"PILEGRP" --- PILE GROUP ANALYSIS PROGRAM

Program Description:

"PILEGRP" is a spreadsheet program written in MS-Excel for the purpose of analysis of pile groups with rigid
caps using the "elastic method". Specifically, the properties of the pile group are calculated, and then based
upon the applied vertical and horizontal loadings, the vertical and horizontal pile reactions are calculated.
There is also a worksheet to check beam and punching shear in the pile cap for a single corner pile, for the
purpose of estimating the required pile cap thickness and subsequent pile cap weight.

This program is a workbook consisting of ten (10) worksheets, described as follows:

Worksheet Name Description


Doc This documentation sheet
Piles (<=25) Pile group analysis for up to 25 total piles and 4 piers/loadings
Piles (<=25)(metric) Pile group analysis for up to 25 total piles and 4 piers/loadings (metric)
Piles (<=75) Pile group analysis for up to 75 total piles and 8 piers/loadings
Piles (<=75)(metric) Pile group analysis for up to 75 total piles and 8 piers/loadings (metric)
Piles (<=300) Pile group analysis for up to 300 total piles and 17 piers/loadings
Piles (<=300)(metric) Pile group analysis for up to 300 total piles and 17 piers/loadings (metric)
Piles (<=400) Pile group analysis for up to 400 total piles and 23 piers/loadings
Piles (<=400)(metric) Pile group analysis for up to 400 total piles and 23 piers/loadings (metric)
Corner Pile Shear Beam and punching shear checks for pile cap for single corner pile

Program Assumptions and Limitations:

1. The Pile Group worksheets assume a minimum of 2 piles and a maximum of either 25, 75, 300, or 400 piles
for a pile group.
2. This program uses the "elastic method" of analysis, assuming that the pile cap is in fact "rigid", so that the
applied loads are linearly distributed among the piles. A common "rule-of-thumb" is to assume a pile cap
thickness equal to least 1/10 of the longest dimension (length or width) of the pile cap. All piles are assumed
to be vertical, and of equal size and length (stiffness). Battered piles are NOT permitted. The tops of all piles
are assumed at the same level.
3. This program assumes an orthogonal X-Y-Z coordinate system. All piles and piers MUST BE located in the
"positive" (1st) quadrant. "Negative" pile or pier/loading location coordinates are NOT permitted.
"Right-Hand-Rule" sign convention is used for all applied forces and moments at pier locations.
4. The piles and piers/loadings can be numbered in any desired order. However, the user should make
sure to either clear the contents of all spreadsheet cells that are not used for input or those cell values should
be input = 0. All piles and piers/loadings MUST BE input in proper numerical sequence with no "breaks" in
the numerical order of input data.
5. This program does NOT include the weight of the pile cap or piers in the calculation of the vertical pile reactions.
However, the total weight of the pile cap and piers may be included by assuming an additional "ficticious" pier
located at the centroid of the pile cap plan area, and applying the total weight at that "pier" location.
6. This program does NOT check the actual calculated pile reactions (vertical and horizontal) against known
or given allowable pile reactions for downward, uplift, or lateral cases. This is done so that the extent of any
acceptable overstress is left up to the judgement of the user. However, in all cases this must be checked by
the user.
7. This program does NOT perform all of the necessary checks for the beam-type shear or punching shear for the
pile cap, as this must be done independently by the user. However the "Corner Pile Shear" worksheet can be
used to estimate the required pile cap thickness and subsequently the pile cap weight to be accounted for.
8. This program does NOT check the flexural requirements of the pile cap, as this must be done independently by
the user.
9. This program contains numerous “comment boxes” which contain a wide variety of information including
explanations of input or output items, equations used, data tables, etc. (Note: presence of a “comment box”
is denoted by a “red triangle” in the upper right-hand corner of a cell. Merely move the mouse pointer to the
desired cell to view the contents of that particular "comment box".)
"PILEGRP.xls" Program
Version 3.6

PILE GROUP ANALYSIS FOR RIGID PILE CAP


Using the Elastic Method for up to 25 Total Piles
(For English Units)
Job Name: Subject: Pile No.:
Job Number: Originator: Checker: ###
###
Input Data: ###
Results: ###
Number of Piles, Np = 6 PILE GROUP PLAN
Pile Coordinates: Pile Reactions (k) 25.0
###
Xo (ft.) Yo (ft.) Vert. Rz Horiz. Rh ###
#1: 0.000 0.000 #1: 120.83 6.01 ###
#2: 6.000 0.000 #2: 110.42 6.01 20.0
###
#3: 12.000 0.000 #3: 100.00 6.01 ###
#4: 0.000 8.000 #4: 100.00 6.01 ###
#5: 6.000 8.000 #5: 89.58 6.01 ###
15.0
#6: 12.000 8.000 #6: 79.17 6.01 ###

Y - AXIS (ft.)
###
###
10.0
###
###
###
5.0
###
###
###
0.0 ###
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0
###
X - AXIS (ft.) ###
Pile Group Properties:
Xc = 6.000 ft.
Yc = 4.000 ft.
Ix = 96.00 ft^2
Iy = 144.00 ft^2
J = 240.00 ft^2
Ixy = 0.00 ft^2
θ = 0.000 deg.
Iy =
Number of Piers, N = 1 Σ Pier Loads @ C.G. of Group:
Σ Pz = -600.00 kips
Pier/Loading Data: Pier #1 Σ Hx = -20.00 kips
X-Coordinate (ft.) = 6.000 Σ Hy = -30.00 kips
Y-Coordinate (ft.) = 4.000 Σ Mx = 250.00 ft-k
Dist. to T/Piles, h (ft.) = 5.000 Σ My = -250.00 ft-k
Vertical Load, Pz (k) = -600.00 Σ Mz = 0.00 ft-k
Horiz. Load, Hx (k) = -20.00 Σ Hy =
Horiz. Load, Hy (k) = -30.00 Pile Reaction Summary:
Moment, Mx (ft-k) = 100.00 Rz(max) = 120.83 kips
Moment, My (ft-k) = -150.00 Rz(min) = 79.17 kips
Moment, Mz (ft-k) = 0.00 Rh(max) = 6.01 kips

