angin 28,500.00 28,500.00
0.2000 Tukang kayu 98,000.00 19,600.00
0.0200 Pekerja 79,000.00 1,580.00
0.0200 Kepala tukang 110,000.00 2,200.00
0.0010 Mandor 110,000.00 110.00
Jumlah 23,490.00 28,500.00 51,990.00
8 1 bh.Pasang Grendel pintu
1.0000 bh pegangan pintu 23,400.00 23,400.00
0.5000 Tukang kayu 98,000.00 49,000.00
0.0500 Pekerja 79,000.00 3,950.00
0.0500 Kepala tukang 110,000.00 5,500.00
0.0025 Mandor 110,000.00 275.00
Jumlah 58,725.00 23,400.00 82,125.00
10 1 bh.Pasang kait angin
1.0000 bh kait angin 18,750.00 18,750.00
0.1500 Tukang kayu 98,000.00 14,700.00
0.0150 Pekerja 79,000.00 1,185.00
0.0150 Kepala tukang 110,000.00 1,650.00
0.0008 Mandor 110,000.00 82.50
Jumlah 17,617.50 18,750.00 36,367.50

12 1 m2.Pasang kaca tebal 5mm


1.1000 m2 kaca 35,000.00 38,500.00
0.1500 Tukang kayu 98,000.00 14,700.00
0.0150 Pekerja 79,000.00 1,185.00
0.0150 Kepala tukang 110,000.00 1,650.00
0.0008 Mandor 110,000.00 82.50
Jumlah 17,617.50 38,500.00 56,117.50
RENCANA ANGGARAN BIAYA
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan
Pekerjaan : Pembangunan RKB SDN 009 Waru (Limau Kembang)
Lokasi : Kec. Waru Kab. Penajam Paser Utara
Tahun : 2014

HARGA SATUAN JUMLAH


NO URAIAN PEKERJAAN SATUAN VOL.
(Rp) (Rp)
1 2 3 4 5 6=4*5
I PEKERJAAN PENDAHULUAN
1 Memasang Bouwplank m' 73.50 72,002.24 5,292,164.64
2 Pembersihan Lokasi ls 1.00 6,500,000.00 6,500,000.00
3 Pembuatan Papan Proyek ls 1.00 550,000.00 550,000.00

Sub Total 12,342,164.64


II PEKERJAAN GALIAN DAN TANAH
1 Galian Tanah Pondasi m3 52.92 36,000.00 1,905,120.00
2 Urugan Tanah Kembali m3 17.64 17,258.00 304,431.12
3 Urugan Tanah Dibawah Lantai m3 95.50 171,900.00 16,416,450.00
4 Urugan Pasir Dibawah Pondasi m3 5.88 174,200.00 1,024,296.00
5 Urugan Pasir Dibawah Lantai m3 19.10 174,200.00 3,327,220.00

Sub Total 22,977,517.12


III PEKERJAAN PONDASI
1 Pas. Batu Kosong Astamping t= 20 cm m3 11.76 398,520.00 4,686,595.20
2 Pas. Batu Gunung 1:4 m3 32.34 694,550.00 22,461,747.00

Sub Total 27,148,342.20


IV PEKERJAAN PASANGAN
1 Pas. Diding Batu Bata 1:2 tebal 1/2 bata m2 15.90 126,150.00 2,005,785.00
2 Pas. Diding Batu Bata 1:4 tebal 1/2 bata m2 159.79 116,751.00 18,655,642.29
3 Pas. Rollag Bata Camp 1:4 tebal 1/2 bata m2 22.80 116,751.00 2,661,922.80
4 Plesteran Dinding 1:2 tebal 15 mm m2 31.80 45,975.40 1,462,017.72
5 Plesteran Dinding 1:4 tebal 15 mm m2 319.58 41,854.00 13,375,701.32
6 Plesteran Pas Rollag Bata Camp 1:2 tebal 15 m2 45.60 45,975.40 2,096,478.24
7 Plesteran Tali Air Tiang Teras tebal 15 mm m2 7.20 41,854.00 301,348.80

Sub Total 40,558,896.17


V PEKERJAAN BETON
1 Cor Lantai t = 5 cm 1:3:5 m3 13.37 1,013,710.00 13,553,302.70
2 Slof Beton 15 / 20
- Cor beton camp. 1 : 2 : 3 m3 2.21 1,291,020.00 2,846,699.10
- Pembesian kg 393.65 12,704.00 5,000,946.12
- Bekisting m2 14.70 191,234.40 2,811,145.68
3 Kolom Struktur 15 / 25
- Cor beton camp. 1 : 2 : 3 m3 1.89 1,291,020.00 2,440,027.80
- Pembesian kg 394.99 12,704.00 5,018,014.96
- Bekisting m2 18.50 342,002.80 6,327,051.80
4 Kolom Praktis 12/12
- Cor beton camp. 1 : 2 : 3 m3 5.18 1,291,020.00 6,692,647.68
- Pembesian kg 55.91 12,704.00 710,218.64
- Bekisting m2 2.59 342,002.80 885,787.25
5 Kolom Teras 15/15
- Cor beton camp. 1 : 2 : 3 m3 0.57 1,291,020.00 732,008.34
- Pembesian kg 152.79 12,704.00 1,941,077.70
- Bekisting m2 7.56 351,532.80 2,657,587.97
6 Ring Balk 15/20
- Cor beton camp. 1 : 2 : 3 m3 2.21 1,291,020.00 2,846,699.10
- Pembesian kg 380.17 12,704.00 4,829,697.47
- Bekisting m2 22.05 351,532.80 7,751,298.24
Sub Total 67,044,210.54
VI PEKERJAAN KERAMIK
1 Pas. Keramik Type Halus 40x40 m2 112.00 202,135.60 22,639,187.20
2 Pas. Keramik Teras Type Kasar 40x40 m2 24.00 202,135.60 4,851,254.40

Sub Total 27,490,441.60


VII PEKERJAAN PINTU DAN JENDELA
1 Kusen Kayu Ulin Pintu 5/12 m3 0.10 7,637,000.00 783,556.20
2 Daun Pintu Ganda ( Double ) Panel Kayu Ulin bh 4.00 620,000.00 2,480,000.00
3 Pasangan Kusen Almunium Jendela m' 80.00 120,000.00 9,600,000.00
4 Pasangan Jendela rangka alumunium + kaca 5 bh 30.00 345,000.00 10,350,000.00
5 Roster bh 33.00 550,741.00 18,174,453.00

Sub Total 41,388,009.20


VIII PEKERJAAN KERANGKA ATAP DAN ATAP
1 Kuda-kuda+Gording+Kasau+Reng Baja Ringan m2 109.46 187,000.00 20,469,020.00
2 Pasangan Atap Genteng Metal m2 109.46 177,252.00 19,402,003.92
3 Bubungan Atap Genteng Metal m' 26.64 76,030.00 2,025,439.20
4 Listplank Kayu Ulin ( 1 x 2/20 ) m' 57.00 81,430.00 4,641,510.00
5 Angin angin Atap bh 2.00 365,000.00 730,000.00

Sub Total 47,267,973.12


IX PEKERJAAN PLAFOND
1 Pas. Plafond Calcyboard dan Rangka Besi Hollo m2 189.00 217,565.00 41,119,785.00
2 Lis Plafond m' 106.00 33,500.00 3,551,000.00

Sub Total 44,670,785.00


X PEKERJAAN PENGGANTUNG,
PENUTUP DAN PENGUNCI
1 Pasangan kunci bh 4.00 215,470.00 861,880.00
2 Pasangan Engsel Pintu (3 bh/pintu) bh 12.00 56,367.50 676,410.00
3 Pasangan engsel jendela friction stay 16" bh 30.00 40,245.00 1,207,350.00
4 Grendel jendela bh 30.00 27,500.00 825,000.00
5 Grendel tanam pintu double bh 4.00 82,125.00 328,500.00
6 Hendle Jendela bh 30.00 23,500.00 705,000.00

Sub Total 4,604,140.00


XI PEKERJAAN ELEKTRIKAL
1 Instalasi Listrik titik 16.00 160,000.00 2,560,000.00
2 Pas. Lampu Pijar 18 Watt bh 12.00 47,500.00 570,000.00
3 Pas. Saklar Ganda bh 4.00 27,500.00 110,000.00
4 Pas. Stop Kontak bh 2.00 22,500.00 45,000.00
5 Sekering Kas 3 Group + Instalasi bh 1.00 245,000.00 245,000.00

Sub Total 3,530,000.00


XII PEKERJAAN PENGECATAN
1 Pengecatan Dinding Dalam dan Luar m2 376.36 41,087.00 15,463,503.32
2 Pengecatan Plafond m2 189.00 41,087.00 7,765,443.00
3 Pengecatan Kusen, Daun Pintu Dengan Cat Kil m2 28.70 65,422.50 1,877,625.75

Sub Total 25,106,572.07

Grand Total 364,129,051.66


LAPORAN MINGGUAN

Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV.KARYA SEJATI UTAMA
Pekerjaan : Pembangunan RKB SDN 009 Waru Konsultan Pengawas : CV. ARDHIA ASRI
Lokasi : Kec. Babulu Kab. Penajam Paser Utara Minggu : I ( Pertama )
Tahun : 2014 Periode : 15 Agustus 2014 - 17 Agustus 2014

