Activity Activity Orig Early Early 2011 2012 2013

D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC J
ID Description Dur Start Finish

Water Towers Preliminary Schedule


PROJECT START
STR000 Project Start Milestone 0 02JAN11
TOTAL PROJECT DURATION
TPD000 Total Project Duration 890* 02JAN11 13NOV13
MOBILIZATION AND SITE WORKS
MOB000 Mobilization and Site works 60 02JAN11 14MAR11
SUBMITTALS
SUB000 Submittals (Materials, ShopDrawings & Subcont.) 150 02JAN11 27JUN11
WATER TOWER NO. 1
WT1000 Start Construction of Tower No.1 0 15MAR11
WT1010 Excavation and sub-structure (Foundation) 30 15MAR11 18APR11
WT1020 Lower Shaft 35 19APR11 29MAY11
WT1030 Stiffener Ring Beam 14 30MAY11 14JUN11
WT1040 Uppershaft 15 15JUN11 02JUL11
WT1050 Basket 75 03JUL11 27SEP11
WT1060 Roof 30 28SEP11 01NOV11
WT1070 Electrical Works 200 27MAR11 14NOV11
WT1080 Mech. Works (Internal & External pipes & Valves) 220 27MAR11 07DEC11
WT1090 Finishing Works 35 08NOV11 18DEC11
WT1100 Testing and Commissioning (Electromechanical ) 30 08DEC11 12JAN12
WATER TOWER NO. 2
WT2000 Start Construction of Tower No.2 0 15MAR11
WT2010 Excavation and sub-structure (Foundation) 30 15MAR11 18APR11
WT2020 Lower Shaft 35 07JUN11 17JUL11
WT2030 Stiffener Ring Beam 14 18JUL11 02AUG11
WT2040 Uppershaft 15 03AUG11 20AUG11
WT2050 Basket 75 02NOV11 29JAN12
WT2060 Roof 30 30JAN12 06MAR12
WT2070 Electrical Works 302 27MAR11 15MAR12
WT2080 Mech. Works (Internal & External pipes & Valves) 314 27MAR11 29MAR12
WT2090 Finishing Works 35 13MAR12 22APR12
WT2100 Testing and Commissioning (Electromechanical ) 30 31MAR12 03MAY12
WATER TOWER NO. 3
WT3000 Start Construction of Tower No.3 0 15MAR11
WT3010 Excavation and sub-structure (Foundation) 30 15MAR11 18APR11
WT3020 Lower Shaft 35 19APR11 29MAY11
WT3030 Stiffener Ring Beam 14 30MAY11 14JUN11
WT3040 Uppershaft 15 15JUN11 02JUL11
WT3050 Basket 75 03JUL11 27SEP11
WT3060 Roof 30 28SEP11 01NOV11
WT3070 Electrical Works 203 27MAR11 17NOV11
WT3080 Mech. Works (Internal & External pipes & Valves) 214 27MAR11 30NOV11
WT3090 Finishing Works 35 08NOV11 18DEC11
WT3100 Testing and Commissioning (Electromechanical ) 30 01DEC11 05JAN12
WATER TOWER NO. 4
WT4000 Start Construction of Tower No.4 0 15MAR11
WT4010 Excavation and sub-structure (Foundation) 30 15MAR11 18APR11
WT4020 Lower Shaft 35 11JUN11 20JUL11
WT4030 Stiffener Ring Beam 14 21JUL11 06AUG11
WT4040 Uppershaft 15 07AUG11 23AUG11
WT4050 Basket 75 02NOV11 29JAN12
WT4060 Roof 30 30JAN12 06MAR12
WT4070 Electrical Works 300 27MAR11 13MAR12
WT4080 Mech. Works (Internal & External pipes & Valves) 350 27MAR11 10MAY12
WT4090 Finishing Works 35 13MAR12 22APR12
WT4100 Testing and Commissioning (Electromechanical ) 30 12MAY12 14JUN12
WATER TOWER NO. 5
WT5000 Start Construction of Tower No.5 0 19APR11
WT5010 Excavation and sub-structure (Foundation) 30 19APR11 23MAY11
WT5020 Lower Shaft 35 26JUL11 04SEP11
Start Date 01JAN11 WTP0 Sheet 1 of 3
Early Bar
Finish Date 13NOV13 KHALID ALI ALKHURAFI Date Revision Checked Approved
Float Bar
Data Date 01JAN11
Run Date 15DEC10 17:59 Progress Bar
Water Towers Preliminary Schedule
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
Activity Activity Orig Early Early 2011 2012 2013
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC J
ID Description Dur Start Finish
WT5030 Stiffener Ring Beam 14 05SEP11 20SEP11
WT5040 Uppershaft 15 21SEP11 08OCT11
WT5050 Basket 75 07MAR12 02JUN12
WT5060 Roof 30 03JUN12 07JUL12
WT5070 Electrical Works 300 02NOV11 20OCT12
WT5080 Mech. Works (Internal & External pipes & Valves) 350 27JUN11 11AUG12
WT5090 Finishing Works 35 14JUL12 22AUG12
WT5100 Testing and Commissioning (Electromechanical ) 30 21OCT12 24NOV12
WATER TOWER NO. 6
WT6000 Start Construction of Tower No.6 0 19APR11
WT6010 Excavation and sub-structure (Foundation) 30 19APR11 23MAY11
WT6020 Lower Shaft 35 13SEP11 23OCT11
WT6030 Stiffener Ring Beam 14 24OCT11 08NOV11
WT6040 Uppershaft 15 09NOV11 26NOV11
WT6050 Basket 75 07MAR12 02JUN12
WT6060 Roof 30 03JUN12 07JUL12
WT6070 Electrical Works 300 01MAY11 17APR12
WT6080 Mech. Works (Internal & External pipes & Valves) 350 27JUN11 11AUG12
WT6090 Finishing Works 35 14JUL12 22AUG12
WT6100 Testing and Commissioning (Electromechanical ) 30 12AUG12 15SEP12
WATER TOWER NO. 7
WT7000 Start Construction of Tower No.7 0 19APR11
WT7010 Excavation and sub-structure (Foundation) 30 19APR11 23MAY11
WT7020 Lower Shaft 35 13SEP11 23OCT11
WT7030 Stiffener Ring Beam 14 24OCT11 08NOV11
WT7040 Uppershaft 15 09NOV11 26NOV11
WT7050 Basket 75 08JUL12 02OCT12
WT7060 Roof 30 03OCT12 06NOV12
WT7070 Electrical Works 300 01MAY11 17APR12
WT7080 Mech. Works (Internal & External pipes & Valves) 350 01MAY11 14JUN12
WT7090 Finishing Works 35 13NOV12 23DEC12
WT7100 Testing and Commissioning (Electromechanical ) 30 16JUN12 19JUL12
WATER TOWER NO. 8
WT8000 Start Construction of Tower No.8 0 19APR11
WT8010 Excavation and sub-structure (Foundation) 30 19APR11 23MAY11
WT8020 Lower Shaft 35 01NOV11 11DEC11
WT8030 Stiffener Ring Beam 14 12DEC11 27DEC11
WT8040 Uppershaft 15 28DEC11 15JAN12
WT8050 Basket 75 08JUL12 02OCT12
WT8060 Roof 30 03OCT12 06NOV12
WT8070 Electrical Works 300 01MAY11 17APR12
WT8080 Mech. Works (Internal & External pipes & Valves) 350 01MAY11 14JUN12
WT8090 Finishing Works 35 13NOV12 23DEC12
WT8100 Testing and Commissioning (Electromechanical ) 30 16JUN12 19JUL12
WATER TOWER NO. 9
WT9000 Start Construction of Tower No.9 0 19APR11
WT9010 Excavation and sub-structure (Foundation) 30 19APR11 23MAY11
WT9020 Lower Shaft 35 20DEC11 30JAN12
WT9030 Stiffener Ring Beam 14 31JAN12 15FEB12
WT9040 Uppershaft 15 16FEB12 06MAR12
WT9050 Basket 75 07NOV12 03FEB13
WT9060 Roof 30 04FEB13 12MAR13
WT9070 Electrical Works 300 05APR12 24MAR13
WT9080 Mech. Works (Internal & External pipes & Valves) 350 05FEB12 24MAR13
WT9090 Finishing Works 35 19MAR13 28APR13
WT9100 Testing and Commissioning (Electromechanical ) 30 25MAR13 28APR13
ELECTRICAL AND CONTROL BUILDING
ECB000 Start const. Electrical & Control Bulding 0 24MAY11
ECB010 Concrete works 65 24MAY11 07AUG11
ECB020 Finishing Works 60 08AUG11 16OCT11
GUARD HOUSE
GH0000 Start Construction of Guard House 0 28JUN11

