Professional Documents
Culture Documents
Grounding
Practices
1
4 Simple Rules for INU Grounding
2
Incorrect IDU Grounds
3
Correct IDU Grounds
4
Correct Indoor Equipment Grounding
IDU
IDU
5
ODU Grounding
6
Incorrect ODU Grounds
7
Correct ODU Grounds
8
ODU Ground Lead
9
Correct ODU Ground Lead
Service loop
10
Rack & Equipment Grounding
11
Rack Ground
12
High Entryway (1)
• Incorrect
• Grounding at
the bottom of
the rack will
create a path
for surge
current,
Rack Ground possibly
damaging or
destroying the
equipment.
13
High Entryway (2)
• Correct
• Grounding at
Rack Ground the top of the
rack will
minimize the
risk of
damaging
current going
through the
rack.
14
Best Practices
Cable Grounding
• At a minimum, the indoor to outdoor cable is required to be
grounded at the top and bottom of the vertical cable run, as well
as the cable entryway to the equipment room.
• All cable ground wires need to be angled downward as much
as possible.
• Cable runs over 50m in vertical height require additional
cable grounds.
15
Ground Conductors
• Cable grounds at
bottom of cable run
• Note that the ground
wires go straight
downward toward the
tower ground bar
• Never exceed an 8
inch bend radius on
ground conductors
16
Coax Cable Grounding
• If the tower is taller than 150 feet (45.72m), then the grounding
must be at the uppermost point and at intervals of no more than
75 feet (22.86m) until the bottom 150 feet (45.72m) section is
reached.
17
Cable Ground Locations for Lightning Protection
18
Cable Ground Locations
19
Grounding
• Integrated Ground
* Building Steel
* Air Conditioners
* Power
* Water Pipes
* Cable Trays
• Isolated Ground
* Equipment
20
Ground Connections
21
Common Ground Terminations
22
Anti-corrosion Compounds
• Apply to all
outdoor ground
connections to
prevent corrosive
build up.
23
Anti-corrosion Compounds
24
Ground Measurements
• Specifications
• Locations
• Tools
25
Ground Measurement Specifications
26
Ground Measurements
• Ground
conductor
measurement
using an AEMC
clamp-on ground
tester
27
Ground Measurement Locations
• IDU/INU Ground
• ODU Ground
• Switch Ground
• Rack Ground
• Master Ground Bar
• Cable Entryway Plate
• All Cable Grounds
• All Lightning Arrestor Grounds
• Antenna Tower Legs
28
Ground Testers
29
Lightning Protection
30
Lightning – What is it?
Step Leader
Distance
10kV/m to 30kV/m
E - Fields
31
Lightning Protection
32
Rolling Ball Theory
33
Why is it important?
34
ESD Prevention
35
Bend radius
36
Lightning Protection Q & A
Lightning
Protection
Q&A
37
Cable Preparation
Cable
Preparation
38
Cable Preparations
* Crimp / Crimp
• Weatherproofing
39
50 ohm N-Type Connector for IF Cable
40
Cable Terminations
Wire Braid
Center Conductor
Foil
41
Crimp Tools
42
Weatherproofing
• Wrapping Guidelines
• 1. Ensure connectors are firmly hand-tightened, dry, and free from all
grease and dirt. If necessary clean with a rag lightly moistened with an
alcohol-based cleaner.
• 2. Apply the tape tensioned, using at least a 75% overlay. The
tensioning (slight stretching) of the tape is required to allow it to bind to
the host and to amalgamate the layers.
• 3. Where possible, apply the tape 25 mm past the ends of the connector
barrels to ensure the weatherproof bond extends beyond the areas
requiring protection. Regardless, the application of the tape must be
such that there is no doubt as to the effectiveness of the sealing
provided.
• 4. To avoid curl-back, do not stretch the tape too tightly at the end point
and never stretch it until it tears. Always cut the tape instead.
• 5. To provide UV protection, an additional double wrap using vinyl tape
must be applied using a 75% overlap.
43
Cable Preparation Q & A
Cable
Preparation
Q&A
44
Antenna Considerations
• Drain Hole
• Strut Requirement
• Hardware Tightening Values
45
Antenna Drain Holes
When the antenna is installed, and you are sure that the
orientation is correct, be sure to remove the bottom drain hole.
Removing the top drain hole will allow water ingress into the
antenna which will greatly reduce the receive signal level.
46
Strut Requirement
47
Antenna Hardware Torque Values
Galvanized Steel
48
Antenna
Considerations
Q&A
49
Installation CIT
Installation Continuous
Improvement Program
What is it?
50
Continuous Improvement Program
51
Stratex Networks Global Helpdesks
52