Professional Documents
Culture Documents
Table of Contents
Section:
01 02 03
Project Overview Task 1 Summary: Task 2 Summary:
Stakeholder Interviews Data Gaps
07
History of BioDistrict 11 15
New Orleans Task 1 Overview Task 2 Overview
07 11 15
The BioDistrict Task 1 Findings Data collection Efforts
to Date
07
The Mission 15
Reports and Studies
07 Collected to Date
The Planning Team
15
08 Continued Data Gaps
The Planning Effort
3
04 05
Task 3 Summary: Task 4 Summary:
Analysis Programming
19 31
Task 3 Overview Task 4 Overview
21 32
Community Context Real Estate
Overview Programming Overview
21 36
Urban Design Overview Bioscience
Programming Overview
23 Acknowledgement
Transportation 37
Overview Educational Institutions The AECOM team would like to acknowledge
and Hospital Facility the GNOBEDD Board and staff for their input and
25 Programming engagement during this Task. This report has also
Utilities Overview
39 been developed in coordination with the entire
27 Sustainability AECOM team. The team includes: EDAW / AECOM,
Sustainability Overview Programming AECOM Economics, AECOM Transportation, Bright
Moments, Cannon Design, CBRE, Chester Engineers
27 and The Ehrhardt Group. Special thanks also to GCR
SWOT Anlaysis Consulting, whose data supported the development the
programming summary.
4 Working Paper 4 Table of Contents September 2010
Section 01:
BioDistrict
New Orleans
Project Overview
6 Working Paper 4 BioDistrict Overview September 2010
BioDistrict New Orleans. The Louisiana Superdome, New Orleans Arena and key existing and
proposed institutional developments are shown in blue.
7
The Planning Effort The planning effort is broken down into three phases:
Initiation & Discovery, Concept Exploration and
The objective of this planning effort is to create a short- BioDistrict Master Plan. The fourth and final phase of the
and long-term vision and “Action Plan” for the BioDistrict plan, Execution, will commence once the BioDistrict Plan
that identifies a realistic and achievable framework has been completed. The Discovery phase of the project
for economic development within the District. The has been completed and a summary of findings from
BioDistrict Plan will identify and analyze sustainable each of the completed tasks is provided in this Section.
public realm improvements such as vehicle, pedestrian,
and infrastructure connectivity; increasing affordable and
market-rate rental and home ownership opportunities;
streetscape design; green space and community
space; retail and commercial uses; and creative ideas to
enhance the BioDistrict for future biosciences industry
creation and economic development.
The BioDistrict Master Plan Process. The three phase master planning process for the BioDistrict Plan is expected to take 15 months.
9
Section 02:
Task 1 Summary:
Stakeholder
Interviews
10 Working Paper 4 Task 1 Summary September 2010
Task 1 Findings
Task 1 Overview BioDistrict New Orleans staff, developed a list of
stakeholders to be interviewed as part of the initial public
The purpose of Task 1 was to initiate the comprehensive outreach process for development of the BioDistrict Plan.
Plan for BioDistrict New Orleans and to understand the During the three weeks of March 15, March 22, and April
framework within which the planning process will be 12, the AECOM Team coordinated and conducted over 75
prepared. Four elements comprised this first task: (1) separate meetings with over 160 individual stakeholders.
a series of kick-off meetings; (2) extensive stakeholder
interviews; (3) the establishment of a public participation Stakeholder groups included community / neighborhood
program; and (4) an understanding of the media coverage associations; education, medical and faith-based
to date on BioDistrict New Orleans. institutions; relevant city, regional, state, and federal
agencies; business / commercial entities; industry
Task 1 Findings leaders; and workforce development and job training
agencies.
Kick-Off Meetings
Key Themes / Issues / Opportunities
Members of the AECOM Team participated in the
BioDistrict New Orleans Board of Commissioners Over the course of the interviews, several recurring
meeting on Monday, March 15, 2010, marking the issues, opportunities, and needs were identified that
beginning of an approximately 15-month planning must be addressed to ensure that BioDistrict New
process to establish a comprehensive plan for the Orleans is a success. These include:
BioDistrict. Additional kick-off meetings were held with 1. “Creating a Visible Place” - Developing
Yolanda Rodriguez of the City Planning Commission and creative concepts and ideas for the plan and its
her key staff to review the project scope, schedule, and implementation that define the BioDistrict as a
stakeholder engagement plans for the BioDistrict Plan. distinct place reflecting the unique character and
This was a critical meeting to determine how the plan quality of New Orleans;
relates to the City of New Orleans’ newly adopted 2030
2. “Increase Public and Civic Leadership” - Using
Master Plan and Comprehensive Zoning Ordinance.
public-private partnerships with strong business
leadership that align with the new administration’s
The team also participated in a productive meeting with
strategic goals;
transition leaders for Mayor-elect, Mitch Landrieu. This
introductory meeting afforded the team and transition 3. “Acting as One” - Funding and incentives for
leaders an opportunity to exchange valuable data, BioDistrict New Orleans’ continuing operations,
timelines, and views on a wide range of issues affecting as well as for business attraction and community
the BioDistrict, which will also have an impact on the revitalization;
entire City. 4. “Enhanced Review Procedures” - Establishing
processes and procedures that expedite the City’s
Stakeholder Meetings approval process for developments within the
As part of Task 1, the consultant team, aided by BioDistrict;
12 Working Paper 4 Task 1 Summary September 2010
5. “Creating a Biosciences Industry” - Developing milestones in the project schedule, as well as regular,
a strategy to encourage key stakeholders, public ongoing contact with the client, stakeholders, and
agencies, research institutions, and private governing agencies.
companies to work together for the successful
establishment of a biosciences industry; As part of Task 1, research was done to catalog
6. “Be Responsive to Historic Context” - Adaptive and understand early-image building efforts for the
reuse of some of the buildings, with a focus on BioDistrict, establish a media outreach program, and
Charity Hospital and VA complexes; strategize the development of key messages regarding
BioDistrict New Orleans.
