Professional Documents
Culture Documents
Programme
Introductions
Hilary Skinner (BGA Chairman) & Alain Guilloux (Président du CFMS)
Bruno SIMON
9 Stiff inclusions
9 Pile caps
9 Reinforcement (occasionally)
9 Granular mattress
9 Floor slab (occasionally)
2
Development on the last 30 years
3
Main advantages
4
Present situation
• No national standard
– not a widely accepted technique for common works
• A wide range of design methods is used
– No comprehensive model of all mechanisms involved
• Soil investigations often inappropriate
5
ASIRI project (2005- 2009)
6
ASIRI project (2005- 2009)
FNTP / Fe de r a t i on
M a î t r e s d ' o u v r a g e / Own e r s
M a î t r e s d ' œu v r e / En g i n e e r s
C o n su l t a n t s
En t r e p r i se s g én ér a l e s
/ Ge n e r a l c o n t r a c t o r s
L a b o r a t o i r e s, U n i v e r si t és
/ Ac a de mi c s
En t r e p r i se s sp éc i a l i sée s
/ F o u n d a t i o n sp e c i a l i st s
0 2 4 6 8 10 12 14
Themes Tr 1 Tr 2 Tr 3 Tr 4
1-Full scale o or
e a nk
Fl llagb m b
experiments Dasla E nt
me
2 –Monitored works
tio
n
e & ting
3 –Laboratory and za ugr tes
ct er i if
ntrmbe
physical modelling a e
ar C ha
ch c
4 –Numerical
modelling
8
Président F. Schlosser
Vice -Président O. Combarieu
9
St Ouen full scale experiment (2006)
• Floor slab foundation
IR refoulantes IR refoulantes
IR non refoulantes
10
CNAM PhD work J. Andromeda
St Ouen full scale experiment (2006)
• Floor slab foundation
10 m 4m
3D 2D
6m
IR pour base 8m
instrumentation
4D 1D
IR sans refoulement
IR avec refoulement
tassomètre en forage
CPI
Extenso CV
Pige tassomètrique
CA
Tubes inclino horiz
11
CNAM PhD work J. Andromeda
Two kind of inclusions
13
Load transfer onto inclusion heads
2000 Phase 2
Contrainte totale (kPa) .
CPT4D
1500
1000
Phase 1
CPT3D
500
CPT2D
0
0 100 200 300 400
Durée (jours)
14
CNAM PhD work J. Andromeda
Load transfer onto inclusion heads
CPT3D1 CPT3D2
50 cm
CPT3D
500
Contrainte totale (kPa) .
400
IR
300
CPT3D
200
100
CPT3D1 CPT3D2
0
0 100 200 300
Durée (jours)
15
CNAM PhD work J. Andromeda
Settlement at base of the granular layer
10 m 4m
3D 2D
6m
8m
4D 1D
CA
16
CNAM PhD work J. Andromeda
Settlement at pile head elevation
• Plot 1D (unreinforced)
0 50 100 150 200 250 (j)
0
-10
-20
Tassement (mm)
-30
-40
-50
-60
-70
-80 17
CNAM PhD work J. Andromeda
Settlement at pile head elevation
• Differential settlement / inclusion heads
-10
Tassement différentiel (mm) .
