Professional Documents
Culture Documents
2 J u n e 2003
The “Tatara Bridge” is the world’s longest steel-concrete hybrid cable stayed bridge. It measures 1 480 m in
total length and 890 m in the center span. The side spans consist of steel and prestressed concrete (PC) girders.
IHI, as one of the joint venture member companies, received the order for design, fabrication, and erection of
the Ohmishima Island side of the bridge in 1994. The bridge design is described.
1 480 000
50 000 50 000 170 000 890 000 270 000 50 000
T.P.+226.000 T.P.+226.000
T.P.+0.000
T.P.-13.000
T.P.-33.000
1A P1 P2 2P 3P P3 4P
25 000
25 000
105 500 1 312 000 62 500
PC girder Steel girder PC girder
(Note) T.P. : Mid-tide in Tokyo Bay (unit : m)
N.H.H.W.L : Nearly highest tide level (unit : m)
40
V o l . 36 N o . 2 J u n e 2003
2P 3P
6 000 6 000
T.P.+226.000 T.P.+226.000
C4
C8 C8 C8 C7 C7 C7 C7 C7 C6
C8 C8 C7 C7 C7 C7 C7 C6 C6
2 C4 3 4
C1 C 1 C4 C4
4 2 0 8 6
3 1 9 7 5 3 1 9
C3 2 6
C3 C4 9 C4
0 C4
5 C4
8
6 C4
C3
7
5 C4
C3
C C3
7
C C3 0
8
8 5 9 C 5
C
7 C
0
6 C4 2
C5
C3
C 1 1
C5
C3 C3 C3 C2
3
C3
C9 4
C5
4 2 0
1
6 4 2
3
C1 C1 C1
1 C5 6
C1 C5
C2 C2
5
4
C5
8
3
C1
C5
2
7
7
C5
8
5
1 0
C1
9 8
C2 C24
0
C6 C6
C1 C1
7
5
9
C2
C5
7
8
C1
C66 5
C6
C62
C23
C20
180 600
220 000
180 600
220 000
C64
C63
C21
C22
32 500 32 500
3 000
6 000
3 000
▽T.P.+46.215 ▽T.P.+46.215
6 000
T.P.+45.400 T.P.+45.400
T.P.+38.500 T.P.+38.500
15 420 15 420
3 000
3 000
36 900
36 900
32 500
32 500
T.P.+6.000 T.P.+6.000
N.H.H.W.L.T.P.+2.200 N.H.H.W.L.T.P.+2.200
2 500
2 500
19 000
17 000 8 500 17 000 8 500
T.P.-13.000
39 000
43 000 25 000
T.P.-33.000
43 000 25 000
1% 2% 2% 1% 1% 2% 2% 1%
2 700
2 700
V o l . 36 N o . 2 J u n e 2003
1 480 000
Side span length 50 000 50 000 170 000 890 000 270 000 50 000
Interval of cable
anchor points 2 000 10 × 8 000 9 000 13 000 4 × 20 000 22 000 28 000 19 × 20 000 = 380 000 30 000 19 × 20 000 = 380 000 22 000 28 000 8 × 20 000 = 160 000 15 000 10 000 7 × 8 000 2 000
= 80 000 = 80 000 28 000 22 000 28 000 22 000 = 56 000
9 000 16 000 14 000 12 000
11 000
CL
1A P1 P2 2P 3P P3 4P
Section number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Section classification N H I J L M L J I G E D C B A B C D E G I J L M L K I F D N
Sectional change 32 500 21 000 14 000 21 000 60 000 60 000 60 000 250 000 60 000 60 000 60 000 21 000 14 000 61 000 28 000
length 10 500 60 000 32 000 32 000 20 000 20 000 40 000 40 000 20 000 20 000 32 000 32 000 20 000 98 000 10 000
Steel plate deck thickness 16 14 12 14 16 14 16
Steel plate deck trough rib 320 × 240 × 8
Steel plate deck
flat rib 250 × 25 200 × 19 230 × 22 200 × 19 190 × 19 200 × 19 230 × 22 200 × 19 250 × 25
External web plate
thickness 22 16 19 22 19 16 19 22 19 16 22
External web
plate flat rib 250 × 25 200 × 22 250 × 25 200 × 22 170 × 16 200 × 22 250 × 25 200 × 22 250 × 25
Internal web plate
thickness 22 16 19 22 19 16 14 16 19 22 19 15 22
Internal web
plate flat rib 250 × 25 200 × 22 250 × 25 200 × 22 160 × 16 200 × 22 250 × 25 200 × 22 250 × 25
Lower flange thickness 15 13 14 16 22 16 14 12 11 10 11 12 14 16 22 16 14 11 15
Lower flange trough rib 320 × 240 × 8 320 × 240 × 6 320 × 240 × 8
(Note) All materials are SM990Y.
