You are on page 1of 4

Hydrotreater revamps

for ULSD fuel


Scope and capital investment for revamping an existing diesel hydrotreater to meet
the 15wppm sulphur standard. The base design is typical of hydrotreaters
commissioned in the early 1990s to meet on-road specifications of 500wppm sulphur
R E (Ed) Palmer Mustang Engineers and Constructors Inc, Houston, Texas, USA
Salvatore P Torrisi Criterion Catalysts & Technologies

I
n mid-2006, thanks to the US
Environmental Protection Agency
(EPA), 80% of refiners’ on-road diesel Feed Existing Existing recycle and
pool will have to meet a new ultra-low reactor MU compressors
sulphur diesel (ULSD) specification of
no more than 15wppm sulphur. To Reformer
Heater hydrogen
ensure this target is not exceeded at the
ultimate point of distribution, and to Purge
allow for some manufacturing
flexibility, revamped or new facilities Lean To
will need to achieve a desulphurised amine fuel gas

Amine contactor
product sulphur level significantly
below the mandated target. Sulphur Wash
limits and regulations of similar severity water Sour
are being implemented in other areas of water

Steam stripper
the world such as Europe and certain
parts of Asia.
CHPS
For an existing diesel hydrotreater, a HHPS Naphtha
number of options will directionally
improve sulphur removal, including:
— Higher activity catalyst Rich amine
Stripping
— Increased reactor temperature steam
— Installation of high-efficiency reactor
feed distributors
— Increased catalyst volume Diesel product
— Recycle gas scrubbing to remove
hydrogen sulphide. Figure 1 Base case process flow diagram

Revamp design basis operating pressure, catalyst volume and water, power, instrument/plant air, and
The feed basis for this study is identical treat gas rate. The design product the pressure relief system have sufficient
to the original design and consists of a sulphur for the original design was capacity for the revamp
blend of two-thirds straight-run gas oil 470wppm. — The existing DCS has capacity to
and one-third light-cycle oil (LCO). A simplified flow diagram of the base
Table 1 shows the feed constituents and cases is shown in Figure 1. Other study Base case reactor conditions
blended properties. Key design criteria basis criteria were:
for the original facility are shown in — Product sulphur content of 8wppm
Base design condition Base case
Table 2. This includes existing reactor — Utility systems such as steam, cooling
Charge rate, BPSD 30 000
Number of reactors 1
Feed properties Reactor inlet pressure, psig 760
LHSV, hr-1 1.5
Feed property SRGO LCO Blend Catalyst volume, ft3 4680
BPSD 20 000 10 000 30 000 Reactor outlet H2, psia 348
API 34.5 20.0 29.4 Chemical H2, SCF/bbl 250
Sulphur, wt% 0.8 2.0 1.2 SOR WABT, °F 670
N, wppm 100 500 242 Cycle length, months 18
Total aromatics, vol% 20.0 65.0 35.0 Make-up hydrogen, SCF/bbl 290
Mono-aromatics, vol% 12.8 23.0 16.2 Treat gas rate, SCF/bbl 1400
Poly-aromatics, vol% 7.2 42.0 18.7 Quench rate, SCF/bbl 0
Bromine number 1.0 10.0 4.2 Product sulphur content, wppm 470
D86 90 vol% Temp, °F 640 640 640 Recycle gas scrubber Yes
Cetane index 49.9 30.3 42.6

Table 1 Table 2

15
P T Q REVAMPS & OPERATIONS
accommodate all new instrumentation
— Plot space is available near the
hydrotreater unit for new equipment New booster
— The refinery is currently consuming compressors
all available reformer hydrogen. Existing recycle
Feed Existing and MU New
Incremental hydrogen will be purchased
reactor compressors PSA
from a pipeline
PSA
— Hydrotreating kerosene for cloud Reformer
point control in the winter is not Heater hydrogen
Purchased
required
hydrogen Purge
— The existing hydrotreators are not
operating at charge rates significantly
Lean To
above the original design.
amine fuel gas
The original design treat gas rate of

Amine contactor
1400 SCFB was assumed for this study.
Wash
Higher recycle rates, if hydraulically water
feasible, would extend the catalysts Sour
cycle or allow higher throughputs. For water

