You are on page 1of 55

Vol. 8 No.

3 October 1973 Sydney Opera House Special Issue

THEARUP Published by
Ova Arup Partnership
13 Fitzroy Street, London, W1 P 6BO

JOURNAL Editor: Peter Haggett


Art Editor: Desmond Wyeth FSIA
Editorial Assistant: David Brown
Contents

Introduction, 2
by J. Zunz

Sydney Opera House, 4


by Ova Arup and J. Zunz

Design of the Concourse, 22


by Ova Arup and R. Jenkins

The glass walls, 30


by D. Croft and J. Hooper

Grouting prestressing ducts, 42


by J. Nutt

Adhesives for structural jointing, 48


by T. O'Brien and J. Nutt

Influence of corrosion on the design, 52


by J. Nutt

Sydney Opera House Awards, 54

Credits

Editor's note

Cover: East elevation of shell structure

immense imaginative gifts. I n those early years the problem-solving processes which ensued
Introduction he inspired all who came under his magic spell, when new technology had to be developed or
and although there were great difficulties, they even when existing technology had to be
were gradually solved one by one and by adapted for new and untried forms. It is just
Jack Zunz 1963-64 the situation began to look quite possible that, in his seeming blindness to see
that his collaboration with us was vital for the
hopeful.
But then the going got rougher and Litton was technical success of the scheme, lies another
For some years we have considered writing the factor in his urge to leave the job.
Opera House story. We have never done any- pressed to produce drawings for the interiors.
thing about it-perhaps it was lack of time, will, He didn't, couldn't, wouldn't, have it which However, these are personal opinions. Despite
motivation or even the doubt that the building way you will, and he resigned in 1966, leaving the know-ails who have written and lectured
would ever be completed. Now, nearly 15 behind hard feelings, chaos, controversy, but on the subject, no-one will ever really find the
years after construction commenced, the above all a shattered dream. truth. What is truth anyway? Whatever it is it
Queen will officially open it on 20 October. Whatever judgement posterity makes about will remain tucked away in men's minds.
Instead of the book we didn'twrite we thought Utzon's resignation and the subsequentfurore. Post-Utzon, the affair became more orderly,
that the best thing to do would be to celebrate no-one will deny his poetic, conceptual and though cost estimates still kept on rocketing,
the end of the saga with a special issue of The visionary gifts and that his inability (for what- but control was a little tighter and problems
Arup Journal. It contains some of the relatively ever reason) to complete the project is a became more easily soluble. However, the
few technical papers which have been written tragedy. The truth is that he did walk out when whole thing was none-the-less just a shade
about the job as well as some selected photo- information for the interiors and the glass walls duller.
graphs. was virtually non-existent. Hall, Todd and What about Arups? What has the job done to
Littlemore were appointed by the New South us or for us, if anything ? Again, it is probably
It is difficult to believe that the festivities which Wales Government to the unenviable task of
will mark the opening ceremonies take place too early to see it in perspective, but there are
completing the job. some facts and some pointers.
16 years since we started work on the job.
They were faced with the now fixed para- Firstly the facts -we stretched ourselves to the
After the unending technical, human and
meters of the distinctive roof shape, with very limits of our skills. In extending ourselves and
political problems, after spending over £50m,
definite accommodation requirements which making that extra effort we developed our
we may well ask, was it all worthwhile?
could hardly be fitted in, and above all with a know-howjust that little bit more. We use this
It is probably too early to say, but not too early half-finished work of art - and Utzon's Opera knowledge in otherfields. When we have been
to make some observations. Probably the most House has an artistic quality with a capital A. extended as much as we have, it makes our
significant feature of the whole story is the Some of its critics have often said that there ordinary jobs easier and we hope to do them
astonishing reality that in a modern society, was too much art and too little commodity. better. We have had a good deal of publicity,
with all its checks and balances, its account- Unfortunately, Utzon is not at the finishing some critical, but mostly complimentary: we
ants and accountability, its budgets and post to prove whether they were right or have received the Queen's Award for Industry
budgetary controls, a folly on this scale could wrong and half-finished works of art can never and, if travelling broadens the mind, many of
be contemplated. In other words, it is nothing be wholly satisfactorily finished by others. us have had opportunities for mind -stretching.
short of miraculous that it happened at all. Why did Utzon resign - did he jump or was he As for the more speculative consequences -
In concept it is not a building of this age. It has pushed? My guess is that he jumped. His we were and still are in the middle of a great
the romanticism of formereras when autocratic behaviour, his letters, his interviews, all point controversy. Our name is inextricably linked
patronage made great follies possible. Yet, to a path of self-destruction. He ditched his with the building. and while its success will be