S/d Minggu Lalu Minggu ini S/d Minggu ini


NO URAIAN SAT VOL HARGA SAT JUMLAH BOBOT KET
( Rp. ) ( Rp. ) (%) BOBOT VOLUME BOBOT VOLUME BOBOT VOLUME (%)
(%) (%) (%)
I PEKERJAAN PENDAHULUAN
1 Memasang Bouwplank m' 73.50 72,002.24 5,292,164.64 1.45 - - 1.45 73.50 1.45 73.50 100.00
2 Pembersihan Lokasi ls 1.00 6,500,000.00 6,500,000.00 1.79 - - 1.79 1.00 1.79 1.00 100.00
3 Pembuatan Papan Proyek ls 1.00 550,000.00 550,000.00 0.15 - - - - - - -

TOTAL 364,129,051.66 100.00 - 0.05 3.24

Disetujui Oleh Diperiksa Oleh Dibuat Oleh


Pengawas Lapangan Disdikpora KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
CV. INTENCIVINDO CV. NUR KHALIFAH AGUNG

DWI RAHARJO, ST TRI EVI HERAWATI HERMAN, ST FERAWATI MARADDING, ST


Nip. 19770906 200904 1 001 Site Engineer Pelaksana Lapangan

LAPORAN MINGGUAN

Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV.KARYA SEJATI UTAMA
Pekerjaan : Pembangunan RKB SDN 009 Waru Konsultan Pengawas : CV. ARDHIA ASRI
Lokasi : Kec. Babulu Kab. Penajam Paser Utara Minggu : I ( Pertama )
Tahun : 2014 Periode : 15 Agustus 2014 - 17 Agustus 2014

S/d Minggu Lalu Minggu ini S/d Minggu ini


NO URAIAN SAT VOL HARGA SAT JUMLAH BOBOT KET
( Rp. ) ( Rp. ) (%) (%)
NO URAIAN SAT VOL HARGA SAT JUMLAH BOBOT KET
( Rp. ) ( Rp. ) (%) BOBOT VOLUME BOBOT VOLUME BOBOT VOLUME (%)
(%) (%) (%)
I PEKERJAAN PENDAHULUAN
1 Memasang Bouwplank m' 73.50 72,002.24 5,292,164.64 1.45 - - 100.00 73.50 100.00 73.50 100.00
2 Pembersihan Lokasi ls 1.00 6,500,000.00 6,500,000.00 1.79 - - 100.00 1.00 100.00 1.00 100.00
3 Pembuatan Papan Proyek ls 1.00 550,000.00 550,000.00 0.15 - - - - - - -
II PEKERJAAN GALIAN DAN TANAH
1 Galian Tanah Pondasi m3 52.92 36,000.00 1,905,120.00 0.52 - - - - - - -
2 Urugan Tanah Kembali m3 17.64 17,258.00 304,431.12 0.08 - - - - - - -
3 Urugan Tanah Dibawah Lantai m3 95.50 171,900.00 16,416,450.00 4.51 - - - - - - -
4 Urugan Pasir Dibawah Pondasi m3 5.88 174,200.00 1,024,296.00 0.28 - - - - - - -
5 Urugan Pasir Dibawah Lantai m3 19.10 174,200.00 3,327,220.00 0.91 - - - - - - -
III PEKERJAAN PONDASI
1 Pas. Batu Kosong Astamping t= 20 cm m3 11.76 398,520.00 4,686,595.20 1.29 - - - - - - -
2 Pas. Batu Gunung 1:4 m3 32.34 694,550.00 22,461,747.00 6.17 - - - - - - -
IV PEKERJAAN PASANGAN
1 Pas. Diding Batu Bata 1:2 tebal 1/2 bata m2 15.90 126,150.00 2,005,785.00 0.55 - - - - - - -
2 Pas. Diding Batu Bata 1:4 tebal 1/2 bata m2 159.79 116,751.00 18,655,642.29 5.12 - - - - - - -
3 Pas. Rollag Bata Camp 1:4 tebal 1/2 bata m2 22.80 116,751.00 2,661,922.80 0.73 - - - - - - -
4 Plesteran Dinding 1:2 tebal 15 mm m2 31.80 45,975.40 1,462,017.72 0.40 - - - - - - -
5 Plesteran Dinding 1:4 tebal 15 mm m2 319.58 41,854.00 13,375,701.32 3.67 - - - - - - -
6 Plesteran Pas Rollag Bata Camp 1:2 tebal 15 mm m2 45.60 45,975.40 2,096,478.24 0.58 - - - - - - -
7 Plesteran Tali Air Tiang Teras tebal 15 mm m2 7.20 41,854.00 301,348.80 0.08 - - - - - - -
V PEKERJAAN BETON
1 Cor Lantai t = 5 cm 1:3:5 m3 13.37 1,013,710.00 13,553,302.70 3.72 - - - - - - -
2 Slof Beton 15 / 20
- Cor beton camp. 1 : 2 : 3 m3 2.21 1,291,020.00 2,846,699.10 0.78 - - - - - - -
- Pembesian kg 393.65 12,704.00 5,000,946.12 1.37 - - - - - - -
- Bekisting m2 14.70 191,234.40 2,811,145.68 0.77 - - - - - - -
3 Kolom Struktur 15 / 25
- Cor beton camp. 1 : 2 : 3 m3 1.89 1,291,020.00 2,440,027.80 0.67 - - - - - - -
- Pembesian kg 394.99 12,704.00 5,018,014.96 1.38 - - - - - - -
- Bekisting m2 18.50 342,002.80 6,327,051.80 1.74 - - - - - - -
4 Kolom Praktis 12/12
- Cor beton camp. 1 : 2 : 3 m3 5.18 1,291,020.00 6,692,647.68 1.84 - - - - - - -
- Pembesian kg 55.91 12,704.00 710,218.64 0.20 - - - - - - -
- Bekisting m2 2.59 342,002.80 885,787.25 0.24 - - - - - - -
5 Kolom Teras 15/15
- Cor beton camp. 1 : 2 : 3 m3 0.57 1,291,020.00 732,008.34 0.20 - - - - - - -
- Pembesian kg 152.79 12,704.00 1,941,077.70 0.53 - - - - - - -
- Bekisting m2 7.56 351,532.80 2,657,587.97 0.73 - - - - - - -
6 Ring Balk 15/20
- Cor beton camp. 1 : 2 : 3 m3 2.21 1,291,020.00 2,846,699.10 0.78 - - - - - - -
- Pembesian kg 380.17 12,704.00 4,829,697.47 1.33 - - - - - - -
- Bekisting m2 22.05 351,532.80 7,751,298.24 2.13 - - - - - - -
VI PEKERJAAN KERAMIK
1 Pas. Keramik Type Halus 40x40 m2 112.00 202,135.60 22,639,187.20 6.22 - - - - - - -
2 Pas. Keramik Teras Type Kasar 40x40 m2 24.00 202,135.60 4,851,254.40 1.33 - - - - - - -
VII PEKERJAAN PINTU DAN JENDELA
1 Kusen Kayu Ulin Pintu 5/12 m3 0.10 7,637,000.00 783,556.20 0.22 - - - - - - -
2 Daun Pintu Ganda ( Double ) Panel Kayu Ulin bh 4.00 620,000.00 2,480,000.00 0.68 - - - - - - -
3 Pasangan Kusen Almunium Jendela m' 80.00 120,000.00 9,600,000.00 2.64 - - - - - - -
4 Pasangan Jendela rangka alumunium + kaca 5 mm bh 30.00 345,000.00 10,350,000.00 2.84 - - - - - - -
5 Roster bh 33.00 550,741.00 18,174,453.00 4.99 - - - - - - -
VIII PEKERJAAN KERANGKA ATAP DAN ATAP
1 Kuda-kuda+Gording+Kasau+Reng Baja Ringan m2 109.46 187,000.00 20,469,020.00 5.62 - - - - - - -
2 Pasangan Atap Genteng Metal m2 109.46 177,252.00 19,402,003.92 5.33 - - - - - - -
3 Bubungan Atap Genteng Metal m' 26.64 76,030.00 2,025,439.20 0.56 - - - - - - -
4 Listplank Kayu Ulin ( 1 x 2/20 ) m' 57.00 81,430.00 4,641,510.00 1.27 - - - - - - -
5 Angin angin Atap bh 2.00 365,000.00 730,000.00 0.20 - - - - - - -
IX PEKERJAAN PLAFOND
1 Pas. Plafond Calcyboard dan Rangka Besi Hollow m2 189.00 217,565.00 41,119,785.00 11.29 - - - - - - -
2 Lis Plafond m' 106.00 33,500.00 3,551,000.00 0.98 - - - - - - -
X PEKERJAAN PENGGANTUNG,
PENUTUP DAN PENGUNCI
1 Pasangan kunci bh 4.00 215,470.00 861,880.00 0.24 - - - - - - -
2 Pasangan Engsel Pintu (3 bh/pintu) bh 12.00 56,367.50 676,410.00 0.19 - - - - - - -
3 Pasangan engsel jendela friction stay 16" bh 30.00 40,245.00 1,207,350.00 0.33 - - - - - - -
4 Grendel jendela bh 30.00 27,500.00 825,000.00 0.23 - - - - - - -
5 Grendel tanam pintu double bh 4.00 82,125.00 328,500.00 0.09 - - - - - - -
6 Hendle Jendela bh 30.00 23,500.00 705,000.00 0.19 - - - - - - -
XI PEKERJAAN ELEKTRIKAL
1 Instalasi Listrik titik 16.00 160,000.00 2,560,000.00 0.70 - - - - - - -
2 Pas. Lampu Pijar 18 Watt bh 12.00 47,500.00 570,000.00 0.16 - - - - - - -
3 Pas. Saklar Ganda bh 4.00 27,500.00 110,000.00 0.03 - - - - - - -
4 Pas. Stop Kontak bh 2.00 22,500.00 45,000.00 0.01 - - - - - - -
5 Sekering Kas 3 Group + Instalasi bh 1.00 245,000.00 245,000.00 0.07 - - - - - - -
XII PEKERJAAN PENGECATAN
1 Pengecatan Dinding Dalam dan Luar m2 376.36 41,087.00 15,463,503.32 4.25 - - - - - - -
2 Pengecatan Plafond m2 189.00 41,087.00 7,765,443.00 2.13 - - - - - - -
3 Pengecatan Kusen, Daun Pintu Dengan Cat Kilap m2 28.70 65,422.50 1,877,625.75 0.52 - - - - - - -

