You are on page 1of 19

PAPERS Building Value Through Sustainable

Project Management Offices


Mimi Hurt, MI 2 Consulting, Calgary, Alberta, Canada
Janice L. Thomas, Athabasca University, Athabasca, Alberta, Canada

ABSTRACT ■ INTRODUCTION ■
n the 1990s, as organizations began to recognize that their strategies and
Organizations’ attempts to implement and gain
value from investments in project management
have resulted in the rapid growth and, in some
cases, demise of project management offices
(PMOs). The recent research literature on PMOs
provides an ambiguous picture of the value
I initiatives were essentially achieved via projects, their recognition of
project management as a critical competency took shape. As an out-
growth of this recognition, formal development of an organizational
project office (typically referred to as a project management office, or
PMO)—charged with developing and/or maintaining organizational project
management competency—began to take off in the 1990s and continues as
case for PMOs and suggests the tenuous nature a major area of interest for both practitioners and researchers (see, for
of their current position in many organizations. example, Crawford, 2006; Hill, 2004; Hobbs & Aubry, 2007). The Project
In studying project management implementa- Management Institute (PMI) has also taken a major interest in this emerging
tions for the Value of Project Management proj- functional group (see, for example, the release of OPM3 in 2003).
ect, we chose to use three detailed cases and Although PMOs have been around since the mid- to late 1990s, Kerzner
comparisons with the remaining 62 organiza- observed that the vast majority of PMOs have either been recently created or
tions in the value project to study how PMOs are restructured (2003, p. 79). This, coupled with several studies that show
connected to value realization for organizations inconclusive results regarding the value of PMOs to the organization (see, for
investing in project management. Specifically, example, Dai & Wells, 2004; Martin, Pearson, & Furumo, 2007), suggests that
we sought to understand how PMOs deliver sus- the sustainability of PMOs and project management competency is a tenu-
tained value to organizations. Using the theo- ous issue.
ries of Jim Collins (Collins, 2001; Collins & In this article, we set out to explore how and why PMOs create sustain-
Porras, 1994) as an interpretive framework, we able value in some instances and fail to maintain their value contributions in
explore these cases to understand how to cre- others. Drawing on the work of Jim Collins and his research team, as
ate and sustain project management value described in Good to Great (2001) and Built to Last (Collins & Porras, 1994),
through investment in PMOs. as well as previous research into PMOs and project managers, we suggest
ways to help develop a sustainable project management competency and
KEYWORDS: project management; project
PMO. We illustrate these suggestions with observations from three in-depth
management offices; value; sustainability;
case studies and reference to other findings from the PMI–sponsored study,
success; leadership
“Researching the Value of Project Management.”

The Concept of PMOs


While some organizations rely on the functional manager, senior manage-
ment, or professional project managers to fulfill the responsibilities of devel-
oping, maintaining, and managing project management competencies,
others have developed a specialized group to take on some or all of these
activities. A PMO can take many forms, ranging from simply providing
administrative support for projects to providing coaching (e.g., as a center of
excellence, on project management practices, tools, etc.) to acting as a full-
blown execution function whose mandate is to formally manage and deliver
projects for the organization. See Table 1 for a review of previous research on
Project Management Journal, Vol. 40, No. 1, 55–72 PMOs.
© 2009 by the Project Management Institute Many authors have described the basic functions of a PMO (see, for
Published online in Wiley InterScience example, Hill, 2001). However, Hobbs and Aubry’s (2007) empirical research
(www.interscience.wiley.com) provides the most grounded exploration of the functions PMOs perform
DOI: 10.1002/pmj.20095 in organizations today. Working from a comprehensive list of functions

March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj 55


PAPERS
Building Value Through Sustainable Project Management Offices

Authors Focus of Paper Key Findings/Observations


Dai & Wells (2004) • Empirical study on • Majority of PMOs established mid-1990s to 2000
establishment and use of PMO for different motivating factors; top two motivators:
• Likert-type questionnaire improve all elements of project management and
• Two samples of 234 (targeted sample) achieve common project management approach
and 96 (random sample) • Wide range of PMO mission statements, some
• Identified different functions and services business-related (strategic), others project-related
of PMOs (tactical)
• Assessed these against project performance • Proportion of budget devoted to PMO was estimated
for both samples as ⬍ 2% for approx 60% of companies in sample
• Statistical analyses showed:
• Project standards and methods had highest
correlation to project performance
• Use of project historical archives next significant
correlation to project performance for targeted sample
• Reported project performance is higher in
organizations with a PMO, but difference is not
statistically significant; however, these results
were different between the two samples
• Those organizations with a PMO did more in
promoting PMO standards, historical archives,
training, and mentoring than those without a PMO
Hill (2004) Describes continuum of PMO competency • Five stages of increasing competency: project
oversight, process control, process support,
business maturity,center of excellence
• Higher stage has achieved competencies of lower stage
• Stage 3 adequate for most organizations
Desouza & • Outlines nature and characteristics • Roles of PMO fall into three levels: strategic, tactical,
Evaristo (2006) of PMOs operational
• Blends project management and knowledge • PMO archetypes = supporter, information manager,
management concepts knowledge manager, and coaches
• Classifies PMO archetypes with respect • Archetype reflects degree of authority
to administrative vs. knowledge-intensive • CSF:
dimensions • Understand how PMO will fit into corporate culture
• Identifies critical success factors for PMOs and pick appropriate archetype
• Interviews with senior managers and • Understand drivers for creating PMO
directors of PMOs in 32 IT organizations • Match type of project with project manager who has
appropriate skill sets for nature of project
• Have clearly identified roles, responsibilities, and
accountability
• Have a PMO charter, PMO policy, and PMO methodology
methodology
• Create and regularly monitor/report PMO
metrics that measure PMO performance
related to policy objectives
Martin, Pearson, & • Use of formal project management practices • IS project size had significant and inverse influence
Furumo (2007) on information systems (IS) projects on project quality and budget
• Identification of which specific project • Organizations without a PMO were just as likely to
management practices, including PMOs, utilize standard project management practices as
provide most value for IS projects those with a PMO (most likely due to PMI sample
• Survey responses from 129 IS project bias)
managers drawn from PMI
Table 1: Summary of recent research on PMOs.

(Continues on next page)

56 March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj


Authors Focus of Paper Key Findings/Observations
• Having a PMO did not influence project schedule
or project quality
• PMO presence significantly related to meeting
project budget
• Organizations should establish measures of
effectiveness of PMO in order to calculate its
worth
Hobbs & • Three-phase research program to better • Could not identify small number of definitive PMO
Aubry (2007) understand PMOs and their perceived value configurations
• Descriptive survey of 500 PMOs • Most PMOs are young and have a small staff
• Development of classification typology (2007, p. 78)
• In-depth study of four PMOs through • 27 PMO functions grouped into five factors
11 transformations (see Table 2)
• Confirmatory study to validate findings • PMOs are viewed as overhead expenses
(forthcoming) • PMOs are frequently reconfigured every
couple of years
• PMOs need to adapt their functions to the
organizational and strategic context
• Lack of consensus in the project management
community regarding the value for money and
contribution of the PMO to project/program
performance
• “Practitioners and organizations would be well
advised not to implement a PMO under naïve
assumptions of value for money or because
PMOs are popular” (2007, p. 85)
Hobbs, Aubry, & • In-depth qualitative and quantitative • Organizational tensions are primary drivers
Thuillier, (2008) analysis of four PMOs, whose life spans behind implementation and reconfiguration
were 4, 8, 10, and 12 years of PMOs
• Each organization reconfigured its PMO • Organizational politics play an important role
every 3–4 years, resulting in underlying these tensions
11 organizational transformations • The structure of PMOs coevolve with that of the
organization
• Because of the inherent historical instability of
PMOs, it is hard to determine if they are truly a
valuable innovation