when Utzon's scheme was chosen from more friends and collaborators for footling or no linked with Utzon and his successors, its
than 200 competition entries, when the reasons at all and literally overnight left Austra- failure will reflect on us. We became unwilling
Premier of New South Wales was hell-bent on lia never to return - at least not yet. Although pawns in the controversy. On the one hand we
starting the job without drawings, and when Utzon's Opera House was the stuff that dreams wanted to help Utzon and do what was best
all those associated with Utzon caught some are made of, although his use of shapes, for the job, on the other we wanted to act
of the euphoria of creating one of the great materials, textures and colours was individual honourably towards a client who had treated
buildings of the age, it looked as though the and introduced us to unique technical prob- us well and fairly. Whatever we did was bound
improbable would come about after all. lems. I don't think that he ever really under- not to please everybody. So we did all and
Much has been said and written about Utzon's stood the complexity of the problems he was sometimes more than was asked of us and
2 concept of the Opera House. He is a man of creating. Nor do I believe that he understood what we thought was best for the job.
ground level, an assumption which much later
The evolution and was proved not to hold good for the crucial
There are two variants of this layout in other
parts of the final structure, with different spans
southern end of the site. It was also designed
design of the to solve the problem of draining this vast area
and different depth of structure, and before
these dimensions could be fixed the design
(approximately 7000m2). The architect wan-
Concourse at the ted the surface of the Concourse roof to be
went through numerous variations, which
however did not depart essentially from Fig. 2.
absolutely level, without the customary falls to
Sydney Opera drain off the water. Instead, the joints
It will be seen that if it is assumed that horizon-
tal forces could be absorbed at A by the under-
between the proposed 1.83x1.22m sand-
House stone paving slabs would be left open to allow
lying sandstone, and at C by the substructure,
which included a series of reinforced concrete
the water to seep through. This meant that it boxes or longitudinal walls, then C-B and B-A
would not be necessary, and in fact not desir-
Ove Arup and able, to provide a solid slab at the top; the
could be strutted against each other, creating
compression in both struts but reducing the
Ronald Jenkins supporting structure should be formed as,a
series of channels leading the water towards
moments. There would be maximum external
negative moments at B and C and a maximum
the two ends of the Concourse but providing external positive moment somewhere in
This paper first appeared in the Proceedings of support for the sandstone paving slabs along between. A glance at the shape of the 'arch'
the Institution of Civil Engineers, April 7968. line spaced 1.83m apart. Fig. 1 indicates the C-B-E shows that the angle CBA is critical; if
It is reproduced hereby kind permission of the restrictions placed on the cross-section: it is too large the compression forces will be
Council of the Institution of Civil Engineers. (a) Support for paving slabs every 1.83m. excessive, and the strains produced by these
(b) Channels in-.between forces, by the stressing of the cables in these
The structure discussed in this paper generally two members, and by creep and temperature
(c) Total depth of structure should be uniform
known as 'the Concourse' or 'the folded slab stresses, could produce movements which
over the full length of the span, and this might approach a critical stage. However, after
forms a small part of the Sydney Opera House. depth should be as'small as possible.
The architect for the scheme was Jern Utzon, the engineers' proposal had received the bless-
Fig. 2 shows the longitudinal layout of one ing of the architect, a preliminary investigation
of Hellebaak, Denmark, and the structural portion of the final structure. on the basis of the layout as it was then, proved
engineers were Ova Arup & Partners, Con-
sulting Engineers, London. The structure has a that the proposal was structurally sound.
somewhat unusual shape, which was deter- Confining ourselves now to the main section
mined more by architectural than by structural Support for paving slab every 6 ft C-B the task was to design a 'slab' or a series
considerations. As a rule authors of engineering I is is of beams, which would, as economically as
papers only touch lightly on the development possible, meetthe requirements in Fig. 1 which
of a design and the aesthetic intention behind, could take the negative moments at B and C
f mlmum and uniform
it, confining themselves strictly to the struc- chann<t ro
collet
depth over full and the positive at midspan, and which in a
tural, constructional and perhaps functional ninv,aco length of span
dramatic or sculptural way would reflect the
aspects, In the present case, however, the variation in the external forces along the span
authors felt that this approach would be too Fig.1 and indicate how they were resisted at each
narrow, because it would not explain why the Basic requirements for cross-section point.
structure was given this form. Certainly,func-
tional and structural reasons alone would not
have produced it, although they had a consid-
erable influence on it. The first part of the paper Max. positive moment
will therefore try to explain how the design Max. negative moment Max. negative moment