3 500-tf floating crane 3 500-tf floating crane 3 500-tf floating crane Tower top crane (30-tf hoisting capacity)
600-tf floating crane
Traveling crane
Ikuchijima Island side Ohmishima Island side Ikuchijima Island Traveling crane Ohmishima
Large lower main-tower Island side
Large lower main-tower block side
block
3 500-tf floating crane Traveling crane Traveling crane 3 500-tf floating crane
3 500-tf floating crane
Large block and the
Ikuchijima Island side Large block and the tower as a single Ohmishima Island side Ikuchijima Island Ohmishima
tower as a single structure side Island side
structure (L = 163 200)
(L = 123 200)
Displacement protective facility
1A P1 P2 2P 3P P3 4P 1A P1 P2 2P 3P P3 4P
Displacement protective facility
Large block in the side span
( L = 102 000 )
Step 3 Step 6
1. Installing the climbing crane (3 500-tf floating crane) 1. Installing the overhangs in the center span portion
2. Installing the upper single members of the tower 2. Closing the girders in the center span portion
3. Installing the tower top crane Tower top crane
Tower top crane (160-tf hoisting capacity) Traveling crane Traveling crane
(160-tf hoisting capacity)
V o l . 36 N o . 2 J u n e 2003
Ikuchijima Island Ohmishima
Ikuchijima Island side Ohmishima Island side Island side
side
altogether erected as a single large block with floating Table 1 Design specification
cranes to the PC girder section. Item Description
The length of the large girder block in the side span, Road name Route 317 (Onomichi-Imabari route)
which is about 100 m, was determined and designed Bridge name Tatara Bridge
to be self-supporting as a single beam. It is the first Bridge type Three-span continuous composite cable stayed bridge
time in the world that both balancing erection and large Bridge length (m) L = 1 480
block erection were used for erection of girders. For Span length (m) L = 270 + 890 + 320
the center span, the work of main-girder cantilever B live load (Specifications for Highway Bridges)
Design live load Feb. 1994
erection using traveler cranes was conducted block by
block for both work areas. Road specification Category 1, Class 3
Design speed (km/h) V = 80
3. Basic design conditions Number of lanes 4 lanes (9.5 m × 2) + sidewalk (2.5 m × 2)
January 1994 and continued for about one and a half Side span on the 1A side (m) A = 300, R = 600
Horizontal
years. Table 1 shows the design specifications, while alignment Center span Straight line to a plane
Table 2 shows a list of quantities used in the design. Side span on the 4P side (m) A = 539.838, R = 599.700
3.2 Loads Vertical Side span (%) 0.65 grade to straight line
alignment Center span (%) 0.325 parabola
Table 3 and 4 show design loads and combinations of
loads, respectively. Under clearance (m) 26 m from nearly highest tide level
(T.P.+2.200+26.000)
4. General structural analysis Shape
Inverted Y shape with steel slits (base designed
as a trapezoidal structure with the bottom side
shorter than the topside)
4.1 Analytical procedure
Tower height (m) H = 220 (T.P. + 226.000)
The general structural analysis flowchart is shown in Main tower
Base : 12TT × 8.5LL, Top : 6TT × 6LL
Fig. 7. To begin with, cable prestress was determined Sectional dimension (m) (LL : direction of bridge axis; TT : direction
by infinitesimal deformation analysis to finalize the perpendicular to bridge axis)
condition of the final profile. Then, sectional force Shape Steel girder section: 3-cell steel box girder
PC girder section: 3-cell PC box girder
analysis was conducted for each loading case by
Main girder
linearized finite displacement analysis using this Girder height (m) H = 2.7
(at the center of the bridge of the standard part)
completed system model in which initial internal force
Girder width (m) Total width : 30.6, Outside web interval : 21.8,
was set under this condition of the final profile. Then, Cable anchoring width : 23.0
sectional force, displacement and reaction were Two-plane multi-fan 21-level non-grout PWS
Cable shape (strand f 7 mm)