developed from the literature and a A PMO’s effectiveness and success, and implement only what is needed by
previous phase of the research project, according to Hill (2004), depends on the specific organization at a specific
their research proceeded through a choosing which functions to imple- time is a major finding of the Value of
multistep process of refinement. The ment, and adapting and adjusting them Project Management research as well
500 respondents covered a variety of to fit the organization’s needs, which is (Thomas & Mullaly, 2007, 2008).
roles, but most were project managers also an observation from Hobbs and Kerzner (2003) stated that project
or within the PMO. Respondents Aubry (2007, p. 84): “[the relative differ- management competency represents
ranked the importance of each PMO ences in importance of various individ- important intellectual property for the
function on scale of 1 to 5, with 1 ⫽ not ual functions] reinforces the need to company, and therefore must be man-
at all important to 5 ⫽ very important. adapt to the organizational and strate- aged wisely. He argued that this respon-
Ultimately, the study identified 27 func- gic context when deciding which func- sibility is most appropriately that of the
tions that PMOs can perform. Factor tions to include within the mandate of a PMO. Kerzner reviewed the roles and
analyses grouped these into five dis- particular PMO.” This need to contextu- benefits of the project office over sever-
tinct groups as reflected in Table 2. alize the practice of project management al decades. Table 3 lists the benefits of a

March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj 57


PAPERS
Building Value Through Sustainable Project Management Offices

1. Monitoring and Controlling 2. Development of Project 3. Multiproject Management


Project Performance Management Competencies and • Coordinate between projects
• Report project status to upper Methodologies • Identify, select, and prioritize new projects
management • Develop and implement a standard • Manage one or more portfolios
• Monitor and control of project methodology • Manage one or more programs
performance • Promote project management within • Allocate resources between projects
• Implement and operate a proj- organization
ect information system • Develop competency of personnel,
• Develop and maintain a project including training
scoreboard • Provide mentoring for project man-
agers
• Provide a set of tools without an
effort to standardize

5. Organization Learning Other Functions (Not in Any Group):


4. Strategic Management • Monitor and control performance of • Execute specialized tasks for project
• Provide advice to upper manage- managers
PMO
ment • Manage customer interfaces
• Manage archives of project docu-
• Participate in strategic planning • Recruit, select, evaluate, and determine
mentation
• Benefits management salaries for project managers
• Conduct postproject reviews
• Network and environmental • Conduct project audits
scanning • Implement and manage database of
lessons learned
• Implement and manage risk data-
base

Table 2: Importance of 27 PMO functions grouped into factors (n ⫽ 500, Hobbs & Aubry [2007, pp. 82–83]).

1990–2000 2001–present
• Accomplishing more work in less time with fewer resources and • Standardization of operations
without any sacrifice in quality • Company rather than silo decision making
• An increase in profitability • Better capacity planning
• Better control of scope changes • Quicker access to higher-quality information
• More efficient and effective operations • Elimination or reduction of company silos
• Better customer relations • More efficient and effective operations
• Better risk identification and problem solving • Less need for restructuring
• An increase in quality • Fewer meetings that rob executives of valuable time
• A reduction in power struggles • More realistic prioritization of work
• Better company decision making • Development of future general managers
• An increase in business and becoming more competitive
Table 3: Benefits of a project management office (Kerzner, 2003).

PMO in the 1990s and 2000s. Clearly, (Thomas & Mullaly, 2007, 2008). A part attempts to implement and gain value
the purpose of the PMO appears to be of the framework underpinning value is from investment in project manage-
shifting over the course of its lifetime. described in Figure 1. ment have resulted in the rapid growth
The literature just reviewed serves and, in some cases, the demise of
The Concept of Value to highlight the ambiguity of the value PMOs. Our question then is how is a
The idea of value has been discussed at case for PMOs and the tenuous nature PMO connected to value realization for
length in the work of the “Researching the of their current position in many organ- organizations investing in project man-
Value of Project Management” project izations. We see that an organization’s agement? Specifically, we sought to

58 March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj


Different Values of Project Management
Level 1—Satisfaction: Do the key stakeholders perceive that the project management initiatives provided value? This is measured
through perceptions/self-report satisfaction levels as well as through the use of objective measures (such as repeat customers)
wherever possible.
Level 2—Aligned Use of Practices: Did the project management implementation result in the desired processes? Do they do what
they say they do? Do project people know what they are supposed to do? This is assessed through a comparison of practices, poli-
cies, and procedures with what actually happens on projects.
Level 3—Process Outcomes: What project process improvements have been reaped from the project management implementation?
How effective is the project management process? This is evidenced by changes over time in things such as numbers of change
requests, budget performance, learning from past projects, and reliability of delivery.
Level 4—Business Outcomes: What business outcomes are related to these process improvements (e.g., improve customer satis-
faction and retention; the organization's ability to attract new customers through reputation effects, word of mouth, etc.; increased
ability to achieve strategic goals)?
Level 5— Return on Investment: For every dollar invested in the project management initiative, what return in terms of cost sav-
ings, revenue, etc., can be attributed to it?
Figure 1: Value framework (adapted from Phillips in Thomas & Mullaly, 2007).

understand how PMOs deliver sus- surveys. Tables 4 and 5 provide an growing. It relies on contract workers,
tained value to organizations. overview of the case organizations and especially within project management,
In order to explore the creation and their project management implemen- to support its rapid growth. Projects are
sustainability of organizational value tations. viewed as a way to get things done with-
through a PMO, we turn to the theories Each case study was examined in in the company, and effective project
of Jim Collins as expressed in his books two different ways. First, each case management is viewed as critical to pur-
Built to Last (Collins & Porras, 1994) organization’s PMO implementation suing its strategic objectives.
and Good to Great (2001). Collins sug- was examined for similarities and dif- After a merger in the late 1990s, the
gests fundamental activities necessary ferences between the key events and culture of the company represents an
to create and sustain value in organiza- players in the three organizations. interesting blend between the results
tions. The concepts in Good to Great lay Stages in the implementation were orientation of one company and the
the groundwork to get the flywheel turn- identified, as well as fundamentally process orientation of the other. In gen-
ing to create exceptional value, while important characteristics of each eral, adherence to process and proce-
the concepts in Built to Last outline implementation. Second, each case dure is a secondary concern as long as
concepts to keep it turning (i.e., to sus- was studied for evidence of meeting or desired results are obtained. It is also
tain value). The concepts from these failing to meet the constructs as Collins viewed as a very collaborative organiza-
two books are summarized in the describes them (see the Appendix). The tion, with many people consulted
Appendix. interplay between examining the cases before doing anything. Consequently,
for key events and then comparing and some (e.g., contract project managers)
Methodology contrasting these with the concepts perceive AlphaGas as very slow-moving.
In-depth detailed case studies were outlined by Collins provides significant The culture thus creates an interesting
conducted in three organizations as insight into these three PMO imple- context for project management, where
part of a larger PMI study to analyze the mentations. “cowboy” project managers who don’t
value contribution of project manage- necessarily follow all processes appear
ment (Thomas & Mullaly, 2008).
Organization Descriptions rewarded for results; yet clients, senior
The three organizations are summa-
Semistructured interviews were held management, and other project man-
rized and compared in Tables 4 and 5.
with various stakeholders, including agers express great appreciation for
Because AlphaGas has the longer-
senior management, project managers, having a strong project management
running PMO, its history is described in
members of the PMO, and project methodology with detailed processes
greater detail.
sponsors. Data was also collected via and procedures.
online surveys and document reviews. AlphaGas AlphaGas began building its IT
In total, 46 interviews were conducted, AlphaGas is relatively conservative, views project management competency in
and 41 respondents completed online itself as a fast follower, and is rapidly 1999 after several large projects went