Steam stripper
this study, Criterion Catalysts provided
the reaction conditions in Table 3 for CHPS
several options required for the HHPS Naphtha
production of ULSD. All reaction
conditions are based on an assumed
Rich amine
distribution of higher boiling sulphur Stripping
compounds. For a definitive design, steam
pilot testing of the feedstock is
recommended. The base case reaction Diesel product
parameters are also shown for
comparison.
In all revamp cases, the current
catalyst was replaced with Criterion’s Figure 2 Revamped hydrotreater with two new packed beds added to existing reactor,
most active desulphurisation catalyst, new MU compressor and introduction of purchased hydrogen
DC-2118. Three options were
considered. The first (Revamp A) adsorption (PSA) unit. Combined with purity of 99.9 vol%. Revamp cases B and
consisted of purifying the reformer the purchased hydrogen, this resulted in C consisted of adding incremental
hydrogen with a pressure swing the total make-up volume having a catalyst volume to the base case design.
The incremental hydrogen volume was
also supplied by pipeline purchases.
Base case and revamp reaction conditions
Purification of the reformer make-up
was not considered.
Reaction condition Base 1 Revamp A Revamp B Revamp C Using the reaction conditions
Charge rate, BPSD 30 000 30 000 30 000 30 000 specified, computer simulations were
Reactor inlet, psig 760 760 760 760 developed for each revamp alternative.
LHSV, hr-1 1.50 1.70 1.00 0.75 Hydrogen make-up rates were calculated
3
Catalyst volume, ft 4680 4150 7020 9360 based on the sum of chemical hydrogen
Catalyst type (Criterion) 448 DC-2118 DC-2118 DC-2118 consumption, solution losses and purge
SOR WABT, °F 670 709 688 674 gas, if any, from the simulations.
Cycle length, months 18 10 18 27
Additional process information for each
Chemical H2, SCF/bbl 250 33 284 323
revamp is presented in Table 4.
Treat gas rate, SCF/bbl 1400 1400 1400 1400
The simulation results were used to
Product sulphur content, wppm 470 8 8 8
Recycle gas scrubber Yes Yes Yes Yes
rate existing equipment and determine
what modifications were required as
Table 3 well as the size and other design
information for new items. All shell and
tube exchangers, air coolers, pumps and
Simulation results fired heaters were rigorously rated.
Pressure drop across each catalyst bed
(1)
was calculated using the Ergun
Simulation results Base case Revamp 1A Revamp 1B Revamp 1C (2)
equation with the Larkin two-phase
Reactor outlet H2 PP, psia 348 575 403 430 correction parameter. An allowance was
Make-up as 100 % H2, SCF/bbl 290 364 334 374 also included for fouling. The resulting
Make-up purity, mole % H2 83.9 99.9 88.0 87.9 information was used to develop
Treat gas purity, mole % H2 70 93 76 76 hydraulic calculations across the reactor
Quench rate, SCF/bbl 0 400 400 400
loop to establish an operating/design
Purge gas rate, SCF/bbl 14 0 38 38
pressure and temperature profile, check
Reformer hydrogen, SCF/bbl 346 346 346 346
the performance of the recycle
Purchased hydrogen, SCF/bbl 0 74 44 84
compressor, and to identify other
Total make-up, SCF/bbl 346 420 390 430
limitations within the system.
Table 4 Table 5 summarises the detailed

16
P T Q REVAMPS & OPERATIONS
revamp scope for each case. Process flow
diagrams of the hydrotreater revamps
Existing Existing recycle
are shown in Figures 2 and 3
Feed reactor and MU
(equipment and lines shown in bold are New booster
New compressors
new or modified). compressor
reactor

Revamp requirements Reformer


Heater hydrogen
Each revamp case shares the following Purchased
common requirements, including state- hydrogen Purge
of-the-art high-activity catalyst,
increased hydrogen make-up Lean To
compression capacity and the addition amine fuel gas

Amine contactor
of reactor quench.
All cases take advantage of the latest Wash
advances in catalyst technology and are water Sour
based on using Criterion’s DC-2118 water