calculated and the results were edited for use in design Asphalt pavement
Type
of each member. Roadway (mm) Steel girder section : 65, PC girder section : 75
Pavement
4.2 Analytical model Sidewalk (mm) 30
4.2.1 Modeling of main girders Steel girder section : Steel plate deck,
Deck slab type
A three-dimensional skeleton model was used for PC girder section : PC slab
analysis of the overall structure (Fig. 8). It is a fishbone Anchoring Main tower side Fixing block method
model in which each girder is a single road and virtual method Main girder side Web-mounting square column anchoring method
members are extended to cable anchor points. During Main steel Main tower SS400, SM490Y, SM570
members
modeling, the axial centers of girders were placed at Main girder SS400, SM490Y
the middle point between the diagram center and the PC girder member standard (N/mm2) sck = 24
design strength
shear center so as to allow it to be used also as a {kgf/cm2} {sck = 240}
dynamic analysis model. Cable strand allowable ( N/mm2) s = 640
4.2.2 Modeling of main tower stress {kgf/cm2} {s = 6 400}
Cable length was taken into consideration for analysis 1A P1 P2 2P 3P P3 4P
of the main tower by creating a main tower model in Vertical direction F F F F F F F
which virtual members are extended from the axial Supporting
conditions Direction perpendicular to bridge axis F M M F F M F
center of the tower to cable anchor points (Fig. 9). In Direction of bridge axis M M M K = 2 000 t/m K = 2 000 t/m M M
reality, even though the target points of cables for the (Note) F : FIX
center span and the side spans are set on the axial line M : MOVE
45
V o l . 36 N o . 2 J u n e 2003
46
V o l . 36 N o . 2 J u n e 2003
2 P + W + T + SD + E 1.50 Li = L + I
1 P 1.00 14 {140} 0 { 0} P = D + PS + PT + CR + SH + CW
2 P + Li + SD 1.00 14 {140} 0 { 0} Li = L + I
L (EQ) : live load during earthquake
3 P + Li + T + SD 1.15 16 {161} 0.5 { 5}
SD should take a value 50% reduced.
4 P + Li + W + SD 1.50 21 {210} 2.5 {25}
5 P + EQ + L ( EQ ) + T + SD 1.50 21 {210} 3.0 {30}
(Note) P : Main load W : Wind load CR : Creep Li : Live load (including impact) EQ : Seismic load
SH : Dry shrinkage T : Temperature L (EQ) : Live load during earthquake CW : Counterweight SD : Movement of supporting point
PS : Prestress L : Live load E : Fabrication/erection error load PT : Prestress inside PC girder I : Impact coefficient
Calculation of cable
prestress (PS)
Determination of PS
Preparation of two
Preparation of 3D erection stage model dimensional final profile
model for erection stage
Li, T, SD, W, L (EQ) CR, SH EQ (at the time of balancing erection) (at the time of balancing erection)
(all erection step)
(at the time of cantilever erection) (at the time of cantilever erection)
Summation of sectional force, displacement and reaction of completed system Summation of sectional force, displacement, reaction, acceleration, and response
(ordinary time, storm and earthquake) amplitude of erected system (ordinary time, storm and earthquake)
Individual
analyses
Main tower buckling analysis Skeleton analysis for floor FEM analyses for
individual reviews, such
Main girder buckling analysis arrangement system as cable fixing points
Section
design
47
V o l . 36 N o . 2 J u n e 2003
Input direction
Analysis Calculation of ground
Analytical method Input wave Input method
spring Bridge axis Perpendicular
No. to bridge axis Vertical
Same phase
Response spectral analysis
1 A short-cycle spectra (multiple point Kurushima Method
(CQC method) simultaneous input)
49
V o l . 36 N o . 2 J u n e 2003
erection, the two conditions that were considered very reduction of wind speed and spatial correlation
susceptible to wind load, or the maximum overhang of quartering wind, it was confirmed that the
condition immediately before center span closing, and safety factor of allowable stress is 1.7, and that
the maximum balancing condition before large side-span the first horizontal bending mode would be
block erection, were studied to determine appropriate satisfied.