E
was produced by the joint effort of architect
and engineers. I e
Substructure
Introduction
Figs. 3 and 4 (p. 5) show two of the
original competition drawings submitted by the 101 ft 162 ft
architect, on which the location of the Con-
course is indicated. In the following an attempt Fig. 2
will be made to describe the progression of Basic longitudinal layout
architectural and structural considerations put
forward by the architect and the engineers
which led to the chosen design.
In Fig.4(p. 5) it will be seen that the architect
had originally shown the Concourse supported
on a number of columns at midspan. However,
when this structure was first discussed between
the architect and engineers, the architect asked
whether it would not be possible to do without
these columns. A typical question, which
received the typical answer, that of course it
was possible, but would cost a lot of money,
and as the columns did not obstruct anything
this expenditure might not be justified. The
architect then explained that his concept
demanded that the architecture should be
expressed through the structure. in fact the
structure in this case was the architecture; it
should be bold, simple, on an impressive scale
and of a form which combined sculptural
quality with a clear expression of the forces
acting on it. This achieved, finishes could be
simple: the concrete itself would speak. The
area covered by the Concourse was the place
where people would arrive by car to the Opera
House. and the impact of this vast unsupported
roof would be spoilt by centre columns, even
if they did not hinderthe traffic. Hefeltjustified
in achieving the desired architectural effect by
spending the money on a bolder structure
rather than on expensive finishes.
The solution proposed bythe engineers to meet
these aspirations was based on the borehole Fig. 3
data supplied by the client, according to which Cross-sections of various schemes (a)-(d)
22 firm sandstone would be found 3-4.6 in below
This aspiration to have the structure 'truthfully
displayed', to achieve 'structural honesty', is of
course very familiar to students of architectural 1 2 3 4 5 4 3 1
theory. It is a declared architectural ideal of
long standing, and rightly so. But it must not d d d d I d d d
be taken too literally. Geoffrey Scott showed
50 years agothatthis requirement was psycho-
logical rather than factual. It has nothing to do (a)
with choosing the most efficient structure.
The spectator does not in fact understand the
subtleties of a modern concrete structure,
whose strength in any case may be hidden
from the eye in the form of reinforcement or
cables. It is not so much a question of how the
structure really acts, but rather of how the (b)
spectator thinks it acts, or whether he can relate
it to some simple structural facts which lie
within his experience. Thus he may be able to
appreciate the strength of an arch springing
from solid abutments, a cantilever which is
strong at its root, a simply-supported 'fish-
belly' beam or a fixed beam with haunches
producing an arching effect, and this may give (c)
him an impression of structural 'rightness'.
More subtle effects would be lost on him; they
would not form part of his architectural
experience.
In this particular case the most economical
answer would probably have been a series of
box-sections or I-beams spaced 1.83m apart,
(d)
uniform over the whole length, with prestress-
ing cables catering for the variations in the
moment. But this would obviously not have
met the architect's request at all. It seemed t
natural to the engineers, therefore, to seek the
solution by exploiting a typical and by now
very familiar reinforced concrete form, the Fig. 4
T-beam. This can be said to be the best shape Soffit of various schemes ( a)-(d)
to take positive moments in reinforced con-
crete. And the same shape, only upside-down,
is the best shape for negative moments. In this section along the axis of the beam. In order to side of the top slab. Another minor modifica-
way the desired expression of the variation in make the shape as smooth and flowing as tion was that the beam sides, instead of being
the external moments could be obtained by possible the engineers decided to make the vertical in sections 1 and 5, were slightly
varying the shape from a series of inverted T- change in section follow a sinusoidal variation. slanted to facilitate withdrawal of the form-
beams at the supports to T-beams at midspan In scheme (a) this form of variation would work.
- or from section 1 to section 5 in Fig. 3. produce a series of beams 1.83m apart con- Scheme (d) was at once approved by the
Such a solution would make structural sense nected by a wavy slab; in (b) there would be architect, and was the one incorporated in the
in reinforced concrete if the formwork could be 'wavy' beams connected in alternate bays by preliminary design submitted to the client by
made reasonably simple, and full use made of flat top and bottom slabs, and in (c) the wavy the architect and engineers in April 1958, and
the repetitive nature of the job. It would also be beams would be twisted at the same time. In approved. The architect had however intro-
appropriate for prestressed concrete if the live Fig.4 (a), (b), (c) and (d) are attemptstoshow duced a further modification in the design,
load were small compared with the dead load, how the soffits would appear. In the engineers' which the engineers were not too happyabout.
which was thought to be the case at the time. opinion there was a progression from (a) to (c) He insisted that the visible corners between