Steam stripper
CoMo catalyst. Catalyst beds were
assumed to be dense loaded with 1/20”
CHPS
catalyst to provide maximum cycle HHPS Naphtha
length and to ensure even contacting
between the catalyst and oil. Also to
ensure maximum cycle length, the Rich amine
Stripping
existing feed distributors were upgraded. steam
Good feed distribution and proper
catalyst installation is critical for the
production of ULSD. Design and cost Diesel product
information for new feed distributors
and inter bed quench internals was
provided by Shell Global Solutions.
Producing ULSD requires a significant Figure 3 Base revamp Case B and C flow diagram with modified flow from recycle
increase in chemical hydrogen compressor into existing reactor
consumption compared to what is
needed to make diesel meeting the equipment. The existing make-up service. This is a result of the increased
500wppm specification. This is due to cylinders also required replacement heat capacity ratio associated with the
additional, marginal saturation of because of the higher capacity and higher-purity hydrogen.
aromatics and the removal of sulphur operating pressure. This would also be an issue for the
from aromatic sulphur compounds. To Another option to consider for existing make-up compressors for Case
provide the incremental make-up providing increased make-up is to add A, where the reformer hydrogen is
capacity, a new spared reciprocating new compression capacity in parallel purified in a PSA unit. With the new
booster compressor is added upstream with the existing make-up compressors. compressor installed in series with the
of the existing first-stage make-up The new machine would handle existing make-up machines, the total
cylinders. Due to design pressure purchased hydrogen, while the existing supply to the hydrotreater could be
limitations, the existing first-stage compressors would still be dedicated to furnished with high-purity purchased
make-up compressor intercooler and reformer off-gas. The new compressor hydrogen when the reformer is out of
knock-out drum were re-piped to would require three stages, however, to service for catalyst regeneration or
service the new booster compressor. comply with API Standard 618, which maintenance. Due to the discharge
A new intercooler and knock-out recommends a maximum discharge temperature limitations previously
drum designed for a higher pressure temperature of 275°F for reciprocating noted, this flexibility would be lost with
were specified to replace this compressors in high-purity hydrogen a parallel make-up compressor
installation.
Revamp scope The higher hydrogen consumption
results in a significant increase in
reaction heat for all cases and, thus,
Case A * Install Criterion DC-2118 catalyst quench was added to limit the
* Add hydrogen booster compressor and replace cylinders in the existing temperature rise in the reactor and
make-up compressor extend catalyst cycle life. In revamp
* Add quench to reactor Case A, the existing reactors were
* Add PSA Unit with tail gas surge drum and compressor modified to include inter-bed quench by
* Revamp cost: $108 000 000
splitting the catalyst volumes into two
beds. In the other cases where a new
Case B * First three items in Revamp 1A plus
reactor is added in series, quench gas is
* 50% more catalyst in a new reactor
added between the reactors. Modifying
* Revamp cost: $8 100 000
the existing reactors for inter-bed
Case C * First three items in Revamp 1A plus quench requires four vertical feet that
* 100% more catalyst in a new reactor otherwise would have been occupied by
* Revamp cost: $8 660 000 catalyst. The loss of catalyst volume is
(Items in Italics are unique to that revamp option)
more than offset by quenching the
reaction and limiting the overall
Table 5 temperature rise of the reactor.