-20
-30
2D
-40 3D
4D
-50
-60
-70
-80
18
CNAM PhD work J. Andromeda
Differential settlement at pile head elevation
• Test unit 3D (ID with • Test unit 2D (ID without
0
slab) 0
slab)
-5 -5
-10 -10
-15 -15
-20
3.5 m -20
3.5 m
• Test unit 4D (I non D with
0
slab)
-5 3D 2D
-10
-15
4D
-20
19
CNAM PhD work J. Andromeda
Chelles full scale experiment (2007)
• Piled embankment
SC1
qc (MPa)
fs (MPa) 20
Chelles full scale experiment (2007)
• Piled embankment
PLOT 1R PLOT 2R
Unreinforced Reinforced
PLOT 3R PLOT 4R
21
CNAM PhD work J. Andromeda
Surface settlement monitoring
• Multipoint extensometer/ surface transducers
06-août 16-août 26-août 05-sept 15-sept 25-sept 05-oct 15-oct 25-oct
0
-5
T35
Tassement (cm)
T36
Bague 1
-10
-15
-20
-25
22
CNAM PhD work J. Andromeda
Monitoring reinforced works
• Parking and pavement foundation (Carrières sous
Poissy, 2006)
• Fill embankment (Chelles, 2007-2008)
24
URGC/INSA Lyon
Transfer layer material (Saint Ouen)
25
CERMES PhD work Anh Quan Dinh
Transfer layer material (Saint Ouen)
ρd=95 % ρd,opm ρd=85 % ρd,opm
1000 1000
Grave Silico-calcaire Grave Silico-calcaire
900 3 900 3
w=7.7 % ; ρd=1,96 g/cm w=7,5 % ; ρd=1,76 g/cm
800 800
700 700
c'=50 kPa c'=10 kPa
600 600
ϕ'=46,9° ϕ'=46,8°
500 500
400 400
300 300
200 200
100 100
0 0
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300
26
CERMES PhD work Anh Quan Dinh
Global/local strain measurement
ρd=85 % ρd,opm
27
CERMES PhD work Anh Quan Dinh
Calibration chamber testing (scale 1/5)
28
CERMES PhD work Anh Quan Dinh
Calibration chamber testing (scale1/5)
• Influence of the transfer layer grain-size distribution
HM = 10 cm
5000 20
3000
Efficacité (%)
12
Force (N)
2000 8
0 0
0 20 40 60 80 100 120 0 20 40 60 80 100 120
Contrainte appliquée (kPa) Contrainte appliquée (kPa)
29
CERMES PhD work Anh Quan Dinh
Centrifuge testing
• Elementary cell behaviour (acceleration 27,8 g)
Load or displacement controlled loading
30
LCPC Nantes PhD work Gaelle Beaudouin
Centrifuge testing
• Behaviour of an elementary cell
31
Centrifuge testing for outstanding work
33
Numerical modelling
• 3D continuum model
Reference model
• Parametrical study
– Geometry
– Constitutive model
• To simulate physical tests
• To evaluate
– Analytical tools
– 2D axisymmetric models
– Biphasic models
URGC/INSA Lyon 34
Reference case : piled embankment
5m
5m
γ = 15 kN/m3
2.5 m
φ= 30° ψ = 0 c’ = 0
E = 5 MPa υ = 0.3 URGC/INSA Lyon 35
Reference case : piled embankment
30 mm
Settlement Stresses
5m
2 mm
5m
URGC/INSA Lyon 36
Reference case : piled embankment
Distance à l'axe de l'inclusion (m)
0,0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9 1,0 1,1 1,2 1,3 1,4 1,5 1,6 1,7 1,8
0
-5 CR3 - E = 10 MPa
CR1 - E = 20 MPa (réf.)
-10 CR2 - E = 50 MPa
-15
20 mm
Tassement (mm)
-20
-25
-30 53 %
-35
42 mm
-40
-45
URGC/INSA Lyon 37
Reference case : floor slab
qo
0,5 m
5m
2.5 m
URGC/INSA Lyon 38
Reference case : floor slab
12,8 mm
Floor slab
0,8 mm
Transfer layer
Inclusion
URGC/INSA Lyon 39
Reference case : floor slab
1300
1200 CD1 (réf.)
1100
CD0 - sans renforcement
1000 1200 kPa
Contrainte σ (kPa)
900
800
700
600
500
400
300 Contrainte uniforme 65 kPa 25 kPa
200
100
62 %
0
0,0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9 1,0 1,1 1,2 1,3 1,4 1,5
Distance à l'axe de l'inclusion (m)
ENPC/LMSGC 41
A simplified approach : the biphasic model
• 2D plane biphasic model
0
Settlement (m)
0 10 20 30 40 50 60 70
-0,005
-0,01
2D - Matrice
-0,015
2D - Renforcement
-0,02
0
0 10 20 30 40 50 60 70
Settlement (m)
-0,005
-0,01
2D – Soil matrix
-0,015
2D - Reinforcement
3D - Above inclusions
-0,02
3D - Between inclusions
-0,025
• Clusters (2 connected
elements)
– linear constitutive law of
contact (normal, tangent)
– adhesion (tensile strength)
• Micro-mechanical
parameter values adjusted
to fit triaxial test results
45
3S-R UJF Grenoble (PhD work B. Chevallier)
3D discrete numerical modelling
• An application example
46
3S-R UJF Grenoble (PhD work B. Chevallier)
Displacement field in granular layer during loading - without concrete slab
48
0,50
Efficacy
a/s = 22%
0,40
a/s = 15%
0,30
0,20
0,10
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7
H (m)
49
URGC/INSA Lyon
An analytical approach : Foxta (Taspie+)
Qp(0)cell studyQ(0)
• Elementary Qs(0)
50
Terrasol
An analytical approach : Foxta (Taspie+)
Qp(0) Top boundary conditions Qs(0)
τ Qp(0)+Qs(0) =Q qsl
Floor slab/ equal settlement plane
yp(0) ~ys(0)
Frank et al.
