W A S T E W A T E R - W A S T E
ADVISORY LEAFLET
ATV M 101E
May 1996
ISBN 3-934984-38-X
Marketing:
Gesellschaft zur Förderung
der Abwassertechnik e.V.
(GFA)
Theodor-Heuß-Allee 17
D-53773 Hennef.
Postfach 11 65 53758
Hennef
ATV A 101E
ATV Working Group 1.2.1 "Calculation Methods", which elaborated the ATV Standard A
101 in January 1992 has the following members:
Dr.-Ing. H. W. Bröker, Köln
BOR Dipl.-Ing. W. Ebeling, Wolfenbüttel
Prof. Dr.-Ing. G. Euler, Darmstadt (†)
Ltd. RBD a.D. Dipl.-Ing G. Friesecke, Düsseldorf
BD Dr.-Ing. L. Gniosdorsch, Frankfurt/Main (†)
Ltd. BD Dipl.-Ing U. Keseling, Hagen/Westf.
Dipl.-Ing. W. Königer, München
BD Dipl.-Ing. A. Kreil, Kassel
BD a.D. Dipl.-Ing. E. Malpricht, Stuttgart
Dipl.-Ing. G. Milkov, Hamburg
Dr.-Ing. R. Pecker, Erkrath (Chairman)
Ltd. BD a.D. Dipl.-Ing. R.H. Rieger, Köln
Prof. Dr.-Ing F. Sieker, Hannover
Dipl.-Ing. K.J. Ueker, Köln
This ATV Advisory Leaflet is based on the ATV Standard A 101, January 1992 and was
revised by the following members in an ad hoc working group. The following took part in
the 1995 revision:
Dr.-Ing. Holger W. Bröker, Köln
StBD Dipl.-Ing. Volker Jansen, Troisdorf
Ltd. BD Dipl.-Ing Ulrich Keseling, Hagen/Westf.
BD Dipl.-Ing. Albert Kreil, Kassel
Dr.-Ing. R. Pecker, Erkrath (Chairman)
Guest:
Dipl.-Ing. Rüdiger Heidebrecht, Hennef
The Advisory Leaflet presented here has been prepared within the framework of the ATV
committee work, taking into account the ATV Standard A 400 "Principles for the
Preparation of Rules and Standards" in the Rules and Standards Wastewater/Waste, in
the January. 1994 version. With regard to the application of the Rules and Standards,
Para. 1 of Point 5 of A 400 includes the following statement: The Rules and Standards
are freely available to everyone. An obligation to apply them can result for reasons of
legal regulations, contracts or other legal grounds. Whosoever applies them is
responsible for the correct application in specific cases. Through the application of the
Rules and Standards no one avoids responsibility for his own actions. However, for the
user, prima facie evidence shows that he has taken the necessary care.
All rights, in particular those of translation into other languages, are reserved. No part of
this Advisory Leaflet may be reproduced in any form by photocopy, microfilm or any
other process or transferred or translated into a language usable in machines, in
particular data processing machines, without the written approval of the publisher.
May 1996
2
ATV A 101E
Contents
Foreword 5
1 Scope 5
1.1 Objective 5
1.2 Area of application 6
2. Definitions 6
3. Principles for planning 7
3.1 General 7
3.2 Planning objectives 8
3.3 Requirements on the planner 9
3.4 Given planning data 9
4. Explanatory report 10
5. Water pollution control 10
6. Hydrologic and wastewater engineering initial data 12
7. Hydrologic and hydraulic calculations 12
8. Supplementary investigations 13
9. Quantitative determination 13
9.1 Quantitative determination for the cost assumption 14
9.2 Quantitative determination for the cost appraisal 14
9.3 Quantitative determination for the cost calculation 14
9.4 Quantitative determination for the drawing up of articles and conditions 14
(cost estimate)
10. Determination of costs 14
10.1 General 14
10.2 Cost assumptions 15
10.3 Cost appraisal 15
10.4 Cost calculation 15
10.5 Cost estimate 16
11 Evaluation of planning alternatives 16
11.1 Fundamentals 16
11.2 Economic efficiency investigations 17
11.3 Further evaluation criteria 17
12 Plans 18
12.1 Types and scales of plans 18
12.2 Contents of plans 18
13 Potential for cost savings 19
Bibliography 19
May 1996
3
ATV A 101E
Appendix 1: Structure and formation of an explanatory report 21
1 Ordering and tasking 21
2 Local conditions 22
3 Fundamental technical principles 23
4 Results of planning 24
5 Constructional organisation, equipment and operation 24
6 Costs 25
7 Time and cost planning 25
8 Summary 25
9 References 25
10 List of annexes and plans 25
May 1996
4
ATV A 101E
Foreword
There are numerous specialist aspects to be taken into account with the planning of new
construction, rehabilitation and renewal measures for drainage systems. If these do not,
from the start and to the respectively required degree, flow into the project work,
planners, customers and test authorities must reckon with considerably more work than
would otherwise be avoidable. Enquiries, subsequent correction or modification of
already executed project tasks play an important role in this.