March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj 59


PAPERS
Building Value Through Sustainable Project Management Offices

Attributes AlphaGas BetaGas ITM Consulting


Ownership Publicly traded Publicly traded Private
corporation income trust
Industry Pipeline and energy Pipeline and energy IT consulting
Size Very large Large Medium
Organization Operational Operational Strong matrix
Competitive Regulated and deregulated Regulated and deregulated Many small competitors, 1–2
Environment industries industries larger ones operating
Fast-paced, with rapid growth in Fast-paced, with rapid growth in in this space
some sectors some sectors
Competitors are often partners Competitors are often partners
and/or customers and/or customers
Strategy Growth in all areas; build/acquire Double in size in 3–5 years Strategy ⫽ grow by 30% a year
Focus on build rather than buy in
order to increase size
Culture Fast follower; conservative Hard-working, results-oriented; tight Professional, open, careful
Conflict between results- vs. control from top; fast-moving screening of employees and
process-oriented subcultures clients for fit with values
and culture

Table 4: Organization attributes.

off the rails. There was also a pent-up proper project initiation and plann- 2008, these metrics—while still high—
demand for new projects, as well as a ing procedures. These were quickly have been trending downward.
need to replace or upgrade many legacy followed by other project manage- After the founder of the PMO
applications and infrastructure. A ment processes. He created com- retired in 2004, an internal senior proj-
trusted senior project manager, with a prehensive documentation for the ect manager was put in charge of the
strong process background, was tasked complete project management metho- PMO. All project managers were trans-
with improving project performance. dology, as well as developed and deliv- ferred to the PMO, making it both a
Based on the belief that the company ered detailed training materials and coaching- and executing-type PMO.
would be unable to hire sufficient num- seminars. In 2008, there were approxi- The move was to help ensure adher-
bers of expert project managers, he mately 50 project management proce- ence to process and procedures and
developed a comprehensive project dures, 50 job aids, 20 checklists, and 30 provide better oversight of projects as
management methodology based on templates accessible via the company their numbers significantly increased.
the Project Management Body of intranet—which had changed very lit- In 2006, the director of the PMO was
Knowledge (PMBOK) and industry tle since the PMO founder’s retirement transferred to a senior executive posi-
“best practices” to provide a consistent in 2004. tion across the country in another busi-
structure for junior and contract proj- Both tangible and intangible value ness unit; after several months’ search,
ect managers. He felt that such a was quickly realized, as measured by a new director was brought in from the
methodology would improve project standard on-budget, on-schedule, and banking industry in the second quarter
performance and provide better con- satisfaction metrics as well as anecdot- of 2007. While never acting in a formal
trols, especially around project costs. al data. Senior management and project manager position, she had
He invested significant time training project sponsors expressed great confi- experience with several large IT proj-
project managers and senior executives dence and satisfaction around IT’s ects in the bank and had been manager
on the methodology and provided improved ability to reliably and effi- of client relations.
extensive coaching and mentoring. His ciently get projects completed. In 2005, As mentioned, over the next few
first priority was getting proper status the company received a PMI award for years, the number of projects managed
reports established; next, he focused on project management excellence. For per year increased dramatically (from
project closure, followed by establishing the last few quarters leading up to Q2 12–20 to 60–70 projects). The types

60 March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj


AlphaGas BetaGas ITM Consulting
Length of Time of Project Approximately 8 years 2 1兾2 years 2 1兾2 years
Management Capability
Reasons for Creating • Projects failing • Projects failing • Projects failing
Project Management • Wanted better control of costs • Wanted better control of costs • Wanted better control/predictability
• Projects getting bigger, more • Projects getting bigger, more of project-related costs
numerous, more complex numerous, more complex • Improve quality of projects,
• Fundamental belief that • Fundamental belief that reduce rework
competence in project competence in project • Wanted better confidence/
management is critical to management is critical to satisfaction around ability to
strategic success strategic success execute projects
• Wanted better confidence/ • Wanted better confidence/ • Projects getting bigger, more
satisfaction around ability satisfaction around ability numerous, more complex
to execute projects to execute projects • Larger partners asking for project
manager
Types of Projects • IT infrastructure • IT infrastructure • IT infrastructure
• Software development • Vendor configurations • IT consulting
(Buy, not build)
Number of Projects 60–70 13 200
in Pipeline
Previous Approach to Informal, ad hoc, varied by project Contract project managers “Cowboy” project managers
Project Management manager; internal and contracted hired for ability to deliver usually were technical leads
project managers projects; each brought own
project management
approach
Project Management Very formal with medium Moderately formal with Moderately formal with high
Methodology adherence medium adherence adherence
What Implemented • Adapted from PMBOK/best • Adapted from PMBOK/best • Adapted from PMBOK/best
practices to fit needs of company practices to fit needs of practices to fit needs of company
• Comprehensive methodology company • Basic processes, tools, and
and supporting tools/ • 13 basic processes, a few templates
documentation templates for reporting, • Portal to access project
• Portal to access all project-related charter management documentation
material, including project archives • Various tools/techniques and project archives
• Initially, lots of training/coaching • Ongoing training/coaching • Initially, lots of training/coaching
of project managers, senior execs, of project managers, senior of project managers, senior execs,
IT personnel execs, IT personnel IT personnel
• Initially, close monitoring/follow-up • Close monitoring/follow-up • Close monitoring/follow-up of
of project managers of junior project managers junior project managers, weekly
• Monthly project management • Program managers project management meetings on
meetings around projects projects and project management
• Program managers • Program managers
• Resource management
Project Manager 88% have 1–4 years 83% have 10–20 years 57% have 1–9 years
Experience
Table 5: Comparison of project management implementations.

of projects went from primarily development projects. In 2008, approx- managers were added to the PMO;
infrastructure- and telecommunications- imately 70% of the 300 IT PMO project however, each operated in a different
type projects to include vendor appli- managers and staff were contract way. Some acted as true program man-
cation configurations and software employees. In 2005–2006, program agers, and others simply oversaw a

March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj 61


PAPERS
Building Value Through Sustainable Project Management Offices

Year Milestone Key Accomplishments


1999 Experienced project manager tasked • Focus on costs, status reporting, and formal change
with improving project management in IT process
• Introduction of project management as a discipline
• Began development of project management methodology
2000–2002 Continued development of project • Began work on closure phase: getting projects
management methodology completed
• Initiation phase focused on next, followed by
turnover and change control processes
• Extensive coaching, mentoring, training
2003 New CIO • Established strong foundation for project management
Project center of excellence created • Implemented changes to methodology once a year,
followed by extensive training
2004 New director of PMO • CIO edict: PMO would run all big IT projects
• Transfer of project managers to PMO
• Increase in number of projects (12–20)
• Increase in number of contract project managers and
PMO staff
2005 Won PMI Award for Project Excellence • Continued increase in number of projects (60⫹)
• Program managers introduced
2006 Director of PMO transferred • More project managers hired/contracted (little or no
orientation or on-boarding done—directed to project
management documentation on website)
2007 New director of PMO hired • Begin refresh of project management methodology,
develop vision and strategy for PMO
• Reposition most of existing program managers, hire
new ones
• Begin to develop resourcing strategy
2008 Previous director of PMO appointed as CIO • Continue work on refresh of PMO

Table 6: Critical project management events—AlphaGas.