yp-ys
yp τ −τ ys
dQ p ( z ) = (τ p + γ p s p ) dz
( )
dQ p ( z ) + dQs ( z ) = γ p s p + γ s ss dz
Q ( z)
dy x ( z ) = x dz
sx Ex
51
Terrasol
An analytical approach : Foxta (Taspie+)
• Piled embankment • Floor slab
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 0 0.2 0.4 0.6 0.8 1 1.2 1.4
0 0
Settlement (mm)
Settlement (mm)
‐5
reference case CR1 reference case CD1
‐10
‐5
‐15
‐20
‐10
‐25
‐30
‐15
‐35
Dis tanc e to inc lus ion c entre‐line(m)
Dis tanc e to inc lus ion c entre‐line (m)
Flac
1 0.8
0.8
Taspie+
0.6
0.6
0.4
0.4
0.2 0.2
0
0 1 2 3 4 5 6 7 8 9 10 0
0 20 40 60
E quivalent fill load (m) Applied dis tributed load (kP a)
52
Terrasol
Benchmark exercise I (Saint Ouen)
• Settlement
53
Benchmark exercise I (Saint Ouen)
• Settlement Plot 4D
0.00
0
R1 (M)
-20
-5.00 R1C (M)
-40
R1 (M) :2,5mm
-60
-10.00 R1C (M) R2
: 3,5mm
(M)
(mm) ..
-80
h (mm)
R2 (M) : 11 mm
-15.00
-100
R2C (M) : 18mm
Δh
-20.00
-140
-160
-25.00
-180
-30.00
-200 R1
R1
11 22 33 44 55 66 77 88 99 10
10 11
11 12
12 13
13 14
14 15
15 16
16 17
17 18
18
R1 R1 + 60 jours R2 R2 + 60 jours
54
Benchmark exercise I (Saint Ouen)
• Pile head vertical stress
3300 4D (CPT4D) 3350
3000 Remblai 2
Remblai 2C
2500 R2 (M)
R2+19 j (M)
R2+60 j (M)
2000
Δσ (kPa) .
1500
1000
500
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
55
ASIRI Recommendations (2009)
Summary
• Description and developments
• Mechanisms and behaviour
• Conception and design
• Investigations and tests
• Construction
• Specifications and inspections
57
Keller Ground Engineering
Barry Slocombe
Engineering Manager
BGA-CFMS 7th December 2007
59
BGA-CFMS 7th December 2007
• Site investigation
60
BGA-CFMS 7th December 2007
• Site investigation
61
BGA-CFMS 7th December 2007
• Sustainability/Embodied energy
62
BGA-CFMS 7th December 2007
• Sustainability/Embodied energy
• Vibro Stone Columns typically use “waste aggregate” from nearby quarries/cement works
for normal lightly reinforced shallow foundations and ground-bearing slabs
• Currently approx. 50% of Keller English contracts use reclaimed materials, often from on-
site demolition, see comments Ground Engineering, May 2004
• Have been re-developing/testing former Keller Vibro contracts for over 10 years, NB legal
responsibilities
63
BGA-CFMS 7th December 2007
• Vibro Stone Column design
64
BGA-CFMS 7th December 2007
• Vibro Stone Column design
• Can add VSC on top of concrete pile for more efficient slab design
65
BGA-CFMS 7th December 2007
• Vibro Stone Column design
• Cannot influence long-term decay of degradable constituents within fills (max 10-
15%, well distributed?)
• Secondary compression??
66
BGA-CFMS 7th December 2007
• Vibro Stone Column design
• Start with the capacity of an individual stone column – Hughes and Withers,
Ground Engineering, May 1974
• Column capacity depends on the confining action of the soils (enhanced when
densification occurs)
• Column capacity is increased when ground is surcharged since increases
confinement of column eg embankment, raising site levels, floor loads
• Care with rapid load application due to development of excess pore water
pressures eg slopes, silos, tanks, coal stockpiles
• Care possible undermining due to nearby excavation (take foundations deeper)
• Care decay of degradable constituents (extra reinforcement/cantilever/span?)