Prime aim of this Advisory Leaflet is to increase the quality of planning. In the interest of
its sound applicability, the planning aspects are presented to a considerable extent as
headings or in the form of a check-list. The scope of the planning is divided according to
different planning phases in order to contain results capable of providing statements for
the respectively necessary decisions and actions.
The requirements of the ATV Standard A 101 produced in January 1992 are now
covered in DIN prEN 752 " Drainage Systems Outside Buildings". Therefore, this ATV
Standard A 101 required adjustment. In accordance with the new rules in the ATV A 400
"Principles for the Preparation of Rules and Standards", January 1994 edition, there is
now an issue as Advisory Leaflet.
The Advisory Leaflet attempts, as far as possible without gaps, to present and elucidate
the principles and elements of planning of public and larger non-public drainage systems.
In this connection particular value is placed on the planning of rehabilitation and renewal
measures.
In addition, efforts are made to bring the planning phases into line with the activity
phases described in the Remuneration Regulation for Architects and Engineers (HOAI).
1 Scope
1.1 Objective
May 1996
5
ATV A 101E
These results can be summarised by those responsible for the disposal of wastewater
into a technical wastewater action plan (AMP = "Abwasser Maßnahmenplan").
The Advisory Leaflet applies for the planning of new construction, rehabilitation and
renewal measures of drain and sewer systems.
Below are listed, in abbreviated form, the contents and scope of the planning which, in
individual cases, derive from the tasking and the desired services for the solution of the
tasks under consideration.
The planning tasks are divided, in accordance with the HOAI, into the following activity
phases:
- determination of the basic elements (DBE);
- initial planning (IP);
- draft planning (DP);
- approval planning (AP), and
- implementation planning (IMP).
The fundamental contents of these activity phases are laid down in the HOAI and are
defined precisely in this Advisory Leaflet for the special requirements placed on the
planning of drainage systems. With this, the breakdown into activity phases represents a
vertical structure by which the respective subsequent activity is built up smoothly from its
predecessor.
In addition, there is a horizontal breakdown within the individual activity phases into
"basic activities" and "special activities". Basic activities include the activities which are,
in general, necessary for the correct fulfilment of a planning task. Special activities are
those which, in special cases, are necessary to supplement the basic activities in order
to achieve a desired result.
A particular form of planning activity for drainage systems is represented by the Study
and the General Drainage Plan. (GDP).
2 Definitions
The special forms of planning activity not described in the HOAI are defined below.
Study
The study gives first general statements on the realisation of the planning intentions with
larger drainage areas. In order to avoid allowing the development of technical drainage
problems at this point in the planning, Federal State and local planning objectives,
requirements of water management plans, local bylaws, public and private legal
contracts and other similar interests should already be taken into account. As a rule, a
study includes the determination of basic elements and part of the initial planning.
May 1996
7
ATV A 101E
3.2 Planning Objectives
In accordance with § 18b of the Water Resources Law (WHG) wastewater treatment
plants are to be erected and operated taking into account the usage conditions and the
directions for the discharge of wastewater in accordance with the respective rules of
technology which come into question. In this respect, seen today, the following objectives
are to be observed with the planning of drainage installations:
- harmless collection and conveyance of wastewater, not least for epidemic-hygienic
reasons;
- harmless collection and conveyance of stormwater insofar as it cannot be percolated
or irrigated;
- reduction of the loading of lakes and rivers;
- production of lasting leakproof sewers and the rehabilitation of leaking sewers;
- optimisation of production and operating costs;
- avoidance of non-acceptable interference with the ecology.
The first two objectives can be achieved with sewers and storage volumes (damping of
discharge peaks) or open systems (stormwater) which are sufficiently hydraulically
dimensioned. In addition, a wastewater engineering practical layout of sewers,
installation of emergency overflows, a control of discharge as well as an appropriate
design with the application of suitable materials which satisfy wastewater engineering
and hygienic requirements, are of significance.