As it happened, due to the exigencies of the in aesthestic interest and also in some ways in the modulating walls or beams and the soffits
programme, it was not practical to place the structural suitability, but unfortunately the of top slab and beam should be rounded off, as
paving slabs before prestressing, and these had complexity of formwork was also increasing. shown in Fig. 5, and explained that this was
therefore to be counted in with the live load, However, as the twisted surfaces of (c) con- very necessary in order to bring out the sculp-
making the two about even. This considerably tained straight lines, these could be produced tural quality of the design. The engineers did
reduced the structural usefulness of the chang- easily enough from straight boards or twisted not dispute this, but were worried about how
ing concrete sections, and made it impossible plywood. This was therefore the solution put to producethese rounded corners, and thought
to justify the design on economic grounds. But forward to the architect, but in a slightly it would be very difficult and expensive. It had
it met the architectural requirements and there modified form, as indicated in Fig. 3 (d). It been their idea that the forms should be made
was no question of going back to a straight- seemed to the engineers that scheme (c), seen of straight narrow boards forming the twisted
forward box-section. from below, looked too much like a flat soffit surfaces, which would therefore show the
with certain regular hollows scooped out of it. familiar boardmarkings characteristic of struc-
The question then was howgradually to merge By connecting the hollows together, i.e. by
section 1 into section 5 (Fig, 3) in a manner tural concrete. However, the architect demon-
introducing a piece of top slab between the strated on a small model that these board marks
which 'beams' of the same width as the beam at mid- and the sharp corners would be out of scale,
(a) Produced a sculpturally interesting soffit span, the appearance was more of a series of and that the desired effect could only be
(b) Produced the lightest possible structure swelling and undulating beams, and the shape achieved by smooth rounded surfaces.
for the given depth, i.e. least redundant of the beam soffits was repeated in the under-
material Ajointvisit paid bythe architect and the engin-
eers to the Sydney plywood factory of Messrs.
(c) Was easy to construct. Symonds, who were masters in the manipula-
Fig. 3 shows four ways of doing this. In (a) tion of plywood, confirmed that the architect's
the slab is simply raised through successive ideas would be difficult to realize, and on the
sectionsfrom 1 to 5. In (b) the walls are moved return journ ey from Sydney the designer there-
sidewaysfrom 1 through 2, 3,4and 5, gradually fore considered other and more practical ways
extending the top slab and contracting the of effecting the transition from section 1 to
bottom slab. In (c) the walls are gradually section 5 in Fig. 3 (d).
twisted, inclining more and more towards each
It appeared that there were not so many simple
other and reducing the area of the bottom slab
ways of effecting this transition, if one observed
until both slabs reach the same minimum, then
the rule that the cross-sections should always
twisted the other way, thereby increasing the
be made up of straight lines, which would then
area of the top slab until this covers the whole
produce twisted surfaces which could be made
area, when section 5 is reached.
up of plywood. The method proposed in Fig. 3
In these three cases a further variable must be Fig.5 (c) and (d) seemed to bethe simplest possible,
determined before the shape of the soffit is Proposed round-edged sections i.e. tilting the side B-C (Fig. 12, p.7), rotating
defined, namely the 'speed' of the change in it round point B until point C coincided with D, 23
then twisting the side back in the other direc-
tion, rotating about D until point B coincided
with F. The next simple method (Fig. 6)
seemed to be to rotate the side B-C round
point B as before, and simultaneously to rotate
part of the beam soffit D-C round D, in such a
way that the point of intersection C between
the two lines moved on a straight line from C
to its ultimate destination, point F. The result-
ing shape of the beam, assuming that the sinu-
soidal variation of cross-sections was main-
tained, proved to be very interesting and to
possess that roundness or voluptuousness
which the architect was looking for, in spite of
the fact that there were no rounded corners.
Fig. 13 (p.8) shows some typical cross-
sections and Fig. 14 (p.8) a dimensioned
section of the executed scheme.
After considering this new proposal and mak-
ing models to judge its effect, the architect
wholeheartedly approved of it, adopted it, and
had it passed by the Technical Panel.
The engineers, having concentrated their
attention on obtaining an architecturally-
interesting solution which could be produced
with fairly simple formwork, had at that stage Fig. 6
possibly given too little weight to one possible Isometric view of executed scheme
disadvantage of the last scheme compared
with that in Fig. 3, namely that the 'kink' in the
side walls might increase the internal bursting
stresses produced by the bending stresses
resulting in an increase of ordinary reinforce-
ment, thereby adding to the difficulties of com-
pacting the concrete. Butthiswas only a minor
snag compared with many others which
emerged during the detailed design and the