67
BGA-CFMS 7th December 2007
• Vibro Stone Column design
• Settlement performance is a function of the density of stone column per unit area,
normally termed “Area Ratio”
• Settlement is reduced within the depth of treatment, then add for other
settlements below the treatment depth and self-weight movements
• Have “flushed out” up to 80% soft soil using larger more powerful vibrators with
water-flush
68
BGA-CFMS 7th December 2007
• Vibro Stone Column Design
69
BGA-CFMS 7th December 2007
• Vibro Rigs
70
BGA-CFMS 7th December 2007
• Case history – Glasgow
• 18,300 m2 of whisky warehouses
71
BGA-CFMS 7th December 2007
• Case history – Aberdeen
• 5/6 – storey offices
72
BGA-CFMS 7th December 2007
• Case history – Gloucester
• Bridge approach embankments
• Up to 14m height
73
BGA-CFMS 7th December 2007
• Conclusions
– Vibro Stone Columns are very adaptable to a wide range of soils and
developments
– Vibro design is based on conventional geotechnical design
– Vibro modifies the stiffness and drainage parameters within the depth of
treatment
– Settlements occur within the Vibro zone, beneath and possible other causes
– Settlements are reduced by factors that depend on the Area Ratio
replacement of the soils
– Very sustainable/low embodied energy technique
– Vibro Stone Column design is only as good as the site investigation data upon
which it is based
74
BGA-CFMS 7th December 2007
• Questions?
75
GEOTECHNICAL AND CIVIL ENGINEERING CONTRACTORS
› Geomix
• Soil mix panel using a cutter (hydrofraise)
› SpringSol
• Soil mix columns using an opening tool
› Trenchmix
• Soil mix trenches
› Key factors:
• Stability of the mix above the tool
• Final soil mix caracteristics
• Homogeneity
› Geomix
• Soil mix panel using a cutter (hydrofraise)
› SpringSol
• Soil mix columns using an opening tool
› Trenchmix
• Soil mix trenches
› 400 mm column
› 150 mm ID tube
platform
fill
chalk
•C/E = 1
•40 l/m
•250 kg/m3
Loaded up to
275 kN
4 mm
› Geomix
• Soil mix panel using a cutter (hydrofraise)
› SpringSol
• Soil mix columns using an opening tool
› Trenchmix
• Soil mix trenches
› What is Trenchmix
› Example of applications : soil improvement
› Control of the works
› Design
› Other applications
• Cut-off wall
• Soil stabilisation
Résistance (kPa)
0 200 400 600 800 1000
0,00
P ro fo n d e u r d u p ré lè v e m e n t (m )
1,00
Tranchée 1
2,00 Tranchée 3
Tranchée 7
3,00
Tranchée 9
Tranchée 13
4,00
5,00
BGA CFMS conference – London – 7 December 2007
Soil improvement for a storage area (grape !)
Scotland (2007)
4500 m @ 6m depth
› Montereau (2007)
• 9400 lm @ 4,5 m depth
TN
remblais
Alluvions
modernes
Alluvions
anciennes
BGA CFMS conference – London – 7 December 2007
BGA CFMS conference – London – 7 December 2007
Zone test in Montereau
› What is Trenchmix
› Example of applications : soil improvement
› Control of the works
› Design
› Other applications
• Cut-off wall
• Soil stabilisation
Monitoring :
- advance speed
- water flow
- mixing ratio
Par analogie avec les colonnes de sol traité, on définit un indice de malaxage correspondant au
nombre total de passages de lames de malaxage pendant 1 mètre d ’avance:
1 1
P rofondeur (m )
Profondeur (m )
2 2
3 3
4 4
8,0
R c (M P a)
6,0
4,0
2,0
0,0
0 20 40 60 80 100 120 140
Chainage (m)
1,E-08
P erm éabilité (m /s)
1,E-09
1,E-10
1,E-11
0 20 40 60 80 100 120 140
Chainage (m)
Design principles
2D geometry…
› Pre-design :
failure hand calculation → ULS checking
› Design :
Finite elements calculation 2D or 3D
→ pre-design confirmation
→ SLS checking
Pavement cracking
Terzaghi’s method:
Distribution layer (C3, Φ3, γ3)
σ1 e1
a
σ2
b e2
Treated soil
(C2, Φ2, γ2)