The third objective can be realised, in particular with the following measures:
- reduction of the overflow parameters (overflow frequency, sum of discharges,
discharge duration and load) at the structures with overflow in the combined sewer
system;
- removal of faulty connections in the separate sewer system (with storm and
wastewater sewers);
- reduction of the amount of wastewater (stormwater, combined wastewater and
wastewater), e.g. through rainwater percolation, cooling and industrial usage water
circulation in commercial and industrial concerns, reduction of water consumption;
- reduction of water inflow from ditches, springs, streams and drainage pipelines
(discharge only exceptionally and exclusively into stormwater sewers of the separate
system taking into account possible flooding);
- sewer network management.
The fourth objective can be achieved in that a leakproof sewer network is created in the
public zone (sewers, shafts) and on private property and leaking sewers are
rehabilitated. Through this, on one side, a penetration by ground and percolation water
and, on the other hand, an escape of wastewater and its contents into the subsoil and
thus into the groundwater are avoided.
The fifth objective can, above all, be realised through greater planning resources, in
particular with investigation of different alternative solutions, also with the selection of the
May 1996
8
ATV A 101E
drainage system, the site of the special structure or by control of discharge. The
selection of the drainage system (combined, separate system) can, incidentally, take
place according to ATV Standard A 105 "Selection of Drainage Systems". In addition,
realistic estimates for the discharges and a sewer network plan matched to the sewage
treatment plant are important.
Finally, the sixth objective can be observed if the natural and ecological characteristics
such as, for example, the affected fauna and flora, the subsoil and groundwater
conditions and their possible changes with the construction and operation of the drainage
system can already be taken into account in the planning. With serious conflicts of aims,
hydraulic interests take priority with the planning of a sewer system.
In order to ensure well-founded planning results and thus the preconditions for a faultless
function of the drainage system, planning is to be given only to qualified and
appropriately experienced specialists who are familiar with the rules of wastewater
engineering. Insofar that, in addition, installations are to be planned in accordance with
the status of technology, for example with
- new calculation principles and procedures,
- new principles of construction as well as new technology in production, operation and
maintenance of the wastewater system, its facilities or parts thereof,
additional qualifications such as, for example, relevant references, are to be verified.
Before the start of the actual planning tasks, the following data and planning documents,
as far as respectively necessary, should, in particular, be available:
- general plans, general site plans and site plans of the planning area,
- area usage plan and housing development plans,
- inventory plans of the drainage systems,
- inventory plans of pipelines of other suppliers,
- survey documents and height datum points,
- previous drainage plans,
- aerial photographs of the drainage area
- population and water usage numbers,
- direct and indirect dischargers from commercial and industrial concerns,
- precipitation data and/or actual rainfall assessments,
- water levels and water flows of the surface waters affected,
- subsoil data and groundwater levels,
- measured dry weather and wet weather run-offs,
- details on known bottle-necks and points of constraint within the existing drainage
systems.
May 1996
9
ATV A 101E
Fundamentally, before the recalculation of an existing sewer network, measurements of
the discharges and/or water levels are to be carried out and evaluated for the planning
task. Moreover, observed defects or defects substantiated by measurement as well as
other operational experiences from the rehabilitation of a sewer network are to be taken
into account.
4 Explanatory Report
For each planning activity a summarised but exhaustive explanatory report is to be
produced. It must correspond with the contents of the respective planning phase. With
implementation planning the explanatory report can be dispensed with.
Legal principles for water pollution control in the Federal Republic of Germany are the
introduced supranational agreements (Directives of the Management Board of the
European Community such as, for example, the Water Pollution Control Directive of
1976 with its successive directives), the Water Resources Law (WHG), the Wastewater
Rates Law (AbwAG), the Federal State Water Laws with the associated statutory
regulations and, finally, the decrees, administrative regulations, standards, etc., of the
responsible Federal State Water Authorities.
With the planning of drainage systems the question of the wastewater discharge into a
lake or river can play an important and decisive role. The discharge of wastewater
requires permission under water law in accordance with § 7 of the WHG. It may,
however, only then be given for the discharge of wastewater if the observation of certain
requirements is ensured (see § 7a, Para. 1 of the WHG).
If no hazardous substances reach the receiving waters with the wastewater then the
relevant requirements must be fulfilled according to the recognised rules of technology.