7. “Employment Opportunities” - Job training
programs and policies to ensure a workforce that The Public Participation Program also recommends the
is ready to accommodate the emerging needs of establishement of Advisory Groups for the BioDistrict
the biosciences industry; focused on the following areas:
8. “Ongoing Public Engagement is Critical” - An • Community,
effective and engaging public participation and
outreach program that is an integral and ongoing • Commercial/Economic Development,
part of this planning effort; and, • Government/ Institutional interests, and
9. “Getting the Word Out” - A marketing strategy • Health Sciences
that is backed by media programs that creates
strong community awareness through consistent These groups would help act as a sounding board during
positive messaging. the development of the comprehensive BioDistrict Plan.
Section 03:
Task 2 Summary:
Data Gaps
14 Working Paper 4 Task 2 Summary September 2010
Task 2 Findings
Task 2 Overview the New Orleans Historic District and Landmarks
Commission (HDLC) and the National Register of
The purpose of Task 2 is to collect all information, reports, Historic Places;
and mapping relevant to the BioDistrict New Orleans. • Existing and proposed residential and retail
This data will be the foundation for the Team’s analysis developments within the Biosciences District;
and plan development used in subsequent tasks.
• Existing institutional boundaries, including existing
hospital and medical school locations;
Data Collection Efforts To Date
• Proposed campus boundaries for the University
Data collected during this task will assist the AECOM Medical Center (UMC) and Veterans Administration
Team in understanding the physical and natural (VA) hospitals, as well as the Louisiana Cancer
characteristics of the BioDistrict, and the regulations and Research Center and New Orleans BioInnovation
existing and proposed developments that will impact Center, both currently under construction; and
how the BioDistrict is developed in the future. Specific • Blighted property information, including properties
information collected to date includes: designated as blighted by the New Orleans
• BioDistrict boundary; Redevelopment Authority, properties considered
blighted pre-Katrina, and properties defined as
• 2009 aerial;
blighted by Chapter 28 of the New Orleans City
• Property ownership information, including city, Code.
state, and institution;
• Existing utilities/infrastructure, including sewage, A full list of collected data can be found in Working Paper
power, water, gas, and storm water drainage; 2.
• Building footprints;
Reports and Studies Collected To Date
• Roadways and evacuation routes;
• Transit, including streetcar and existing and A summary of the numerous plans, studies, and reports
proposed bus and bike routes; have been developed and written that are relevant to
the BioDistrict and its larger context area was provided
• Natural resource information such as soils,
in Working Paper 2. Some of these documents can
topography, and hydrology;
be regulatory in nature, related to proposed real
• Floodplain information, including flood depths just estate or infrastructure developments in or around the
after Katrina and Advisory Base Flood Elevations BioDistrict, or related to the biosciences industry and its
(ABFE); establishment in New Orleans.
• Regulatory framework information, including
existing and future land use as proposed by the Continued Data Gaps
2030 Master Plan, and applicable building and
zoning codes or design requirements; While a tremendous amount of information was collected
• Historic districts and landmarks as identified by during this task, there are still substantial gaps that need
16 Working Paper 4 Task 2 Summary September 2010
High Priority:
• Plans, preferably in a digital format, are needed for
the following developments:
• New UMC and VA campus programs,
including total area and employment by
category
• Delgado, Tulane, LSU, UNO and Xavier faculty/
staff expansion per master plans.
• New detention facilities complex from Sheriff
Gusman
• New Orleans BioInnovation and Louisiana
Cancer Research Centers
• Jacob’s Study for the Charity Complex and the
former VA, including building condition and square
footages.
Other:
• DDD’s Parking Mgmt Study 2008
• The former Texaco Building on Canal Street
• Common Ground’s Plan for permanent supported
housing on Tulane Avenue
• Blue Plate Loft development by JCH Development
• Domain’s retail development on Tulane Ave
• Boston Consulting New Orleans Tourism Study for
New Orleans Convention and Visitors Bureau
• Redevelopment plans for BW Cooper and Jung
Hotel
• New Congress plans and findings for Claiborne
Ave. – David Waggonner
17
Section 04:
Task 3 Summary:
Anlaysis
18 Working Paper 4 Task 3 Summary September 2010
Task 3 Findings
Task 3 Overview districts are either economically, zoning, or culturally
related.
The purpose of Task 3 is to provide a detailed
assessment of the existing physical, functional and Key Developments
regulatory conditions of BioDistrict New Orleans. The
analysis is based on a detailed review of existing data, There are numerous important developments in the
plans, reports and other information collected during Task Biosciences District that are either recently completed,
1, Stakeholder Interviews, and Task 2, Data Gathering. in-progress (i.e. under construction) or in the planning
The analysis is divided into eight sections: Biosciences process. Development projects fall generally into three
District Overview; Community and Social Context; Urban categories: institutional (schools, universities and
Design; Traffic Analysis; Utilities; Sustainability; and hospitals), non-residential and residential.