z
σ3 h
b
Trench
(C1, Φ1, γ1)
γ ⋅ B − 2⋅C
m
σ sol (H ) =
2 ⋅ K ⋅ tan(Φ )
( )
⋅ 1 − e −2⋅K ⋅tan( Φ )⋅H / B + σ 0 ⋅ e −2⋅K ⋅tan( Φ )⋅H / B
Bouassida’s method
on the top (based on Prandtl’s
Failure – analytic formulas available):
Mohr-Coulomb criteria:
1 + sin(Φ ) ⎛π Φ ⎞
σ1 = σ 3 ⋅ + 2 ⋅ C ⋅ tan ⎜ + ⎟
1 − sin(Φ ) ⎝4 2⎠
20
Rc 7j
Rc 14j
18 Rc 28j
Rc 4j
Puissance (Rc 28j)
16 Puissance (Rc 14j)
Puissance (Rc 7j)
Puissance (Rc 4j)
14
Rc (bars)
12
10
⎛π Φ ⎞
6
Rc = 2 ⋅ C ⋅ tan ⎜ + ⎟ 4
⎝4 2⎠ 2
E #150 ⋅ Rc 0
0 50 100 150 200 250
Dosage (kg/m3)
› What is Trenchmix
› Example of applications : soil improvement
› Design process
› Control of the works
› Other applications
• Cut-off wall
• Soil stabilisation
Photo de porte
Viviez –Decazeville
-Trenchmix :
180 m x 7 m
-Draining trench :
180 m x 4 m
Sète- Raffinerie BP
-Trenchmix :
200 m x 6 m
Hauconcourt (F) :
Watertight trench under a floodprotecting
dyke L: 3500m D: 6m
Linéaire : 3 455 ml
Profondeur : 5,7 m moyen
Surface totale: 19 850 m²
Incorporation de ciment : 120 kg / m3
Débit d’eau ajusté pour : slump de 19-20
Durée du chantier : 5 semaines (+mob/demob)
Introduction
The Process
Aspects of Design
Applications
UK Case Histories
DEEP DRY SOIL MIXING (DDSM)
1 2 3 4
Rotating mixing Binder is injected Columns achieve initial Embankment fill &
tool penetrates to as mixing tool is set and working temporary surcharge
desired depth of extracted with platform can be placed placed - followed by
treatment reversed rotation removal of surcharge
VARIOUS MIXING TOOLS EMPLOYED IN DDSM
800mm PB3-Tool
• Performance requirements
Establishment of performance
Results of soil investigation
requirements
q
column
σc
σs
natural soil
ε
TYPES OF BINDER
• Cement
• Lime
• Blast Furnace Slag
• Gypsum
Geotechnical and chemical properties of natural soil affect the choice of binder.
Soil Description
Silt Clay Organic Clay Peat
Binder Organic Content Organic Content Organic Content Organic Content
0-2% 0-2% 2-30% 50-100%
Cement
Cement + Gypsum
Cement + Blast Furnace Slag
Lime + Cement
Lime + Gypsum
Lime + Slag
Lime + Gypsum + Slag
Lime + Gypsum + Cement
Column Exhumation
PULL OUT RESISTANCE TEST (PORT)
Advantages
Test is robust and correlated by large database
of test results.
No problems with test deviation.
High strength columns can be tested (<600
kPa).
Disadvantages
The columns to be tested must be selected in
advantage.
The bottom part (about 1 m) of the column can
not be checked when installed to firm ground.
PUSH IN RESISTANCE TESTS
Advantages
Equipment is simple and cheap
Works well in columns <5m long with
shear strength 150 – 300 kPa
Disadvantages
Have a tendency to deviate from the
column at depth larger then 5 – 8m.
Length > 8m requires a guide hole in the
column
CONE PENETRATION TESTS
Advantages
Common method
Easy to use
Disadvantages
Tendency to deviate from the column
at depths > 5 – 8m and in columns with
high shear strength.
Testing on a very local part of the
column
The shear strength may vary through
the column, which is not representative
for the whole column
UNDISTURBED SAMPLING & LABORATORY TESTING
Advantages
Evaluation of many parameters
Evaluation of the amount of binder in the
sample
Unconfined compression and elasticity
modules can be evaluated
Disadvantages
Only discrete sections of the columns can
be tested
Requires a great amount of samples to
give a proper mean value of the column
The properties in the columns vary a lot
between the samples
EXCAVATION & EXHUMATION OF TRIAL COLUMNS
SOIL MIXED COLUMN STRENGTH VERIFICATION
Reduce settlements
Reduce active/increase
passive earth pressures on
retaining walls
Excavation support.