large portfolio of diverse projects. At BetaGas there was a heavy reliance on external
the time of the case study, it did not As with AlphaGas, project manage- project managers.
appear that the role of the program ment was introduced at BetaGas by the In 2006, an experienced project
manager was clearly documented or chief information officer (CIO) to pro- manager was brought in to manage
integrated with the project manage- vide a formal structure for managing several projects and develop a basic
ment methodology. Currently, a refresh projects with standardized, repeatable project management methodology. She
and refocusing of the PMO and project processes, as well as clear metrics for had seen project managers who were
management methodology are being tracking status and costs. His underly- familiar with its fundamental princi-
done to improve the management, ing vision was to use formal project ples use the project management
accountability, and effectiveness of the management methodologies and tools methodology and provided thorough
PMO, project managers, and stakehold- on IT projects as a prototype for how training on it to anyone who had any-
ers. A long-term strategy and resourc- projects should be run in the rest of the thing to do with projects, including
ing strategy is also being developed. organization. Similar to AlphaGas, project managers, senior executives,
Table 6 recaps the critical project there were numerous IT projects that technical resources, and business staff.
management events in AlphaGas’s his- needed to be done to acquire or upgrade Initially, she focused on providing sim-
tory. infrastructure and applications, and ple, regular project status reports to

62 March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj


Year Milestone Key Accomplishments
2005 Experienced project manager, with strong • Focus on status reports and standard project reporting
PMBOK background hired to improve • Introduction of project management as a discipline
project management in IT • Demonstrated value of formal project management
practices
2006–2007 Formal IT PMO established • Monthly overall project status report to senior executive
Continued development of project committee
management methodology • Extensive coaching, mentoring, and training of project
managers, executives, and other stakeholders
• Hiring new project managers
• Project sponsors begin writing project charters
2008 Introduce portfolio management • Introduce role of program managers
• Senior executives begin to take portfolio approach to
project prioritization and selection

Table 7: Critical project management events—BetaGas.

senior executives. Then she focused on and customer satisfaction are equally one time, they were on the verge of dis-
getting proper charters written to initi- as important as profitability on its bal- continuing their relationship with ITM
ate projects. anced scorecard. It currently has Consulting. After experiencing the
The results quickly demonstrated approximately 135 employees. Its proj- results of ITM’s formal project man-
value to senior management, and ect management methodology was agement methodology, they now not
quickly improved resource manage- introduced in much the same fashion only gladly pay for project manage-
ment. In interviews, senior executives as at AlphaGas and BetaGas, using an ment fees, but also write letters of ref-
strongly endorsed the use of formal experienced project manager to devel- erence for ITM Consulting. ITM
project management practices, and the op its project management methodolo- Consulting feels that its project man-
chief operating officer (COO) advocated gy, using experienced project managers agement practices deliver such consis-
the use of formal project management to quickly demonstrate its value, and tency and reliability that they are mov-
practices on other types of projects in providing thorough training on the ing toward offering fixed-price con-
the organization (e.g., major capital project management methodology to tracts for some types of projects.
projects, acquisitions, and organiza- everyone, especially junior project Table 8 recaps the critical project
tional change projects). Within the IT managers. management events in ITM Consulting’s
PMO, the role of program manager is ITM Consulting knows that it has history.
being introduced due to an increasing received significant value for its
number of projects being undertaken. approximate $500K investment in Perceptions of Value
Table 7 recaps the critical project developing its project management In all three organizations, senior man-
management events in BetaGas’s his- office and project management com- agement, project managers, project
tory. petency. Costs are better under con- sponsors, and customers reported ben-
trol, and customer and employee efits and satisfaction with the project
ITM Consulting satisfactions have improved. There is management implementation. These
ITM Consulting is a small-to-medium, significantly less rework on delivered were categorized into tangible and
regionally focused IT consulting com- projects and fewer disputes over intangible benefits by the researchers,
pany, delivering infrastructure-type invoices. They also bill clients for proj- with different types of value observed.
projects, managed services, and devel- ect management fees, which repre- These are reported in Table 9.
oping security, business continuity sents an additional revenue stream. Using the specific types of value
management/disaster recovery (BCM/ They feel they are more professional described previously in Figure 1 (from
DR), and IT strategies for small-to- and have greater credibility in the mar- Thomas & Mullaly, 2008), Table 10 rep-
medium-sized companies. Revenues of ket. They are getting larger, more com- resents the researchers’ perceptions of
$20M are split 40/60% between proj- plex projects based on their success specific types of value that each of the
ects and managed services. Employee record. One client indicated that, at three organizations have received from

March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj 63


PAPERS
Building Value Through Sustainable Project Management Offices

Year Milestone Key Accomplishments


2006 Q1—Formal project launched to develop • Charter written—Q2
project management methodology, • Methodology, templates created, piloted
created by experienced project managers • Approved by senior management—Q3
• Rolled out, with training to relevant employees—Q4
2007 Implement continuous improvement • Continuous improvement of processes, tools
• Hired several more project managers as number of
projects increased
2008 Develop PM-Lite • Created PM-Lite for smaller projects
• Introduced program management
• Created resource manager position within PMO
Table 8: Critical project management events—ITM Consulting.

AlphaGas BetaGas ITM Consulting


Focus of Project Within IT Within IT Organization-wide
Management/PMO
Organizational High Very high High
Commitment to Project
Management
Tangible Benefits • Cost savings in time • Revenue increases (through • Cost savings
• Reduced write-offs and rework support of acquisitions) • Revenue increases
• Reduced write-offs/rework • Reduced write-offs/rework
• Customer retention
• Increased customer share
• Greater market share
• Improved competitiveness
Intangible Benefits • Attainment of strategic • Strategic alignment • Attainment of strategic objectives
objectives • More effective human resources • New product/service streams
• More effective human resources • Improved general use of resources • Strategic alignment
• Improved reputation • Better project decision making • More effective human resources
• Improved regulatory compliance • Improved regulatory compliance • Improved reputation
Perceptions of Value • High • Significant • High
of Project Management • Spreading project management • Planning on spreading project • Increased revenues
principles to other types of management principles to other • Decreased costs for similar
projects types of projects projects
• Moving towards fixed-price
contracts
• Taking on bigger, more
complex projects
Table 9: Benefits of project management implementation.

Satisfaction Aligned Use Process Outcomes Business Outcomes ROI


AlphaGas

BetaGas Q Q Q Q
ITM Consulting Q Q Q Q Q
Table 10: Specific types of value from project management implementation.

64 March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj


Understanding the Dimensions of Value

A company's hedgehog concept is at the intersection of three circles:


• what they are deeply passionate about,
• what drives their economic engine, and
• what they can be better at than anyone else in the world.
=====
• Project managers are deeply passionate about delivering projects that meet requirements.
• Efficiently managing costs and effectively managing resources to meet on-time, on-budget requirements drive their economic engine.
• Project managers and PMOs should be better than anyone in the organization at managing projects.

their project management implemen- focus from a coaching-focused PMO • Staff the PMO carefully.
tation since its inception. to an executing one? Is it the heavy • Create a culture of discipline.
As can be seen, all organizations reliance on external project man- • Confront the brutal facts, but keep the
received significant value from their agers? We began to ponder the sus- faith.
investment in formal project manage- tainability of project management
Build a Core Ideology for the
ment practices, especially in the early value. Is there a point of inflection, as
Long Term
years. There was an apparent shown in Figure 2, where value levels
Collins’s (2001) recommended strategy
deterioration of value in AlphaGas— off or even decreases?
for building an organization that can
the organization with the longest project Exploring the diagram in Figure 2
endure and adapt through multiple
management implementation. They with the other case study teams in a
organizational life cycles and leaders
still report significant value and satis- research workshop, we realized that
suggests that the key is to start with a
faction from project management and other researchers were observing simi-
long-term focus and vision and then
would never discontinue following a lar issues with the PMOs in their case
put in place the values and frameworks
formal project management methodol- study organizations. Clearly, a question
that will support this vision. Applying
ogy. In fact, they are looking at transfer- of major importance is “How do organ-
this to PMOs and project management
ring the project management method- izations increase or sustain the value
competency means that both must sur-
ology to other types of projects outside received from investments in project
vive transitions in leadership of both
of IT. However, according to their own management and, more specifically for
the organization and the PMO, and
analyses, if the downward trend contin- us, in PMOs?”
adapt to changes in the needs of the
ues, they will not meet their on-budget,
on-schedule target levels.
Discussion organization. Drawing on several of
In all three cases, the mechanism for Collins’s concepts, a PMO’s core ideolo-
What caused this deterioration?
managing the investment in project gy should be based on a clear vision
Was it the rapid growth in numbers
management was through the estab- and focus, guided by a frame of refer-
of projects? Was it a change in type of
lishment of a PMO. Also, all three cases ence, which comes from its hedgehog
projects? Was it simply a lack of adher-
began in a very similar fashion and concept (see sidebar), and the “genius
ence to processes? Was it the change
quickly realized similar benefits and of AND”1 as it applies to project man-
in leadership? Was it the change of
value, but the oldest PMO—AlphaGas— agement.
has struggled to sustain these contribu- In essence, the PMO’s core ideology
tions. In this section, we discuss the influ- should be based on the notion that:
ences on the value and sustainability of • No one else in the organization is
PMOs by applying a lens of value cre- more passionate or knows more
ation and sustainability adapted from about how to manage/deliver projects
Value