TOTAL 364,129,051.66 100.00 - 10.00 200.00

Disetujui Oleh Diperiksa Oleh Dibuat Oleh


Pengawas Lapangan Disdikpora KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
CV. INTENCIVINDO CV. NUR KHALIFAH AGUNG
DWI RAHARJO, ST TRI EVI HERAWATI HERMAN, ST FERAWATI MARADDING, ST
Nip. 19770906 200904 1 001 Site Engineer Pelaksana Lapangan
LAPORAN MINGGUAN

Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : II ( Kedua )
Tahun : 2014 Periode : 23 Juni 2014 - 30 Juni 2014

S/d Minggu Lalu Minggu ini S/d Minggu ini


HARGA SAT JUMLAH BOBOT KET
NO URAIAN SAT VOL ( Rp. ) ( Rp. ) (%) BOBOT BOBOT BOBOT (%)
(%) VOLUME (%) VOLUME (%) VOLUME
I PEKERJAAN PENDAHULUAN
1 Memasang Bouwplank Ls 1.00 2,500,000.00 2,500,000.00 1.43 1.45 73.50 1.45 0.50 2.91 74.00 7,400.00
2 Pembuatan Papan Proyek unit 1.00 350,000.00 350,000.00 0.20 1.79 1.00 0.20 1.00 1.99 2.00 200.00
3 Pembongkaran dan Perbaikan Tiang Bendera Ls 1.00 2,000,000.00 2,000,000.00 1.14 - - - - - - -

II PEKERJAAN GALIAN DAN TANAH


1 Galian Tanah Beton 1 : 2 : 3 m3 4.05 36,400.00 147,420.00 0.08 - - 0.08 4.05 0.08 4.05 100.00
2 Urugan Pasir Dibawah Beton m3 0.75 173,600.00 130,200.00 0.07 - - 0.07 0.75 0.07 0.75 100.00
3 Urugan Pasir Dibawah Paving Block m3 60.00 173,600.00 10,416,000.00 5.96 - - - - - - -

III PEKERJAAN BETON DAN PAVING BLOCK


1 Cor Beton 15 / 40
- Cor beton camp. 1 : 2 : 3 m3 6.00 1,355,970.00 8,135,820.00 4.65 - - - - - - -
- Bekisting m2 76.70 192,054.40 14,730,572.48 8.42 - - - - - - -
2 Pas. Paving Block m2 600.00 227,500.00 136,500,000.00 78.04 - - - - - - -

TOTAL 174,910,012.48 100.00 3.24 1.81 5.05

Disetujui Oleh Diperiksa Oleh Dibuat Oleh


Pengawas Lapangan Disdikpora KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
CV. INTENCIVINDO CV. NUR KHALIFAH AGUNG

DWI RAHARJO, ST TRI EVI HERAWATI HERMAN, ST FERAWATI MARADDING, ST


Nip. 19770906 200904 1 001 Site Engineer Pelaksana Lapangan
LAPORAN MINGGUAN

Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : III ( Ketiga )
Tahun : 2014 Periode : 1 Juli 2014 - 6 Juli 2014

S/d Minggu Lalu Minggu ini S/d Minggu ini


HARGA SAT JUMLAH BOBOT KET
NO URAIAN SAT VOL ( Rp. ) ( Rp. ) (%) (%)
BOBOT BOBOT BOBOT
(%) VOLUME (%) VOLUME (%) VOLUME
I PEKERJAAN PENDAHULUAN
1 Memasang Bouwplank Ls 1.00 2,500,000.00 2,500,000.00 1.43 2.91 74.00 - - 2.91 74.00 7,400.00
2 Pembuatan Papan Proyek unit 1.00 350,000.00 350,000.00 0.20 1.99 2.00 - - 1.99 2.00 200.00
3 Pembongkaran dan Perbaikan Tiang Bendera Ls 1.00 2,000,000.00 2,000,000.00 1.14 - - - - - - -

II PEKERJAAN GALIAN DAN TANAH


1 Galian Tanah Beton 1 : 2 : 3 m3 4.05 36,400.00 147,420.00 0.08 0.08 4.05 - - 0.08 4.05 100.00
2 Urugan Pasir Dibawah Beton m3 0.75 173,600.00 130,200.00 0.07 0.07 0.75 - - 0.07 0.75 100.00
3 Urugan Pasir Dibawah Paving Block m3 60.00 173,600.00 10,416,000.00 5.96 - - - - - - -

III PEKERJAAN BETON DAN PAVING BLOCK


1 Cor Beton 15 / 40
- Cor beton camp. 1 : 2 : 3 m3 6.00 1,355,970.00 8,135,820.00 4.65 - - 1.55 2.00 1.55 2.00 33.33
- Bekisting m2 76.70 192,054.40 14,730,572.48 8.42 - - 2.81 25.57 2.81 25.57 33.33
2 Pas. Paving Block m2 600.00 227,500.00 136,500,000.00 78.04 - - - - - - -

TOTAL 174,910,012.48 100.00 5.05 4.36 9.41

Disetujui Oleh Diperiksa Oleh Dibuat Oleh


Pengawas Lapangan Disdikpora KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
CV. INTENCIVINDO CV. NUR KHALIFAH AGUNG

DWI RAHARJO, ST TRI EVI HERAWATI HERMAN, ST FERAWATI MARADDING, ST


Nip. 19770906 200904 1 001 Site Engineer Pelaksana Lapangan
LAPORAN MINGGUAN

Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : IV ( Keempat )
Tahun : 2014 Periode : 07 Juli 2014 - 13 Juli 2014

S/d Minggu Lalu Minggu ini S/d Minggu ini


HARGA SAT JUMLAH BOBOT KET
NO URAIAN SAT VOL ( Rp. ) ( Rp. ) (%) BOBOT BOBOT BOBOT (%)
(%) VOLUME (%) VOLUME (%) VOLUME
I PEKERJAAN PENDAHULUAN
1 Memasang Bouwplank Ls 1.00 2,500,000.00 2,500,000.00 1.43 2.91 74.00 - - 2.91 74.00 7,400.00
2 Pembuatan Papan Proyek unit 1.00 350,000.00 350,000.00 0.20 1.99 2.00 - - 1.99 2.00 200.00
3 Pembongkaran dan Perbaikan Tiang Bendera Ls 1.00 2,000,000.00 2,000,000.00 1.14 - - - - - - -

II PEKERJAAN GALIAN DAN TANAH


1 Galian Tanah Beton 1 : 2 : 3 m3 4.05 36,400.00 147,420.00 0.08 0.08 4.05 - - 0.08 4.05 100.00
2 Urugan Pasir Dibawah Beton m3 0.75 173,600.00 130,200.00 0.07 0.07 0.75 - - 0.07 0.75 100.00
3 Urugan Pasir Dibawah Paving Block m3 60.00 173,600.00 10,416,000.00 5.96 - - 5.96 60.00 5.96 60.00 100.00

III PEKERJAAN BETON DAN PAVING BLOCK


1 Cor Beton 15 / 40
- Cor beton camp. 1 : 2 : 3 m3 6.00 1,355,970.00 8,135,820.00 4.65 1.55 2.00 3.10 4.00 4.65 6.00 100.00
- Bekisting m2 76.70 192,054.40 14,730,572.48 8.42 2.81 25.57 5.61 51.13 8.42 76.70 100.00
2 Pas. Paving Block m2 600.00 227,500.00 136,500,000.00 78.04 - - 55.93 430.00 55.93 430.00 71.67