Land reclamation
Encapsulate contaminated
material on site ( e.g. heavy
metals)
TILBURY DOCKS BERTHS 7 & 8
DDSM CASE HISTORY
Stockpile material
γ = 18kN/m3, φ’=38° Idealised loading
+15mAOD
distribution
+5mAOD
-5mAOD
Thames Gravels
-15mAOD
0 10 20 30 40 50 60 70
TILBURY DOCKS BERTHS 7 & 8
SUMMARY
WORKSHOP
Overview TC 17 activities
S. Varaksin, Ménard Soltraitement
J. Maertens, Jan Maertens bvba & KULeuven
1 2
1. Terms of Reference & WG (cont.)
1 3
2. Formal TC 17 Meetings
1 4
3. TC 17 involvement/representation
8th IGS, 18-22 Sept. 2006, Yokohama, Japan
TC 17 Specialty Session ‘Reinforced slopes & walls”
1 6
4. TC 17 Website
http://www.bbri.be/go/tc17
1 7
5. Canvas ground improvement techniques
1 8
5. Canvas ground improvement techniques
1 9
5. Canvas ground improvement techniques
1 10
5. Canvas ground improvement techniques
1 11
6. Core Member Country reports
1 12
1 13
1 14
A joint CFMS and BGA Meeting - Une journée britannique – 7th December 2007
ISSMGE TC - 17
PROJECT
KING ABDULLAH
STRUCTURE
ARAMCO
INFRASTRUCTURE
DREDGING ROADS
MARINE CIVIL
WORKS WORKS
GROUND
IMPROVEMENT
A joint CFMS and BGA Meeting – Une Journée Britannique
AREAS TO BE TREATED
SCHEDULE
• 8 month
A joint CFMS and BGA Meeting – Une Journée Britannique
SPECIFICATIONS
+4 SITE ≅ 1,5 km
+3
LAGOON FILLED BY SABKAH +3
+2
+1
+1
0
c e
RED SEA
-1
-2
e c 4
-3
CORAL
-4
BARRIER
2
-5
-6
-7
-8
4
-9
-10
Qc PL EP
LAYER USC w % % fines N FR %
BARS BARS BARS
4 - LOOSE TO MED DENSE SAND SM - 12-37 3-18 15-80 0,5-1,8 4-12 28-85
A joint CFMS and BGA Meeting – Une Journée Britannique
TYPICAL SOIL PROFILE
Limit Pressure Pressuremeter Modulus Cone Resistance
0 5 10 15 20 25 30
3.0 0 40 80 120 160 200 240 0 2 4 6 8 10 12 14
3.0 3.0
2.5
2.0
2.0
2.0
1.5
7.5 64.9 1.0
1.0 1.0 0.5
36.0 0.0
2.8
-0.5
0.0
0.0
-1.0
9.8 -1.5
Elevation (m E
1.0
Elevation (m E
Elevation (m E -1.0 -2.0
-1.0
3.8 -2.5
0.9 -3.0
-2.0
-3.5
-2.0 61.5
-4.0
2.2 -3.0 -4.5
22.9 -5.0
-3.0
-4.0 -5.5
3.2 -6.0
-4.0 -6.5
-5.0
-7.0
-7.5
-5.0
-6.0 -8.0
Pl (bar) qc (Mpa)
Ep (bar)
A joint CFMS and BGA Meeting – Une Journée Britannique
VARIATION IN SOIL PROFILE OVER 30 METERS
A joint CFMS and BGA Meeting – Une Journée Britannique
Concept
150 TONS
Depth of footing = 0.8m
Below G.L.
SELECTION OF TECHNIQUE
DC (Dynamic Compaction)
A joint CFMS and BGA Meeting – Une Journée Britannique
Saturation energy
h(m) = Cδ E
(E, in ton.meters)
No Yes
No Deep silt (Sabkha) layer, ie bottom Deep silt (Sabkha) layer, ie bottom
elevation higher than 5 m below elevation lower than 5 m below
Working Platform Level Working Platform Level
Transition Transition
layer > 2 m layer < 2 m
Sabkha
HDR +
Substitution
DC DR temporary
over 1 m +
surcharge
DR
A joint CFMS and BGA Meeting – Une Journée Britannique
PRESSUREMETER TEST (PMT)
In-situ stress controlled loading test to measure the in-situ strength and
stress-strain (deformation) characteristics of soil at depth.