execution of this work. For one thing, the
assumptions on which the design was based
underwent various changes, all for the worse.
It was found, for instance, that the underlying Fig. 7
sandstone dipped down at the southern end of Cross-section through proposed slab
the site, making it doubtful whether the safe
bearing which the design called for could be
provided at this end. Then the architect chan-
ged, at the Technical Panel's request, the ratio
between treads and risers of the steps, flatten-
ing the slope of A-B (Fig. 2). As pointed out
earlier, the angle C-B-A had a vital influence
on the horizontal forces which had to be
absorbed. For these reasons it was found desir-
able to introduce tie-beams between the
foundations atA and C. This added to the cost,
but put the design on a much sounder basis,
and part of the cost was offset by the fact that Fig. 8
the prestress produced by the cables in the tie- Cross-section through executed slab
beams made it possible to reduce the number
of cables in the folded slab itself.
All these changes naturally delayed the com- shape of the slab as seen from below, should by anybody. However, the architect was insis-
pletion of the detailed drawings which were register this fact: one should be aware of what tentand the engineers were bracing themselves
urgently needed on site, and further aggravated happened above, just as one should be aware to attempt a solution to the problem when the
the almost impossible situation which was of the forces acting on the slab. The cross- heating engineers intervenedwith ademandfor
created by the client's insistence that work section in Fig. 7 shows what the architect space overtheslab in whichthey could accom-
should begin on site early in 1959, long before wanted to do: the beams under the higher modate their pipes and other services. This
the brief - let alone any finished and dimen- portion are lifted up and there is a gradual clinched the matter: by keeping the beams at
sioned drawings - had been completed. The transition to the normal level, more or less the same level as in Fig. 8, the desired space
situation was not improved by the contractor's following the steps above. It was difficult to would automatically be created and everybody
insistence that his programme demanded an argue that this could not be done, although it was satisfied!
early start on exactly this particular part of the posed tremendous problems, because the five
job. Add to this the difficult nature of the job, Figs. 9 and 10 show the appearance of the
special beams were unsymmetrical in cross- Concourse slab from underneath and from the
complicated or unusual formwork, narrow sec- section and the prestressing would create
tions packed with steel, etc., and the contrac- side, and Fig. 11 is an aerial view of thefinish ed
torsional movements which would have to be slab without the pavement.
tor's unfamiliarity with prestressed concrete. absorbed by the adjoining, already fully-
and it is no wonderthat the atmosphere on the stressed, beams. This would require structural This account of the development of the design
job deteriorated and the workmanship suffered. additions and might even prove to be almost is necessarily brief and deals only with the
typical case. Amongst otherthings it leaves out
A description of the snags which developed impossible - apart from the fact that it would
the considerable difficulties in creating the
and of how they were overcome would per- upset the whole arrangement of stressing two
correct boundary conditions, especially for the
haps be useful but falls outside the scope of adjoining beams at a time, and would require
cross-beams spanning the openings in the
this paper. But it may be of interest to mention five sets of special and more complicated
supporting wall at the north end, but these are
another complication which was happily forms, thereby invalidating the excuse of repe-
dealt with in the next part of the paper.
avoided, because it concerns the design, and it titive formwork.
throws some light on the somewhat different The engineers' view was that even if the archi- Structural design
points of view of architect and engineers. tect was correct in preferring his solution from The Concourse is a folded-plate structure in
It arose from the fact that a part of the Con- an aesthetic point of view-which they did not prestressed concrete and the analysis was quite
course slab (the part and er the restaurant) was dispute - the very considerable cost, and the conventional. Some unusual features were
raised a few steps over the rest. It was part of disturbance itwould cause in an alreadycritical present, however, because it was not simply a
the architect's philosophy - to use a now situation, would be too high a price to pay for bridge but had also to have the architectural
24 popular phrase - that the structure, i.e. the something which after all would not be missed attributes already described.
The depth/span ratios were low and the shape into account its torsional rigidity or assumes it The control devices used to make these struc-
was not ideally suited to prestressing. The does not twist. tures largely independent of concrete move-
structural design was. thus, mainly concerned ments not accurately known will be described.
The portal part of the Concourse contained 47 However, for the sake of the correlation the
with keeping withintheworking stresses under
folded slab units, 1.83 an wide. The slabs were designers made some research into published
all conditions. The cross-sections continuously