wind loads. r As an extra vibration-damping countermeasure,
6.2.1 Maximum balancing condition a tie-down plan to connect sinkers under the
When cables are installed to the seventh level, the water and girders was checked by wind tunnel
bridge would look like a balancing toy. As it was tests and analyses, which confirmed the
important to ensure stability of the bridge under such effectiveness of the method and indicated a
a condition against wind, wind tunnel tests were possibility of reducing both girder horizontal
conducted, which indicated that excessive negative displacement and bending moment of girders at
reaction would occur at the diagonal bent by gust the bases of the towers to about 60% compared
response. Subsequent analytical study lead to re- with the case of no such plan.
examination of the erection procedure to reduce negative t It was finally decided that no special
reaction at the diagonal bent. To be specific, large countermeasure would be taken because of the
main-girder blocks in side spans were erected at the special characteristics of wind direction and
lower first and second level cables under the side spans. speed, low reproduction probability and the
No tension was given until the system became stabilized proven fact that the first horizontal mode would
so as not to generate negative reaction at the diagonal be satisfied.
bent.
6.2.2 Maximum cantilever condition
7. Check of stability of main girders
The maximum cantilever erection of the center span
against buckling
goes to about 430 m, the largest ever in the world. How In case axial compressive stress in the bridge axial
to stabilize the cantilever against wind load had been direction prevails for a long-span cable stayed bridge
one of the earliest issues. Before commencement of the with flattened box girder, such as the “Tatara Bridge,”
design work by the Joint Venture, various wind tunnel it is essential to study stability against whole buckling.
tests were conducted to work on the issue. Major points One of the standard methods to evaluate stability
of focus were identified as follows. against whole buckling is use of the stability inspection
(1) Characteristics of local wind were studied by a equation using effective buckling length (Le), as given
wind tunnel test using a model formed after the in the Specifications for Highway Bridges (“SHB”).
local topography. It was found that quartering wind But if this method is applied to variable sectional
with very hard turbidity is likely to blow because members, as seen in main girders of a cable stayed
of the influence of the mountains behind the “Tatara bridge, the effective buckling length at the center span
Bridge.” where axial compressive strength level is low becomes
(2) The maximum cantilever span length is 430 m too long and the resultant design would have to be
and its primary natural frequency is about 16 sec. made based on a practically unassumable buckling
If this condition is handled by a conventional length. Then, uneconomical cross sections could result.
vibration-damping device, the device would have Today, thanks to the improved capability of computers,
to be very big and could not be manufactured in some cases, elastoplastic analysis of an entire system
because of its size. with residual stress and initial irregularity taken into
With these points in mind, analyses and wind consideration is conducted to carry out stability
tunnel tests were conducted to work on the design inspection. For the “Tatara Bridge,” the Bridge Planning
of sections and vibration control during actual Committee for the “Tatara Bridge” (hereafter called
erection. The following points were actually Tatara Committee) of the Honshu-Shikoku Bridge
reviewed. Authority decided to carry out elastoplastic analysis
q Erection machinery was converted into a model, for an entire system and also carried out buckling
which was used in an erection system wind force experiments using an entire system model. It was
test. Then, detailed data, such as aerodynamic ultimately found that the experiment results have a
coefficient, necessary for design work were good agreement with the elastoplastic analysis results
obtained. for buckling modes and buckling load capacity and
w Gust response analysis of the maximum confirmed the validity of the analysis.