(ASTM D4719-87; N.M.IS2; NEN-EN-ISO 22476-4:2005; Eurocode 7)
A direct design procedure using PMT test data for the calculation of:
• Bearing capacity of shallow and deep foundations
• Settlement of foundations
A joint CFMS and BGA Meeting – Une Journée Britannique
TYPICAL LOADING TESTS
EP
Pressure up to 40 bars
σ acting on surrounding soil
PY PL = shear deformations test.
A joint CFMS and BGA Meeting – Une Journée Britannique
PMT COMPARED WITH PMT loading test applies the cavity expansion
LOADING OF COLUMN theory which is similar to granular column bulging
under applied vertical load.
PMT
⎛π φ ⎞
q ult,sc = tan 2 ⎜ + sc ⎟PL
⎝4 2 ⎠
direct measurement of PL
> 2,80
WPL
> 4,50
BSL (variable)
DR (Dynamic Replacement)
HDR (High Energy Dynamic Replacement) + surcharge
A joint CFMS and BGA Meeting – Une Journée Britannique
HUMAN RESOURCES
Pass 1 NA 2 blows
Pass 3 NA 5 blows
A joint CFMS and BGA Meeting – Une Journée Britannique
PARAMETERS QUALITY CONTROL VISUAL
DC DR / HDR
Description of
High intensity Soft in 2 first blows
impacts
0 5 10 15 20 25 30 0 5 10 15 20 25 30
3 3.0
2 2.0
1 1.0
0 0.0
Elevation (m EL)
-1 -1.0
Elevation (m EL)
-2 -2.0
-3 -3.0
-4 -4.0
-5 -5.0
-6 -6.0
-7 -7.0
-8 -8.0
Pl (bar) Pl (bar)
Minimum Average Between columns Inside columns
A joint CFMS and BGA Meeting – Une Journée Britannique
Before DR After DR – Between columns
Limit Pressure Limit Pressure
0 5 10 15 20 25 30 0 5 10 15 20 25 30
3.0 3.0
2.0 2.0
7.5 23.4
1.0 1.0
0.0 0.0
Elevation (m EL)
0.9 3.3
Elevation (m E
16,7
-2.0 -2.0
-6.0 -6.0
-7.0 -7.0
-8.0 -8.0
Pl (bar) Pl (bar)
Between columns Inside columns
A joint CFMS and BGA Meeting – Une Journée Britannique
0 kJ/m3
(energy / m3)
0 100 200 300 400 500
A joint CFMS and BGA Meeting – Une Journée Britannique
STRESS DISTRIBUTION
ANALYSIS OF WORST CASE FOR VARIOUS GRIDS
3.80
5.5
3.80
5.5
A joint CFMS and BGA Meeting – Une Journée Britannique
STRESS DISTRIBUTION
Grid 5,50 x 5,50 Grid 3,80 x 3,80
Stresses at El (0)
100 kPa
Stresses at El (-1,0 m)
12 kPa
80 kPa 14 kPa
85 kPa
A joint CFMS and BGA Meeting – Une Journée Britannique
STRESS DISTRIBUTION
Grid 5,50 x 5,50 Grid 3,80 x 3,80
Stresses at El (-2,0 m)
62 kPa
12 kPa 9 kPa
65 kPa
Stresses at El (-3,0 m)
7 kPa
10 kPa
50 kPa
55 kPa
A joint CFMS and BGA Meeting – Une Journée Britannique
SITE PROCEDURE
Limit Pressure
pl'2 2,46 MPa Hence pl'e 1,81 MPa Thus he/R 0,83
pl'3 1,33 MPa And he 1,13 m And k 1,07
CALCULATION RESULTS
Bearing Capacity Settlement
α 2,16
k
qa = p 'le 1.33 ⎛ R ⎞ α1
qa 643 kPa w= pRo ⎜⎜ λ2 ⎟⎟ + pλ3R w 5,83 mm
3 3EB ⎝ Ro ⎠ 4.5EA
Higher than 200 kPa => Specification reached Lower than 25 mm => Specification reached
A joint CFMS and BGA Meeting – Une Journée Britannique
PROVISIONNAL
MASTER PLAN
A joint CFMS and BGA Meeting – Une Journée Britannique
ISSMGE TC - 17
CFMS / BGE Joint Meeting
7th December, 2007
Ken Watts
Building Technology Group
Contents
Contenu
• Former
Formerlyironstone
Orgreave opencast mine, Corby
deep / opencast mine
• Depth of fill 80m
24m - 129m
• Small
280 haexperimental
restored sitesite
• Whole
UK Coalarea
willnow restored
develop for housing93,000 sq m of
approximately
business space and up to 4,000 new homes in a new
community close to Sheffield.