Strengths, Weaknesses, Opportunities, Threats (SWOT)
Analysis. Section 2, Biosciences District Overview, Recently completed projects include:
provides an overview of the existing conditions within • Canal Condominiums
the Biosciences District, including its physical and
• Marquis Apartments
regulatory context. Detailed assessments on the
community and social infrastructure, urban design as it • Falstaff Apartments
relates to the areas around the proposed VA Hospital and • Crescent Club
University Medical Center (UMC) hospital campuses,
traffic, utilities, sustainability and a SWOT analysis are Projects currently in progress include:
provided in subsequent sections.
• Benson Tower
Overlay Districts cover most of the BioDistirct. These • Delgado School of Nursing
20 Working Paper 4 Task 3 Summary September 2010
In addition, identifying key streets to allow for improved also serve as a long-term directory for BioDistrict New
stormwater management throughout the BioDistrict is Orleans that can be easily referenced and updated as
critical. Such explorations should be integrated with the needed.
Dutch Dialogue explorations/recommendations for the
City. Urban Design Overview
Community Context Overview The seciton on Urban Design provides the following:
1. An analysis of the architectural character and
A categorical listing of key stakeholders is provided citing context of existing buildings within the BioDistrict.
their roles, mission, accomplishments and recommended
2. Highlights key facilities while defining their general
workshops that should be conducted to develop plans
use and condition.
for the BioDistrict in key areas of concern and focus.
This process is recommended as the next phase of work 3. A building system assessment of select structures
for action-oriented planning that will brand BioDistrict to evaluate their capacity /appropriateness for
New Orleans as the key coordinator and arbiter of the redevelopment, while considering future planned
BioDistrict’s development and substantively advance the improvements within the BioDistrict and how
process with critical input by the community. these will affect the surrounding context.
The list is divided into the following groupings: The six main identified areas of focus include: VA
Hospital Complex, LSU Health Science Center Complex,
• Instiutional / Governance (Governance, City,
Tulane University –Downtown Medical Campus, Xavier
State, Federal, Planning, Utilities)
University, Old Charity Hospital/ VA Hospital Complex,
• Commercial / Economic Development and nodal development along the two primary vehicular
(Economic Development, Workforce arteries (Tulane Avenue and Canal Street).
Development, Financial Institutions The BioDistrict is dominated by a few land uses.
Developers, Primary and Secondary Schools) Institutional, medical and industrial uses, parking (travel
• Health Sciences / Healthcare (Health or movement activities) and vacant land and structures
Sciences (no human activity or unclassifiable activity) make up
• Neighborhood / Community (Housing, Faith- nearly three-quarters of the land in the BioDistrict.
Based, Neighborhood Groups, Preservation,
Social Justice) An overview is provided on the following land uses:
A matrix provides the names, contact information, residential; commercial; industrial, manufacturing
mission, structure, and accomplishments of significant and waste related activities; social, institutional or
stakeholders relevant to the BioDistrict. This database is infrastructure-related activities; parking; religious and
intended to benchmark the capacity of significant health, cultural institutions; leisure and recretional activities; no
community, economic, transit, housing, and education human activity or unclassifiable activity.
institutions and organizations, which we will rely on for
a successful Community Benefits Agreement. It will Maps and matrix summary are provided for existing
22 Working Paper 4 Task 3 Summary September 2010
structures that are considered significant and offer Avenue and Canal Street, are not living up to their
potential individual and shared opportunities within the potential.
BioDistrict. These structures have been identified both 4. Tulane Avenue is a strong central axis which could
on a base map and corresponding matrix along with best link the large academic /medical institutions
the following applied classifications. The classification in the BioDistrict.
terminology utilized is intended to help establish potential
5. Xavier University has significant strength in
for future development and is not intended to define
pharmaceutical formulations and research, but
value (intrinsic, subjective, emotional or otherwise).
could also be well positioned to commercialize
ideas and products with the assistance of partners
Clustering physical and intellectual resources helps to
to take their research to the next level.
build a powerful engine for growth. Specific goals should
be to: 6. Overhead pedestrian bridges contribute to
disinvestment in the pedestrian realm at street
1. Benefit from the intersection/ overlap/ adjacency
level and should only be used as a last resort.
of major institutional entities;
7. The Claiborne Avenue/I-10 exchange is a physical
2. Encourage the smart development and utilization
barrier that bisects the BioDistrict into two distinct
of common ground among these institutions;
halves. A creative solution for the area under
3. Promote a coordinated, mixed-use zoning strategy the overpass should have better illumination
in the areas surrounding major institutional sites; and improving the walking path experience
4. Promote well conceived and convenient with amenities such as a community artwork
transportation modalities; and, installation, mass transit station, etc. would bring
5.
Facilitate a diverse range (size and complexity) of noticeable improvement.
start-up and expanding businesses.
Key observations include:
1. A maximum 15 minute walking distance or a
5 minute trolley loop is the prescribed limiting
distance to where academic /medical related
commercial incubator /research space is most
successful.
2. There are currently few well-thought out and/or
planned outdoor gathering and activity spaces
within the BioDistrict. Linked open and green
spaces, as well as attractive, tree-lined roadways
are physical elements which will facilitate thematic
and real linkage of integrated activities and
Under highway retail in Zaanstadt, Netherlands; combination of retail,
commerce within the BioDistrict. signage and lighting.