TOTAL 174,910,012.48 100.00 9.41 70.60 80.01

Disetujui Oleh Diperiksa Oleh Dibuat Oleh


Pengawas Lapangan Disdikpora KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
CV. INTENCIVINDO CV. NUR KHALIFAH AGUNG

DWI RAHARJO, ST TRI EVI HERAWATI HERMAN, ST FERAWATI MARADDING, ST


Nip. 19770906 200904 1 001 Site Engineer Pelaksana Lapangan
LAPORAN MINGGUAN

Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : V ( Lima )
Tahun : 2014 Periode : 14 Juli 2014 - 16 Juli 2014

S/d Minggu Lalu Minggu ini S/d Minggu ini


HARGA SAT JUMLAH BOBOT KET
NO URAIAN SAT VOL ( Rp. ) ( Rp. ) (%) BOBOT BOBOT BOBOT (%)
(%) VOLUME (%) VOLUME (%) VOLUME
I PEKERJAAN PENDAHULUAN
1 Memasang Bouwplank Ls 1.00 2,500,000.00 2,500,000.00 1.43 2.91 74.00 - - 2.91 74.00 7,400.00
2 Pembuatan Papan Proyek unit 1.00 350,000.00 350,000.00 0.20 1.99 2.00 - - 1.99 2.00 200.00
3 Pembongkaran dan Perbaikan Tiang Bendera Ls 1.00 2,000,000.00 2,000,000.00 1.14 - - - - - - -

II PEKERJAAN GALIAN DAN TANAH


1 Galian Tanah Beton 1 : 2 : 3 m3 4.05 36,400.00 147,420.00 0.08 0.08 4.05 - - 0.08 4.05 100.00
2 Urugan Pasir Dibawah Beton m3 0.75 173,600.00 130,200.00 0.07 0.07 0.75 - - 0.07 0.75 100.00
3 Urugan Pasir Dibawah Paving Block m3 60.00 173,600.00 10,416,000.00 5.96 5.96 60.00 - - 5.96 60.00 100.00

III PEKERJAAN BETON DAN PAVING BLOCK


1 Cor Beton 15 / 40
- Cor beton camp. 1 : 2 : 3 m3 6.00 1,355,970.00 8,135,820.00 4.65 4.65 6.00 - - 4.65 6.00 100.00
- Bekisting m2 76.70 192,054.40 14,730,572.48 8.42 8.42 76.70 - - 8.42 76.70 100.00
2 Pas. Paving Block m2 600.00 227,500.00 136,500,000.00 78.04 55.93 430.00 22.11 170.00 78.04 600.00 100.00

TOTAL 174,910,012.48 100.00 80.01 22.11 102.12

Disetujui Oleh Diperiksa Oleh Dibuat Oleh


Pengawas Lapangan Disdikpora KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
CV. INTENCIVINDO CV. NUR KHALIFAH AGUNG

DWI RAHARJO, ST TRI EVI HERAWATI HERMAN, ST FERAWATI MARADDING, ST


Nip. 19770906 200904 1 001 Site Engineer Pelaksana Lapangan
LAPORAN BULANAN

Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Bulan : I ( Pertama )
Tahun : 2014 Periode : 18 Juni 2014 - 30 Juni 2014

S/d Bulan Lalu Bulan ini S/d Bulan ini


NO URAIAN SAT VOL HARGA SAT JUMLAH BOBOT KET
( Rp. ) ( Rp. ) (%) BOBOT BOBOT BOBOT (%)
VOLUME VOLUME VOLUME
(%) (%) (%)
I PEKERJAAN PENDAHULUAN
1 Memasang Bouwplank Ls 1.00 2,500,000.00 2,500,000.00 1.43 - - 2.91 74.00 2.91 74.00 7,400.00
2 Pembuatan Papan Proyek unit 1.00 350,000.00 350,000.00 0.20 - - 1.99 2.00 1.99 2.00 200.00
3 Pembongkaran dan Perbaikan Tiang Bendera Ls 1.00 2,000,000.00 2,000,000.00 1.14 - - - - - - -

II PEKERJAAN GALIAN DAN TANAH


1 Galian Tanah Beton 1 : 2 : 3 m3 4.05 36,400.00 147,420.00 0.08 - - 0.08 4.05 0.08 4.05 100.00
2 Urugan Pasir Dibawah Beton m3 0.75 173,600.00 130,200.00 0.07 - - 0.07 0.75 0.07 0.75 100.00
3 Urugan Pasir Dibawah Paving Block m3 60.00 173,600.00 10,416,000.00 5.96 - - - - - - -
- - -
III PEKERJAAN BETON DAN PAVING BLOCK - - -
1 Cor Beton 15 / 40 - - -
- Cor beton camp. 1 : 2 : 3 m3 6.00 1,355,970.00 8,135,820.00 4.65 - - - - - - -
- Bekisting m2 76.70 192,054.40 14,730,572.48 8.42 - - - - - - -
2 Pas. Paving Block m2 600.00 227,500.00 136,500,000.00 78.04 - - - - - - -

TOTAL 174,910,012.48 100.00 - 5.05 5.05

Disetujui Oleh Diperiksa Oleh Dibuat Oleh


Pejabat Pelaksana Teknis Kegiatan KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
CV. INTENCIVINDO CV. NUR KHALIFAH AGUNG

SONNY JANUAR IKHSAN TRI EVI HERAWATI HERMAN, ST FERAWATI MARADDING, ST


Nip : 19801026 201001 1 004 Site Engineer Pelaksana Lapangan
LAPORAN BULANAN

Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : II ( Kedua )
Tahun : 2014 Periode : 01 Juli 2014 - 16 Juli 2014

S/d Bulan Lalu Bulan ini S/d Bulan ini


HARGA SAT JUMLAH BOBOT KET
NO URAIAN SAT VOL ( Rp. ) ( Rp. ) (%) (%)
BOBOT VOLUME BOBOT VOLUME BOBOT VOLUME
(%) (%) (%)
I PEKERJAAN PENDAHULUAN
1 Memasang Bouwplank Ls 1.00 2,500,000.00 2,500,000.00 1.43 2.91 74.00 - - 2.91 74.00 7,400.00
2 Pembuatan Papan Proyek unit 1.00 350,000.00 350,000.00 0.20 1.99 2.00 - - 1.99 2.00 200.00
3 Pembongkaran dan Perbaikan Tiang Bendera Ls 1.00 2,000,000.00 2,000,000.00 1.14 - - - - - - -

II PEKERJAAN GALIAN DAN TANAH


1 Galian Tanah Beton 1 : 2 : 3 m3 4.05 36,400.00 147,420.00 0.08 0.08 4.05 - - 0.08 4.05 100.00
2 Urugan Pasir Dibawah Beton m3 0.75 173,600.00 130,200.00 0.07 0.07 0.75 - - 0.07 0.75 100.00
3 Urugan Pasir Dibawah Paving Block m3 60.00 173,600.00 10,416,000.00 5.96 - - 5.96 60.00 5.96 60.00 100.00

III PEKERJAAN BETON DAN PAVING BLOCK


1 Cor Beton 15 / 40
- Cor beton camp. 1 : 2 : 3 m3 6.00 1,355,970.00 8,135,820.00 4.65 - - 4.65 6.00 4.65 6.00 100.00
- Bekisting m2 76.70 192,054.40 14,730,572.48 8.42 - - 8.42 76.70 8.42 76.70 100.00
2 Pas. Paving Block m2 600.00 227,500.00 136,500,000.00 78.04 - - 78.04 600.00 78.04 600.00 100.00

TOTAL 174,910,012.48 100.00 5.05 97.07 102.12

Disetujui Oleh Diperiksa Oleh Dibuat Oleh


Pejabat Pelaksana Teknis Kegiatan KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
CV. INTENCIVINDO CV. NUR KHALIFAH AGUNG

SONNY JANUAR IKHSAN TRI EVI HERAWATI HERMAN, ST FERAWATI MARADDING, ST


Nip : 19801026 201001 1 004 Site Engineer Pelaksana Lapangan
LAPORAN MINGGUAN

Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. BUANA UMAR
Pekerjaan : Pembangunan RKB SDN 010 Waru Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Waru Kab. Penajam Paser Utara Minggu : I ( Pertama )
Tahun : 2014 Periode : 17 Agust. 2014 - 24 Agust. 2014