cantilever erection system was conducted and the These reports indicated that critical points in terms
gust response coefficient for the main girder of buckling are the same members whose effective
erection stage was newly established to be 2.0 buckling length was found shortest by the buckling
(while it is 1.9 for the final profile). analysis. For the “Tatara Bridge,” the sectional design
e Considering the effect of quartering wind on that satisfies the stability inspection equation given in
51
V o l . 36 N o . 2 J u n e 2003
the SHB by using their effective buckling length was e The tower blocks were designed as block
used only for members whose effective buckling length members for the axial force and two-directional
was shortest, located near the main tower. bending. Since the in-plane effective buckling
When the effective buckling length was calculated, length is close to the out-plane effective buckling
the effective shearing modulus method (Ef method) length, the bi-axial bending stability inspection
was used. As a result, the effective buckling length for equation was adopted.
the main girders (Le) turned out to be 34.9 m, almost r Since the large blocks for the lower part were
twice (40 m) the cable fixing interval. This value was to be assembled on the ground, each block volume
rounded off to 35 m and the stability inspection equation was determined to be 160 tons considering the
was applied only to the main girders near the towers. lifting capability of companies. Single member
Fig. 10 shows the portions to which the buckling stability erection blocks for the upper parts were
inspection was conducted. For allowable stress relative determined to be less than 145 tons each so that
to local buckling, values given by the block model they could be handled by cranes to be set up at
approach were used. the site.
t Blocks were all connected by friction joints
8. Design of main tower using high tensile bolts (HTB). The steel plates
8.1 Design outline of main tower were to be designed as 50% metal touch. Large
The design of the main tower was developed based on block interfaces and horizontal members were
supplementary review, including FEM, in addition to designed as 100% high tensile bolts to absorb
the use of the sectional force used in the whole bridge production and erection errors.
analysis. The major components to be designed were 8.2 Effective buckling length of main tower
as follows. The effective buckling length of the main tower was
(1) The tower anchor frame and the base of the determined based on the values calculated from the
tower three methods as follows.
(2) Tower blocks (1) The effective buckling length of all members
(3) Crossing zone and knuckle parts was calculated based on Pcr (buckling load) of the
(4) Lower horizontal beam (horizontal beam at the primary mode.
level of the road) (2) The effective buckling length was calculated
(5) Upper and intermediate horizontal beam based on Pcr of the primary mode of each member.
(6) Cable anchor (3) Inflection points of a mode in which each member
The major design points of the tower are as follows. buckles were selected from the mode diagram and
q The shape of the main tower is an inverted Y the effective buckling length was calculated using
with a cut-off corner section, which was found the mode diagram.
to be excellent in wind resistance by the wind 8.3 Design of crossing zone and knuckle
tunnel tests. Corner cut-off is different between At a crossing zone of a conventional rectangular cross-
the lower part of the tower and the upper part. section, flange forces of horizontal members are
The corner cut-off for the lower part is effective transmitted to the webs of the tower blocks as shear
in controlling the vortex induced vibration. The via the diaphragms of the crossing zones. But since the
corner cut-off for the upper part is designed to “Tatara Bridge” has a single-chamber 12-angle cross
provide a section effective against galloping. section with cut-off corners, stress would not smoothly
w For the cross section of the main tower, as transmit. For stress of webs of horizontal members,
ease of production and erection was considered smooth stress transmission would not be realized due
important, a single chamber box section was to the small width of the webs in the tower blocks.
adopted. A three-chamber section divided by Thus, internal webs were extended for the crossing
vertical diaphragms had to be used for the zones of the horizontal members to turn the cross section
crossing zone and knuckle of the lower horizontal near the crossing zones into a three-chamber shape for
members and the cable anchor in the upper part positioning stays of horizontal members (Fig. 11). In
for unavoidable structural reasons. terms of calculation, the plate thickness of the internal
web and the external web was converted as a single
plate so that the cross-section is interpreted as a single-
chamber rectangular shape and the Okumura-Ishizawa
Method was used to carry out simple design. Then, the
3D FEM analysis was used to check the design before
The minimum effective buckling
length was used. finally determining the plate thickness.