Source: http://pruned.blogspot.com/2009/09/under-spaces-1.html
3. Several major street arteries, such as Tulane
23
8. The new VA hospital and University Medical compatibility and to serve as a baseline for
Center Campus plans should address all comparisons with other plans;
significant boundary thoroughfares with an 2. A series of discussions regarding various other
attractive face which enhances the neighborhood projects and proposals that are in process; these
and must address vehicular and pedestrian will continue to require updating; and
traffic as well as the context of the adjoining and
3. An estimate of long-term transportation
surrounding cityscape.
needs based on an estimate of changes in the
9. Canal Street is a critical streetscape that must be transportation demand model variables and
addressed more attractively. based on the mid and long-term BioDistrict Plan
10. A comprehensive street improvements effort, proposals.
including defining gateways and incorporating
wayfinding signage, lighting and sidewalk UMC and SLVMC Traffic Impact Analysis Review:
improvements is warranted to improve the
cohesiveness of the BioDistrict. The following are the key findings from the two Traffic
11. The street intersection at S Claiborne Avenue and Impact Analyses:
Tulane Avenue represent a physical and symbolic • Neither project will adversely impact either Tulane
connection between the downtown Tulane and Avenue or Canal Street in terms of exceeding the
LSU campuses. This could be a prime location capacity of either roadway.
for collaborative development between these • The surrounding area traffic network within the
institutions. BioDistrict will not be significantly adversely
12. A reasonable solution to the abandoned Charity affected by the net gain in trips generated by either
Hospital and VA complex needs to be adopted, or both projects.
along with a timetable for its implementation. • The traffic analyses both indicate that Canal Street
and Tulane Avenue and the majority of the area
Follow-up activity should include a BioDistrict New streets both currently and after construction will
Orleans team review of this inventory and an in-field, operate at a Level of Service (LOS) C or better.
multidiscipline team survey of selected buildings from
this inventory. US 61/ Tulane Avenue Corridor Improvemennts:
The current Transportation Improvement Program (TIP) between LaSalle and Galvez streets, or a demand
only provides funding for the planning portion of the responsive shuttle; an internal system along the
Tulane Avenue improvement project, not construction. Cleveland Avenue ROW; or a vehicle fleet, which
Therefore, it is possible that the proposed improvements can be shared by the various individuals making the
may not be completed prior to the completion of the two trips, either on an internal route or public streets.
medical centers due to lack of funding. This could cause
increased congestion and difficulty in accessing parking Xavier University:
for the hospitals due to restricted turning movements
forcing U-turns to access parking. Both short and longer-term plans must be made to
satisfy the travel demand for students, faculty and others
At present, UMC, SLVMC, and the Louisiana Cancer between Xavier University and the five institutions.
Research Center (LCRC) have three different landscape
plans for Tulane Avenue and another consultant was Transportation improvements that Xavier is pursuing, or
hired by DPW to prepare concept drawings, suggesting a at least considering, include the following: a pedestrian
possible fourth plan. bridge in the vicinity of Fern Street; a traffic signal at
Washington Avenue and Pine Street; a pedestrian
Trips Betweeen the Hospitals and Medical Schools: corridor; and a parking facility among others.
A discussion was provided on how individuals woudl Criminal Justice Area Parking:
move between the proposed hospitals and the existing
medical schools. Key findings are below: There is a serious lack of parking and the difficult
• There are three institutional shuttles: tulane circulation patterns in the immediate area of the
University, VA Hospital and LSU HSC criminal justice facilities. The sheriff is considering the
addition of a parking garage to the ongoing redesign and
• Once the UMC is completed, the LSU plans to reconstruction of the Orleans Parish Prison complex.
terminate their shuttle service.
• Walking between the existing medical districts in Coroner’s Office:
the CBD and the new hospitals will be much more
difficult. There are several concerns with the current site selected
• Anyone moving between these facilities with a for the coroner’s office. There is a possibility of relocating
walk of 10 to 15 minutes or more; a bicycle ride; the proposed facility to a site in conjunction with the
a transit ride after a minimum wait of 15 or 20 contemplated criminal justice area parking garage.
minutes; or a need to use an automobile.
RTA:
• Prior to detailed analysis, the alternative solutions
appear to be: shorter RTA headways of 3 to 5
RTA service in the BioDistrict will evolve as RTA
minutes on Canal Street and Tulane Avenue lines
restructures the citywide service plan, including the use
and an extension of operating hours; a shuttle
of UPT as a transfer terminal in place of Canal Street for
route circulating on Gravier and Canal streets
25
many lines, and the development of the Canal Street to UMC campuses would have to park in the visitor
UPT streetcar service on Loyola Avenue. lots.
• There is an overabundance of poorly designed and
Long-Term Demand and Plan: maintained surface parking lots.
application is straining the system to the extent LONI network. BioDistrict New Orleans should
that sewage has overflowed from manholes near help facilitate Xavier’s membership to the network.
the complex. The SWB claims there is sufficient This would enable Xavier to readily share its data at
capacity for the current flow and the overflows are a high rate of speed with research universities all
being caused by the amount of debris that is being over the state and the surrounding region.
placed into the system. • Xavier is in negotiations with Entergy concerning
• Orleans Parish Prison Complex (OPP) must the installation of a second electrical feeder to its
maintain operations concurrent with design campus as a reliability upgrade. The second feeder
modifications. Most of their construction is will provide much needed redundancy
financed by FEMA which reserves design approval
prior to providing funding. It is imperative that if Further information on these key developments and
there are opportunities for OPP to benefit from associated mapping will be provided when the complete
any green technology initiatives, immediate action body of information is available. The AECOM team will
should be taken in planning to provide adequate re-visit this task component at an appropriate time.
lead-time while the design(s) can still be easily
amended within an anticipated more restrictive The Team also investigated whether there were other
time-frame. entities having utility related involvements that might
have bearings on our work (such FEMA, COE, etc.)
VA Hosptial: related to such issues as outstanding contractual or
• The SWB has resolved all the utility upgrade obligation restrictions, design limitations or development
concerns of the VA Hospital. constraints. The Team has found none within the
BioDistrict.