Start Date 01JAN11 WTP0 Sheet 2 of 3


Early Bar
Finish Date 13NOV13 KHALID ALI ALKHURAFI Date Revision Checked Approved
Float Bar
Data Date 01JAN11
Run Date 15DEC10 17:59 Progress Bar
Water Towers Preliminary Schedule
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
Activity Activity Orig Early Early 2011 2012 2013
D JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC J
ID Description Dur Start Finish
GH0010 Concrete Works 30 28JUN11 01AUG11
GH0020 Finishing Works 25 02AUG11 30AUG11
PUMP ROOM
PR0000 Start Construction of Pump Room 0 11OCT11
PR0010 Concrete works 30 11OCT11 14NOV11
PR0020 Finishing works 25 15NOV11 13DEC11
SUBSTATION
PR0040 Start Construction of Sub-station 0 16JUN13
PR0050 Concrete Works 60 16JUN13 24AUG13
PR0060 Finishing Works 70 25AUG13 13NOV13
BOUNDRY WALL
PR0080 Boundry Wall 100 03NOV11 01MAR12
EXTERNAL WORK
PR0100 External Works 101 22MAY13 16SEP13
PROJECT COMPLETION AND HANDING OVER
PR0130 Project Completion and Handing over 0 13NOV13

Start Date 01JAN11 WTP0 Sheet 3 of 3


Early Bar
Finish Date 13NOV13 KHALID ALI ALKHURAFI Date Revision Checked Approved
Float Bar
Data Date 01JAN11
Run Date 15DEC10 17:59 Progress Bar
Water Towers Preliminary Schedule
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.