PEKERJAAN KAYU
HARGA
KODE
INDEK SAT URAIAN HARGA SATUAN (Rp) BAHAN UPAH JUMLAH HARGA (Rp)
ANALISA
( Rp ) ( Rp )
A. PEKERJAAN PONDASI KAYU
A.1.BOW SEBUAH TONGKAT ULIN UK.10/10 CM TINGGI 2,00 M
DICINCIN, DILANCIP DAN DITUMBUK
0.0200 M3 Balok ulin @ 4,500,000.00 90,000.00
0.5100 OH tukang kayu @ 98,000.00 49,980.00
0.8750 OH pekerja @ 79,000.00 69,125.00
0.0510 OH kepala tukang @ 110,000.00 5,610.00
0.0440 OH mandor @ 110,000.00 4,840.00
JUMLAH 90,000.00 129,555.00 219,555.00
A.2 SEBUAH TONGKAT ULIN UK.12/12 CM TINGGI 8,00 M
2 SAMBUNGAN DGN PIPA GALVANIS
0.0800 M3 Balok ulin @ 4,500,000.00 360,000.00
0.5100 OH tukang kayu @ 98,000.00 49,980.00
0.8750 OH pekerja @ 79,000.00 69,125.00
0.0510 OH kepala tukang @ 110,000.00 5,610.00
0.0440 OH mandor @ 110,000.00 4,840.00
JUMLAH 360,000.00 129,555.00 489,555.00
A.3 SEBUAH TONGKAT ULIN UK.10/10 CM TINGGI 4,00 M'
0.0400 M3 Balok ulin @ 4,500,000.00 180,000.00
0.5100 OH tukang kayu @ 98,000.00 49,980.00
0.8750 OH pekerja @ 79,000.00 69,125.00
0.0510 OH kepala tukang @ 110,000.00 5,610.00
0.0440 OH mandor @ 110,000.00 4,840.00
JUMLAH 180,000.00 129,555.00 309,555.00
A. 4 1 M3 MENGERJAKAN PAPAN SIRING KAYU ULIN
1.1000 M3 papan siring kayu ulin @ 5,300,000.00 5,830,000.00
3.0000 kg paku ulin @ #REF! #REF!
15.0000 OH tukang kayu @ 98,000.00 1,470,000.00
4.0000 OH pekerja @ 79,000.00 316,000.00
1.5000 OH kepala tukang @ 110,000.00 165,000.00
0.2000 OH mandor @ 110,000.00 22,000.00
JUMLAH #REF! 1,973,000.00 #REF!
A. 5 1 M3 RANGKA BAWAH KAYU ULIN ( tiang + kalang, sunduk )
1.1000 M3 balok ky ulin @ 4,500,000.00 4,950,000.00
15.0000 OH tukang kayu @ 98,000.00 1,470,000.00
5.0000 OH pekerja @ 79,000.00 395,000.00
1.5000 OH kepala tukang @ 110,000.00 165,000.00
0.2500 OH mandor @ 110,000.00 27,500.00
JUMLAH 4,950,000.00 2,057,500.00 7,007,500.00
B. PEKERJAAN LANTAI KAYU
B. 1 1 M3 MENGERJAKAN SLOOF DAN GELAGAR KY ULIN
1.1000 M3 balok ky ulin @ 4,500,000.00 4,950,000.00
10.0000 Kg paku ulin @ #REF! #REF!
15.0000 OH tukang kayu @ 98,000.00 1,470,000.00
5.0000 OH pekerja @ 79,000.00 395,000.00
1.5000 OH kepala tukang @ 110,000.00 165,000.00
0.2500 OH mandor @ 110,000.00 27,500.00
JUMLAH #REF! 2,057,500.00 #REF!
B. 2 1 M2 LANTAI PAPAN KAYU ULIN DIKETAM
0.0254 M3 papan kayu ulin @ 5,300,000.00 134,620.00
0.2500 Kg paku ulin @ #REF! #REF!
0.8000 OH tukang kayu @ 98,000.00 78,400.00
0.2800 OH pekerja @ 79,000.00 22,120.00
0.0800 OH kepala tukang @ 110,000.00 8,800.00
0.0140 OH mandor @ 110,000.00 1,540.00
JUMLAH #REF! 110,860.00 #REF!