S/d Minggu Lalu Minggu ini S/d Minggu ini


NO URAIAN SAT VOL HARGA SAT JUMLAH BOBOT KET
( Rp. ) ( Rp. ) (%) BOBOT VOLUME BOBOT VOLUME BOBOT VOLUME (%)
(%) (%) (%)
I PEKERJAAN PENDAHULUAN
1 #REF! m' #REF! #REF! #REF! #REF! - - #REF! #REF! #REF! #REF! #REF!
2 #REF! ls #REF! #REF! #REF! #REF! - - #REF! #REF! #REF! #REF! #REF!
3 #REF! ls #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
II PEKERJAAN GALIAN DAN TANAH
1 #REF! m3 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
2 #REF! m3 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
3 #REF! m3 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
4 #REF! m3 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
5 #REF! m3 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
III PEKERJAAN PONDASI
1 #REF! m3 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
2 #REF! m3 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
IV PEKERJAAN PASANGAN
1 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
2 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
3 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
4 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
5 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
6 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
7 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
V PEKERJAAN BETON
1 #REF! m3 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
2 Slof Beton 15 / 20
- Cor beton camp. 1 : 2 : 3 m3 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
- Pembesian kg #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
- Bekisting m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
3 Kolom Struktur 15 / 25
- Cor beton camp. 1 : 2 : 3 m3 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
- Pembesian kg #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
- Bekisting m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
4 Kolom Praktis 12/12
- Cor beton camp. 1 : 2 : 3 m3 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
- Pembesian kg #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
- Bekisting m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
5 Kolom Teras 15/15
- Cor beton camp. 1 : 2 : 3 m3 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
- Pembesian kg #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
- Bekisting m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
6 Ring Balk 15/20
- Cor beton camp. 1 : 2 : 3 m3 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
- Pembesian kg #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
- Bekisting m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
VI PEKERJAAN KERAMIK
1 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
2 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
VII PEKERJAAN PINTU DAN JENDELA
1 #REF! m3 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
2 #REF! bh #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
3 #REF! m' #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
4 #REF! bh #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
5 #REF! bh #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
VIII PEKERJAAN KERANGKA ATAP DAN ATAP
1 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
2 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
3 #REF! m' #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
4 #REF! m' #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
5 #REF! bh #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
IX PEKERJAAN PLAFOND
1 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
2 #REF! m' #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
X PEKERJAAN PENGGANTUNG,
PENUTUP DAN PENGUNCI
1 #REF! bh #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
2 #REF! bh #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
3 #REF! bh #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
4 #REF! bh #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
5 #REF! bh #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
6 #REF! bh #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
XI PEKERJAAN ELEKTRIKAL
1 #REF! titik #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
2 #REF! bh #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
3 #REF! bh #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
4 #REF! bh #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
5 #REF! bh #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
XII PEKERJAAN PENGECATAN
1 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
2 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!
3 #REF! m2 #REF! #REF! #REF! #REF! - - #REF! - #REF! - #REF!

TOTAL #REF! #REF! - #REF! #REF!

Disetujui Oleh Diperiksa Oleh Dibuat Oleh


Pengawas Lapangan Disdikpora KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
CV. INTENCIVINDO CV. BUANA UMAR

DWI RAHARJO, ST ZAENAL ABIDIN, ST AINURROPIQ SIDHARTA, ST


Nip : 19770906 200904 1 001 Site Engineer Pelaksana Lapangan
LAPORAN MINGGUAN

Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. BUANA UMAR
Pekerjaan : Pembangunan RKB SDN 010 Waru Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Waru Kab. Penajam Paser Utara Minggu : II ( Dua )
Tahun : 2014 Periode : 25 Agust. 2014 - 31 Agust. 2014

S/d Minggu Lalu Minggu ini S/d Minggu ini


NO URAIAN SAT VOL HARGA SAT JUMLAH BOBOT KET
( Rp. ) ( Rp. ) (%) BOBOT VOLUME BOBOT VOLUME BOBOT VOLUME (%)
(%) (%) (%)
I PEKERJAAN PENDAHULUAN
1 Memasang Bouwplank m' 73.50 77,830.00 5,720,505.00 1.57 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
2 Pembersihan Lokasi ls 1.00 1,650,000.00 1,650,000.00 0.45 #REF! #REF! - - #REF! #REF! #REF!
3 Pembuatan Papan Proyek ls 1.00 250,000.00 250,000.00 0.07 #REF! - 0.07 1.00 #REF! 1.00 100.00
II PEKERJAAN GALIAN DAN TANAH
1 Galian tanah pondasi m3 52.92 34,400.00 1,820,448.00 0.50 #REF! - 0.50 52.92 #REF! 52.92 100.00
2 Urugan tanah kembali m3 17.64 16,490.00 290,883.60 0.08 #REF! - - - #REF! - -
3 Urugan tanah bawah lantai m3 95.50 172,500.00 16,473,750.00 4.51 #REF! - - - #REF! - -
4 Ur.pasir bwh pondasi m3 5.88 168,600.00 991,368.00 0.27 #REF! - 0.27 5.88 #REF! 5.88 100.00
5 Ur.pasir bwh lantai m3 19.10 168,600.00 3,220,260.00 0.88 #REF! - - - #REF! - -
III PEKERJAAN PONDASI
1 Pas. bt kosong Aanstamping t = 20 cm m3 11.76 427,290.00 5,024,930.40 1.38 #REF! - 1.38 11.76 #REF! 11.76 100.00
2 Pondasi batu gunung 1 : 4 m3 32.34 765,950.00 24,770,823.00 6.79 #REF! - - - #REF! - -
IV PEKERJAAN PASANGAN
1 Pas.Dinding Batu Bata 1:2 1/2 Bata m2 15.90 135,580.00 2,155,722.00 0.59 #REF! - - - #REF! - -
2 Pas.Dinding Batu Bata 1:4 1/2 Bata m2 159.79 124,135.00 19,835,531.65 5.43 #REF! - - - #REF! - -
3 Pas.Rollag Bata Camp. 1: 4 tebal 1/2 Bata m2 22.80 124,135.00 2,830,278.00 0.78 #REF! - - - #REF! - -
4 Plesteran Dinding 1 : 2 tebal 15 mm m2 31.80 46,347.00 1,473,834.60 0.40 #REF! - - - #REF! - -
5 Plesteran Dinding 1 : 4 tebal 15 mm m2 288.98 41,320.00 11,940,653.60 3.27 #REF! - - - #REF! - -
6 Plesteran Tali Air m2 45.60 46,347.00 2,113,423.20 0.58 #REF! - - - #REF! - -
7 Plesteran Pas Rollag Bata Camp 1 : 2 tebal 15 mm m2 7.20 41,320.00 297,504.00 0.08 #REF! - - - #REF! - -
V PEKERJAAN BETON
1 Cor Lantai t : 5 cm 1 : 3 : 5 m3 13.37 1,088,400.00 14,551,908.00 3.99 #REF! - - - #REF! - -
2 Slof Beton 15 / 20
- Cor beton camp. 1 : 2 : 3 m3 2.21 1,398,250.00 3,090,132.50 0.85 #REF! - - - #REF! - -
- Pembesian kg 393.65 13,963.00 5,496,534.95 1.51 #REF! - - - #REF! - -
- Bekisting m2 14.70 189,030.00 2,778,741.00 0.76 #REF! - - - #REF! - -
3 Kolom Struktur 15 / 25
- Cor beton camp. 1 : 2 : 3 m3 1.89 1,398,250.00 2,642,692.50 0.72 #REF! - - - #REF! - -
- Pembesian kg 394.99 13,963.00 5,515,245.37 1.51 #REF! - - - #REF! - -
- Bekisting m2 18.50 331,040.00 6,124,240.00 1.68 #REF! - - - #REF! - -
4 Kolom Praktis 12/12
- Cor beton camp. 1 : 2 : 3 m3 5.18 1,398,250.00 7,242,935.00 1.98 #REF! - - - #REF! - -
- Pembesian kg 55.91 13,963.00 780,671.33 0.21 #REF! - - - #REF! - -
- Bekisting m2 2.59 331,040.00 857,393.60 0.23 #REF! - - - #REF! - -
5 Kolom Teras 15/15
- Cor beton camp. 1 : 2 : 3 m3 0.57 1,398,250.00 797,002.50 0.22 #REF! - - - #REF! - -
- Pembesian kg 152.79 13,963.00 2,133,406.77 0.58 #REF! - - - #REF! - -
- Bekisting m2 7.56 341,900.00 2,584,764.00 0.71 #REF! - - - #REF! - -
6 Ring Balk 15/20
- Cor beton camp. 1 : 2 : 3 m3 2.21 1,398,250.00 3,090,132.50 0.85 #REF! - - - #REF! - -
- Pembesian kg 380.17 13,963.00 5,308,313.71 1.45 #REF! - - - #REF! - -
- Bekisting m2 22.05 341,900.00 7,538,895.00 2.07 #REF! - - - #REF! - -
VI PEKERJAAN KERAMIK
1 Pas.Keramik Type Halus 40 x 40 m2 112.00 189,788.00 21,256,256.00 5.82 #REF! - - - #REF! - -
2 Pas.Keramik Type Kasar 40 x 40 m2 24.00 189,788.00 4,554,912.00 1.25 #REF! - - - #REF! - -
VII PEKERJAAN PINTU DAN JENDELA
1 Kusen kayu Ulin (5/12) m3 0.10 8,533,000.00 853,300.00 0.23 #REF! - - - #REF! - -
2 Daun Pintu Double Panel Kayu Ulin bh 4.00 862,000.00 3,448,000.00 0.94 #REF! - - - #REF! - -
3 Pasangan Kusen Almunium m' 80.00 237,735.00 19,018,800.00 5.21 #REF! - - - #REF! - -
4 Pasangan Jendela Rangka Almunium Panel Kaca bh 30.00 237,735.00 7,132,050.00 1.95 #REF! - - - #REF! - -
5 Rooster bh 33.00 65,300.00 2,154,900.00 0.59 #REF! - - - #REF! - -
VIII PEKERJAAN KERANGKA ATAP DAN ATAP - -
1 Kuda-Kuda + Gording + Kasau + Reng Baja Ringan m2 109.46 195,000.00 21,344,700.00 5.85 #REF! - - - #REF! - -
2 Pasangan Atap Genteng Metal m2 109.46 141,386.00 15,476,111.56 4.24 #REF! - - - #REF! - -
3 Bubungan Atap Genteng Metal m' 26.64 101,110.00 2,693,570.40 0.74 #REF! - - - #REF! - -
4 Listplank Kayu Ulin ( 1x2/20 ) m' 57.00 73,568.00 4,193,376.00 1.15 #REF! - - - #REF! - -
5 Angin - angin Atap bh 2.00 850,000.00 1,700,000.00 0.47 #REF! - - - #REF! - -
IX PEKERJAAN PLAFOND
1 Pas. Plafond Dan Rangka Besi Hollow m2 189.00 304,875.00 57,621,375.00 15.79 #REF! - - - #REF! - -
2 List Plafond Kayu Klas 2 m' 106.00 21,000.00 2,226,000.00 0.61 #REF! - - - #REF! - -
X PEKERJAAN PENGGANTUNG,
PENUTUP DAN PENGUNCI
1 Pasangan Kunci bh 4.00 260,830.00 1,043,320.00 0.29 #REF! - - - #REF! - -
2 Pas.Engsel Pintu (3 bh/Pintu ) bh 12.00 50,207.50 602,490.00 0.17 #REF! - - - #REF! - -
3 Pas.Engsel Jendela Friction Stay 16' bh 30.00 33,805.00 1,014,150.00 0.28 #REF! - - - #REF! - -
4 Grendel Jendela bh 30.00 82,959.00 2,488,770.00 0.68 #REF! - - - #REF! - -
5 Grendel Tanam Pintu Double bh 4.00 82,959.00 331,836.00 0.09 #REF! - - - #REF! - -
6 Handle Jendela bh 30.00 9,259.00 277,770.00 0.08 #REF! - - - #REF! - -
XI PEKERJAAN ELEKTRIKAL
1 Instalasi Listrik titik 16.00 40,000.00 640,000.00 0.18 #REF! - - - #REF! - -
2 Pas.Lampu Pijar 18 Watt bh 12.00 42,650.00 511,800.00 0.14 #REF! - - - #REF! - -
3 Pas.Saklar Ganda bh 4.00 32,700.00 130,800.00 0.04 #REF! - - - #REF! - -
4 Pas.Stop kontak bh 2.00 27,000.00 54,000.00 0.01 #REF! - - - #REF! - -
5 Sekering Kas 3 Group + Instalasi bh 1.00 132,120.00 132,120.00 0.04 #REF! - - - #REF! - -
XII PEKERJAAN PENGECATAN
1 Cat dinding dalam dan Luar m2 376.36 37,900.00 14,264,044.00 3.91 #REF! - - - #REF! - -
2 Cat plafond m2 189.00 37,900.00 7,163,100.00 1.96 #REF! - - - #REF! - -
3 Pengecatan Kusen, Daun Pintu Dengan Cat kilap m2 28.70 43,704.50 1,254,319.15 0.34 #REF! - - - #REF! - -