• All aerial electrical lines within its footprint will be
removed, and there are plans to move the existing Utility Costs and Concerns:
overhead lines adjacent to the property on S.
Galvez Street below ground. Every address location within the BioDistrict has access
• The new hospital is a LEED building and will to all basic utilities: water, wastewater, stormwater,
require 18% less drainage than its predecessor. electricity, gas and telecommunications. While
It will also have tanks holding approximately two availability is not an issue, adequate supply can pose a
million gallons for gray water applications. problem depending on the functional demands of future
development beyond that of existing facility use.
UMC: Moving forward, we will analyze demand requisites for
• The SWB has resolved all the utility upgrade such specific additional structures/projects when the
concerns of the UMC. locations are identified to determine whether or not the
existing utilities are adequate and/or other issues of
Xavier University: concern come to light.
Utilities and Sustainability: identified. The matrix should be seen as a working tool to
help facilitate discussion and idea generation, both with
Sustainable street lighting options were examined, Team members and with stakeholders, but clearly shows
including specifications on lights that meet the necessary even at this stage the tremendous opportunity that exists
hurricane wind loads. However,he lumen output does for the creation of a truly sustainable place.
not meet current City of New Orleans standards. The
city is currently replacing mercury vapor lights with more SWOT Analysis
energy efficient, high pressure sodium fixtures.
A SWOT analysis is provided to identify the key
Sustainablility Overview threats, weaknesses, strengths, and opportunities
for the development of the BioDistrict. The SWOT
Sustainability is an important principle for the City. By analysis provides an understanding of key fundamental
integrating sustainability principles upfront into the opportunities and challenges that will need to be
design and planning of the BioDistrict, there is great addressed in order to establish and implement a
opportunity to optimize its long term performance and successful bioscience cluster in New Orleans.
efficiency, so that residents, students and workers,
businesses and city agencies can operate in a Threats include:
sustainable, equitable and low impact way. • Significant competition from other states.
• The large up-front funding requirement and
In order to help understand what the sustainability
long product development to market timeframe
objectives and targets for the BioDistrict should be, it
presents risks to funding.
is important to consider the current conditions of the
BioDistrict, potential opportunities and constraints in a • The BioDistrict is lacking long-term funding
holistic way, integrating the specialties of the different commitments.
Team members. Drawing out such cross disciplinary • While the state does have a small, active and
relationships and identifying the most relevant growing bioscience industry base, it lacks many
sustainable development opportunities within the key industry components such as those with
BioDistrict are the two primary goals of this task. higher education degrees.
Section 05:
Task 4 Summary:
Programming
30 Working Paper 4 Task 4 Summary September 2010
Task 4 Findings
Task 4 Overview Together with the market assessment, these items
will impact the physical design and development of the
The purpose of Task 4 is to outline the conceptual BioDistrict.
programming for various facilities within the BioDistrict
that will provide the foundation for the design The programming information provided within this
development phase of the overall planning process for working paper outlines the proposed quantity and type
the BioDistrict. Specific areas of focus include: global of space mix desirable within the BioDistrict over 5, 10
medical and bioscience research market trends; potential and 20 year periods. This data will be a fundamental
industries that could be targeted for the BioDistrict; driver of the future population, density, FAR and
medical-, biosciences-, and research-related facilities and other related projections, all of which are inextricably
their anticipated demands; sustainability programming; linked to economic activity, transportation, recreation,
and, community facilities needs. entertainment, retail, housing and other infrastructure
needs for the BioDistrict and the region.
Key items provided relative to global medical and
bioscience research market trends include a review of
the following:
The Real Estate Program for the Biosciences District was The significant increase in employment as well as
developed in coordination with various AECOM team ancillary employment related to the core institutional
members as well as GCR, an independent economic functions create an opportunity for additional market-
consultant, which provided specifics on the local market. driven real estate program throughout the area. The
Utilizing information on office, manufacturing, research, AECOM Team was tasked with evaluating the potential
and development space, a series of case studies of for added retail, residential, long term say, and other
other comparable medical districts, and Team project commercial or office development potential. Additionally,
experience with comparable projects elsewhere, when comparing the BioDistrict to comparable districts
program estimates were developed and assessed. A elsewhere, given the level of employment and activity
program summary is provided at right. Key findings the BioDistrict is currently underdeveloped with respect
and conclusions are also provided within this summary to amenities and spinoff development.
document. Please see the separate appendices for the
detailed report on real estate programming, bioscience Program Summary
research programming and institutional programming.
As the integrated program table on the following page
Employment indicates market-driven and institutional development in
the BioDistrict over the course of the 20-year planning
Figures developed by GCR and Associates indicate a period is estimated to be in excess of 13 million sq.
potential BioDistrict institution-related employment in the ft. Most of this development, nearly 7 million sq. ft., is
order of 17,000+ at full development, with an additional anticipated within the next 5-years. Given the significant
medical, R&D, and medical manufacturing potential of level of development potential there is likely opportunity
nearly 5,000 full time jobs. Thus the direct potential for supportive, coordinated action with respect to major
employment in the BioDistrict is estimated to exceed transportation, infrastructure, and overall development
22,000 jobs, before indirect and induced economic activity.
33
Summary Totals
Total Dev. Sq. Ft. (ex. parking) 6,755,000 3,814,000 2,588,000
Cumulative Dev. Sq. Ft. (ex. parking) 6,755,000 10,569,000 13,157,000
*Note: Includes some parking sq. ft.