B. 3 1 M2 LANTAI PAPAN KAYU MERANTI DIKETAM
0.0254 M3 papan kayu meranti klas 1 @ 2,920,320.00 74,176.13
0.2500 Kg paku biasa @ 20,500.00 5,125.00
0.8000 OH tukang kayu @ 98,000.00 78,400.00
0.2800 OH pekerja @ 79,000.00 22,120.00
0.0800 OH kepala tukang @ 110,000.00 8,800.00
0.0140 OH mandor @ 110,000.00 1,540.00
JUMLAH 79,301.13 110,860.00 190,161.13
B. PEKERJAAN DINDING KAYU
B. 4 1 M3 MENGERJAKAN RANGKA RUMAH KAYU ULIN (termasuk kusen)
1.1000 M3 balok ky ulin @ 4,500,000.00 4,950,000.00
5.0000 Kg paku ulin @ #REF! #REF!
20.0000 OH tukang kayu @ 98,000.00 1,960,000.00
10.0000 OH pekerja @ 79,000.00 790,000.00
2.0000 OH kepala tukang @ 110,000.00 220,000.00
0.5000 OH mandor @ 110,000.00 55,000.00
JUMLAH #REF! 3,025,000.00 #REF!
B. 5 1 M3 MENGERJAKAN RANGKA RUMAH KAYU MERANTI (termasuk kusen)
1.1000 M3 balok ky meranti @ 2,650,000.00 2,915,000.00
5.0000 Kg paku biasa @ 20,500.00 102,500.00
20.0000 OH tukang kayu @ 98,000.00 1,960,000.00
10.0000 OH pekerja @ 79,000.00 790,000.00
2.0000 OH kepala tukang @ 110,000.00 220,000.00
0.5000 OH mandor @ 110,000.00 55,000.00
JUMLAH 3,017,500.00 3,025,000.00 6,042,500.00
B Harga Bahan
1
2 Ampelas Lbr 3,000.00 - 3,000.00
5 Atap Metal Berkualitas ( 2 ssn, 8 daun ) Lbr 87,000.00 - 87,000.00
25 Balok Klas I Ulin M3 4,500,000.00 - 4,500,000.00
26 Balok Kayu Meranti M3 2,650,000.00 - 2,650,000.00
29 Batu Bata Bh 1,000.00 - 1,000.00
30 Batu apung Kg 950.00 - 950.00
31 Batu Gunung M3 220,000.00 - 220,000
35 Besi Beton Polos Kg 10,500.00 - 10,500.00
47 Cat Air / tembok Kg 75,000.00 - 75,000.00
48 Cat Air / tembok ex.setara ICI,dulux,mowilex Kg 110,000.00 110,000.00
50 Cat Dasar / plamir Kg 21,000.00 - 21,000.00
51 Cat Kilap / Kayu Kg 37,800.00 - 37,800.00
52 Cat Menie kayu Kg 21,600.00 - 21,600.00
57 Daun Jendela Uk. Besar (Fabrikasi) Kc 5 mm Bh 337,500.00 - 337,500.00
58 Daun Jendela Uk. Kecil (Fabrikasi) Kc 5 mm Bh 298,600.00 - 298,600.00
61 Dempul Halus ( INFRA ) Kg 45,000.00 - 45,000.00
62 Dempul kayu Kg 27,500.00 - 27,500.00
63 Dempul Politur Kg 32,500.00 - 32,500.00
64 Engsel Jendela Lokal 3 " Bh 28,500.00 - 28,500.00
65 Engsel Pintu Lokal 5 " Bh 38,750.00 - 38,750.00
NO URAIAN SAT SUN BIAYA ANGKUT HARGA DASAR KETERANGAN
SATUAN
1 2 3 4 5 6 7
71 Grendel Jendela Bh 27,500.00 - 27,500.00
72 Grendel Pintu Bh 23,400.00 - 23,400.00
73 Grendel tanam Pintu Bh 65,000.00 - 65,000.00
75 Hak Angin Bh 18,750.00 - 18,750.00
76 Handle Jendela putih Bh 23,500.00 - 23,500.00
77 Handle Pintu Bh 27,500.00 - 27,500.00
78 Jalusi Atap Bh 365,000.00 - 365,000.00
85 Kaca polos 5 mm M2 35,000.00 - 35,000.00
88 Kawat Bendrat / Beton Kg 22,000.00 - 22,000.00
94 Kayu Klas 2 M3 2,900,000.00 - 2,900,000.00
95 Kayu galam dia 10 - 12 cm Btg 25,000.00 - 25,000.00
98 Keramik 20 x 20 cm M2 65,000.00 - 65,000.00
99 Keramik 40 x 40 cm Halus M2 72,300.00 - 72,300.00
100 Keramik 40 x 40 cm Kasar M2 72,300.00 - 72,300.00
104 Batu Split ( ukuran 2-3 cm/1-2 )Ex. Krayan M3 425,000.00 - 425,000.00
106 Koral (ex.Lokal) M3 425,000.00 - 425,000.00
109 Kuas 3 " Bh 23,500.00 - 23,500.00
110 Kunci Pintu 2 Slag berkualitas Bh 145,000.00 - 145,000.00
111 Kunci Pintu Double Ex Cisa Bh 165,000.00 - 165,000.00