TOTAL 364,974,793.89 100.00 #REF! #REF! #REF!

Disetujui Oleh Diperiksa Oleh Dibuat Oleh


Pengawas Lapangan Disdikpora KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
CV. INTENCIVINDO CV. BUANA UMAR

DWI RAHARJO, ST ZAENAL ABIDIN, ST AINURROPIQ SIDHARTA, ST


Nip : 19770906 200904 1 001 Site Engineer Pelaksana Lapangan
LEMBAR PENGESAHAN DED & RAB
KEGIATAN PISEW TA.2018

NO KABUPATEN KECAMATAN PEKERJAAN NOMOR HARI TANGGAL

1 Muara Badak Peningkatan Jalan Akses Pariwisata (Rigid Beton) HK.0203/PKP/370 Senin 16 Juli 2018

2 Sebulu Peningkatan Jalan Produksi Perkebunan (Perkerasan Batu Laterite) HK.0203/PKP/370.1 Senin 16 Juli 2018
KUTAI KARTANEGARA
3 Loa Kulu Peningkatan Jalan Produksi Pertanian (Telford) HK.0203/PKP/393 Jumat 20 Juli 2018

4 Kota Bangun Pembangunan Rumah Produksi Pakan Ikan (Konst. Kayu) HK.0203/PKP/394 Jumat 20 Juli 2018

5 Pasir Belengkong Pembangunan Jalan Produksi Perkebunan (Galian Tanah Setempat) HK.0203/PKP/376.1 Rabu 18 Juli 2018

6 Tanah Grogot Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/378.1 Rabu 18 Juli 2018

7 Tanjung Harapan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/377.1 Rabu 18 Juli 2018
PASER
8 Kuaro Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/380.1 Rabu 18 Juli 2018

9 Long Ikis Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/381.1 Rabu 18 Juli 2018

10 Long Kali Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/379.1 Rabu 18 Juli 2018

11 Sambaliung Peningkatan Jalan Produksi Perkebunan (Urugan Sirtu) HK.0203/PKP/399 Senin 23 Juli 2018

12 Talisayan Pembangunan Gedung Pengering Jagung (Permanen) HK.0203/PKP/400 Senin 23 Juli 2018
BERAU
13 Biduk-Biduk Pembangunan Dermaga Wisata Kuliner dan Pelabuhan Pendaratan Ikan (Kayu) HK.0203/PKP/401 Senin 23 Juli 2018

14 Pulau Derawan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/402 Senin 23 Juli 2018

15 Rantau Pulung Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/411 Kamis 26 Juli 2018
KUTAI TIMUR
16 Sangkulirang Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/412 Kamis 26 Juli 2018
LEMBAR PENGESAHAN DED & RAB
KEGIATAN PISEW TA.2018

NO KABUPATEN KECAMATAN PEKERJAAN NOMOR HARI TANGGAL

1 Kuaro Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/833 Kamis 15 November 2018
PASER
2 Long Ikis Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/374 Selasa 17 Juli 2018
PEMERIKSAAN HASIL PEKERJAAN
KEGIATAN PISEW TA.2018

NO KABUPATEN KECAMATAN PEKERJAAN NOMOR HARI TANGGAL

1 Muara Badak Peningkatan Jalan Akses Pariwisata (Rigid Beton) HK.0203/PKP/867 Senin 26 November 2018

2 Loa Kulu Peningkatan Jalan Produksi Pertanian (Telford) HK.0203/PKP/868 Senin 26 November 2018
KUTAI KARTANEGARA
3 Sebulu Peningkatan Jalan Produksi Perkebunan (Perkerasan Batu Laterite) HK.0203/PKP/872 Selasa 27 November 2018

4 Kota Bangun Pembangunan Rumah Produksi Pakan Ikan (Konst. Kayu) HK.0203/PKP/876 Rabu 28 November 2018

5 Tanah Grogot Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/934 Kamis 13 Desember 2018

6 Kuaro Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/935 Kamis 13 Desember 2018

7 Pasir Belengkong Pembangunan Jalan Produksi Perkebunan (Galian Tanah Setempat) HK.0203/PKP/942 Jumat 14 Desember 2018
PASER
8 Tanjung Harapan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/943 Jumat 14 Desember 2018

9 Long Ikis Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/944 Sabtu 15 Desember 2018

10 Long Kali Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/945 Minggu 16 Desember 2018

11 Pulau Derawan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/891 Selasa 04 Desember 2018

12 Sambaliung Peningkatan Jalan Produksi Perkebunan (Urugan Sirtu) HK.0203/PKP/897 Rabu 05 Desember 2018
BERAU
13 Talisayan Pembangunan Gedung Pengering Jagung (Permanen) HK.0203/PKP/898 Rabu 05 Desember 2018

14 Biduk-Biduk Pembangunan Dermaga Wisata Kuliner dan Pelabuhan Pendaratan Ikan (Kayu) HK.0203/PKP/902 Kamis 06 Desember 2018

15 Rantau Pulung Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/889 Senin 03 Desember 2018
KUTAI TIMUR
16 Sangkulirang Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/899 Rabu 05 Desember 2018
SERAH TERIMA KEGIATAN BKAD - PPK
KEGIATAN PISEW TA.2018

NO KABUPATEN KECAMATAN PEKERJAAN NOMOR HARI TANGGAL

1 Sebulu Peningkatan Jalan Produksi Perkebunan (Perkerasan Batu Laterite) HK.0203/PKP/976 Kamis 27 Desember 2018

2 Loa Kulu Peningkatan Jalan Produksi Pertanian (Telford) HK.0203/PKP/977 Kamis 27 Desember 2018

3 Kota Bangun Pembangunan Rumah Produksi Pakan Ikan (Konst. Kayu) HK.0203/PKP/978 Kamis 27 Desember 2018

4 Pasir Belengkong Pembangunan Jalan Produksi Perkebunan (Galian Tanah Setempat) HK.0203/PKP/979 Kamis 27 Desember 2018

5 Tanah Grogot Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/980 Kamis 27 Desember 2018

6 Tanjung Harapan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/981 Kamis 27 Desember 2018
PASER
7 Kuaro Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/982 Kamis 27 Desember 2018