Collins (2001) to our case studies and more efficiently or effectively.


focus on the insights this lens reveals. • Flexibility AND a standard methodol-
The insights are identified in the follow- ogy are compatible concepts, as is the
ing themes:
Time • Build a core ideology for the long 1 The “genius of AND” refers to being able to embrace both
term. ends of a continuum as feasibly possible rather than view-
Figure 2: Value sustainability.
• Pick the right PMO leadership. ing the ends as “either/or” options.

March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj 65


PAPERS
Building Value Through Sustainable Project Management Offices

ability to be both a competent leader ect managers is so necessary. Investing Pick the Right PMO Leadership
AND manager, have both a people AND in proper on-boarding allows the com- Collins (2001, p. 20) reviewed qualities
a task focus, and manage internal pany to explain its adaptation of key of leaders that headed up long-lasting
AND external relationships. processes, identifies those artifacts that successful companies. The three PMO
• It is better at supporting, managing, are mandatory, and reinforces why it is founders we studied all exemplified
and developing project managers important to do certain tasks. Second, Collins’s successful leadership charac-
than anyone else in the organization. PMOs should not get distracted from teristics (also see the Appendix for the
their primary focus, their hedgehog leadership model) of successful, value-
This core ideology should be principles, by taking on other responsi- sustaining companies.
reflected in the PMO’s project manage- bilities like benefits realization or addi- • They were passionate, focused, and
ment methodology. Furthermore, as tional governance functions. determined about what constituted
others have shown, organizational staff In order to continue to add value to effective project management.
and project managers must be involved the organization, PMOs must stay • Each founder had a low-key, patient,
in developing their project manage- focused on managing projects; however, but confident personality. Given they
ment methodology, even if from the this does not mean stagnating or were dealing with senior executives,
outside it seems like only minor adap- neglecting core principles. As Collins engineers, IT personnel, or clients/
tations from best practices (see the (2001, p. 108) observed, “If you success- businesspeople, a more forceful, direct,
Andersen and Vaagaasar; Eskerod and fully apply these ideas, but then stop or aggressive personality would have
Riis; and Mengel, Cowan-Sahadath, doing them, you will slide backward . . . quickly met with resistance from the
and Follert papers in this issue). The the only way to remain great is to keep folks they were trying to persuade to
process of development and adapta- applying the fundamental principles adopt new behaviors and methods.
tion increases a sense of ownership and that made you great.” As discussed in • Each focused on quickly demonstrat-
commitment to the methodology. It later sections, we think that AlphaGas, ing the proof and value of what they
becomes the organization’s way of somewhere in rapidly expanding were advocating with quick, simple
managing projects, not the PMBOK’s the number of projects it took on, the wins. For example, the senior execu-
or anyone else (i.e., “This is the way we number of project managers it hired, tives quickly came to appreciate regu-
do things around here.”). This lack of and the changes in PMO leadership, lar, consistent, simple status reports.
perceived ownership may provide neglected to apply the fundamental The project management founder in
explanations for some of the uncer- principles that provided value. AlphaGas took this a step further,
tainty of value found in the full set of “Stimulate progress” can relate to sev- illustrating how much money could
case studies when organizations eral PMO-related issues, including be saved in labor-hours by adopting
attempted or were forced to imple- developing project managers by having this standard procedure. Getting sen-
ment a new project management them take on more challenging roles or ior management on board provided
methodology that had been developed different types of projects, periodically the project management founder
elsewhere (Thomas & Mullaly, 2008). updating or refreshing the project man- additional support for persuading
In all three case studies, the PMO agement methodology, or adding new others (e.g., project managers) to fol-
founder clearly created a core ideology functions to the PMO that enhance its low standardized procedures.
around managing projects, into which ability to manage projects on the orga-
they indoctrinated relevant stake- nization’s behalf (see Hobbs and It is important to note, however, that
holders through training, mentoring, Aubry’s 27 PMO functions in Table 2). it is not just the organization the PMO
coaching, and rejection of noncompli- The key considerations are that all founder has to convince. He or she
ant work. One could argue that these changes should be based in preserving also must convince, persuade, or dic-
activities are fundamentally why formal core features of the original hedgehog tate to the project managers to follow
project management methodologies principle—embodied in the company’s new practices. If the PMO is simply a
and PMOs add value to organizations. project management methodology— support or coaching role, then the PMO
Collins (2001) suggested that sus- while stimulating progress via modifying does not necessarily have the authority
taining the value generated from orga- and changing it around the periphery. to enforce compliance or accountabili-
nizational investments requires both Any attempt to disrupt the core, for ty of project managers, and must draw
“preserving the core” and “stimulating example, a drastic change of the core heavily on personality, soft skills, and
progress.” “Preserve the core” has two project management methodology higher leadership qualities to persuade
important implications. First, it such as when a new PMO leader comes compliance and create discipline.
explains why appropriate on-boarding on scene, will be dangerous and should Kellerman (2008) stated that “increas-
of even experienced and contract proj- be approached with great care. ingly, followers think of themselves as