The stability inspection equation was applied only to this range. For the “Tatara Bridge,” knuckle points of the tower
blocks were aligned with the line of the girder edge
Fig. 10 Check for buckling stability of main girder for the appearance and thus there is a clearance of
52
V o l . 36 N o . 2 J u n e 2003
(a) Crossing zone section in basic design stage the knuckle part would be the largest plate thickness
Internal web External web Horizontal beam web in this bridge (t = 44 mm, SM 570).
8.4 Cable anchor of main tower
For the structure of the cable anchor, it was decided
that cast fixing blocks would be fixed to longitudinal
Flange Elevator Horizontal beam flange
opening girders of the main tower via HTB M30. Fixing blocks
are aligned to the positions of the horizontal diaphragms
so that horizontal force of center span and side span
Internal web External web Horizontal web cables will be transmitted via longitudinal girders and
Strees concentration caused diaphragms (Fig. 13).
by the suddenly change of
stress transmission
9. Design of steel main girders
9.1 Design outline of steel main girders
(b) Crossing zone section in detailed design stage Major design review items for steel main girders are
Internal web extended as follows.
Internal web External web
Horizontal beam web (1) Design of steel deck and floor
(2) Design of sidewalk
(3) Design of main girder cross section
Elevator
Flange
opening
Horizontal beam flange (4) Design of cable anchor
(5) Strengthened design of supporting point
(6) Design of connection girder
Internal web External web Horizontal web Major points to note for design consideration are as
The internal web was extended to follows.
modify the structure for smooth
transmission of stress q U-formed ribs with 8 mm thickness are used
for longitudinal ribs of steel plate decks. The
Fig. 11 Crossing zone section
standard interval of lateral ribs is 2.5 m. Joints
of steel plate decks are welded, while HTB
about 4 m between the knuckle of the lower part of the friction jointing is used for longitudinal ribs.
main tower and the upper flanges of the lower horizontal For shop-assembled joints, such as large blocks
beams. Therefore any sudden change in bending moment and the tower as a single structure, longitudinal
could cause a large stress to the knuckle parts. As a ribs are also welded.
solution, the structure of the crossing zone was extended w If stress of the main girder system is applied
to the knuckle part to broaden the internal web to to the sidewalk, its design will become
provide a strengthening member to the structure. At the uneconomical. To avoid this, expansion joints
same time, the cross section of the longitudinal rib of are to be installed at an interval of 10 m and
the flange was also broadened to cope with the secondary designed as non-composite separate structures
stress due to the curvature of the knuckle part. Finally, independent of main girders.
the design results, including the crossing zone, were e The main girders are flattened box girders with
checked by 3D FEM analysis (Fig. 12). As a result, a height of 2.7 m and a total width of 30.6 m.
Its structure is a single-box girder with three-
chamber structure composed of four web plates.
The center cell, in which the interval of web
plates is largest, has a width of 9.04 m. Thus,
the main girders were designed as wide stiffened
plates. For steel plate decks, a bi-axial
Fixing block
Cable
Tower wall (flange)
Tower wall (web)
Fig. 12 Analysis model for 3-D FEM Fig. 13 Cable anchor (tower)
53
V o l . 36 N o . 2 J u n e 2003
compression check was conducted since it was bridge, axial compressive force acts on them due to
impossible to ignore stress in the direction horizontal components of cable tension. Therefore, it
perpendicular to the bridge axis caused by cable is necessary to check longitudinal ribs for their resistance
fixing. to local buckling.