3 of 24 03/30/2011 06:25:45
"PILEGRP.xls" Program
Version 3.6

PILE GROUP ANALYSIS FOR RIGID PILE CAP


Using the Elastic Method for up to 25 Total Piles
(For Metric Units)
Job Name: Subject: Pile No.:
Job Number: Originator: Checker: ###
###
Input Data: ###
Results: ###
Number of Piles, Np = 6 PILE GROUP PLAN
Pile Coordinates: Pile Reactions (kN) 8.0
###
Xo (m) Yo (m) Vert. Rz Horiz. Rh ###
#1: 0.000 0.000 #1: 537.49 26.73 7.0 ###
#2: 1.829 0.000 #2: 491.16 26.73 ###
#3: 3.658 0.000 #3: 444.82 26.73 6.0 ###
#4: 0.000 2.438 #4: 444.82 26.73 ###
#5: 1.829 2.438 #5: 398.49 26.73 5.0 ###
#6: 3.658 2.438 #6: 352.15 26.73 ###

Y - AXIS (m)
4.0 ###
###
3.0 ###
###
2.0 ###
###
1.0 ###
###
0.0 ###
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0
###
X - AXIS (m) ###
Pile Group Properties:
Xc = 1.829 m
Yc = 1.219 m
Ix = 8.92 m^2
Iy = 13.38 m^2
J = 22.30 m^2
Ixy = 0.00 m^2
θ = 0.000 deg.
Iy =
Number of Piers, N = 1 Σ Pier Loads @ C.G. of Group:
Σ Pz = -2668.93 kN
Pier/Loading Data: Pier #1 Σ Hx = -88.96 kN
X-Coordinate (m) = 1.829 Σ Hy = -133.45 kN
Y-Coordinate (m) = 1.219 Σ Mx = 338.95 kN-m
Dist. to T/Piles, h (m) = 1.524 Σ My = -338.95 kN-m
Vertical Load, Pz (kN) = -2668.93 Σ Mz = 0.00 kN-m
Horiz. Load, Hx (kN) = -88.96 Σ Hy =
Horiz. Load, Hy (kN) = -133.45 Pile Reaction Summary:
Moment, Mx (kN-m) = 135.58 Rz(max) = 537.49 kN
Moment, My (kN-m) = -203.37 Rz(min) = 352.15 kN
Moment, Mz (kN-m) = 0.00 Rh(max) = 26.73 kN

4 of 24 03/30/2011 06:25:45
"PILEGRP.xls" Program
Version 3.6

PILE GROUP ANALYSIS FOR RIGID PILE CAP


Using the Elastic Method for up to 75 Total Piles
(For English Units)
Job Name: Subject: Pile No.:
Job Number: Originator: Checker: ###
###
Input Data: ###
###
Number of Piles, Np = 40
Pile Coordinates: Pile Coordinates: Pile Coodinates:
Xo (ft.) Yo (ft.) Xo (ft.) Yo (ft.) Xo (ft.) Yo (ft.)
#1: 0.000 0.000 #26: 6.000 15.000 ###
#2: 0.000 3.000 #27: 6.000 18.000 ###
#3: 0.000 6.000 #28: 6.000 21.000 ###
#4: 0.000 9.000 #29: 6.000 24.000 ###
#5: 0.000 12.000 #30: 6.000 27.000 ###
#6: 0.000 15.000 #31: 9.000 0.000 ###
#7: 0.000 18.000 #32: 9.000 3.000 ###
#8: 0.000 21.000 #33: 9.000 6.000 ###
#9: 0.000 24.000 #34: 9.000 9.000 ###
#10: 0.000 27.000 #35: 9.000 12.000 ###
#11: 3.000 0.000 #36: 9.000 15.000 ###
#12: 3.000 3.000 #37: 9.000 18.000 ###
#13: 3.000 6.000 #38: 9.000 21.000 ###
#14: 3.000 9.000 #39: 9.000 24.000 ###
#15: 3.000 12.000 #40: 9.000 27.000 ###
#16: 3.000 15.000 ###
#17: 3.000 18.000 ###
#18: 3.000 21.000 ###
#19: 3.000 24.000 ###
#20: 3.000 27.000 ###
#21: 6.000 0.000 ###
#22: 6.000 3.000 ###
#23: 6.000 6.000 ###
#24: 6.000 9.000 ###
#25: 6.000 12.000 ###
###
No. Piers = 2 ###
Pier/Loading Data:
Pier #1 Pier #2
X (ft.) = 4.500 4.500 ###
Y (ft.) = 9.000 18.000 ###
h (ft.) = 5.000 5.000 ###
Pz (k) = -1500.00 -1500.00 ###
Hx (k) = -20.00 -20.00 ###
Hy (k) = -30.00 -30.00 ###
Mx (ft-k) = 100.00 100.00 ###
My (ft-k) = -150.00 -150.00 ###
Mz (ft-k) = 0.00 0.00 ###
###
###

5 of 24 03/30/2011 06:25:45
"PILEGRP.xls" Program
Version 3.6

(continued)

6 of 24 03/30/2011 06:25:45
"PILEGRP.xls" Program
Version 3.6

###
PILE GROUP PLOT
Results: 30.0
###
Pile Group Properties: ###
Xc = 4.500 ft. ###
Yc = 13.500 ft. 25.0
###
Ix = 2970.00 ft^2 ###
Iy = 450.00 ft^2 20.0 ###
J = 3420.00 ft^2 ###