66 March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj


free agents, not as dependent under- that project management practices cre- strategic perspective and vision are
lings,” and thus their management and ate value, which in turn reinforces the unimportant and even detrimental in
leadership is more challenging. In the need for disciplined action and adher- project managers (2007, p. 31). The
world of North American knowledge ence to standards. leadership aspect of projects is the area
workers and contract project man- In the AlphaGas case, when replac- of skill that may be lacking for many
agers, this self-perception of free ing the PMO founder, the organization project managers” (Gehring, 2007, p. 50).
agency is predominant. An in-depth took the position that the visionary, Clearly the controversy over a project
discussion of the nature of project commitment gaining, and setting up manager’s need for leadership and
managers as followers is beyond the part of the PMO was “done” and all that strategic capabilities rages on.
scope of this article; however, accord- was needed in the replacement was a Given the greater need for the PMO
ing to Goffee and Jones (2006), follow- transactional manager to be the keeper to take an organizational focus, man-
ers want authenticity, significance, of the methodology and processes. This age a broad range of stakeholders, and
excitement, and the sense of being part is similar to other cases in the global act more like a functional department
of a community from their leaders. value project where consultants were than a project, and taking Collins’s
In the realm of project managers, hired to set up the PMO and then a advice for building sustainable value
they want their leaders to be genuine caretaker manager was put in place. In into account, we believe managing and
and have credibility as project man- these cases, the methodology stag- leading the PMO requires strong trans-
agers; they want to feel recognized for nates, as there is no one working to formational and people-oriented lead-
their success as project managers and engage the periphery and adapt the ership skills and behaviors—that is,
made to feel important. Project man- methodology to changing environments. Level 4-type leaders. Given that the
agers want their leader to engender Not any project manager can aspire research suggests that these skills are
excitement around project manage- to lead the PMO. In Collins’s hierarchy, not typically required or used by proj-
ment “through their passionate com- successful project managers are most ect managers to a significant extent, the
mitment to clearly articulated personal likely to be at a Level 3 (competent PMO should ensure that evaluating and
values and to a vision” (Goffee & Jones, managers). Research on project man- developing such competencies is part
2006, pp. 194–195). Interestingly, Keegan agers’ leadership styles tends to be of its career advancement strategies for
and Den Hartog found no correlation mixed. While many project managers those project managers that want to
between project managers’ leadership can be people- or relationship-focused move into PMO leadership roles.
styles and the project team’s motivation (Mäkilouko, 2004; Lee-Kelley & Leong,
and commitment, although they did 2003, as reported in Turner and Müller, Carefully Staff the PMO
find a significant correlation between a 2005), others have found that project In Collins’s (2001, p. 63) terms, one
line manager’s leadership style and managers prefer task-oriented leader- should “get the right people on the bus,
employees’ commitment, motivation, ship styles (Turner & Müller, 2005, the wrong people off, get the right peo-
and stress (Keegan & Den Hartog, 2004, p. 57) and tend to use transactional ple in the right seats THEN figure out
in Neuhauser, 2007, p. 23). In the three more than transformational-style lead- where to drive it.” Like Collins acknowl-
PMOs we studied, each of the founders ership behaviors (Neuhauser, 2007). edged, one doesn’t always have this lux-
exhibited these qualities and abilities, as This was especially true for project ury in project management and in the
reflected in comments from both senior managers who came from a technical PMO. As pointed out by Graham and
and junior project managers. In background. However, Neuhauser Englund (1997, in Gehring, 2007), “For
AlphaGas, even though the founder had (2007, p. 23) stated “general leadership most organizations, the most natural
retired 3 years previously, his passion, research has found that transforma- thing to do is to draft a technician or
values, and vision for project manage- tional leadership is correlated with administrator with a good reputation
ment were still talked about and referred more satisfied employees and a posi- within the organization to lead the
to with great respect and frequency. tive effect on productivity and financial project. . . . Accidental project man-
Effective ongoing leadership is nec- results.” Moreover, Müller and Turner agers typically have strong skills for
essary, especially with respect to main- (2007, p. 31) reported “. . . we do see understanding the technical aspects of
taining a clear and compelling vision of that vision in the project manager can the project. However, the technical
what project management competency be detrimental to project performance part of a project is often the smallest
means to the organization and how this [especially for engineering, informa- and easiest part.” Walker and Peterson
competency should be managed, tion systems, and organizational and (1999) stated that “in order to create a
developed, and maintained. Both sen- business projects], and vision is a key mutually successful corporate environ-
ior managers and project managers component of the transformational ment, it is important to create an envi-
require regular, consistent reminding leadership style.” They concluded that ronment for success by putting people

March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj 67


PAPERS
Building Value Through Sustainable Project Management Offices

into positions to succeed. Not everyone contract employees. Thus, in a world and RACI charts for each project).
is destined to become a project leader, dominated by contract project man- These actions reinforced responsibility
any more than everyone is destined to agers, good hiring and screening mech- and accountability.
become the CEO” (p. 5). anisms need to be developed to ensure After his departure, an experienced
Recognizing that not all people are good contract hiring. In addition, effort project manager with senior manage-
suited to managing projects, it is must be expended to ensure that the ment experience was put in charge of the
incumbent upon the PMO leader to PMO’s culture is strong enough to pull PMO. The successor reaped the benefit
develop an understanding of the skill these contract staff into its realm and of inheriting disciplined people who had
sets and competencies that are preva- indoctrinate them appropriately into disciplined thoughts and actions.
lent within the organization and among their core ideology through good on- Because they successfully executed proj-
its project managers. This is critical to boarding mechanisms. ects, the number of projects began to
building something that will be able increase. Larger projects, more complex
to add value to the organization. Create a Culture of Discipline projects, and different types of projects
The “right people in the right seats” The notion of discipline around project were launched. The growth in projects
concept also relates to what role project management is profoundly important. and project managers caused the new
management support staff should play According to Collins, success and sus- PMO leader to introduce the role of pro-
and what their respective competencies tainability require disciplined people, gram managers. One can assume he del-
should be. Developing role/job descrip- disciplined thought, and disciplined egated much of the coaching and moni-
tions, competency profiles (including action—in that order. toring activities to them. Although most
competency profiles for specific types Key elements in a culture of disci- of the program managers had worked in
of projects), and RACI2 charts are ways pline are disciplined people and disci- a project environment, some were new
of addressing these issues. A corollary to plined action. This relates to accounta- or contract hires (and conceivably un-
developing competency profiles is that bility and responsibility. In all three indoctrinated to the PMO’s core ideolo-
one needs to develop effective, accurate organizations, professional managers gy) and/or had little true project man-
evaluation processes of such compe- in all business areas welcomed clear agement experience. (It is unclear if they
tencies. Developing these profiles and delineation of roles and responsibili- would be classified as competent man-
evaluation processes, as well as follow- ties, and actively fulfilled them. agers or effective team members in
ing and managing them, typically falls Furthermore, as mentioned, each PMO Collins’s leadership hierarchy.) The pro-
within the realm of the PMO. Lastly, founder closely monitored, coached, gram managers who were interviewed
related to the PMO leadership concept, and mentored project managers in ful- acknowledged that coaching and moni-
clear career paths and professional filling their responsibilities, thereby toring compliance was part of their role;
development should be provided to enforcing disciplined action while they however, the project managers reported
those who want to advance into PMO developed inexperienced project man- that coaching, training, and discipline
leadership roles. agers to have self-enforcing disciplined around accountability and delivery
According to Collins, time and pro- thought and action. dropped off. Concerns around cumber-
moting from within are ways to pre- In AlphaGas, despite having no some or inconsistent adherence to proj-
serve the core and achieve sustained direct authority, the PMO founder cul- ect management processes were not
value. This is supported by the Value tivated a significant amount of disci- heard, much less addressed. Project man-
Project, which found that organizations pline around following the project agers began to lose faith in the project
relying heavily on contract project man- management methodology and appro- management processes and became
agers do not realize improvements in priately applying its artifacts. He close- resistant to following them. As noted in
project metrics (Thomas & Mullaly, ly monitored status reports, change Collins (2001, p. 121), increased bureau-
2008). An organization that relies heavi- requests, and so forth. He required cracy—which creates greater overhead
ly on contract project managers is more project managers to redo them if he felt costs—usually takes place in the absence
focused on immediate project needs they weren’t adequate—and provided of disciplined people, thought, and action.
(time telling, in Collins’s terms) rather hours of coaching on why these tools These increased costs can contribute to
than organizational competency devel- were important and how to do them decreased perceptions of PMO value.
opment (clock building). Organizations properly. He diligently followed up to
risk losing valuable insights, learning, see if corrective actions were imple- Confront the Brutal Facts
and knowledge through dependence on mented, and that all relevant parties Collins (2001) explained that it is vitally
properly fulfilled their roles and important for organizations to always
2 RACI charts identify who is Responsible, who is
responsibilities (which were detailed in understand the brutal facts of its envi-
Accountable, who needs to be Consulted, and who needs
to be Informed about an activity. project management documentation ronment, its reality, its problems, and