r For the cable anchor, square column anchors For 8-mm-thick trough ribs, blocks composed of deck
were used at the outside of external web plates. plates and trough ribs were put to load capacity tests
The detailed structure was determined after to confirm that no local buckling will occur. Based on
fatigue testing and FEM analysis. the results of buckling tests and elastoplastic analysis,
t Composite girders play a pivotal role in a structural arrangement in which another row of bolts
connecting PC girders to steel box girders. Rear is added only to splice plates at one side, as shown in
face fixing, a composite girder system with Fig. 14, was applied to reduce the stress concentration
proven performance from the “Ikuchi Bridge” immediately before the splices so as not to reduce load
experience, was used. For backing concrete, high- capacity at joints. For 6-mm-thick trough ribs, elastic
fluidity concrete was cast in-situ to realize buckling analysis was made to set allowable stress with
downsizing of blocks, use of smaller erection regard to local buckling to 167 N/mm2 {1 700 kgf/cm2}.
cranes, and reduction in site work. 9.4 Design of cable anchor
9.2 Design of wide stiffened plates Web plate fixing square column anchors were used for
At the center cell of the “Tatara Bridge,” the interval cable fixing. Where stress was expected to intensify,
of web plates is 9.04 m and that of lateral ribs is 2.5 the results of large fatigue tests, conducted in an earlier
m. They are sufficiently wide compression-stiffened stage of design, as well as other reviews including FEM
plates with an aspect ratio (a) of 0.277. The SHB, analysis were used to determine shapes of elements,
however, assumes compression stiffened plates of about such as the fillet shape of bearing plates used for cable
2 in aspect ratio and defines a level of stiffness of fixing assemblies. The structure of the cable anchor is
stiffened plates that makes the buckling mode become shown in Fig. 15.
nodes at the lateral rib positions. According to the The following points were reviewed in designing the
regulation of compression-stiffened plates in the section of the cable anchor.
superstructure design standard of HSBA, the definition (1) Structure of bearing plate (FEM analysis)
of the SHB is used as an applicable specification. But (2) Stress check at anchor and the area near it (FEM
for such wide compression-stiffened plates as used for analysis)
the “Tatara Bridge,” the required stiffness for a stiffened (3) Load sharing ratio of vertical component of cable
plate would be so large that it would be a large cross- tension (grid analysis)
section of unrealistic size. (4) Main girder in-plane bending stress distribution
The Tatara Committee then came up with the Tatara (FEM analysis)
Bridge Design Procedure (draft), based on which wide
stiffened plates were designed for longitudinal and 75
lateral stiffeners and allowable stress of local buckling
was calculated using the block model approach. For A A
longitudinal ribs of the “Tatara Bridge,” closed section
ribs (U ribs) were to be used both at the steel plate 5
deck side and the bottom flange side and thus the load
capacity curve in the Buckling Design Guideline (Japan
Road Association) that is almost equal to the Standard
Load Capacity Curve (V) in the SBH (Feb. 1994, Japan
A-A
Society of Civil Engineers) was used for ultimate
strength of effective stiffeners used in the block model
Fig. 14 Joint of longitudinal rib (unit : mm)
approach. Since steel plate decks are supported at cable
fixing points and loaded by in-plane compression in the Deck plate
direction of bridge axis and the direction perpendicular
ragm
to bridge axis, they were given bi-axial buckling checks. Anchor Diaph
flange
9.3 Longitudinal ribs Square
column Anchor rib
Trough ribs (320 × 240 × 8) were used for all anchor Auxiliary rib
longitudinal ribs at the steel plate deck side and almost Bearing plate Internal
strengthening Internal
all other longitudinal ribs except for those of bottom web strengthening
Internal structure
flanges around the center of the center span. Ribs strengthening
flange
measuring 320 × 240 × 6 were used for some bottom Bottom flange External web plate
flanges near the center of the center span. Since
longitudinal ribs form part of the main girders of the Fig. 15 Cable anchor (main girder)
54
V o l . 36 N o . 2 J u n e 2003
(5) Main girder axial direction stress distribution check was made assuming tensile force is transmitted
(FEM analysis) only by w stud pins. For the mechanism to transmit
(6) Main girder internal strengthening structure shear to backing concrete, q adhesion and friction and
Based on the results of these reviews, stress sharing w stud pins may be considered effective, but to be on
ratio and stress concentration coefficient were examined the safe side, adhesion/friction is ignored and w stud
to check the level of working stress. For stress pins alone were included in the design consideration.