8 Long Ikis Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/983 Kamis 27 Desember 2018

9 Long Kali Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/984 Kamis 27 Desember 2018

10 Sambaliung Peningkatan Jalan Produksi Perkebunan (Urugan Sirtu) HK.0203/PKP/966 Jumat 21 Desember 2018

11 Talisayan Pembangunan Gedung Pengering Jagung (Permanen) HK.0203/PKP/967 Jumat 21 Desember 2018
BERAU
12 Biduk-Biduk Pembangunan Dermaga Wisata Kuliner dan Pelabuhan Pendaratan Ikan (Kayu) HK.0203/PKP/968 Jumat 21 Desember 2018

13 Pulau Derawan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/969 Jumat 21 Desember 2018

14 Rantau Pulung Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/985 Kamis 27 Desember 2018
KUTAI TIMUR
15 Sangkulirang Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/986 Kamis 27 Desember 2018
PENYERAHAN INFRASTRUKTUR OLEH KASATKER - DESA
KEGIATAN PISEW TA.2018

NO KABUPATEN KECAMATAN PEKERJAAN NOMOR HARI TANGGAL

1 Sebulu Peningkatan Jalan Produksi Perkebunan (Perkerasan Batu Laterite) HK.0203/PKP/987 Kamis 27 Desember 2018

2 Loa Kulu Peningkatan Jalan Produksi Pertanian (Telford) HK.0203/PKP/988 Kamis 27 Desember 2018

3 Kota Bangun Pembangunan Rumah Produksi Pakan Ikan (Konst. Kayu) HK.0203/PKP/989 Kamis 27 Desember 2018

4 Pasir Belengkong Pembangunan Jalan Produksi Perkebunan (Galian Tanah Setempat) HK.0203/PKP/990 Kamis 27 Desember 2018

5 Tanah Grogot Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/991 Kamis 27 Desember 2018

6 Tanjung Harapan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/992 Kamis 27 Desember 2018
PASER
7 Kuaro Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/993 Kamis 27 Desember 2018

8 Long Ikis Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/994 Kamis 27 Desember 2018

9 Long Kali Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/995 Kamis 27 Desember 2018

10 Sambaliung Peningkatan Jalan Produksi Perkebunan (Urugan Sirtu) HK.0203/PKP/966.1 Jumat 21 Desember 2018

11 Talisayan Pembangunan Gedung Pengering Jagung (Permanen) HK.0203/PKP/967.1 Jumat 21 Desember 2018
BERAU
12 Biduk-Biduk Pembangunan Dermaga Wisata Kuliner dan Pelabuhan Pendaratan Ikan (Kayu) HK.0203/PKP/968.1 Jumat 21 Desember 2018

13 Pulau Derawan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/969.1 Jumat 21 Desember 2018

14 Rantau Pulung Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/996 Kamis 27 Desember 2018
KUTAI TIMUR
15 Sangkulirang Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/997 Kamis 27 Desember 2018
LAPORAN BULANAN

Proyek : Peningkatan Sarana Dan Prasarana Pendidikan


Pekerjaan : Pembangunan RKB SDN 010 Waru Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Waru Kab. Penajam Paser Utara Bulan : I ( Pertama )
Tahun : 2014 Periode : Agust 2014 - 31 Agust. 2014

S/d Bulan Lalu Bulan ini S/d Bulan ini


NO URAIAN SAT VOL HARGA SAT JUMLAH BOBOT KET
( Rp. ) ( Rp. ) (%) BOBOT VOLUME BOBOT VOLUME BOBOT VOLUME (%)
(%) (%) (%)
I PEKERJAAN PENDAHULUAN
1 Memasang Bouwplank m' 73.50 77,830.00 5,720,505.00 1.57 - - #REF! #REF! #REF! #REF! #REF!
2 Pembersihan Lokasi ls 1.00 1,650,000.00 1,650,000.00 0.45 - - #REF! #REF! #REF! #REF! #REF!
3 Pembuatan Papan Proyek ls 1.00 250,000.00 250,000.00 0.07 - - #REF! 1.00 #REF! 1.00 100.00
II PEKERJAAN GALIAN DAN TANAH
1 Galian tanah pondasi m3 52.92 34,400.00 1,820,448.00 0.50 - - #REF! 52.92 #REF! 52.92 100.00
2 Urugan tanah kembali m3 17.64 16,490.00 290,883.60 0.08 - - #REF! - #REF! - -
3 Urugan tanah bawah lantai m3 95.50 172,500.00 16,473,750.00 4.51 - - #REF! - #REF! - -
4 Ur.pasir bwh pondasi m3 5.88 168,600.00 991,368.00 0.27 - - #REF! 5.88 #REF! 5.88 100.00
5 Ur.pasir bwh lantai m3 19.10 168,600.00 3,220,260.00 0.88 - - #REF! - #REF! - -
III PEKERJAAN PONDASI
1 Pas. bt kosong Aanstamping t = 20 cm m3 11.76 427,290.00 5,024,930.40 1.38 - - #REF! 11.76 #REF! 11.76 100.00
2 Pondasi batu gunung 1 : 4 m3 32.34 765,950.00 24,770,823.00 6.79 - - #REF! - #REF! - -
IV PEKERJAAN PASANGAN
1 Pas.Dinding Batu Bata 1:2 1/2 Bata m2 15.90 135,580.00 2,155,722.00 0.59 - - #REF! - #REF! - -
2 Pas.Dinding Batu Bata 1:4 1/2 Bata m2 159.79 124,135.00 19,835,531.65 5.43 - - #REF! - #REF! - -
3 Pas.Rollag Bata Camp. 1: 4 tebal 1/2 Bata m2 22.80 124,135.00 2,830,278.00 0.78 - - #REF! - #REF! - -
4 Plesteran Dinding 1 : 2 tebal 15 mm m2 31.80 46,347.00 1,473,834.60 0.40 - - #REF! - #REF! - -
5 Plesteran Dinding 1 : 4 tebal 15 mm m2 288.98 41,320.00 11,940,653.60 3.27 - - #REF! - #REF! - -
6 Plesteran Tali Air m2 45.60 46,347.00 2,113,423.20 0.58 - - #REF! - #REF! - -
7 Plesteran Pas Rollag Bata Camp 1 : 2 tebal 15 mm m2 7.20 41,320.00 297,504.00 0.08 - - #REF! - #REF! - -
V PEKERJAAN BETON - -
1 Cor Lantai t : 5 cm 1 : 3 : 5 m3 13.37 1,088,400.00 14,551,908.00 3.99 - - #REF! - #REF! - -
2 Slof Beton 15 / 20
- Cor beton camp. 1 : 2 : 3 m3 2.21 1,398,250.00 3,090,132.50 0.85 - - #REF! - #REF! - -
- Pembesian kg 393.65 13,963.00 5,496,534.95 1.51 - - #REF! - #REF! - -
- Bekisting m2 14.70 189,030.00 2,778,741.00 0.76 - - #REF! - #REF! - -
3 Kolom Struktur 15 / 25
- Cor beton camp. 1 : 2 : 3 m3 1.89 1,398,250.00 2,642,692.50 0.72 - - #REF! - #REF! - -
- Pembesian kg 394.99 13,963.00 5,515,245.37 1.51 - - #REF! - #REF! - -
S/d Bulan Lalu Bulan ini S/d Bulan ini
HARGA SAT JUMLAH BOBOT KET
NO URAIAN SAT VOL ( Rp. ) ( Rp. ) (%) BOBOT BOBOT BOBOT (%)
(%) VOLUME (%) VOLUME (%) VOLUME