116 Kuda-kuda baja ringan modern trus m2 187,000.00 - 187,000.00
123 Lampu Pijar 18 Wat Bh 47,500.00 - 47,500.00
138 List Plafond Plywood M' 33,500.00 - 33,500.00
149 Minyak cat Ltr 9,500.00 - 9,500.00
150 Minyak bekisting Ltr 10,800.00 - 10,800.00
159 Nok Model U ukuran 110 x 5 x 6 cm M' 33,750.00 - 33,750.00
168 Paku Genteng metal Kg 27,500.00 - 27,500.00
169 Paku Kayu / biasa Kg 20,500.00 - 20,500.00
174 Paku Sekrup Kg 3,000.00 - 3,000.00
175 Papan Kayu Bangkirai M3 6,500,000.00 - 6,500,000.00
176 Papan Kayu Ulin M3 5,300,000.00 - 5,300,000.00
177 Papan Kayu kelas 2 M3 2,920,320.00 - 2,920,320.00
178 Papan Kayu Meranti M3 2,920,320.00 - 2,920,320.00
179 Papan Nama Proyek Bh 550,000.00 - 550,000.00
183 Pasir Beton Ex. Lokal samuntai M3 365,000.00 - 365,000.00
184 Pasir Beton (sepaku) M3 477,000.00 - 477,000.00
185 Pasir Pasang sungai ex. Kandilo M3 365,000.00 - 365,000.00
186 Pasir pasang putih M3 87,000.00 - 87,000.00
188 Pasir Urug M3 87,000.00 - 87,000.00
190 Pasangan Jendela rangka alumunium + kaca 5 mm Bh 345,000.00 - 345,000.00
191 Pasangan Kusen Almunium Jendela m' 120,000.00 - 120,000.00
196 Pintu Panel kayu Ulin Ukuran Besar L 80 cm Bh 620,000.00 - 620,000.00
212 Plamir Kg 16,650.00 - 16,650.00
213 Plitur Kg 17,500.00 - 17,500.00
219 Plywood 9 mm Lbr 185,000.00 - 185,000.00
224 Rangka besi hollow M' 23,500.00 - 23,500.00
227 Roster beton 20 x 20 cm Bh 19,000.00 - 19,000.00
231 Saklar Ganda Bh 27,500.00 - 27,500.00
232 Saklar Tunggal Bh 19,500.00 - 19,500.00
233 Sekering Kas 3 Group + Instalasi Unit 245,000.00 - 245,000.00
234 Semen Abu - Abu / PC ( 50 kg/Zak ) Zak 66,000.00 - 66,000.00
235 Semen Warna Kg 9,000.00 - 9,000.00
236 Semen putih Kg 1,600.00 - 1,600.00
246 Stop Kontak Bh 22,500.00 - 22,500.00
249 Tanah Urug M3 87,000 - 87,000.00
266 Titik Mata Lampu Ttk 160,000.00 - 160,000.00
272 Pasir beton Exs. Palu m3 490,000.00 490,000.00
275 Kalsiboard 4 mm Lbr 85,000.00 85,000.00
276 Washtafel Unit - -
Catatan :
1. Harga diatas adalah harga disumber material ( disungai, dilokasi penggalian) khusus utk bahan lokal
2. Untuk bahan-bahan non lokal harga tersebut adalah harga toko / harga yang berlaku dipasaran
3. Harga sudah terrmasuk keuntungan kontraktor dan ongkos angkut
4 Harga belum termasuk PPn
Daftar Analisa Satuan Pekerjaan ( SNI )
A Pekerjaan Persiapan
3 1 m' Pengukuran dan pemasangan bouwplank
0.0120 m3 Kayu meranti 2,650,000.00 31,800.00
0.0200 kg Paku kayu 20,500.00 410.00
0.0070 m3 Papan kayu meranti 3/20 2,920,320.00 20,442.24
0.1000 Tukang kayu 98,000.00 9,800.00
0.1000 Pekerja 79,000.00 7,900.00
0.0100 Kepala Tukang 110,000.00 1,100.00
0.0050 Mandor 110,000.00 550.00
Jumlah 19,350.00 52,652.24 72,002.24
B Pekerjaan Tanah
1 1 m3 Galian tanah biasa sedalam 1 meter
0.4000 Pekerja 79,000.00 31,600.00
0.0400 Mandor 110,000.00 4,400.00
Jumlah 36,000.00 36,000.00
9 1 m3 Pemadatan tanah
0.5000 Pekerja 79,000.00 39,500.00
0.0500 Mandor 110,000.00 5,500.00
Jumlah 45,000.00 - 45,000.00
10 1 m3 Urugan tanah
1.2000 m3 Tanah 87,000.00 104,400.00
0.2500 Pekerja 79,000.00 19,750.00
0.0250 Mandor 110,000.00 2,750.00
1.0000 ls Biaya pemadatan 45,000.00 45,000.00
Jumlah 67,500.00 104,400.00 171,900.00
11 1 m3 Mengurug tanah kembali