concentration at some special positions, such as near For the shear fracture mode at PC girders, the following
the scallop, the cross section design was developed two points were focused upon, while the design check
directly from FEM analysis results. for shear was made and shear reinforcement using
9.5 Design of connection girders between PC rebars was considered:
deck and steel deck · Fracture by shear cracking at PC beams
9.5.1 Stress transmission mechanism of connection · Fracture by direct shear at the interfaces between
girders PC girders and backing concrete
The “rear face plate method of partial connection backing 9.5.2 Field construction of connection girders
concrete type” adopted for the “Ikuchi Bridge” was High-fluidity concrete was used for backing concrete
used for the structure of connections jointing steel and for composite girders and was cast in-situ. This aimed
PC girders. The structure of the composite girder is at reducing the weight of composite girder blocks,
illustrated in Fig. 16. Connections are located near the eventually helping downsize crane ships for erection.
P2 and P3 intermediate piers. Focusing on negative Prior to field casting, a casting experiment using a full-
reaction on supporting points and girder bending size model was conducted to check if concreting would
moment, the positions optimal for both of them were be feasible or not. Gap filling between composite girders
determined. The structural arrangement was developed and PC girders was also conducted together with placing
so that stress working on the steel girders is dispersed of backing concrete. These gaps also play a role of hinge
by steel girder strengthening members and ultimately connection to prevent PC girder construction error from
transmitted smoothly to PC girders via backing concrete. affecting steel girders. To be specific, composite girders
The arrangement for axial direction compressive force are placed in the direction of the steel girder target
working on steel cells is that it is transmitted to PC regardless of the workmanship of PC girder erection
girders by three stress transmission mechanisms, or q so as to prevent workmanship error of PC girders from
rear face plate, w stud pins, and e adhesion and affecting the entire system.
friction of steel plate and concrete, via backing concrete. With this method, if PC girder dead load error or
As in the case of the “Ikuchi Bridge,” adhesion and rigidity error occurs, the road surface should break at
friction were not considered in the cross-section design the gaps. As it turned out, however, no major error
so as to be on the safe side. The sharing ratio of stud actually occurred and if any had it could be absorbed
pins against axial direction compressive force in a by the pavement. No actual problem prevented the
system that ignores adhesion and friction is as follows work.
for a 19-to-25-mm-thick rear face plate.
· Headed stud (f22 × 80 mm, 3 × 7 rows) -- 35%
10. Displacement control mechanism
· Angular steel block (28 × 28 × 250 mm) -- 50% Elastic rubber bearing shoes were used for vertical
The following three measures were reviewed for bearing shoes on the tower of the “Tatara Bridge.” In
tensile force in the axial direction. case spring constant in the direction of bridge axis is
q Adhesion and friction of steel and concrete low, the buckling mode of the tower will appear first
w Stud pins and as spring constant rises, the buckling mode of the
e PC steel members girder will become critical. As spring constant increases,
Axial compressive stress prevails at composite girders the total load capacity also increases, but when it comes
and tensile stress is very small. Therefore, the design to a certain level of elastic fixed spring, the total load
e
capacity will not change with any further increase of
sid
der the spring. Raising the spring constant can limit girder
gir
el
e Ste displacement in the direction of bridge axis. For the
sid
der “Tatara Bridge,” the buckling mode, total load capacity
gir
PC and bridge displacement in the bridge axial direction
were totally considered and the spring constant of 39.2
× 103 kN/m {4 000 tf/m} was adopted for the entire
bridge.
In addition, one of the special characteristics of the
“Tatara Bridge” is that PC girders at the side spans
Fairing serve as a counterweight and that the dead load reaction
Fig. 16 Joint structure of concrete and steel girders of the vertical bearing shoes at PC girders (BP-B shoe)
55
V o l . 36 N o . 2 J u n e 2003
– Acknowledgment –
56