178mm thick: therewere 21 units 50m in span experimental information and made use of
varied according to geometrical rules. For this
and 1.37m deep; the remainder were 41.5m what they thought was the latest at the time,
main reason most of the numerical work was
in span and 1.14m deep. Both types were not very different from that given in the British
programmed for the electronic digital com-
designed in a similar way. The longer span has Standard Code of Practice (CP115:1959).
puter. The analysis was done and the working
been selected for description in the paper.
drawings prepared in 1959. A pair of connected folded slab units 3.66m
The remarkable feature was the extremely flat With the sloping leg at such a flat angle, a wide, were cast at a time. A gap, to be filled in
angle of 191° of the leg from A to B (Fig. 11, structure with unusual sensitivity to concrete later, was left between one pair and the next
p.7 ). This madethe portal part of the structure movements seemed to provide a good oppor- pair. In this way stressing operations could be
(A, B, C), very sensitive to the phenomena of tunity for correlating calculated and measured carried out on a pair of connected units without
concrete movements. Time, temperature and strains and deflections. The distance from disturbing the adjacent units.
load gave many combinations to investigate London, where the design was done, made the The pairof ties corresponding to a pairof folded
and reinforced the case for computer working. site measurements less extensive and accurate slab beams passed on opposite sides of the
A general description of the whole structure thanwas desirable forthe exercise. The authors T-sectionsatAand were connected bya cross-
will now be given. do not believe that the results add anything to head. Hydraulic ship jacks of 203 tonnes pres-
present knowledge (a common finding unless sure were introduced into the gap between the
The part denoted by RC substructure in Figs.
the instrumentation is good) and the correla- cross-head and the foot of the portal. Two
10 and 11 (p.7) consisted of two-storey box-
tion will not be given in this paper. ship jacks were used and oneotherwas keptas
like structures which received the prestressed
tie-beams in a floor at that level. The com- Long-term movements were important. The a standby in case of breakdown. Also in the
pression in the tied portal due to the thrust at construction of the portals was begun in gap was a pair of steel wedge assemblies. The
the foot, A, was taken up at the other end by November 1960, and finished in January 1963. details of the jack and wedge apparatus are
shear walls in the substructure. The laying of paving slabs, which are a perma- shown in Figs. 11 (p.7) and Fig. 15 (p.8).
nent superimposed load, may not commence The former also shows the profiles of the 28.6
The couple thus imposed on the substructure
until 1968/9. The application of full live load mm diameter strand post-tensioning cables.
required special measures forstability, but was
a greatly reduced problem compared with the will be a rare and short-term event. Load cells or dynamometers were used with
original idea of thrusting against the rock, the hydraulic jacks and the prestressing jacks
because the indicated rock level was well Ultimately the concrete of the portals will be so as to obtain more accurate force measure-
below the tie level. shielded from direct sunlight by the paving. ments than could be relied upon from pressure
The average temperature condition will be gauges. The order of prestressing and jacking
The substructure was not there just for the when the temperature of the portal concrete is was carefully worked out so that the structure
structural purpose described. The shear-wall the same as that of the tie concrete. Long-term could be converted from an unstressed, inert
spacings were determined by the various uses factors are that the paving should be quite flat state supported by soffit props to a fully-
of the rooms. A certain amount of structural
at average temperature when there are few stressed free-standing condition without at
irregularity was a small thing compared with
people on it and the possibility of further creep any stage exceeding the permissible design
the large spaces required for main stairway
dueto changes of stress from the weight of the stresses attransfer. Creep and shrinkage losses
entrances and especially for the service road, paving. in the portals were made good by periodic
1 2.8 m wide, which entered the Opera House
attie-beam level atthecentreof the Concourse.
These boundary conditions at the north side of
the portal are shown diagrammatically in Fig.
10 (p.7).
The upper reaches of the Concourse shown
typically from C, D to E in Fig. 11 (p.7), were
subject to several varieties of spans, slopes and
flats. The figure indicates that where visible to
the public, the architect required the 1.83m
wide, varying section, folded slabs to flow
continuously into the upper reaches. Because
of the reduced depth the most critical point
was found in the upper sloping part.
For an ordinary continuous beam one would
have introduced something like a concrete
hinge overthe intermediate support at C. How-
ever, the vertical reaction at C was combined Fig. 9 Fig.10
with a horizontal reaction of the order of Completed structure 1 Completed structure 2
203 tonnes/1.83m wide Concourse beam. A
hinge under these conditions would have
required costly mechanical devices. It was
decided to make the beams monolithic with the
shear walls, which in the region of C had thus