0.1920 Pekerja 79,000.00 15,168.00
0.0190 Mandor 110,000.00 2,090.00
Jumlah 17,258.00 17,258.00
12 1 m3 Urugan pasir
1.2000 m3 Pasir urug 87,000.00 104,400.00
0.3000 Pekerja 79,000.00 23,700.00
0.0100 Mandor 110,000.00 1,100.00
1.0000 ls Biaya pemadatan 45,000.00 45,000.00
Jumlah 69,800.00 104,400.00 174,200.00
C Pekerjaan Pondasi
1 1 m3 Pasang pondasi batu kosong/Aanstamping
1.2000 m3 Batu gunung 220,000.00 264,000.00
0.3000 m3 Pasir urug 87,000.00 26,100.00
0.7800 Pekerja 79,000.00 61,620.00
0.3900 Tukang Batu 98,000.00 38,220.00
0.0390 Kepala Tukang 110,000.00 4,290.00
0.0390 Mandor 110,000.00 4,290.00
Jumlah 108,420.00 290,100.00 398,520.00
3 1 m3 Pasang pondasi batu gunung 1 : 4
1.1000 m3 Batu gunung 220,000.00 242,000.00
3.2600 zak Semen PC 50 kg 66,000.00 215,160.00
0.5200 m3 Pasir pasang 87,000.00 45,240.00
1.5000 Pekerja 79,000.00 118,500.00
0.6000 Tukang batu 98,000.00 58,800.00
0.0600 Kepala Tukang 110,000.00 6,600.00
0.0750 Mandor 110,000.00 8,250.00
Jumlah 192,150.00 502,400.00 694,550.00
Harga Satuan Upah Bahan Jumlah Harga
No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)
D Pekerjaan Struktur
1 1 m2 pasang bekisting untuk pondasi
0.0400 m3 Papan kayu kelas 2 2,920,320.00 116,812.80
0.3000 kg Paku kayu 20,500.00 6,150.00
0.1000 lt minyak bekisting 10,800.00 1,080.00
0.3000 Pekerja 79,000.00 23,700.00
0.2600 Tukang kayu 98,000.00 25,480.00
0.0260 Kepala Tukang 110,000.00 2,860.00
0.0050 Mandor 110,000.00 550.00
Jumlah 52,590.00 124,042.80 176,632.80
2 1 m2 pasang bekisting untuk sloof
0.0450 m3 Papan kayu kelas 2 2,920,320.00 131,414.40
0.3000 kg Paku kayu 20,500.00 6,150.00
0.1000 lt minyak bekisting 10,800.00 1,080.00
0.3000 Pekerja 79,000.00 23,700.00
0.2600 Tukang kayu 98,000.00 25,480.00
0.0260 Kepala Tukang 110,000.00 2,860.00
0.0050 Mandor 110,000.00 550.00
Jumlah 52,590.00 138,644.40 191,234.40
3 1 m2 pasang bekisting untuk kolom
0.0400 m3 Papan kayu kelas 2 2,920,320.00 116,812.80
0.4000 kg Paku kayu 20,500.00 8,200.00
0.2000 lt minyak bekisting 10,800.00 2,160.00
0.0150 m3 Balok kayu meranti 2,650,000.00 39,750.00
0.3500 lbr plywood tebal 9 mm 185,000.00 64,750.00
2.0000 btg kayu galam 25,000.00 50,000.00
0.3000 Pekerja 79,000.00 23,700.00
0.3300 Tukang kayu 98,000.00 32,340.00
0.0330 Kepala Tukang 110,000.00 3,630.00
0.0060 Mandor 110,000.00 660.00
Jumlah 60,330.00 281,672.80 342,002.80
E Pekerjaan Dinding
1 1 m2 Pasangan batu bata tebal 1/2 bata 1 : 2
60.0000 bh Batu bata 1,000.00 60,000.00
0.3790 zak Semen PC 50 kg 66,000.00 25,014.00
0.0380 m3 Pasir pasang putih 87,000.00 3,306.00
0.3200 Pekerja 79,000.00 25,280.00
0.1000 Tukang batu 98,000.00 9,800.00
0.0100 Kepala Tukang 110,000.00 1,100.00
0.0150 Mandor 110,000.00 1,650.00
Jumlah 37,830.00 88,320.00 126,150.00
2 1 m2 Pasangan batu bata tebal 1 bata 1 : 2
### bh Batu bata 1,000.00 120,000.00
0.8700 zak Semen PC 50 kg 66,000.00 57,420.00
0.0800 m3 Pasir pasang putih 87,000.00 6,960.00
0.6500 Pekerja 79,000.00 51,350.00
0.2000 Tukang batu 98,000.00 19,600.00
0.0200 Kepala Tukang 110,000.00 2,200.00
0.0300 Mandor 110,000.00 3,300.00
Jumlah 76,450.00 184,380.00 260,830.00
3 1 m2 Pasangan batu bata tebal 1/2 bata 1 : 4
60.0000 bh Batu bata 1,000.00 60,000.00