17
P T Q REVAMPS & OPERATIONS
Utilising reactor quench directionally operational upsets, including product capable of meeting the more stringent
lowers the reactor loop pressure drop stripper performance sulphur specification, will lack some of
and heater duty for all revamp cases, — Segregation of offsite product the robust design features of a new
because quench gas bypasses the handling systems to minimise grass-roots facility custom designed for
feed/effluent exchangers and charge contamination with other streams this purpose.
heater. This may allow for some increase — Handling and reprocessing of off-
in the recycle gas rate by operating the spec product Acknowledgements
spare recycle compressor and further — Equipment reliability. The PSA POLYBED unit budgetary yield
extending the cycle length. A more The specific revamp scope costs for and cost estimate was provided by UOP
detailed analysis of the reactor loop these issues have not been addressed in Process Plants division.
hydraulics and unloading capabilities of this article. The authors also wish to thank Shell
the existing compressors would be Global Solutions for verifying the
required to determine the magnitude of Conclusions feasibility of modifying an existing
this improvement. Most hydrotreaters that were installed hydrotreater reactor for inter-bed
Upgrading the catalyst alone is not to meet the 1993 low sulphur diesel hydrogen quench and providing cost
sufficient to meet the lower sulphur requirements (500wppm) can be estimates for the same.
specification. As noted previously, in modified to meet the future
revamp case A the reformer make-up specification for ULSD of 15wppm for a
hydrogen is purified using a PSA unit, modest on-site capital investment. The R E (Ed) Palmer is currently the manager
which concentrates the hydrogen key alternatives to consider for the of downstream process engineering for
from 83.9–99% with a hydrogen yield of revamp design are: Mustang Engineering. He is responsible for
86%. High-purity hydrogen from the — Installation of the most active process design and marketing support for
pipeline is used to satisfy the commercially available hydrotreating all refining, petrochemical and chemical
incremental demand. The combined catalyst projects. At Mustang, he has led numerous
make-up gas has a hydrogen — Increased catalyst volume studies, technology evaluations and
concentration of 99.9 vol%, which — Removal of hydrogen sulphide via projects relating to clean fuels production.
increases the purity in the treat gas recycle gas amine scrubbing He has been the author/co-author of
(compared to the base case) from 70–93 — Improved reactor hydrogen partial numerous articles and industry meeting
vol%. As a result, the hydrogen partial pressure. presentations relating to petroleum
pressure at the reactor outlet increases For all designs, the use of high- refining. Prior to assuming his current
from 348–575psia. The resulting catalyst efficiency reactor vapour/liquid feed position at Mustang, he spent 23 years
cycle length, however, is reduced to distributors is essential. with Litwin Engineers and Constructors in
10 months. For revamp case A, even though the a variety of assignments in process design.
The PSA unit could be installed hydrogen partial pressure was increased Palmer spent the first five years of his
outside the hydrotreater plot area, substantially, the loss of catalyst volume career as a refinery process engineer for
which may have particular appeal if associated with the reactor quench Conoco in Oklahoma.
space inside the unit is limited. required an unusually high start-of-run E-mail: ed.palmer@mustangeng.com
Installation at a remote location allows WABT, which in turn limited the cycle Salvatore P Torrisi, clean fuels technical
for construction to be completed while length to just 10 months. This may not specialist for Criterion Catalysts &
the hydrotreater is operating, leaving be acceptable to many refiners. Technologies, has responsibility for clean
only minimal piping tie-ins for a unit The revamp designs presented in this fuels project coordination in the Americas.
shutdown. In addition to the PSA unit, a study, although sufficient to meet the He joined the CRI International family in
knock-out drum and tail gas future requirements of ULSD, only 1996, becoming lab manager within the
compression system are required. Also, marginally improve other product research and commercial development
additional purchased hydrogen is properties such as cetane number, group where he was responsible for
required to make-up for hydrogen yield polynuclear aromatics, total aromatics supporting regeneration and
losses across the PSA. and gravity. Improvement of these presulphurisation technologies. More
The catalyst volumes are increased in quality specifications, which are the recently, with Criterion he has been
revamp options B and C in lieu of subject of regulations in certain areas of involved with new product market
purifying the reformer make-up North America and Europe, requires introduction, particularly with application
hydrogen. New reactors in series with another stage of treating for the of CENTINEL catalysts. Prior to joining CRI,
the existing reactors were sized to reduction of aromatics and possibly Torrisi spent 10 years in a variety of
increase the catalyst volume by 50% and partial destruction of polycyclic assignments including process engineering,
100% in cases B and C, respectively. saturated compounds. It may be technical service and R&D with Exxon in
Direct hydrogen quench is added possible to integrate this equipment Baton Rouge and Florham Park. He holds
between reactors. The additional into the existing hydrotreater; a BS degree in chemical engineering from
volume of catalyst more than otherwise, a new grass roots facility is the Virginia Tech.
compensates for the less pure make-up required.
hydrogen and increases the cycle life to The offsite revamp scope and cost
18 and 27 months for cases B and C, was not addressed in this work, but
respectively. could substantially increase total
References
1 Ergun S, Fluid Flow through packed
project cost. This includes modifications columns, Chem Eng Progr, 48, 89, 1952.
Other considerations to product rundown, storage and 2 Larkin R P, White R R and Jeffery D W, Two-
phase concurrent flow in packed beds,
Manufacturing ULSD will require the shipping systems to prevent AIChE J., 7231, 1961.
consideration of a number of other contamination with other middle 3 Bjorklund B L, Heckel T L, Howard N D,
(3) Lindsay D A and Piasecki D J, The lower it
factors, including : distillate streams. Also, infrastructure
goes, the tougher it gets (The practical
— Dedicated feed storage to minimise systems for hydrogen supply and implications of producing ultra-low sulphur
feed quality variability utilities could be impacted. Further, the diesel), presented at the 2000 NPRA Annual
— Rapid response to routine revamp designs, although theoretically Meeting.

18
P T Q REVAMPS & OPERATIONS

You might also like