68 March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj


so forth, but never lose faith in the board. (This CIO left shortly before this team member or sponsor held to
organization’s ability to win out in study was done.) The CIO launched a account for each time rework didn’t
the long run. Recent research suggest- strategy to rein in spending and get the happen on a project, each time a
ing best organizational practices for IT budget under control. Several hun- client/sponsor and project team satis-
project management similarly suggests dred IT positions were eliminated. faction report came out, and each time
that the best way to improve project Growth was slowly restarted, with a project celebration was held—started
management is to have the “difficult more projects being launched. We turning the flywheel. By many different
conversations” necessary to keep proj- heard project managers comment on a measures and various stakeholder per-
ects healthy (Grenny, Maxfield, & “reign of terror” and how bearers of spectives, each PMO can be seen to have
Shimberg, 2007). bad news tended to get beat up in lead- effectively developed a project manage-
PMOs, as well as the project manag- ership meetings. Not surprisingly, bru- ment competency that delivers value to
er, need to ensure that the brutal facts tal facts started to be downplayed or its organization. And when, in the case
associated with a project are recognized hidden or budget/schedule/scope of AlphaGas, attention was not paid to
and addressed in an effective, timely changes were approved, causing the maintaining and continuing these
manner, as these are warning signs that yellow/red flags to disappear. Although nudges, value started to fade away.
things aren’t going the way they should. formal change processes were fol-
These issues are compounded in multi- lowed, these did not necessarily Conclusion
project environments. The PMO is typi- address the causes of the original yel- There are many articles, blogs, and
cally responsible for facilitating the low/red flags. A root cause analysis of books on PMOs that cover the different
handling of issues and ensuring people project failures over a several-year peri- roles and responsibilities that the PMO
feel safe to act on concerns. More od revealed that a similar set of prob- can fulfill, its benefits and challenges,
importantly, the brutal facts must be lems consistently caused problems and how to go about establishing one.
responded to; otherwise, project man- from project to project. So while brutal Research has shown that PMOs are rel-
agers and other project team members facts may have been surfacing, nothing atively new creations in the organiza-
will quickly come to view the proce- was done to address them. tional milieu and undergo frequent
dures as simply bureaucratic red tape. While an individual project manag- changes in relatively short periods
One of the first tasks undertaken in er must not lose faith that a project will (Hobbs, Aubry, & Thuillier, 2008). Our
each of the three PMOs was the imple- be completed, the PMO must not lose discussion adds to this knowledge base
mentation of regular, consistent, clear faith that the company’s best interests by examining the start-up of three
status reports presented to project are paramount, even if that means can- PMOs, their success, and their sustain-
stakeholders. They each followed the celling or stopping a project. A project ability. All three PMOs experienced sig-
simple green-yellow-red indicator for manager who has developed the ability nificant initial success, but after 9 years
key metrics. The PMO ensured a con- to doggedly pursue a project until its and several changes, one PMO started
sistent, standardized report across all end might not have the ability to recog- to exhibit cracks in its effectiveness.
projects and project managers, includ- nize brutal facts that indicate a project Using concepts from Good to Great
ing external contract project managers. should be stopped. This is where a (Collins, 2001) and Built to Last (Collins
In each organization, senior manage- strong, strategic-oriented PMO leader & Porras, 1994), we examined reasons
ment and project sponsors quickly must step in. The prolonged absence of for this success and decline. Given the
came to appreciate these; it was one of such a person in AlphaGas potentially research suggesting the short lifespan
the tangible products that led them to affected its ability to effectively surface of many PMOs, we believe that explor-
recognize the value in formal project and address project-related brutal ing these cases in detail provides useful
management methodologies. Problems facts. insights for both practice and research.
were quickly surfaced and addressed. Space limits discussion of technolo- Hobbs et al. (2008) reported that
In BetaGas, senior managers soon real- gy enablers and the flywheel concepts. PMOs have a short life span before they
ized that red flags associated with their One can see, however, how each are restructured or refocused. They
projects were not good, as the CEO and founder in AlphaGas, BetaGas, and ITM imply that this is a negative finding and
peers put pressure on them for correc- Consulting unconsciously incorporat- speculate it is a reflection that PMOs
tive action during monthly project ed and applied the Good to Great con- ultimately add little sustainable value
review meetings. Consequently, project cepts in developing their respective to an organization. We disagree with
sponsors took quick action when yel- project management competencies. this notion. We think effective PMOs
low flags surfaced. Each nudge—each status report filed, continue to add value specifically by
In AlphaGas, just before the PMO each coaching instance, each monitor- changing and reinventing themselves—
founder retired, a new CIO came on ing and control effort enacted, each as long as they stay focused on the

March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj 69


PAPERS
Building Value Through Sustainable Project Management Offices

principle of improving project manage- you want to become stronger, faster, or Desouza, K. C., & Evaristo, J. R. (2006).
ment in the organization. PMOs are improve another aspect of your fitness, Project management offices: A case of
typically formed to address a specific in other words, to increase the value knowledge-based archetypes.
set of problems (e.g., help get project you’ve gained—not just maintain it— International Journal of Information
costs under control). When those prob- then you need to develop a new vision Management, 26, 414–423.
lems are addressed, effective PMOs and goal (e.g., improve your endurance), Gehring, D. (2007). Applying traits the-
identify new goals and objectives for identify new strategies and procedures ory of leadership to project manage-
themselves (e.g., ensure adherence to to get you there, and invest even more ment. Project Management Journal,
processes or manage a broader span of than what it takes to simply maintain 38(1), 44–54.
projects). These new goals may require the current state and value. (In many Goffee, R. & Jones, G. (2006). Authentic
a new structure and new processes for respects, the PMO plays the role of per- followership. In R. Goffee & G. Jones,
the PMO, but as long as they preserve sonal trainer.) Building a project man- Why should anyone be led by you?
the core project management ideology agement competency and an effective What it takes to be an authentic leader
and focus, they will continue to provide PMO function that continues to deliver (pp. 189–201). Boston: Harvard
and add value to the organization. value is not a one-time effort, nor an Business School Press.
Building a good PMO doesn’t nec- overnight one—it is an ongoing, con-
Graham, R., & Englund, R. (1997).
essarily guarantee the sustainability of tinuously evolving investment that
Creating an environment for successful
project management competency needs to be managed by qualified,
projects. San Francisco: Jossey-Bass.
or project management value. Certain visionary, effective leaders.
elements need to be put in place, as Grenny, J., Maxfield, D., & Shimberg, A.
well as certain activities regularly carried
Acknowledgments (2007). How project leaders can over-
We would like to thank all the research come the crisis of silence. Sloan
out, in order to facilitate the sustain-
participants—both organizational and Management Review, 48(4), 46–52.
ability of a value-adding PMO and the
individual—who made this project
sustainability of project management Hill, G. M. (2001). The complete project
possible. In addition, PMI deserves
competency. The qualifications and management office handbook. New
recognition for the financial and other
competencies necessary to build and York: Auerbach Publications.
support provided to the Researching
sustain a project management compe- Hill, G. M. (2004). Evolving the project
the Value of Project Management proj-
tency are not necessarily the same ones management office: A competency
ect that made this study possible.
that make for a good project manager. continuum. Information Systems
Finally, our fellow researchers in the
In other words, a good project manager Management, 21(4), 45–51.
value project contributed to our under-
will not necessarily make a good PMO
standing of value and project manage- Hobbs, B., & Aubry, M. (2007). A multi-
manager/director; consequently, it
ment in so many ways—we gratefully phase research program investigating
should not be assumed that a project
acknowledge their insights on this topic project management offices (PMOs):
manager’s career path naturally lies
that are embedded in this article. ■ The results of phase 1. Project
within a PMO.
Management Journal, 38(1), 74–86.
Developing an organizational proj-
ect management competency that pro-
References Hobbs, B., Aubry, M., & Thuillier, D.
Collins, J. (2001). Good to great: Why (2008). The project management office
vides sustainable value is like getting
some companies make the leap and as an organisational innovation.
physically fit. It takes vision, will, per-
others don’t. New York: HarperCollins. International Journal of Project
sistence, discipline, and many, many
nudges to reach one’s goal. You have to Collins, J., & Porras, J. (1994). Built to Management, 26, 547–555.
confront the brutal facts of your current last: Successful habits of visionary com- Keegan, A. E., & Den Hartog, D. N.
unfit state, your slow progress, and panies. New York: HarperCollins. (2004). Transformational leadership
your constraints and setbacks, while Crawford, L. (2006). Developing orga- in a project-based environment: A
never losing faith that you will attain nizational project management capa- comparative study of the leadership
your goal. But simply achieving your bility: Theory and practice. Project styles of project managers and line
goal and becoming fit isn’t the end. Management Journal, 37(3), 74–86. managers. International Journal
This is your inflection point of value. As Dai, C. X., & Wells, W. G. (2004). An of Project Management, 228,
with any other sustainability initiative, exploration of project management 609–618.
continuous effort and focus must be office features and their relationship to Kellerman, B. (2008). Followership:
expended to simply maintain your new project performance. International How followers are creating change and
level. If you stop exercising, if you lose Journal of Project Management, 22, changing leaders. Boston: Harvard
focus, you will become unfit again. If 523–532. Business Press.