Source: AECOM, Cannon Design, CBRE
34 Working Paper 4 Task 4 Summary September 2010
the 2%-3% range, equating to an additional potential of AECOM’s experience elsewhere with similar medical
roughly 500 – 700 additional owner occupied units in the districts indicates that most conferences and related
BioDistrict. For the purposes of this analysis AECOM spaces for medical districts are needed for meetings
distributes these units over years 5 to 20. Given the of 150 to 300 attendees on average; however, some
large number of proposed but undeveloped residential conferences of 500 to 600 attendees could be possible
projects in and around the site area, it is unclear at this if the space were higher in quality and larger than
time how many of these units would need to be in that which currently exists. Using a planning factor of
new, as yet un-proposed developments. Nevertheless capacity for 400 persons per meeting, ratios of 15 sq.
this does provide a range of the order of magnitude of ft.per person for the core banquet and divisible meeting
residential offerings related to the redevelopment of the space, as well as 1.5 to 2 times this figure for additional
BioDistrict. breakout and supportable meeting space, this would
imply potential for 9,000 to 12,000 sq. ft.of contiguous
Long-Term Stay and Meeting Space space in the BioDistrict. AECOM would not recommend
a facility larger than this at the current time given the
In comparing the BioDistrict to other medical districts notable capacity of other hotels in the market as well as
with long term stay offerings the BioDistrict falls within the sizable convention center.
range of comparable development elsewhere – which
makes it unclear that there is a pressing need for new Office, Medical Office, Research and
facility space. However, as noted in this analysis, the Development
type of offering currently available through the Clarion Inn
and Suites (the only current long term stay offering in the Medical districts with a stronger focus on servicing
BioDistrict) does not fit with comparable offerings related the local populations typically have fewer opportunities
to medical districts. Overall, AECOM finds that between for research and development, education programs,
90 and 120 units could be supportable in the BioDistrict incubators, and specialty care and are less likely to
given the level of expected visits from out of the area require greater capacity for office, medical office, and
which is consistent with the case studies indicating an related manufacturing, research, and development space.
average of 110 units per comparable development in As the case studies in this analysis suggest, a successful
medical related long term stay facilities. combination of these elements could significantly grow
the amount of space demanded for medical districts – up of these variables cannot be predicted accurately for a
to 10 times that experienced in smaller medical districts long-term period such as the 20-years for this analysis.
and the range currently experienced in the BioDistrict. Accordingly, the actual development absorption trends in
the BioDistrict will most likely vary significantly from the
To understand the additional range of potential new estimated 5, 10, 20 year ‘benchmark’ guidelines provided
square footage related to planned and future medical above.
related operations CBRE provided the project team
with estimates based on their experience with similar Key developments anticipated or estimated to occur
developments elsewhere. The total potential of net new within the next 5, 10 and 20 years are provided below
demand related to the BioDistrict and not solely for the with a detailed report found in Appendix B, BioDistrict
purposes of local health care service could be in the Bioscience Programming Strategy.
order of 1.6 million sq. ft. Some portion this net new
demand could likely be accommodated in existing and Year 1-5
unoccupied buildings or spaces.
The concurrent development of the Louisiana Cancer
Bioscience Programming Overview Research Center (LCRC) and the New Orleans
BioInnovation Center (NOBIC) incubator facility, along
Based on analysis of the prevailing and potential with the proposed VA hospital and University Medical
opportunities for the evolution of a research park in New Center (UMC) complexes, represent a massive influx
Orleans, the AECOM Team estimates that the bioscience of new medical office and research lab space for a
absorption (in addition to the planned LCRC, New community such as New Orleans. With expected budget
Orleans BioInnovation Center and VA/UMC hospitals) cuts in research at LSU and other institutions – there
within the BioDistrict could total 175,000 sq. ft. by Year 5, will likely be little or no demand for new private sector
another 625,000 sq. ft. for Years 5 to 10, and 800,000 sq. space during the next 5 years. The AECOM Team has
ft. more for Years 11 to 20, for a likely new development also assumed that Tulane and LSU will accommodate
potential of 1.6 million sq. ft. over 20 years. These their internal research facility needs on their respective
numbers are reflected in the programming summary campuses – given the one million sf of surplus space that
chart provided at the beginning of this section. is available now (including Charity).
It must be noted that above estimates are highly There are two new bioscience tenant prospects for
susceptible to changes in market conditions, political BioDistrict New Orleans that could see development
willingness, strength of coalition of educational partners, begin by Year 5.
state workforce preparedness for biosciences industry 1. Pharmaceutical packaging and manufacturing -
from Louisiana universities, public agencies’ support, 50,000 to 200,000 sq. ft. industrial facility within
economic incentives and regulatory facilitation, growth of the industrially zoned land riverside of Xavier
biosciences industry in U.S. and in Louisiana, access to University (part of a +50-acre pharma industrial
venture capital and Angel investors, and breakthroughs area)
in research by any of the local research centers. Most
2. Regenerative Sports Research Facility – a
37
100,000 sq. ft. facility for treatment of veterans, Park clusters (i.e. 25,000 – 50,000 sq. ft. per year) during
as well as the New Orleans Hornets and New the second decade of operation – reaching a total of
Orleans Saints (part of a 25-acre campus to be 500,000 sq. ft., plus 100,000 sq. ft. of medical office,
located lakeside of the Louisiana Health Sciences 175,000 sq. ft. for the Sports Medicine and 750,000 sq. ft.
Center as shown on the attached site plan). TIF for pharmaceutical and medical device manufacturing and
funding is important, since this facility is expected packaging. If no cooperation occurs with LSU and Tulane
to bring in significant out of state visitors/ there will be no growth in the R&D area.
customers.