Foundation problems on non-engineered fills
Problèmes de foundation sur des remblais non contrôlés
Mechanisms of collapse:
• Inter-granular bonds within the fill may be
weakened or eliminated by an increase in
moisture content
• Parent material from which the fill is formed may
lose strength as its moisture content increases
and approaches saturation
• Where a fill is formed of aggregations of fine
particles, such as lumps or clods of clay, these
aggregations may soften and weaken as the
moisture content increases
Inundation through rising ground water
Inondation par élévation du niveau de la nappe d’eau
0
(m)
-400
• Mudstone, 11
9
siltstone
0.0
11.9
-600
and sandstone
7
5
24.0
36.5
3 48.3
• Dragline and face58.6
1
-800
shovel
85 86 87 88 89 90 91 92 93 94 95 96
• Loose tipped with top
97 98 99
New inundation
-45 corridor
-50
-55
-60
85 86 87 88 89 90 91 92 93 94 95 96 97 98 99
Inundation through rising ground water
Inondation par élévation du niveau de la nappe d’eau
Clay fill
Collapse compression - percolation into fill
Compression d’affaissement – percolation dans le
remblai
90 90
85
40
40 80 80
75
70 70
65
Settlement (mm)
60 60
Chainage (m)
Settlement (mm)
55
20
20 50 50
45
40 40
35
30 30
25
00
20 20
15
10 10
5
0 0
0 20 40 60 80 100
Chainage (m)
Levelling point
Damage to structures
Dommage aux structures
Collapse compression - research
Compression d’affaissement - recherche
Prevention
Empêchement
Reduce air voids to the point:
• Re-engineer to a suitable
specification
• Surface compaction
• Surcharge (preloading)
Current solutions – dynamic compaction
Solutions courantes – compactage dynamique
• Commonly used
in UK to treat
unsaturated fills
• Object to reduce voids
between particles
• Increase in density
and overall
improvement in
properties
• Typical tamper 5 to
20 tonnes, dropping
from heights of up to
25 metres.
• Highest energy
suggest max. depth
of improvement
approx. 10m
Current solutions – dynamic compaction
Solutions courantes – compactage dynamique
• Other techniques
using surface
impact compaction
• Rapid impact
compactor developed
generally to compact
relatively shallow fills
• Now used in the
UK and increasingly
globally
• 7-9 tonne mass
dropped 1.2m at 40
blows/min
• Total energy
similar. Generally
effective to 4m but
considerably better
in suitable
conditions
Current solutions - surcharge
Solutions courantes – surcharge (préchargement)
• Boulder clay
overlying oolitic
limestone
• 9m high surcharge
• Stresses during
pre-loading were
much greater than
later applied by
foundation loads
• The surcharge was
effective down to a
depth of 10m
• Subsequent
movements due to
creep in fill, not
foundation loads
Alternative solution - objectives
Solutions alternatives - objectifs
Overall:
• To enable deep fill sites suitable for redevelopment through
the innovative use of grouting using waste materials.
Specifically:
• To develop suitable economic grout using pfa or other waste
such as quarry dust
• To demonstrate that, at laboratory scale, grout can permeate
and stabilise fill by reducing collapse potential
• To develop an economic grouting technique to eliminate
collapse potential in loose fills
Potential advantages
Avantages potentiels
DISPLACEMENT
Compressed
air LOAD
SAMPLE 3 SAMPLE 9G
2
ρd = 1.6Mg/m2 ρd = 1.6Mg/m2
m = 4% m = 4%
4 Collapse on
initial av = 33% initial av = 33%
Collapse on grout injection
water inundation Grout injection
water inundaton
6
10
12
Test 3
Test 9G
14
16
18
20
Field studies
Études de terrain
Full-scale field trial