to receive the vertical reaction, the portal com-
pression and a couple equal to the difference
between the end moment of the portal part and
that of the upper part of the Concourse.
Transom beams, in one case of considerable
size.were introduced acrossthewide openings
mentioned above.
The transoms were in a state of vertical and
horizontal bending and torsion. The torsion
arose from the beam end moment differences
which depended on the combinations of tem-
perature and loading. The minimum would be
obtained if maximum clockwise and anticlock-
wise moment differences were numerically
equal. By preloading and other devices the
upper spans were made as far as possible to
bring about this optimum condition.
The stresses in the transoms resulted in deflec-
tions and rotations, but these were of a small
enough order not to influence the assumed
fixed end condition of the Concourse. One
meets a parallel case in the edge beam of a F1g.11
cylindrical shell. When the beam is of normal Aerial photograph of site showing Concourse area
size it makes no material difference if one takes 25
rejacking, which meant moving the ship jacks
around quite a lot.
The folded slabs were cast to true final shape.
The knee at B could be maintained to correct
height by the ship jacking and geometrical
non-linearity could thus be avoided. The jack-
ing was not simplyto allow for concrete move-
ments. The calculated force obtained optimum
stress conditions in the portals. The jacks were,
in fact, a second method of prestressing.
The tie-beam had been previously prestressed
to a concrete compression of about 9 N/mm2.
Thus the operation of the jacks decompressed
the concrete. Data of creep recovery for the
intended correlation were found to be too
scanty for consideration.
A case could be made for the use of Freyssinet
flat jacks throughout in place of the ship jacks
and wedges. Th e ship jacks were ordered when
it was thought the jacking might be against
rock instead of ties. The jack travel might then
have been quite large to an extent that could
not be predetermined.
To deal with the possibility of extra creep due
to the paving load the intention is to stack the
paving slabs in transverse lines across the
Concourse. The jacks will then be put into
position again and used to compensatefor any
loss of thrust and maintain the correct level at
B. The jacking gap will be concreted in when
everything has settled down and the gap left Fig. 12
between every pair of units will be made good. Construction sequence
The paving will then be laid true to level at a
period of average temperature.
It should be mentioned that since there was an housed in Kopex ducting with an inside diam- out paving. The loss at transfer was distin-
odd number of folded slab units of the long eter of 38 mm. guished from the ultimate loss after several
span type, one unit had to be made by itself years under dead load.
with a gap on each side. The mechanical properties of the strand,
assumed in design were: The ultimate loss averaged about 33 per cent.
The approximate average contributions were
Materials Young's modulus, tangent 1 65 kN/mm2
19 per cent due to friction, 5 per cent due to
Concrete Secant modulus at 63 tonnes 131 kN/mm2 creep and shrinkage, 5 per cent due to anchor-
The fine aggregate was a uniformly-graded Friction constant between age slip and elastic shortening and 4 per cent
Cronulla sand with approximately 4 per cent cable and ducting p=0.30 due to relaxation of the strand. The latter was
moisture content. The coarse aggregate was reduced from 6 per cent by holding the maxi-
Prospect Blue Metal, a crusher run aggregate, Wobble constant K=0.0010
mum force of 63 tonnes for five minutes before
uniformly graded with a maximum size of The use of the calibrated dynamometers at the wedging-off. The high friction loss was partly
22 mm. A concrete mix was designed whose live end and dead end of several cablesshowed due to the large proportion of cables stressed
proportion by weight was 1 :1.19:2.43. The K=0.0013 and p=0.25,. It was found that the from one end only through restrictions in fitting
water/cement ratio was 0.39. An additive, change of these constants from those assumed stressing jacks into position at both ends. The
Darex WRDA, was included at the rate of did not materially affect the analysis. restrictions arose from having all theanchorage
2.2 kg/ma of concrete mixed. in the upper hollowed-out part of the beams,
Theauthors' specification called fora minimum Loss of prestress for the visible undersides could not be marred
cube strength of 48.3N/mm2 at 28 days, and The relaxation of the strand cables was deter- by the making good of anchorage pockets. The
prestressing was allowed to begin when mined by experiments carried out at the elastic shortening mainly arose from the thrust
field cubes reached an average strength of University of Sydney. of the ship jacks. The prestressing cables were
41.4 N/mm2. grouted before the ship jacks were brought
Loss of prestress partly depended on the dis-
into full operation.
The permissible working concrete stresses tance from anchorages, the angle turned
adopted in design, were: through and the concrete stress at the centroid Thermometers
N/mm2 of the cables, under dead load conditionswith- Thetemperature difference between the folded
Bending compression 1 5.5
Bending tension 1.5
c-FOLDED SLAB CENTROID
Shear stress 1.2 B
Local bond stress 1.2
0
Average bond stress 0.8
I H . KNOWN
Principal tensile stress 1.1
The prestressing strand was augmented with
mild steel reinforcement where tensile stresses V, UNKNOWN T