Y - AXIS (ft.)
Ixy = 0.00 ft^2 ###
15.0
θ= 0.000 deg. ###
###
Σ Loads @ C.G. of Pile Group: 10.0 ###
Σ Pz = -3000.00 kips ###
Σ Hx = -40.00 kips ###
5.0
Σ Hy = -60.00 kips ###
Σ Mx = 500.00 ft-k ###
Σ My = -500.00 ft-k 0.0
###
0.0 5.0 10.0 15.0 20.0 25.0 30.0
Σ Mz = 0.00 ft-k ###
X - AXIS (ft.)
###
Pile Reactions (k) Pile Reactions (k) Pile Reactions (k)
Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh
#1: 82.27 1.80 #26: 73.08 1.80
#2: 81.77 1.80 #27: 72.58 1.80
#3: 81.26 1.80 #28: 72.07 1.80
#4: 80.76 1.80 #29: 71.57 1.80
#5: 80.25 1.80 #30: 71.06 1.80
#6: 79.75 1.80 #31: 72.27 1.80
#7: 79.24 1.80 #32: 71.77 1.80
#8: 78.74 1.80 #33: 71.26 1.80
#9: 78.23 1.80 #34: 70.76 1.80
#10: 77.73 1.80 #35: 70.25 1.80
#11: 78.94 1.80 #36: 69.75 1.80
#12: 78.43 1.80 #37: 69.24 1.80
#13: 77.93 1.80 #38: 68.74 1.80
#14: 77.42 1.80 #39: 68.23 1.80
#15: 76.92 1.80 #40: 67.73 1.80
#16: 76.41 1.80
#17: 75.91 1.80
#18: 75.40 1.80
#19: 74.90 1.80
#20: 74.39 1.80
#21: 75.61 1.80
#22: 75.10 1.80
#23: 74.60 1.80
#24: 74.09 1.80
#25: 73.59 1.80

Pile Reaction Summary:


Rz(max) = 82.27 kips
Rz(min) = 67.73 kips
Rh(max) = 1.80 kips

7 of 24 03/30/2011 06:25:45
"PILEGRP.xls" Program
Version 3.6

8 of 24 03/30/2011 06:25:45
"PILEGRP.xls" Program
Version 3.6

PILE GROUP ANALYSIS FOR RIGID PILE CAP


Using the Elastic Method for up to 75 Total Piles
(For Metric Units)
Job Name: Subject: Pile No.:
Job Number: Originator: Checker: ###
###
Input Data: ###
###
Number of Piles, Np = 40
Pile Coordinates: Pile Coordinates: Pile Coodinates:
Xo (m) Yo (m) Xo (m) Yo (m) Xo (m) Yo (m)
#1: 0.000 0.000 #26: 1.829 4.572 ###
#2: 0.000 0.914 #27: 1.829 5.486 ###
#3: 0.000 1.829 #28: 1.829 6.401 ###
#4: 0.000 2.743 #29: 1.829 7.315 ###
#5: 0.000 3.658 #30: 1.829 8.230 ###
#6: 0.000 4.572 #31: 2.743 0.000 ###
#7: 0.000 5.486 #32: 2.743 0.914 ###
#8: 0.000 6.401 #33: 2.743 1.829 ###
#9: 0.000 7.315 #34: 2.743 2.743 ###
#10: 0.000 8.230 #35: 2.743 3.658 ###
#11: 0.914 0.000 #36: 2.743 4.572 ###
#12: 0.914 0.914 #37: 2.743 5.486 ###
#13: 0.914 1.829 #38: 2.743 6.401 ###
#14: 0.914 2.743 #39: 2.743 7.315 ###
#15: 0.914 3.658 #40: 2.743 8.230 ###
#16: 0.914 4.572 ###
#17: 0.914 5.486 ###
#18: 0.914 6.401 ###
#19: 0.914 7.315 ###
#20: 0.914 8.230 ###
#21: 1.829 0.000 ###
#22: 1.829 0.914 ###
#23: 1.829 1.829 ###
#24: 1.829 2.743 ###
#25: 1.829 3.658 ###
###
No. Piers = 2 ###
Pier/Loading Data:
Pier #1 Pier #2
X (m) = 1.372 1.372 ###
Y (m) = 2.743 5.486 ###
h (m) = 1.524 1.524 ###
Pz (kN) = -6672.33 -6672.33 ###
Hx (kN) = -88.96 -88.96 ###
Hy (kN) = -133.45 -133.45 ###
Mx (kN-m) = 135.58 135.58 ###
My (kN-m) = -203.37 -203.37 ###
Mz (kN-m) = 0.00 0.00 ###
###
###

9 of 24 03/30/2011 06:25:45
"PILEGRP.xls" Program
Version 3.6

(continued)

10 of 24 03/30/2011 06:25:45
"PILEGRP.xls" Program
Version 3.6

###
PILE GROUP PLAN
Results: 12.0
###
Pile Group Properties: ###
Xc = 1.372 m ###
Yc = 4.115 m 10.0
###
Ix = 275.92 m^2 ###
Iy = 41.81 m^2 8.0 ###
J= 317.73 m^2 ###