0.2300 zak Semen PC 50 kg 66,000.00 15,180.00
0.0430 m3 Pasir pasang putih 87,000.00 3,741.00
0.3200 Pekerja 79,000.00 25,280.00
0.1000 Tukang batu 98,000.00 9,800.00
0.0100 Kepala Tukang 110,000.00 1,100.00
0.0150 Mandor 110,000.00 1,650.00
Jumlah 37,830.00 78,921.00 116,751.00
4 1 m2 Pasang dinding roster 20 x 20
26.0000 bh Roster 19,000.00 494,000.00
0.2560 zak Semen PC 50 kg 66,000.00 16,896.00
0.0350 m3 Pasir pasang putih 87,000.00 3,045.00
0.3000 Pekerja 79,000.00 23,700.00
0.1000 Tukang batu 98,000.00 9,800.00
0.0150 Kepala Tukang 110,000.00 1,650.00
0.0150 Mandor 110,000.00 1,650.00
Jumlah 36,800.00 513,941.00 550,741.00
Harga Satuan Upah Bahan Jumlah Harga
No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)
F Pekerjaan Plesteran
2 1 m2 Plesteran tebal 15 mm dengan 1 : 2
0.1704 zak Semen PC 50 kg 66,000.00 11,246.40
0.0170 m3 Pasir pasang putih 87,000.00 1,479.00
0.2000 Pekerja 79,000.00 15,800.00
0.1500 Tukang batu 98,000.00 14,700.00
0.0150 Kepala Tukang 110,000.00 1,650.00
0.0100 Mandor 110,000.00 1,100.00
Jumlah 33,250.00 12,725.40 45,975.40
L Pekerjaan Cat-catan
1 1 m2 Mendempul
0.0800 kg Dempul 27,500.00 2,200.00
0.0200 liter Minyak cat 9,500.00 190.00
0.0100 Kg Batu apung 950.00 9.50
0.0400 Pekerja 79,000.00 3,160.00
0.0400 Tukang cat 98,000.00 3,920.00
0.0040 Kepala Tukang 110,000.00 440.00
0.0025 Mandor 110,000.00 275.00
Jumlah 7,795.00 2,399.50 10,194.50
2 1 m2 Mengecat tembok yang baru
( 1 lapis plamir, 1 lapis cat dasar, dan
2 lapis cat penutup )
0.1000 kg Plamir 16,650.00 1,665.00
0.1000 kg Cat dasar 21,000.00 2,100.00
0.2600 kg Cat tembok ( Cat Penutup ) 2x 110,000.00 28,600.00
0.0200 Pekerja 79,000.00 1,580.00
0.0630 Tukang cat 98,000.00 6,174.00
0.0063 Kepala Tukang 110,000.00 693.00
0.0025 Mandor 110,000.00 275.00
Jumlah 8,722.00 32,365.00 41,087.00
Harga Satuan Upah Bahan Jumlah Harga
No. Nama Pekerjaan
(Rp) (Rp) (Rp) (Rp)
3 1 m2 Pekerjaan cat kilap ( 1 lapis plamir ;
1 lapis cat dasar ; 2 lapis cat penutup )
0.2000 kg Cat meni 21,600.00 4,320.00
0.1500 kg Plamir 16,650.00 2,497.50
0.1700 kg Cat dasar 21,000.00 3,570.00
0.2600 kg Cat penutup 2 kali 110,000.00 28,600.00
0.0700 Pekerja 79,000.00 5,530.00
0.0090 Tukang cat 98,000.00 882.00
0.0060 Kepala Tukang 110,000.00 660.00
0.0025 Mandor 110,000.00 275.00
Jumlah 7,347.00 38,987.50 46,334.50
4 1 m2 Pekerjaan cat kilap ( 1 lapis plamir ;
1 lapis cat dasar ; 3 lapis cat penutup )
0.2000 kg Cat meni 21,600.00 4,320.00
0.1500 kg Plamir 16,650.00 2,497.50
0.1700 kg Cat dasar 21,000.00 3,570.00
0.3500 kg Cat penutup 3 kali 110,000.00 38,500.00
0.0700 Pekerja 79,000.00 5,530.00
0.1050 Tukang cat 98,000.00 10,290.00
0.0040 Kepala Tukang 110,000.00 440.00
0.0025 Mandor 110,000.00 275.00
Jumlah 16,535.00 48,887.50 65,422.50
5 1 m2 Plituran
0.5220 kg Politur 17,500.00 9,135.00
2.0000 lbr Ampelas 3,000.00 6,000.00
0.0600 Tukang cat 98,000.00 5,880.00
0.0160 Kepala Tukang 110,000.00 1,760.00
0.0025 Mandor 110,000.00 275.00
Jumlah 7,915.00 15,135.00 23,050.00
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV.KARYA SEJATI UTAMA
Pekerjaan : Pembangunan RKB SDN 009 Waru Konsultan Pengawas : CV. ARDHIA ASRI