were found. Fig. 13


The coefficients assumed for calculating Diagram for analysis with one unknown
deflections were:
Young's modulus at transfer 34.5 kN/mmz
Long-term Young's modulus 17.2 kN/mm2 FOLDED SLAB CENTROID
B
Young's modulus in tie 34.5 kN/mm2
Shrinkage strain 0.03%
Prestressing ^71E H
The prestressing equipment for 28.6 mm diam-
UNKNOWN
eterstrandwas by Gifford-Udal and a dynamo-
meter of Swedish construction was added for o
t
V,UNKNOWN i
accurate measurement of stress. The 28.6 mm
diameter prestressing strand, which had then Fig. 14
been only recently marketed, had a guaranteed Diagram for analysis with two unknowns
26 minimum tensile strength of 82 tonnes. It was
E is constant throughout, which would be the
case if creep is proportional to stress, it does
PArR
T'.
sue WL, S
not enter into load analysis because its value
comes in the denominator on both sides of the
equation of relative movements due to loads
tR 30
in v raceo and those due to the unknowns (redundants).
0 In fact, influence coefficient methods amount
to finding the redundants by this equation. If
sso there is more than one redundant, the equa-
tions are simultaneous, as in the second case.
10 When there was a relative temperature change
while the horizontal thrust was held on the
wedges, the second case of two unknowns
s o lac , arose. Further, in this case there were relative
Fig. 15 10 100
Relaxation/time curves NUMBER OF DAYS AFTER PRESTRESSING C LOS SCALE I movements in the released system which com-
prised the change of vertical height of the
sloping leg and the relative changes of hori-
zontal length of folded slab to the tie-beam.
which had to be eliminated to restore continuity
by redundant actions, It is therefore evident
that the value of Ecomes into only one side of
this equation and can not be cancelled. The
folded slabs were exposed to the air and the tie
beams were not. The daily alterations of tem-
perature were small, but there were sometimes
larger of the same sign
over pee ods of severe le days to a week or more.
The temperature differentials were regarded as
short-term events, and the E value used was
34.5 kN/mm2. Thus, in the judgement of the
designers, creep due to temperature stresses
Fig. 16 was ignored.
Diagram for structural analyses As regards the application of the permanent
paving load, the structure will still be under the
wedge and jack apparatus, and any further
creep will still betaken up. If it is presumed that
creep will take place where the compressive
stress is increased but notwhere it is decreased,
400 the creep will be resisted by peculiar stress
distributions overthe cross-sections, unless the
creep recovery factor is equal to that of creep
strain which seems unlikely. These are stress
history matters on which published research
was entirely lacking.
N The loadings taken for design were:
a_
kg/m per unit
FOLDED SLAB FOLDED SLAB Dead load or self
- 350
COLDER THAN WARMER THAN weight 2315 x area of section
27
TIE BEAM TIE BEAM
Paving = 171 kg
x
r Live = 272 kg
In plan these are:
kg/m2
Dead load = 1025 average
Paving = 308
Live = 488
300 Integrations for the analysis were performed
Fig.17 numerically in the computer by summing
Gain or loss of thrust -25 -10 t0 +10 .25 according to repeated Simpson's rule, These
due to temperature were both total integrals over the whole struc-
TEMPERATURE DIFFERENTIAL IN DEGREE FAHRENHEIT
ture and integrals from A to the interval points.
Cross-sections were drawn to scale at each
interval (numbered 0-27 on Fig. 16), to pro-
slab and the tie had an influence, as will be Thefirst case is shown diagrammatically in Fig. vide dimensions for the two purposes of mak-
explained, on the forces applied by the ship 13. At A, the horizontal thrust is known and the ing the formwork and a computer run to give
jacks. Eight thermometers were located in each vertical reaction is the unknown. The second the area A, the moment of inertia / and the
pair of tie beams. The thermometers were case is shown in Fig. 14.The unknowns arethe distance of the centroid. { in the figure, from
immersed in water in specially constructed vertical and horizontal reactions at A. The the straight reference lines, AB, BC, at each
temperature pockets and read just before the designers had to consider the effects of con- cross-section. Due to certain changes afterthe
jacking operation. The temperature range used crete movements on these indeterminate struc- cross-sections had been drawn, some unequal
in the structural design was ±14°C. tures. In the first case, the horizontal thrustwas intervals appeared, which required modifica-
Portal design to be brought up from time to time to a known tiontotheSimpson coefficients in their regions.
The portal foot at A rested on a foundation force over a period of several years. From this preliminary program, the co-ordinates
through lubricated sliding plates. There was no doubt that shrinkage, creep, 'of the true axial line (centroid) at each interval
elastic tie extension, and the loss of the hori- were given, denoted by y, z in Fig. 16.
Two cases of statically indeterminate structures
were analysed by the influence coefficient zontal component of folded slab compression The graph used on the site to determine the
method. The analyses were programmed forthe would be taken up by jack travel, The vertical appropriate jacking force at various tempera-
electronic digital computer to eight significant component of the compression in the sloping ture differentials is shown in Fig. 17.
figures. In view of this the simplest released leg, naturally, came into the analysis. When it Computer runs, for the two spans, were made
system was adopted, that of cantilevering the came to rejacking, it was found, as expected, for 19 conditions. These comprised transfer,
whole folded slab structure from C. Bending that when the thrust was just taken up there self-weight and paving, and live load; maxi-
and direct strain were taken into account, but had been a loss. Fig. 15 shows two plots for mum and minimum temperature differences;
not shear strain. However, the program was loss of initial thrust against days on a logarith- and jack thrusts ranging from 203 to 376
arranged to give shear forces. Part of the data mic scale. The differences in the curves were tonnes. The latter were for determining how
was the prestressing tensions and their slope, due to differences in time from casting the much loss of thrust could be tolerated and to
which were taken into account for resultant concrete to stressing operations. what extent over-jacking could be employed
shear on the concrete. Itis well known that if the modulus of elasticity to compensate for future losses. 27
SS pp su,ydwoy g uosdwogl Aq puel6u3 ul pO UIld (uopmo$ AmH ologd)
ZA/
!' ^
`lnu""4150^
• ^ kM

P
©e^aARO

^ - ^.
^^^^®®-1111au

You might also like