- Bekisting m2 18.50 331,040.00 6,124,240.00 1.68 - - #REF! - #REF! - -


4 Kolom Praktis 12/12
- Cor beton camp. 1 : 2 : 3 m3 5.18 1,398,250.00 7,242,935.00 1.98 - - #REF! - #REF! - -
- Pembesian kg 55.91 13,963.00 780,671.33 0.21 - - #REF! - #REF! - -
- Bekisting m2 2.59 331,040.00 857,393.60 0.23 - - #REF! - #REF! - -
5 Kolom Teras 15/15
- Cor beton camp. 1 : 2 : 3 m3 0.57 1,398,250.00 797,002.50 0.22 - - #REF! - #REF! - -
- Pembesian kg 152.79 13,963.00 2,133,406.77 0.58 - - #REF! - #REF! - -
- Bekisting m2 7.56 341,900.00 2,584,764.00 0.71 - - #REF! - #REF! - -
6 Ring Balk 15/20
- Cor beton camp. 1 : 2 : 3 m3 2.21 1,398,250.00 3,090,132.50 0.85 - - #REF! - #REF! - -
- Pembesian kg 380.17 13,963.00 5,308,313.71 1.45 - - #REF! - #REF! - -
- Bekisting m2 22.05 341,900.00 7,538,895.00 2.07 - - #REF! - #REF! - -
VI PEKERJAAN KERAMIK
1 Pas.Keramik Type Halus 40 x 40 m2 112.00 189,788.00 21,256,256.00 5.82 - - #REF! - #REF! - -
2 Pas.Keramik Type Kasar 40 x 40 m2 24.00 189,788.00 4,554,912.00 1.25 - - #REF! - #REF! - -
VII PEKERJAAN PINTU DAN JENDELA
1 Kusen kayu Ulin (5/12) m3 0.10 8,533,000.00 853,300.00 0.23 - - #REF! - #REF! - -
2 Daun Pintu Double Panel Kayu Ulin bh 4.00 862,000.00 3,448,000.00 0.94 - - #REF! - #REF! - -
3 Pasangan Kusen Almunium m' 80.00 237,735.00 19,018,800.00 5.21 - - #REF! - #REF! - -
4 Pasangan Jendela Rangka Almunium Panel Kaca bh 30.00 237,735.00 7,132,050.00 1.95 - - #REF! - #REF! - -
5 Rooster bh 33.00 65,300.00 2,154,900.00 0.59 - - #REF! - #REF! - -
VIII PEKERJAAN KERANGKA ATAP DAN ATAP
1 Kuda-Kuda + Gording + Kasau + Reng Baja Ringan m2 109.46 195,000.00 21,344,700.00 5.85 - - #REF! - #REF! - -
2 Pasangan Atap Genteng Metal m2 109.46 141,386.00 15,476,111.56 4.24 - - #REF! - #REF! - -
3 Bubungan Atap Genteng Metal m' 26.64 101,110.00 2,693,570.40 0.74 - - #REF! - #REF! - -
4 Listplank Kayu Ulin ( 1x2/20 ) m' 57.00 73,568.00 4,193,376.00 1.15 - - #REF! - #REF! - -
5 Angin - angin Atap bh 2.00 850,000.00 1,700,000.00 0.47 - - #REF! - #REF! - -
IX PEKERJAAN PLAFOND - -
1 Pas. Plafond Dan Rangka Besi Hollow m2 189.00 304,875.00 57,621,375.00 15.79 - - #REF! - #REF! - -
2 List Plafond Kayu Klas 2 m' 106.00 21,000.00 2,226,000.00 0.61 - - #REF! - #REF! - -
X PEKERJAAN PENGGANTUNG,
PENUTUP DAN PENGUNCI
1 Pasangan Kunci bh 4.00 260,830.00 1,043,320.00 0.29 - - #REF! - #REF! - -
2 Pas.Engsel Pintu (3 bh/Pintu ) bh 12.00 50,207.50 602,490.00 0.17 - - #REF! - #REF! - -
3 Pas.Engsel Jendela Friction Stay 16' bh 30.00 33,805.00 1,014,150.00 0.28 - - #REF! - #REF! - -
4 Grendel Jendela bh 30.00 82,959.00 2,488,770.00 0.68 - - #REF! - #REF! - -
5 Grendel Tanam Pintu Double bh 4.00 82,959.00 331,836.00 0.09 - - #REF! - #REF! - -
6 Handle Jendela bh 30.00 9,259.00 277,770.00 0.08 - - #REF! - #REF! - -
XI PEKERJAAN ELEKTRIKAL
S/d Bulan Lalu Bulan ini S/d Bulan ini
HARGA SAT JUMLAH BOBOT KET
NO URAIAN SAT VOL ( Rp. ) ( Rp. ) (%) BOBOT BOBOT BOBOT (%)
(%) VOLUME (%) VOLUME (%) VOLUME

1 Instalasi Listrik titik 16.00 40,000.00 640,000.00 0.18 - - #REF! - #REF! - -


2 Pas.Lampu Pijar 18 Watt bh 12.00 42,650.00 511,800.00 0.14 - - #REF! - #REF! - -
3 Pas.Saklar Ganda bh 4.00 32,700.00 130,800.00 0.04 - - #REF! - #REF! - -
4 Pas.Stop kontak bh 2.00 27,000.00 54,000.00 0.01 - - #REF! - #REF! - -
5 Sekering Kas 3 Group + Instalasi bh 1.00 132,120.00 132,120.00 0.04 - - #REF! - #REF! - -
XII PEKERJAAN PENGECATAN
1 Cat dinding dalam dan Luar m2 376.36 37,900.00 14,264,044.00 3.91 - - #REF! - #REF! - -
2 Cat plafond m2 189.00 37,900.00 7,163,100.00 1.96 - - #REF! - #REF! - -
3 Pengecatan Kusen, Daun Pintu Dengan Cat kilap m2 28.70 43,704.50 1,254,319.15 0.34 - - #REF! - #REF! - -

TOTAL 364,974,793.89 100.00 - #REF! #REF!

Disetujui Oleh Diperiksa Oleh Dibuat Oleh


Pejabat Pelaksana Teknik Lapangan KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
CV. INTENCIVINDO CV. BUANA UMAR

ISWAN PADDA, ST #REF! #REF!


Nip : 1975 1215 2009 0110 12 Site Engineer Pelaksana Lapangan
TIME SCHEDULE BULAN JUNI

PROGRESS
Minggu ke - (%)
NO. URAIAN PEKERJAAN HARGA ( Rp.) Bobot ( % )
I II III IV V VI VII VIII

I. PEKERJAAN PENDAHULUAN 6,050,000.00 3.43 3.43 100

Chart Title
II. PEKERJAAN GALIAN, PASIR DAN TANAH 10,693,620.00 6.05 2.02 2.02 2.02 50

III. PEKERJAAN BETON DAN PAVING BLOCK 159,880,149.48 90.52 18.10 18.10 18.10 18.10 18.10 0

JUMLAH 176,623,769.48 100.00


REALISASI RENCANA 3.43 18.10 2.02 2.02 20.12 18.10 18.10 18.10
KOMULATIF REALISASI RENCANA 3.43 21.53 23.55 25.57 45.69 63.79 81.90 100.00
REALISASI 1.29 1.65 4.36 - - - - -
KOMULATIF REALISASI 1.29 2.94 7.30 - -

Disetujui Oleh Diperiksa Oleh Dibuat Oleh


Pejabat Pelaksana Teknis Kegiatan KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
CV. INTENCIVINDO CV. NUR KHALIFAH AGUNG

SONNY JANUAR IKHSAN TRI EVI HERAWATI HERMAN, ST FERAWATI MARADDING, ST


Nip : 19801026 201001 1 004 Site Engineer Pelaksana Lapangan
TIME SCHEDULE BULAN JULI

PROGRESS
Minggu ke - (%)
NO. URAIAN PEKERJAAN HARGA ( Rp.) Bobot ( % )
I II III IV V VI VII VIII
Chart Title
I. PEKERJAAN PENDAHULUAN 6,050,000.00 3.43 3.43 100

II. PEKERJAAN GALIAN, PASIR DAN TANAH 10,693,620.00 6.05 2.02 2.02 2.02 50

III. PEKERJAAN BETON DAN PAVING BLOCK 159,880,149.48 90.52 18.10 18.10 18.10 18.10 18.10 0

JUMLAH 176,623,769.48 100.00


REALISASI RENCANA 3.43 18.10 2.02 2.02 20.12 18.10 18.10 18.10
KOMULATIF REALISASI RENCANA 3.43 21.53 23.55 25.57 45.69 63.79 81.90 100.00
REALISASI 1.29 1.65 4.36 70.60 22.11 - - -
KOMULATIF REALISASI 1.29 2.94 7.30 77.90 100.00

Disetujui Oleh Diperiksa Oleh Dibuat Oleh


Pejabat Pelaksana Teknis Kegiatan KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
CV. INTENCIVINDO CV. NUR KHALIFAH AGUNG

SONNY JANUAR IKHSAN TRI EVI HERAWATI HERMAN, ST FERAWATI MARADDING, ST


Nip : 19801026 201001 1 004 Site Engineer Pelaksana Lapangan
TIME SCHEDULE

PROGRESS
Minggu ke - (%)
NO. URAIAN PEKERJAAN HARGA ( Rp.) Bobot ( % )
I II III IV V VI VII VIII

I. PEKERJAAN PENDAHULUAN 6,050,000.00 3.43 3.43 100

II. PEKERJAAN GALIAN, PASIR DAN TANAH 10,693,620.00 6.05 2.02 2.02 2.02 50

III. PEKERJAAN BETON DAN PAVING BLOCK 159,880,149.48 90.52 18.10 18.10 18.10 18.10 18.10 0

JUMLAH 176,623,769.48 100.00


REALISASI RENCANA 3.43 18.10 2.02 2.02 20.12 18.10 18.10 18.10
KOMULATIF REALISASI RENCANA 3.43 21.53 23.55 25.57 45.69 63.79 81.90 100.00
REALISASI
KOMULATIF REALISASI

Penajam, 10 Juni 2014


CV. NUR KHALIFAH AGUNG

WA ODE RAHMIN, ST
Direktris