Y - AXIS (m)
Ixy = 0.00 m^2 ###
6.0
θ= 0.000 deg. ###
###
Σ Loads @ C.G. of Pile Group: 4.0 ###
Σ Pz = -13344.67 kN ###
Σ Hx = -177.93 kN ###
2.0
Σ Hy = -266.89 kN ###
Σ Mx = 677.91 kN-m ###
Σ My = -677.91 kN-m 0.0
###
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5
Σ Mz = 0.00 kN-m ###
X - AXIS (m)
###
Pile Reactions (kN) Pile Reactions (kN) Pile Reactions (kN)
Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh
#1: 365.97 8.02 #26: 325.08 8.02
#2: 363.72 8.02 #27: 322.83 8.02
#3: 361.47 8.02 #28: 320.59 8.02
#4: 359.23 8.02 #29: 318.34 8.02
#5: 356.98 8.02 #30: 316.09 8.02
#6: 354.73 8.02 #31: 321.49 8.02
#7: 352.49 8.02 #32: 319.24 8.02
#8: 350.24 8.02 #33: 316.99 8.02
#9: 347.99 8.02 #34: 314.75 8.02
#10: 345.75 8.02 #35: 312.50 8.02
#11: 351.14 8.02 #36: 310.25 8.02
#12: 348.89 8.02 #37: 308.01 8.02
#13: 346.65 8.02 #38: 305.76 8.02
#14: 344.40 8.02 #39: 303.51 8.02
#15: 342.15 8.02 #40: 301.27 8.02
#16: 339.91 8.02
#17: 337.66 8.02
#18: 335.41 8.02
#19: 333.17 8.02
#20: 330.92 8.02
#21: 336.31 8.02
#22: 334.07 8.02
#23: 331.82 8.02
#24: 329.57 8.02
#25: 327.33 8.02

Pile Reaction Summary:


Rz(max) = 365.97 kN
Rz(min) = 301.27 kN
Rh(max) = 8.02 kN

11 of 24 03/30/2011 06:25:45
"PILEGRP.xls" Program
Version 3.6

12 of 24 03/30/2011 06:25:45
"PILEGRP.xls" Program
Version 3.6

PILE GROUP ANALYSIS FOR RIGID PILE CAP CALCULATIONS:


Using the Elastic Method for up to 300 Total Piles
(For English Units) Pile Dist. to X,Y axis:
Job Name: Subject: Pile No.:
Job Number: Originator: Checker: ###
###
Input Data: ###
###
Number of Piles, Np = 40 ###
###
Pile Coordinates: Pile Coordinates: Pile Coodinates: Pile Coodinates: Pile Coodinates: Pile Coodinates: ###
Xo (ft.) Yo (ft.) Xo (ft.) Yo (ft.) Xo (ft.) Yo (ft.) Xo (ft.) Yo (ft.) Xo (ft.) Yo (ft.) Xo (ft.) Yo (ft.) ###
#1: 0.000 0.000 ###
#2: 0.000 3.000 ###
#3: 0.000 6.000 ###
#4: 0.000 9.000 ###
#5: 0.000 12.000 ###
#6: 0.000 15.000 ###
#7: 0.000 18.000 ###
#8: 0.000 21.000 ###
#9: 0.000 24.000 ###
#10: 0.000 27.000 ###
#11: 3.000 0.000 ###
#12: 3.000 3.000 ###
#13: 3.000 6.000 ###
#14: 3.000 9.000 ###
#15: 3.000 12.000 ###
#16: 3.000 15.000 ###
#17: 3.000 18.000 ###
#18: 3.000 21.000 ###
#19: 3.000 24.000 ###
#20: 3.000 27.000 ###
#21: 6.000 0.000 ###
#22: 6.000 3.000 ###
#23: 6.000 6.000 ###
#24: 6.000 9.000 ###
#25: 6.000 12.000 ###
#26: 6.000 15.000 ###
#27: 6.000 18.000 ###
#28: 6.000 21.000 ###
#29: 6.000 24.000 ###
#30: 6.000 27.000 ###
#31: 9.000 0.000 ###
#32: 9.000 3.000 ###
#33: 9.000 6.000 ###
#34: 9.000 9.000 ###
#35: 9.000 12.000 ###
#36: 9.000 15.000 ###
#37: 9.000 18.000 ###
#38: 9.000 21.000 ###
#39: 9.000 24.000 ###
#40: 9.000 27.000 ###
###
###
###
###
###
###
###
###
###
###
###
No. Piers = 2 ###
Pier/Loading Data: ###
Pier #1 Pier #2 ###
X (ft.) = 4.500 4.500 ###
Y (ft.) = 9.000 18.000 ###
h (ft.) = 5.000 5.000 ###
Pz (k) = -1500.00 -1500.00 ###
Hx (k) = -20.00 -20.00 ###
Hy (k) = -30.00 -30.00 ###
Mx (ft-k) = 100.00 100.00 ###
My (ft-k) = -150.00 -150.00 ###
Mz (ft-k) = 0.00 0.00 ###
###
###
###
Results: ###
###
Pile Group Properties: Σ Loads @ C.G. of Pile Group: ###
Xc = 4.500 ft. Σ Pz = -3000.00 kips ###
Yc = 13.500 ft. Σ Hx = -40.00 kips ###
Ix = 2970.00 ft^2 Σ Hy = -60.00 kips ###
Iy = 450.00 ft^2 Σ Mx = 500.00 ft-k ###
J = 3420.00 ft^2 Σ My = -500.00 ft-k ###
Ixy = 0.00 ft^2 Σ Mz = 0.00 ft-k ###
θ= 0.000 deg. ###
###
Pile Reaction Summary: ###
Rz(max) = 82.27 kips ###
Rz(min) = 67.73 kips ###
Rh(max) = 1.80 kips ###
###
###
###
###
###
###
(continued)