Lokasi : Kec. Babulu Kab. Penajam Paser Utara Minggu : I ( Pertama )
Tahun : 2014 Periode : 15 Agustus 2014 - 17 Agustus 2014
LAPORAN MINGGUAN
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV.KARYA SEJATI UTAMA
Pekerjaan : Pembangunan RKB SDN 009 Waru Konsultan Pengawas : CV. ARDHIA ASRI
Lokasi : Kec. Babulu Kab. Penajam Paser Utara Minggu : I ( Pertama )
Tahun : 2014 Periode : 15 Agustus 2014 - 17 Agustus 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : II ( Kedua )
Tahun : 2014 Periode : 23 Juni 2014 - 30 Juni 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : III ( Ketiga )
Tahun : 2014 Periode : 1 Juli 2014 - 6 Juli 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : IV ( Keempat )
Tahun : 2014 Periode : 07 Juli 2014 - 13 Juli 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : V ( Lima )
Tahun : 2014 Periode : 14 Juli 2014 - 16 Juli 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Bulan : I ( Pertama )
Tahun : 2014 Periode : 18 Juni 2014 - 30 Juni 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. NUR KHALIFAH AGUNG
Pekerjaan : Pemasangan Paving Block SMAN 5 PPU Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Penajam Kab. Penajam Paser Utara Minggu : II ( Kedua )
Tahun : 2014 Periode : 01 Juli 2014 - 16 Juli 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. BUANA UMAR
Pekerjaan : Pembangunan RKB SDN 010 Waru Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Waru Kab. Penajam Paser Utara Minggu : I ( Pertama )
Tahun : 2014 Periode : 17 Agust. 2014 - 24 Agust. 2014
Proyek : Peningkatan Sarana Dan Prasarana Pendidikan Pelaksana : CV. BUANA UMAR
Pekerjaan : Pembangunan RKB SDN 010 Waru Konsultan Pengawas : CV. INTENCIVINDO
Lokasi : Kec. Waru Kab. Penajam Paser Utara Minggu : II ( Dua )
Tahun : 2014 Periode : 25 Agust. 2014 - 31 Agust. 2014
1 Muara Badak Peningkatan Jalan Akses Pariwisata (Rigid Beton) HK.0203/PKP/370 Senin 16 Juli 2018
2 Sebulu Peningkatan Jalan Produksi Perkebunan (Perkerasan Batu Laterite) HK.0203/PKP/370.1 Senin 16 Juli 2018
KUTAI KARTANEGARA
3 Loa Kulu Peningkatan Jalan Produksi Pertanian (Telford) HK.0203/PKP/393 Jumat 20 Juli 2018
4 Kota Bangun Pembangunan Rumah Produksi Pakan Ikan (Konst. Kayu) HK.0203/PKP/394 Jumat 20 Juli 2018
5 Pasir Belengkong Pembangunan Jalan Produksi Perkebunan (Galian Tanah Setempat) HK.0203/PKP/376.1 Rabu 18 Juli 2018
6 Tanah Grogot Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/378.1 Rabu 18 Juli 2018
7 Tanjung Harapan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/377.1 Rabu 18 Juli 2018
PASER
8 Kuaro Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/380.1 Rabu 18 Juli 2018
9 Long Ikis Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/381.1 Rabu 18 Juli 2018
10 Long Kali Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/379.1 Rabu 18 Juli 2018
11 Sambaliung Peningkatan Jalan Produksi Perkebunan (Urugan Sirtu) HK.0203/PKP/399 Senin 23 Juli 2018
12 Talisayan Pembangunan Gedung Pengering Jagung (Permanen) HK.0203/PKP/400 Senin 23 Juli 2018
BERAU
13 Biduk-Biduk Pembangunan Dermaga Wisata Kuliner dan Pelabuhan Pendaratan Ikan (Kayu) HK.0203/PKP/401 Senin 23 Juli 2018
14 Pulau Derawan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/402 Senin 23 Juli 2018