In addition there would be demand for extended stay
Other research opportunities for New Orleans that hotel facilities for the hospitals and research facilities, and
should be pursued include a Neuro-science Center and a assisted living/senior housing facilities associated with
Regional Center for Coastal Health to study the ongoing Tulane or LSU alumni, as well as commercial support
effects of the BP oil disaster and its cleanup efforts. facilities including a virtual conference center.
Year 11-20
major institutions located in the BioDistrict are on the with associated retail, recreational and entertainment
cusp of undertaking significant building campaigns amenities was viewed as necessary to success both for
to replace facilities and energize their presence in the institutions and the BioDistrict as a whole.
New Orleans. The AECOM Team has identified key
developments in the major health care and educational Key Findings:
institutions within the BioDistrict - the Veterans
Administration, University Medical Center, Louisiana • It is worth special note that the Ochsner system
State University, Tulane, Xavier and Delgado Community has evidenced significant interest in collaborating
College. Ochsner Health System, with which current and on research studies. This, as well as similar
future healthcare, education and research partnerships interest by Pennington, can contribute substantially
will likely occur, is also reviewed. Activities are to the success of other research entities that are
discussed in terms of a five, ten and twenty-year period physically located within the BioDistrict.
from the release of the BioDistrict Master Plan. (The
overall program breakdown is provided at the beginning • VA, UMC, LCRC and New Orleans BioInnovation
of this Section and detailed information can be found Center will create common sites for institutional
in Appendix C: Educational Institutions and Hospital collaboration.
Facilities Programming.) • Development of VA, UMC, LSU, Tulane, Delgado
Nursing School and Xavier campus identities within
Recurring areas of interests and/or current strengths an overarching and cohesive BioDistrict identity
among patient care specialties, education and will require substantial development of open
research were noted among the institutions, and those green spaces, landscape, hardscape, alternative
overlapping interests have been correlated in the “Shared transportation connections and pathways, signage
Thematic Interests” chart included in this section. The and lighting as well as new and renovated
purpose of this chart is to note common themes among buildings.
institutions in the BioDistrict that generate collaborative • Joint investments in public transportation and
opportunities for distinctive joint programs that neighborhood/community residential, recreational
attract more than regional interest, and thus enhance and entertainment development will strengthen all
revenues and employment within the BioDistrict. Also institutions and businesses in the BioDistrict.
noted was a significant emphasis on development of
• If “critical mass” is achieved in the BioDistrict, it
the physical presence and identity of the BioDistrict
will predictably generate research outcomes that
in response to the vacant, industrial and generally
can be commercialized. Other sections of this
unwelcoming impression of much of the real estate
report address the issue of predicting the level of
currently surrounding each institution. An internal focus
new commercial activity this may produce.
on campus identity was presented by each institution’s
master plan, and an interest in uniting the improvements • At this time, the data regarding new short- and
to facilitate branding of the BioDistrict as a safe, long-term employment projections are not
cohesive, accessible and welcoming place is supported. finalized; however, it is a concern that workforce-
Development of a thriving, diverse residential community training demands have not as yet been sufficiently
LCRC
Retail
Office
Xavier
USES
VASites
Housing
Delgado
Ochsner
EcoPark
OtherLSU
UMCSites
Hospitality
OpenSpace
OtherTulane
Infrastructure
SocialServices
Entertainment
CivicStructures
OldVAHospital
CityofNewOrleans
CharterHighSchools
ParksandRecreation
DevelopmentDistrict
CriminalJusticeCenter
OtherResearchFacilities
CharityHospitalComplex
NFLSportsWellnessCenter
IndustrialͲLighttoModerate
WorkforceDevelopmentSites
BioscienceCommercialization
NewOrleansBioInnovationCenter
Interests
GreaterNewOrleans,Inc.+Downtown
INSTITUTIONS,AGENCIES&LAND
SharedThematic
TOPICS
Healthcare
Research/Biomedical/Bioscience
PrimaryCare
NursingEducation
CancerResearch
BenchtoBedsideMedicineFocus
GeneResearch/Therapy
StemCellResearch/Therapy
Prosthetics
CardiologyResearch/HeartDisease
Endocrinology
NanoMedicine/Nanoparticles
SportsMedicine
Orthopedics
Neuroscienceand/orBrainTrauma
InfectiousDisease
Dentistry
Forensics
BariatricResearch/Treatment
MedicalDeviceResearch
MedicalDeviceManufacturing
PharmaceuticalResearch
PharmaceuticalManufacturing
CommunityOutreach
ClinicalTrials
Diabetes
Alzheimer's
Alcohol/SubstanceAbuse
Nutrition/Aging
Stroke
ConnectiveTissue
EffectsofDisaster
EMDR
ExercisePhysiology
ResearchAnimalFacility
PediatricsResearch
BrainTrauma
Education/Teaching
Education/TeachingͲVetMedicine
Education/TeachingͲPharmacy
Education/TeachingͲEngineering
Education/TeachingͲMedical
Education/TeachingͲMedicalIndustryTech
HigherEducation
TransferTechnology
ForͲProfitBusiness
NotͲforͲProfitBusiness
CohesiveCampusSetting
NeedsAccesstoMassTransit/Bikes
NeedsAccesstoParking
NeedsHousing,Amenities&Safety
NeedsChildcare
NeedComputerSciences/InfoTech
NeedHeliport
StrongCommunityInvolvement
NeedsSkilledWorkforce
NeedsAccesstoHospitals
SustainableDesign
Convention/Meeting
LongͲtermmedicalͲrelatedhotel
?