13 of 24 03/30/2011 06:25:45
"PILEGRP.xls" Program
Version 3.6

###
PILE GROUP PLOT ###
###
30.0 ###
###
###
###
###
25.0 ###
###
###
###
###
###
20.0
###
###
###
###

Y-AXIS (ft.)
###
15.0 ###
###
###
###
###
10.0 ###
###
###
###
###
5.0 ###
###
###
###
###
###
0.0
###
4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0
###
X-AXIS (ft.) ###
###
###
Pile Reactions (k) Pile Reactions (k) Pile Reactions (k) Pile Reactions (k) Pile Reactions (k) Pile Reactions (k) ###
Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh ###
#1: 82.27 1.80 ###
#2: 81.77 1.80 ###
#3: 81.26 1.80 ###
#4: 80.76 1.80 ###
#5: 80.25 1.80 ###
#6: 79.75 1.80 ###
#7: 79.24 1.80 ###
#8: 78.74 1.80 ###
#9: 78.23 1.80 ###
#10: 77.73 1.80 ###
#11: 78.94 1.80 ###
#12: 78.43 1.80 ###
#13: 77.93 1.80 ###
#14: 77.42 1.80 ###
#15: 76.92 1.80 ###
#16: 76.41 1.80 ###
#17: 75.91 1.80 ###
#18: 75.40 1.80 ###
#19: 74.90 1.80 ###
#20: 74.39 1.80 ###
#21: 75.61 1.80 ###
#22: 75.10 1.80 ###
#23: 74.60 1.80 ###
#24: 74.09 1.80 ###
#25: 73.59 1.80 ###
#26: 73.08 1.80 ###
#27: 72.58 1.80 ###
#28: 72.07 1.80 ###
#29: 71.57 1.80 ###
#30: 71.06 1.80 ###
#31: 72.27 1.80 ###
#32: 71.77 1.80 ###
#33: 71.26 1.80 ###
#34: 70.76 1.80 ###
#35: 70.25 1.80 ###
#36: 69.75 1.80 ###
#37: 69.24 1.80 ###
#38: 68.74 1.80 ###
#39: 68.23 1.80 ###
#40: 67.73 1.80 ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

14 of 24 03/30/2011 06:25:46
"PILEGRP.xls" Program
Version 3.6

PILE GROUP ANALYSIS FOR RIGID PILE CAP CALCULATIONS:


Using the Elastic Method for up to 300 Total Piles
(For Metric Units) Pile Dist. to X,Y axis:
Job Name: Subject: Pile No.:
Job Number: Originator: Checker: ###
###
Input Data: ###
###
Number of Piles, Np = 40 ###
###
Pile Coordinates: Pile Coordinates: Pile Coodinates: Pile Coodinates: Pile Coodinates: Pile Coodinates: ###
Xo (m) Yo (m) Xo (m) Yo (m) Xo (m) Yo (m) Xo (m) Yo (m) Xo (m) Yo (m) Xo (m) Yo (m) ###
#1: 0.000 0.000 ###
#2: 0.000 0.914 ###
#3: 0.000 1.829 ###
#4: 0.000 2.743 ###
#5: 0.000 3.658 ###
#6: 0.000 4.572 ###
#7: 0.000 5.486 ###
#8: 0.000 6.401 ###
#9: 0.000 7.315 ###
#10: 0.000 8.230 ###
#11: 0.914 0.000 ###
#12: 0.914 0.914 ###
#13: 0.914 1.829 ###
#14: 0.914 2.743 ###
#15: 0.914 3.658 ###
#16: 0.914 4.572 ###
#17: 0.914 5.486 ###
#18: 0.914 6.401 ###
#19: 0.914 7.315 ###
#20: 0.914 8.230 ###
#21: 1.829 0.000 ###
#22: 1.829 0.914 ###
#23: 1.829 1.829 ###
#24: 1.829 2.743 ###
#25: 1.829 3.658 ###
#26: 1.829 4.572 ###
#27: 1.829 5.486 ###
#28: 1.829 6.401 ###
#29: 1.829 7.315 ###
#30: 1.829 8.230 ###
#31: 2.743 0.000 ###
#32: 2.743 0.914 ###
#33: 2.743 1.829 ###
#34: 2.743 2.743 ###
#35: 2.743 3.658 ###
#36: 2.743 4.572 ###
#37: 2.743 5.486 ###
#38: 2.743 6.401 ###
#39: 2.743 7.315 ###
#40: 2.743 8.230 ###
###
###
###
###
###
###
###
###
###
###
###
No. Piers = 2 ###
Pier/Loading Data: ###
Pier #1 Pier #2 ###
X (m) = 1.372 1.372 ###
Y (m) = 2.743 5.486 ###
h (m) = 1.524 1.524 ###
Pz (kN) = -6672.33 -6672.33 ###
Hx (kN) = -88.96 -88.96 ###
Hy (kN) = -133.45 -133.45 ###
Mx (kN-m) = 135.58 135.58 ###
My (kN-m) = -203.37 -203.37 ###
Mz (kN-m) = 0.00 0.00 ###
###
###
###
Results: ###
###
Pile Group Properties: Σ Loads @ C.G. of Pile Group: ###
Xc = 1.372 m Σ Pz = -13344.67 kN ###
Yc = 4.115 m Σ Hx = -177.93 kN ###
Ix = 275.92 m^2 Σ Hy = -266.89 kN ###
Iy = 41.81 m^2 Σ Mx = 677.91 kN-m ###
J= 317.73 m^2 Σ My = -677.91 kN-m ###
Ixy = 0.00 m^2 Σ Mz = 0.00 kN-m ###
θ= 0.000 deg. ###
###
Pile Reaction Summary: ###
Rz(max) = 365.97 kN ###
Rz(min) = 301.27 kN ###
Rh(max) = 8.02 kN ###
###
###
###
###
###
###
(continued)