15 Rantau Pulung Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/411 Kamis 26 Juli 2018
KUTAI TIMUR
16 Sangkulirang Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/412 Kamis 26 Juli 2018
LEMBAR PENGESAHAN DED & RAB
KEGIATAN PISEW TA.2018
1 Kuaro Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/833 Kamis 15 November 2018
PASER
2 Long Ikis Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/374 Selasa 17 Juli 2018
PEMERIKSAAN HASIL PEKERJAAN
KEGIATAN PISEW TA.2018
1 Muara Badak Peningkatan Jalan Akses Pariwisata (Rigid Beton) HK.0203/PKP/867 Senin 26 November 2018
2 Loa Kulu Peningkatan Jalan Produksi Pertanian (Telford) HK.0203/PKP/868 Senin 26 November 2018
KUTAI KARTANEGARA
3 Sebulu Peningkatan Jalan Produksi Perkebunan (Perkerasan Batu Laterite) HK.0203/PKP/872 Selasa 27 November 2018
4 Kota Bangun Pembangunan Rumah Produksi Pakan Ikan (Konst. Kayu) HK.0203/PKP/876 Rabu 28 November 2018
5 Tanah Grogot Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/934 Kamis 13 Desember 2018
6 Kuaro Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/935 Kamis 13 Desember 2018
7 Pasir Belengkong Pembangunan Jalan Produksi Perkebunan (Galian Tanah Setempat) HK.0203/PKP/942 Jumat 14 Desember 2018
PASER
8 Tanjung Harapan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/943 Jumat 14 Desember 2018
9 Long Ikis Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/944 Sabtu 15 Desember 2018
10 Long Kali Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/945 Minggu 16 Desember 2018
11 Pulau Derawan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/891 Selasa 04 Desember 2018
12 Sambaliung Peningkatan Jalan Produksi Perkebunan (Urugan Sirtu) HK.0203/PKP/897 Rabu 05 Desember 2018
BERAU
13 Talisayan Pembangunan Gedung Pengering Jagung (Permanen) HK.0203/PKP/898 Rabu 05 Desember 2018
14 Biduk-Biduk Pembangunan Dermaga Wisata Kuliner dan Pelabuhan Pendaratan Ikan (Kayu) HK.0203/PKP/902 Kamis 06 Desember 2018
15 Rantau Pulung Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/889 Senin 03 Desember 2018
KUTAI TIMUR
16 Sangkulirang Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/899 Rabu 05 Desember 2018
SERAH TERIMA KEGIATAN BKAD - PPK
KEGIATAN PISEW TA.2018
1 Sebulu Peningkatan Jalan Produksi Perkebunan (Perkerasan Batu Laterite) HK.0203/PKP/976 Kamis 27 Desember 2018
2 Loa Kulu Peningkatan Jalan Produksi Pertanian (Telford) HK.0203/PKP/977 Kamis 27 Desember 2018
3 Kota Bangun Pembangunan Rumah Produksi Pakan Ikan (Konst. Kayu) HK.0203/PKP/978 Kamis 27 Desember 2018
4 Pasir Belengkong Pembangunan Jalan Produksi Perkebunan (Galian Tanah Setempat) HK.0203/PKP/979 Kamis 27 Desember 2018
5 Tanah Grogot Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/980 Kamis 27 Desember 2018
6 Tanjung Harapan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/981 Kamis 27 Desember 2018
PASER
7 Kuaro Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/982 Kamis 27 Desember 2018
8 Long Ikis Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/983 Kamis 27 Desember 2018
9 Long Kali Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/984 Kamis 27 Desember 2018