HistoricFocusͲLandmark
Notes
somehousinghaslandmarkstatus
needplasticsmoldingtosupportresearch
prisonsandparking.Sewersystemamajorproblem.
sustainablerealestatedevelopmentcoursew/Tulane
interestedinoutreachtootherinstitutionsandcommunity
sciencehighschoolͲbioscienceandmedicalcampusexposure
newfacilitiesforseveraldept'sinworksͲNOPDfacility,Warehousing,powerplant,
developCharityComplex,VABuilding.NewCityHall,MedicalMart,Residential,hotel
gauged and need additional refinement. These other regions increasingly cope with similar future
projections may produce more building demand challenges;
than has currently been predicted. • Playing an active leadership role in helping the
• Proposed developments highlighted in this Section City and BioDistrict New Orleans efficiently move
of the report total over 6 million sq. ft. of built toward a more sustainable future that sets a global
space and also anticipate a substantial increase precedent; and
in new open-space requirements in the overall • Environmental challenges have put New Orleans
development of the BioDistrict over the 20-year in the spotlight during the last decade, leverage
period analyzed here. exemplary biological and environmental success in
the BioDistrict to turn this into an opportunity and
success story.
Sustainability Programming
This expanded definition of BioDistrict, and the role of
Due to a combination of converging opportunities, sustainability within that definition is more specifically
BioDistrict New Orleans has a unique opportunity to set laid out in the following discussion.
a new precedent for integrated sustainable development,
research, innovation, and leadership. A key objective Four “Corners” of Sustainability for the
of the master plan will be to make the BioDistrict a BioDistrict
sustainable community. However, by expanding the
sustainability approach to include the business, research During the last team workshop four “corners” of the
and educational activities in the BioDistrict, the project BioDistrict were identified which included Economic
may also place itself as a global center of excellence Development, Jobs and Training, Community Building,
for emerging “bio”-oriented sustainability challenges. and Civic Leadership. Sustainability is a foundational
These two aspects of sustainability help frame a broader component of each of these four corners that helps to
definition of what the BioDistrict could be, and the shape the expanded definition of what the BioDistrict
economic and sustainability benefits that it might provide could be.
to the community, the City, the region and globally.
Specifically, the project team has identified this broader Economic Development
definition of sustainability in the BioDistrict to include: Diverse markets and research areas related to bio-
• Biologically and environmentally optimized innovation and sustainability are rapidly emerging.
community design and operations; Identifying and incorporating strategies to place
• Leveraging the region’s and City’s context as the BioDistrict at the forefront of these emerging
one of the most environmentally challenged and sustainability driven markets is a key goal. Some
vulnerable locations in the world to become a opportunity areas include:
center of excellence for innovation, education, and • Climate change and the ways in regions respond
research, particularly related to biosciences, to to these changes (Climate Change Adaptation)
provide workforce, knowledge, and technologies as are anticipated to increase and evolve health,
40 Working Paper 4 Task 4 Summary September 2010
environmental, and social challenges worldwide; with widespread applicability (i.e. flood control,
• The New Orleans Region’s flood and hurricane coastal health, disaster recovery, food deserts,
prone landscape will continue to require innovative etc), could aim to train a workforce and future
environmental and bio-engineering solutions with leaders to address emerging environmental
increasing global applicability; challenges.
Establishing targets and goals for performance is a The following two matrices include a summary of the
common theme for all projects that have sustainability as preliminary sustainability objectives, environmental
a central theme. These targets provide a strong and clear performance targets, and a summary of supporting
statement about what the project intends to achieve and mechanisms for achieving the targets. These qualitative
by which it can be measured against other projects. The objectives and quantitative targets represent an initial
sustainability matrices in the following pages outline framework for creating a high performance sustainable
initial targets for sustainability performance that could development plan for the BioDistrict. All targets and
place BioDistrict New Orleans as a global leader in objectives are preliminary and are based on the findings
sustainable community design. presented in the opportunities and constraints matrix
prepared in the previous sheet for Task 3. Further review
Civic Leadership of relevant sustainability polices, guidelines and analysis
The cornerstones of economics and innovation, jobs and was also performed to identify specific recommendations
community could place the BioDistrict as an exemplar for environmental performance relevant to the site.
in sustainability and bio-oriented land use, education,
research, innovation, and business activities. Strong Targets are intended to be refined and vetted as the
leadership mechanisms will be needed in order for project proceeds, especially following upcoming internal
BioDistrict New Orleans to achieve these goals. Some of and external work sessions. Vetting may reveal that
these might include: some targets and objectives are not appropriate, and
new ones may be revealed and added.
• Establishing ordinances and guidelines for
sustainable community/project development
The next step in the process should be to identify with
specific to the BioDistrict
the project team, the packages of measures/technologies
• Administering a long-term, coordinated monitoring that could achieve these targets. A key decision will
and adaptive management framework (for example be to identify an approach for selecting the preferred
implementation of the LEED ND guidelines, sustainability package of measures. Determining the
or compliance with customized sustainability preferred approach falls within this scope of work,
ordinances) however implementing the approach would need to
• Coordinating district wide activities that can be completed within a subsequent scope work. Two
achieve multiple/expanded benefits through approaches are typically employed in similar projects.
leveraging economies of scale and integrated
multidisciplinary opportunities The first includes a quantitative cost-benefit analysis
Task 4 Summary: Programming
SustainabilityTopic Objective TargetͲ5Years TargetͲ10Years TargetͲ20Years Notes/Benchmarks*
*Proposedobjectivesandlevelsofachievementtobevettedandrefinedasprojectproceeds.
42 Working Paper 4 Task 4 Summary September 2010