15 of 24 03/30/2011 06:25:46
"PILEGRP.xls" Program
Version 3.6

###
PILE GROUP PLOT ###
###
7.0 ###
###
###
###
###
6.0
###
###
###
###
5.0 ###
###
###
###
###
4.0
###

Y-AXIS (m)
###
###
###
3.0 ###
###
###
###
###
2.0
###
###
###
###
1.0 ###
###
###
###
###
0.0
###
1.2 1.4 1.6 1.8 2.0 2.2 2.4 2.6 2.8 3.0 3.2
###
X-AXIS (m) ###
###
###
Pile Reactions(kN) Pile Reactions(kN) Pile Reactions(kN) Pile Reactions(kN) Pile Reactions(kN) Pile Reactions(kN) ###
Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh ###
#1: 365.97 8.02 ###
#2: 363.72 8.02 ###
#3: 361.47 8.02 ###
#4: 359.23 8.02 ###
#5: 356.98 8.02 ###
#6: 354.73 8.02 ###
#7: 352.49 8.02 ###
#8: 350.24 8.02 ###
#9: 347.99 8.02 ###
#10: 345.75 8.02 ###
#11: 351.14 8.02 ###
#12: 348.89 8.02 ###
#13: 346.65 8.02 ###
#14: 344.40 8.02 ###
#15: 342.15 8.02 ###
#16: 339.91 8.02 ###
#17: 337.66 8.02 ###
#18: 335.41 8.02 ###
#19: 333.17 8.02 ###
#20: 330.92 8.02 ###
#21: 336.31 8.02 ###
#22: 334.07 8.02 ###
#23: 331.82 8.02 ###
#24: 329.57 8.02 ###
#25: 327.33 8.02 ###
#26: 325.08 8.02 ###
#27: 322.83 8.02 ###
#28: 320.59 8.02 ###
#29: 318.34 8.02 ###
#30: 316.09 8.02 ###
#31: 321.49 8.02 ###
#32: 319.24 8.02 ###
#33: 316.99 8.02 ###
#34: 314.75 8.02 ###
#35: 312.50 8.02 ###
#36: 310.25 8.02 ###
#37: 308.01 8.02 ###
#38: 305.76 8.02 ###
#39: 303.51 8.02 ###
#40: 301.27 8.02 ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

16 of 24 03/30/2011 06:25:46
"PILEGRP.xls" Program
Version 3.6
PILE GROUP ANALYSIS FOR RIGID PILE CAP CALCULATIONS:
Using the Elastic Method for up to 400 Total Piles
(For English Units) Pile Dist. to X,Y axis:
Job Name: Subject: Pile No.:
Job Number: Originator: Checker: ###
###
Input Data: ###
###
Number of Piles, Np = 40 ###
###
Pile Coordinates: Pile Coordinates: Pile Coodinates: Pile Coodinates: Pile Coodinates: Pile Coodinates: Pile Coodinates: Pile Coodinates: ###
Xo (ft.) Yo (ft.) Xo (ft.) Yo (ft.) Xo (ft.) Yo (ft.) Xo (ft.) Yo (ft.) Xo (ft.) Yo (ft.) Xo (ft.) Yo (ft.) Xo (ft.) Yo (ft.) Xo (ft.) Yo (ft.) ###
#1: 0.000 0.000 ###
#2: 0.000 3.000 ###
#3: 0.000 6.000 ###
#4: 0.000 9.000 ###
#5: 0.000 12.000 ###
#6: 0.000 15.000 ###
#7: 0.000 18.000 ###
#8: 0.000 21.000 ###
#9: 0.000 24.000 ###
#10: 0.000 27.000 ###
#11: 3.000 0.000 ###
#12: 3.000 3.000 ###
#13: 3.000 6.000 ###
#14: 3.000 9.000 ###
#15: 3.000 12.000 ###
#16: 3.000 15.000 ###
#17: 3.000 18.000 ###
#18: 3.000 21.000 ###
#19: 3.000 24.000 ###
#20: 3.000 27.000 ###
#21: 6.000 0.000 ###
#22: 6.000 3.000 ###
#23: 6.000 6.000 ###
#24: 6.000 9.000 ###
#25: 6.000 12.000 ###
#26: 6.000 15.000 ###
#27: 6.000 18.000 ###
#28: 6.000 21.000 ###
#29: 6.000 24.000 ###
#30: 6.000 27.000 ###
#31: 9.000 0.000 ###
#32: 9.000 3.000 ###
#33: 9.000 6.000 ###
#34: 9.000 9.000 ###
#35: 9.000 12.000 ###
#36: 9.000 15.000 ###
#37: 9.000 18.000 ###
#38: 9.000 21.000 ###
#39: 9.000 24.000 ###
#40: 9.000 27.000 ###
###
###
###
###
###
###
###
###
###
###
###
No. Piers = 2 ###
Pier/Loading Data: ###
Pier #1 Pier #2 ###
X (ft.) = 4.500 4.500 ###
Y (ft.) = 9.000 18.000 ###
h (ft.) = 5.000 5.000 ###
Pz (k) = -1500.00 -1500.00 ###
Hx (k) = -20.00 -20.00 ###
Hy (k) = -30.00 -30.00 ###
Mx (ft-k) = 100.00 100.00 ###
My (ft-k) = -150.00 -150.00 ###
Mz (ft-k) = 0.00 0.00 ###
###
(continued)

17 of 24 03/30/2011 06:25:46
"PILEGRP.xls" Program
Version 3.6
###
###
###
PILE GROUP PLOT ###
###
###
30.0 ###
###
###
###
###
###
###
###
###
###
###
25.0 ###
###
###
###
###
###
###
###
###
###
20.0 ###
###
###
###
###
###
###
###
Y-AXIS (ft.)

###
###

15.0 ###
###
###
###
###
###
###
###
###
###
###
10.0 ###
###
###
###
###
###
###
###
###
###
5.0 ###
###
###
###
###
###
###
###
###
###
###
0.0 ###
4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 ###
###
###
X-AXIS (ft.) ###
###
###
(continued)

