ID Task Task Name Duration Start Finish Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr

Duration Start Finish Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Mode Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
1 Upgrade of PHC-IA Restaurant 324 days Tue 9/4/18 Tue 9/10/19
2 Phase One - Restaurant Stage 34 days Tue 9/4/18 Sun 10/7/18
3 Cordon off stage 3 days Tue 9/4/18 Thu 9/6/18
4 Removal of stage floor to access the floor 2 days Fri 9/7/18 Sat 9/8/18
5 Installation of LED TV frame 7 days Sun 9/9/18 Sat 9/15/18
6 Installation/commissioning of LED TV screen 7 days Sun 9/16/18 Sat 9/22/18
7 Installation of wall/floor cladding around the LED screen 14 days Sun 9/23/18 Sat 10/6/18
8 Demobilisation / Housekeeping 1 day Sun 10/7/18 Sun 10/7/18
9 Phase Two - Servery Section 60 days Thu 4/11/19 Tue 6/25/19
10 Send out Notification for partial shut down of the restaurant 1 day Thu 4/11/19 Thu 4/11/19
11 Relocation of food vendors 5 days Sat 4/13/19 Wed 4/17/19
12 Cordon off servery section 1 wk Mon 4/22/19 Fri 4/26/19
13 Relocation of food vendors 1 wk Sat 4/27/19 Wed 5/1/19
14 Stripping off (Civil & Electrical) 1 wk Thu 5/2/19 Wed 5/8/19
15 Repairs of roof slab 2 wks Thu 5/2/19 Wed 5/15/19
16 Erection of scaffold 1 wk Thu 5/2/19 Wed 5/8/19
17 Electrical piping and wiring wrks 1 wk Thu 5/9/19 Wed 5/15/19
18 Installation of POP ceilings 2 wks Thu 5/16/19 Wed 5/29/19
19 Installation of cladding at the servery section 2 wks Thu 5/30/19 Wed 6/12/19
20 Screeding of walls around the servery section 1 wk Thu 5/30/19 Wed 6/5/19
21 Placement of electrical fittings 5 days Thu 6/6/19 Wed 6/12/19
22 Plumbing works around the servery section 2 wks Wed 5/29/19 Tue 6/11/19
23 Furnishing of servery section 1 wk Wed 6/12/19 Tue 6/18/19
24 Painting of walls 3 days Wed 6/19/19 Fri 6/21/19
25 Demobilisation / Housekeeping 2 days Mon 6/24/19 Tue 6/25/19
26 Phase Three - Civil/Electrical/Mechanical works around the Restaurant 104 days Mon 4/22/19 Tue 9/10/19
27 Notification to shut down the Restaurant 1 wk Mon 7/1/19 Fri 7/5/19
28 Erection of scaffold 10 days Mon 7/8/19 Fri 7/19/19
29 Cleaning of ceiling grids 4 wks Mon 7/22/19 Fri 8/16/19
30 Changeout of electromagnetic fittings 7 days Mon 7/22/19 Tue 7/30/19
31 Removal of window blinds 2 wks Wed 7/31/19 Tue 8/13/19
32 Screeding of walls around the dining hall 3 wks Thu 7/25/19 Wed 8/14/19
33 Plumbing works around the dining section 7 days Wed 8/14/19 Thu 8/22/19
34 Cladding of selected sections of the walls around the dining area 2 wks Fri 8/23/19 Thu 9/5/19
35 Painting of walls 1 wk Thu 8/15/19 Wed 8/21/19
36 Installation of window blinds 2 wks Thu 8/22/19 Wed 9/4/19
37 Placement of furniture 4.5 mons Mon 4/22/19 Wed 8/21/19
38 Placement of Air curtain 4.5 mons Mon 4/22/19 Wed 8/21/19
39 Demobilisation / Housekeeping 3 days Fri 9/6/19 Tue 9/10/19

Task Project Summary Manual Task Start-only Deadline

Project: Restaurant Plan Split Inactive Task Duration-only Finish-only Progress


Date: Tue 4/9/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1