10 Sambaliung Peningkatan Jalan Produksi Perkebunan (Urugan Sirtu) HK.0203/PKP/966 Jumat 21 Desember 2018
11 Talisayan Pembangunan Gedung Pengering Jagung (Permanen) HK.0203/PKP/967 Jumat 21 Desember 2018
BERAU
12 Biduk-Biduk Pembangunan Dermaga Wisata Kuliner dan Pelabuhan Pendaratan Ikan (Kayu) HK.0203/PKP/968 Jumat 21 Desember 2018
13 Pulau Derawan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/969 Jumat 21 Desember 2018
14 Rantau Pulung Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/985 Kamis 27 Desember 2018
KUTAI TIMUR
15 Sangkulirang Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/986 Kamis 27 Desember 2018
PENYERAHAN INFRASTRUKTUR OLEH KASATKER - DESA
KEGIATAN PISEW TA.2018
1 Sebulu Peningkatan Jalan Produksi Perkebunan (Perkerasan Batu Laterite) HK.0203/PKP/987 Kamis 27 Desember 2018
2 Loa Kulu Peningkatan Jalan Produksi Pertanian (Telford) HK.0203/PKP/988 Kamis 27 Desember 2018
3 Kota Bangun Pembangunan Rumah Produksi Pakan Ikan (Konst. Kayu) HK.0203/PKP/989 Kamis 27 Desember 2018
4 Pasir Belengkong Pembangunan Jalan Produksi Perkebunan (Galian Tanah Setempat) HK.0203/PKP/990 Kamis 27 Desember 2018
5 Tanah Grogot Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/991 Kamis 27 Desember 2018
6 Tanjung Harapan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/992 Kamis 27 Desember 2018
PASER
7 Kuaro Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/993 Kamis 27 Desember 2018
8 Long Ikis Peningkatan Jalan Produksi Perkebunan (Telford) HK.0203/PKP/994 Kamis 27 Desember 2018
9 Long Kali Peningkatan Jalan Produksi Pertanian (Rigid Beton) HK.0203/PKP/995 Kamis 27 Desember 2018
10 Sambaliung Peningkatan Jalan Produksi Perkebunan (Urugan Sirtu) HK.0203/PKP/966.1 Jumat 21 Desember 2018
11 Talisayan Pembangunan Gedung Pengering Jagung (Permanen) HK.0203/PKP/967.1 Jumat 21 Desember 2018
BERAU
12 Biduk-Biduk Pembangunan Dermaga Wisata Kuliner dan Pelabuhan Pendaratan Ikan (Kayu) HK.0203/PKP/968.1 Jumat 21 Desember 2018
13 Pulau Derawan Pembangunan Jembatan Titian dan Dermaga (Kayu) HK.0203/PKP/969.1 Jumat 21 Desember 2018
14 Rantau Pulung Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/996 Kamis 27 Desember 2018
KUTAI TIMUR
15 Sangkulirang Peningkatan Jalan Produksi Perkebunan (Timbunan Pilihan) HK.0203/PKP/997 Kamis 27 Desember 2018
LAPORAN BULANAN
PROGRESS
Minggu ke - (%)
NO. URAIAN PEKERJAAN HARGA ( Rp.) Bobot ( % )
I II III IV V VI VII VIII
Chart Title
II. PEKERJAAN GALIAN, PASIR DAN TANAH 10,693,620.00 6.05 2.02 2.02 2.02 50
III. PEKERJAAN BETON DAN PAVING BLOCK 159,880,149.48 90.52 18.10 18.10 18.10 18.10 18.10 0
PROGRESS
Minggu ke - (%)
NO. URAIAN PEKERJAAN HARGA ( Rp.) Bobot ( % )
I II III IV V VI VII VIII
Chart Title
I. PEKERJAAN PENDAHULUAN 6,050,000.00 3.43 3.43 100
II. PEKERJAAN GALIAN, PASIR DAN TANAH 10,693,620.00 6.05 2.02 2.02 2.02 50
III. PEKERJAAN BETON DAN PAVING BLOCK 159,880,149.48 90.52 18.10 18.10 18.10 18.10 18.10 0
PROGRESS
Minggu ke - (%)
NO. URAIAN PEKERJAAN HARGA ( Rp.) Bobot ( % )
I II III IV V VI VII VIII
II. PEKERJAAN GALIAN, PASIR DAN TANAH 10,693,620.00 6.05 2.02 2.02 2.02 50
III. PEKERJAAN BETON DAN PAVING BLOCK 159,880,149.48 90.52 18.10 18.10 18.10 18.10 18.10 0
WA ODE RAHMIN, ST
Direktris