18 of 24 03/30/2011 06:25:46
"PILEGRP.xls" Program
Version 3.6
###
###
Results: ###
###
Pile Group Properties: Σ Loads @ C.G. of Pile Group: ###
Xc = 4.500 ft. Σ Pz = -3000.00 kips ###
Yc = 13.500 ft. Σ Hx = -40.00 kips ###
Ix = 2970.00 ft^2 Σ Hy = -60.00 kips ###
Iy = 450.00 ft^2 Σ Mx = 500.00 ft-k ###
J= 3420.00 ft^2 Σ My = -500.00 ft-k ###
Ixy = 0.00 ft^2 Σ Mz = 0.00 ft-k ###
θ= 0.000 deg. ###
###
###
Pile Reaction Summary: ###
Rz(max) = 82.27 kips ###
Rz(min) = 67.73 kips ###
Rh(max) = 1.80 kips ###
###
###
###
###
###
Pile Reactions (k) Pile Reactions (k) Pile Reactions (k) Pile Reactions (k) Pile Reactions (k) Pile Reactions (k) Pile Reactions (k) Pile Reactions (k) ###
Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh ###
#1: 82.27 1.80 ###
#2: 81.77 1.80 ###
#3: 81.26 1.80 ###
#4: 80.76 1.80 ###
#5: 80.25 1.80 ###
#6: 79.75 1.80 ###
#7: 79.24 1.80 ###
#8: 78.74 1.80 ###
#9: 78.23 1.80 ###
#10: 77.73 1.80 ###
#11: 78.94 1.80 ###
#12: 78.43 1.80 ###
#13: 77.93 1.80 ###
#14: 77.42 1.80 ###
#15: 76.92 1.80 ###
#16: 76.41 1.80 ###
#17: 75.91 1.80 ###
#18: 75.40 1.80 ###
#19: 74.90 1.80 ###
#20: 74.39 1.80 ###
#21: 75.61 1.80 ###
#22: 75.10 1.80 ###
#23: 74.60 1.80 ###
#24: 74.09 1.80 ###
#25: 73.59 1.80 ###
#26: 73.08 1.80 ###
#27: 72.58 1.80 ###
#28: 72.07 1.80 ###
#29: 71.57 1.80 ###
#30: 71.06 1.80 ###
#31: 72.27 1.80 ###
#32: 71.77 1.80 ###
#33: 71.26 1.80 ###
#34: 70.76 1.80 ###
#35: 70.25 1.80 ###
#36: 69.75 1.80 ###
#37: 69.24 1.80 ###
#38: 68.74 1.80 ###
#39: 68.23 1.80 ###
#40: 67.73 1.80 ###
###
###
###
###
###
###
###
###
###
###
###
###

19 of 24 03/30/2011 06:25:46
"PILEGRP.xls" Program
Version 3.6
PILE GROUP ANALYSIS FOR RIGID PILE CAP CALCULATIONS:
Using the Elastic Method for up to 400 Total Piles
(For Metric Units) Pile Dist. to X,Y axis:
Job Name: Subject: Pile No.:
Job Number: Originator: Checker: ###
###
Input Data: ###
###
Number of Piles, Np = 40 ###
###
Pile Coordinates: Pile Coordinates: Pile Coodinates: Pile Coodinates: Pile Coodinates: Pile Coodinates: Pile Coodinates: Pile Coodinates: ###
Xo (m) Yo (m) Xo (m) Yo (m) Xo (m) Yo (m) Xo (m) Yo (m) Xo (m) Yo (m) Xo (m) Yo (m) Xo (m) Yo (m) Xo (m) Yo (m) ###
#1: 0.000 0.000 ###
#2: 0.000 0.914 ###
#3: 0.000 1.829 ###
#4: 0.000 2.743 ###
#5: 0.000 3.658 ###
#6: 0.000 4.572 ###
#7: 0.000 5.486 ###
#8: 0.000 6.401 ###
#9: 0.000 7.315 ###
#10: 0.000 8.230 ###
#11: 0.914 0.000 ###
#12: 0.914 0.914 ###
#13: 0.914 1.829 ###
#14: 0.914 2.743 ###
#15: 0.914 3.658 ###
#16: 0.914 4.572 ###
#17: 0.914 5.486 ###
#18: 0.914 6.401 ###
#19: 0.914 7.315 ###
#20: 0.914 8.230 ###
#21: 1.829 0.000 ###
#22: 1.829 0.914 ###
#23: 1.829 1.829 ###
#24: 1.829 2.743 ###
#25: 1.829 3.658 ###
#26: 1.829 4.572 ###
#27: 1.829 5.486 ###
#28: 1.829 6.401 ###
#29: 1.829 7.315 ###
#30: 1.829 8.230 ###
#31: 2.743 0.000 ###
#32: 2.743 0.914 ###
#33: 2.743 1.829 ###
#34: 2.743 2.743 ###
#35: 2.743 3.658 ###
#36: 2.743 4.572 ###
#37: 2.743 5.486 ###
#38: 2.743 6.401 ###
#39: 2.743 7.315 ###
#40: 2.743 8.230 ###
###
###
###
###
###
###
###
###
###
###
###
No. Piers = 2 ###
Pier/Loading Data: ###
Pier #1 Pier #2 ###
X (m) = 1.372 1.372 ###
Y (m) = 2.743 5.486 ###
h (m) = 1.524 1.524 ###
Pz (kN) = -6672.33 -6672.33 ###
Hx (kN) = -88.96 -88.96 ###
Hy (kN) = -133.45 -133.45 ###
Mx (kN-m) = 135.58 135.58 ###
My (kN-m) = -203.37 -203.37 ###
Mz (kN-m) = 0.00 0.00 ###
###
(continued)

20 of 24 03/30/2011 06:25:46
"PILEGRP.xls" Program
Version 3.6
###
###
###
PILE GROUP PLOT ###
###
###
9.0 ###
###
###
###
###
###
###
8.0 ###
###
###
###
###
###
###
7.0 ###
###
###
###
###
###
###
6.0 ###
###
###
###
###
###
###
5.0 ###
Y-AXIS (m)

###
###
###
###
###
###
4.0 ###
###
###
###
###
###
###
3.0 ###
###
###
###
###
###
###
2.0 ###
###
###
###
###
###
###
1.0 ###
###
###
###
###
###
###
0.0 ###
1.2 1.4 1.6 1.8 2.0 2.2 2.4 2.6 2.8 3.0 3.2 ###
###
###
X-AXIS (m) ###
###
###
(continued)