70 March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj


Kerzner, H. (2003). Strategic planning Turner, J. R., & Müller, R. (2005). The program director for the Executive MBA in
for a project office. Project project manager’s leadership style as a Project Management program. She is also a
Management Journal, 34(2), 13–25. success factor on projects: A literature visiting professor with the University of
Lee-Kelley, L., & Leong, K. L. (2003). review. Project Management Journal, Technology, Sydney, and Bond University,
Turner’s five functions of project-based 36(2), 49–61. Australia, where she supervises master’s and
management and situational leader- Walker, C., & Peterson, A. (1999). Are PhD research students. She is well known in
ship in IT services projects. you a project manager/leader or just the international project management commu-
International Journal of Project managing projects? Proceedings of the nity, both from serving on the PMI Research
Management, 21, 583–591. 30th Annual PMI Seminars and Member Advisory Group and in an editorial
Mäkilouko, M. (2004). Coping with Symposiums. Newtown Square, PA: capacity for journals such as the Project
multi-cultural projects: The leadership Project Management Insitute. Management Journal, International Journal of
style of Finnish project managers, Project Management, IEEE Transactions on
International Journal of Project Engineering Management, and the
Management, 22, 387–396. Mimi Hurt holds a PhD in management from the International Journal of Business Performance
Martin, N. L., Pearson, J. M., & University of Texas at Austin. Her broad consult- and Management, and through her involve-
Furumo, K. (2007). IS project manage- ing and research background includes issues ment with collaborative research such as the
ment: Size, practices and the project such as management and delivery of informa- Researching the Value of Project Management
management office. Journal of Computer tion services (IS), IS-user relationships (both project and Rethinking Project Management
Information Systems, 47(4), 52–60. internally and externally based ones), user sat- (funded by the United Kingdom’s National
isfaction, IS service quality, and managing the Science Research Council). She has led a num-
Müller, R., & Turner, J. R. (2007).
next generation of IS professionals. Her current ber of PMI-sponsored research projects includ-
Matching the project manager’s lead-
research focuses on project management and ing the recently completed Researching the
ership style to project type.
project management leadership. Her clients Value of Project Management global study. Her
International Journal of Project
include many large global companies, as well as research interests include organizational
Management, 25(1), 21–32.
municipal and state-level government agencies. change, project management, team building
Neuhauser, C. (2007). Project manager Her academic experience includes over 20 years and leadership, complexity theory in relation to
leadership behaviors and frequency of of developing and teaching a variety of informa- organizations, and the professionalization of
use by female project managers. Project tion systems and e-business courses at the knowledge workers. Ultimately, all of her
Management Journal, 38(1), 21–31. graduate and undergraduate levels at Athabasca research is aimed at understanding and com-
Thomas, J., & Mullaly, M. (2007). University, the University of Calgary, and the municating how the practice of project man-
Understanding the value of project University of Texas. agement in organizations can be improved.
management: First steps on an inter- Prior to becoming an academic, she spent 10
national investigation in search of years as a project manager in the fields of
value. Project Management Journal, Janice L. Thomas is an associate professor in information technology and organizational
38(3), 74–89. the Centre for Innovative Management (CIM). change. In addition to research and teaching,
Thomas, J., & Mullaly, M. (2008). Over her almost 10 years with CIM, she has she maintains close ties to the practical reali-
Researching the value of project man- worked to build links with external organizations ties of project management in organizations
agement. Newtown Square, PA: Project such as PMI and the International Project through consulting and membership in profes-
Management Institute. Management Association. She is currently the sional associations.

March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj 71


PAPERS
Building Value Through Sustainable Project Management Offices

Appendix
Good to Great (Collins, 2001) Built to Last (Collins & Porras, 1994)
Leadership (summarized on pp. 39–40) Clock Building, Not Time Telling
Fully developed Level 5 leaders (executives) at the top who Build an organization that can endure and adapt through
have a combination of professional will and personal multiple generations of leaders and multiple product life
humility (p. 21). cycles (2001, p. 197).
Level 4 leaders (effective leaders) catalyze commitment to This concept of putting in place values, frameworks, and/or
a compelling vision (p. 21). procedures with a long-term focus, rather than an immediate
Level 3 leaders (competent managers) organize resources to or short-term focus, is relevant for other elements in the
an effective and efficient pursuit of objectives (p. 21). framework.
A contributing team member (Level 2 leaders) works
independently to contribute to the goals of the group (p. 21).
Highly competent individuals (Level 1) make valuable
contributions through talent, skills, knowledge, and good
work habits (p. 21).
In Collins’s hierarchy of leadership, higher levels of leadership
embody the traits and abilities of lower leaders—that is,
they have the traits and abilities listed for lower levels (p. 21).
A high-profile, charismatic leader is not necessary to
successfully create a visionary company (p. 32).
First Who, Then What (summarized on pp. 63–64) Genius of AND
Get the right people on the bus, the wrong people off; Embrace both extremes on a number of dimensions
get the right people in the right seats THEN figure out at the same time (2001, p. 198), rather than thinking
where to drive it (p. 41). in limiting “either/or” ways.
The “genius model with a thousand helpers” is not likely
to be successful when the genius leaves (p. 46).
Confront the Brutal Facts, But Never Lose Faith Core Ideology
(pp. 88–89) Instill core values and a core purpose as principles to guide
Create and consciously maintain an atmosphere where decisions and inspire people throughout the organization
“brutal facts” will be heard, but never doubt that you can over a long period of time (2001, p. 198).
and will reach you goal.
The Hedgehog Concept (pp. 118–119) Preserve the Core/Stimulate Progress
Develop a simple, but deeply insightful frame of reference Preserve the core ideology as an anchor while at the same time
for all decisions. stimulating change, improvement, innovation, and renewal
Simplicity within the intersection of three circles: (2001, p. 198).
Circle 1—What you are deeply passionate about
Circle 2—What you can be best in the world at
Circle 3—What drives your economic engine
If you successfully apply these ideas, but then stop doing
them, you will slide backward . . . the only way to remain
great is to keep applying the fundamental principles that
made you great.
A Culture of Discipline (pp. 142–143)
Success and sustainability require disciplined people,
disciplined thought, and disciplined action.
Build a culture around freedom and responsibility
within a framework (p. 124).
Technology Is [Only] an Enabler (2001, p. 160)
Technology is an accelerator of greatness, not a creator of it.
Technology by itself is never a primary root cause of either
greatness or decline.
Become a pioneer in carefully selected technologies that
clearly fit the hedgehog concept.
The Flywheel and the Doom Loop (pp. 162–163)
Many small, persistent, continuous pushes in one direction
are necessary to get a flywheel turning; no single grand
push or initiative is sufficient.

72 March 2009 ■ Project Management Journal ■ DOI: 10.1002/pmj

You might also like