21 of 24 03/30/2011 06:25:46
"PILEGRP.xls" Program
Version 3.6
###
###
Results: ###
###
Pile Group Properties: Σ Loads @ C.G. of Pile Group: ###
Xc = 1.372 m Σ Pz = -13344.67 kN ###
Yc = 4.115 m Σ Hx = -177.93 kN ###
Ix = 275.92 m^2 Σ Hy = -266.89 kN ###
Iy = 41.81 m^2 Σ Mx = 677.91 kN-m ###
J= 317.73 m^2 Σ My = -677.91 kN-m ###
Ixy = 0.00 m^2 Σ Mz = 0.00 kN-m ###
θ= 0.000 deg. ###
###
###
Pile Reaction Summary: ###
Rz(max) = 365.97 kN ###
Rz(min) = 301.27 kN ###
Rh(max) = 8.02 kN ###
###
###
###
###
###
Pile Reactions(kN) Pile Reactions(kN) Pile Reactions(kN) Pile Reactions(kN) Pile Reactions(kN) Pile Reactions(kN) Pile Reactions(kN) Pile Reactions(kN) ###
Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh Vert. Rz Horiz. Rh ###
#1: 365.97 8.02 ###
#2: 363.72 8.02 ###
#3: 361.47 8.02 ###
#4: 359.23 8.02 ###
#5: 356.98 8.02 ###
#6: 354.73 8.02 ###
#7: 352.49 8.02 ###
#8: 350.24 8.02 ###
#9: 347.99 8.02 ###
#10: 345.75 8.02 ###
#11: 351.14 8.02 ###
#12: 348.89 8.02 ###
#13: 346.65 8.02 ###
#14: 344.40 8.02 ###
#15: 342.15 8.02 ###
#16: 339.91 8.02 ###
#17: 337.66 8.02 ###
#18: 335.41 8.02 ###
#19: 333.17 8.02 ###
#20: 330.92 8.02 ###
#21: 336.31 8.02 ###
#22: 334.07 8.02 ###
#23: 331.82 8.02 ###
#24: 329.57 8.02 ###
#25: 327.33 8.02 ###
#26: 325.08 8.02 ###
#27: 322.83 8.02 ###
#28: 320.59 8.02 ###
#29: 318.34 8.02 ###
#30: 316.09 8.02 ###
#31: 321.49 8.02 ###
#32: 319.24 8.02 ###
#33: 316.99 8.02 ###
#34: 314.75 8.02 ###
#35: 312.50 8.02 ###
#36: 310.25 8.02 ###
#37: 308.01 8.02 ###
#38: 305.76 8.02 ###
#39: 303.51 8.02 ###
#40: 301.27 8.02 ###
###
###
###
###
###
###
###
###
###
###
###
###

22 of 24 03/30/2011 06:25:46
"PILEGRP.xls" Program
Version 3.6

BEAM AND PUNCHING SHEAR CHECKS FOR PILE CAP


for Single Corner Pile
Per ACI 318-05 Code
Job Name: Subject: Yes
Job Number: Originator: Checker: No
318-99
Input: 318-02
d/2 E=18'' 318-05
Pile Reaction, Rp = 120.00 kips Vu =
Edge of Pile Cap
Pile Dia., Dp = 12.000 in. φVc =
Pile Edge Dist., E = 18.000 in. For Two-wa
Pile Spacing, L = 48.000 in. Dp=12'' d=
Pile Embedment, dp = 6.000 in. (L-Dp)/2=18'' Pile E=18''
Pile Cap Thk, H = 36.000 in. bo =
Conc. Strength, f 'c = 3000.0 psi φ=
Top Face Reinf.? Yes Dp/2=6''
Applicable ACI Code = 318-05 Critical Section d/2=13''
for Punching
USD Load Factor, LF = 1.6
bo=65.845''
Edge of
Note: one-way, beam and two-way, Pile Cap
punching shear checks for critical Nomenclature b=98.912''
sections relative to pier(s) must also
be performed. Checks for one-way Critical Section
for Beam Shear
deep beam and two-way deep corbel
shear should also be considered.

Results:

For One-way, Beam Shear: Critical Section @ min. of d or (L-Dp)/2 from face of pile
Pile Cap Eff. Depth, d = 26.000 in. d = H-dp-4'' (Assume 4'' from top face to centroid of reinf.)
Critical Section, CS = 18.000 in. CS = minimum of: d or (L-Dp)/2
Shear Width, b = 98.912 in. b = 2*(SQRT(2*E^2)+Dp/2+CS)
φ= 0.75 φ = strength reduction factor for shear
Ultimate Shear, Vu = 192.00 kips Vu = LF*Rp
Allow. Shear, φVc = 211.29 kips φVc = φ*2*SQRT(f 'c)/1000*b*d

Vu <= Allow. Shear, O.K.

For Two-way, Punching Shear: Critical Section @ min. of d/2 or (L-Dp)/2 from face of pile
Pile Cap Eff. Depth, d = 26.000 in. d = H-dp-4'' (Assume 4'' from top face to centroid of reinf.)
Critical Section, CS = 13.000 in. CS = minimum of: d/2 or (L-Dp)/2
Shear Perimeter, bo = 65.845 in. bo = 2*E+(2*π*(Dp/2+CS))/4 <= 2*π*(Dp/2+CS)
φ= 0.75 φ = strength reduction factor for shear
Ultimate Shear, Vu = 192.00 kips Vu = LF*Rp
Allow. Shear, φVc = 281.31 kips φVc = φ*4*SQRT(f 'c)/1000*bo*d

Vu <= Allow. Shear, O.K.

Comments:

23 of 24 03/30/2011 06:25:47
"PILEGRP.xls" Program
Version 3.6

24 of 24 03/30/2011 06:25:47