On the contrary, should the wastewater contain substances which, due to statutory
regulations, are to be assessed as hazardous (see § 7a WHG), then the requirements
must correspond with the status of technology. Such requirements result in the
implementation of § 7a WHG, from the Wastewater Source Regulation (AbwHerkV) and
the "General Outline Administrative Regulation on Minimum Requirements on the
Discharge of Wastewater into Lakes and Rivers (Rahmen-AbwasserVwV)" with the
respective appendices, which are, in particular, to be observed. The Federal States must
May 1996
10
ATV A 101E
ensure that the requirements for hazardous substances are already met before
discharge into a public wastewater system (sewer network).
For this, the respective Federal State water laws and the so-called Indirect Discharger
Regulations are to be observed. In addition, further requirements can be made on a
wastewater discharge by the responsible water authority if this appears to be necessary
for reasons of water pollution control.
Wastewater systems are to be established and operated taking into consideration the
usage conditions and rates for the discharge of wastewater according to the respective
rules of technology which come into consideration for this. These rules can include the
generally recognised rules of technology as well as the status of technology.
The method of consideration which goes beyond local limitations and the agreement of
all users of the lake or river, which are necessary for an effective protection of the
surface waters, should be achieved, according to the WHG, through the production of
plans for wastewater disposal, of water management general plans and of management
plans.
The details on the lakes and rivers, the given planning details as well as the required
verification necessary, from the water pollution control aspect, are summarised in
Appendix 2.
Which planning principles are required in which planning stage is, in individual cases, to
be decided according to the special Federal State regulation, the situation of the lake or
river, the desired accuracy of planning results and the statement of the problem. It is
recommended that, already in the planning stage, one reaches agreement with the
responsible water authorities and with the other users of the lake or river. Should nature,
landscape conservancy or other ecologically valuable areas be affected by the planning
the nature conservancy authorities should be involved at an early stage.
May 1996
11
ATV A 101E
6 Hydrologic and Wastewater Engineering Initial Data
The hydrological and wastewater engineering initial data for the planning of drainage
systems listed in Appendix 3 represents a summary of the overall types of data
necessary or desirable in the various planning phases. With this, the systems "Drainage
Network" (public and non-public sewer systems) and "Lakes and Rivers" are respectively
summarised. Which types of data in which planning phase are necessary depend on the
required accuracy of the planning results and are to be decided on a case-by-case basis.
In accordance with the required accuracy and in accordance with the selected calculation
procedure the drainage area is subdivided into sub-catchment areas and calculation
stretches.
The types of data, as far as necessary, are to be raised for the actual status and forecast
respectively.
The scope and the execution capability of the applied calculation procedures, as a rule,
increase with the size and wastewater engineering significance of the planning object.
Thus one can, for example, continue to apply the time coefficient procedure even with
the planning of a small sewer network.
With the rehabilitation calculation of a large city drainage network one would, on the
other hand, for example apply a hydraulic-dynamic sewer network model which works,
according to the tasking, with different area and network distribution. Further, one would
either be able to fall back on existing precipitation details or one would have to base the
planning on an own locally executed, valid precipitation analysis. In addition an intensive
observation and analysis of the given discharge conditions should take place over an as
long as possible period of time.
May 1996
12
ATV A 101E
8 Supplementary Investigations
Further investigations, inter alia, on the subjects below, can be necessary with the
planning of a drainage system:
- operational safety of the drainage system
• accident prevention measures
• operational instructions
• maintenance plans
• precautions against operational faults
• selection of suitable materials
- Determination of the soil permeability (permeability coefficient)
- Condition of existing sewer networks (cadastral register)
• age
• constructional condition, e.g. fracture sites, leaks, corrosion
• deposit condition
• faulty connections
• commercial and industrial dischargers
- Measurement and control
• planning and installation of measurement systems
• calibration of measurement sites
• production of software for data recording
• remote transmission of measured data
• development of regulation and control systems
- Data management and evaluation
• software production, e.g. for data banks, special evaluations
• evaluation of measurements of, for example, precipitation, discharges, water
levels, water
and wastewater quality as well as damage reports and operational logbooks
9 Quantitative Determination
The Quantitative determination is necessary as preparatory task for cost determination
(Sect. 10) and the assessment of the planning (Sect. 11). It depends on the requirements
to be placed there. With this, the following accuracy is recommended:
May 1996
13
ATV A 101E
9.1 Quantitative Determination for the Cost Assumption
- determination of area size of the drainage area in ha
- rough determination of main and connecting interceptor sewers according to length in
m and profile size in mm,
- determination of number of special structures such as, for example, stormwater
overflows, stormwater tanks with overflows, stormwater sedimentation tanks,
stormwater retention tanks, stream and river intersections including inverted siphon
structures and pump stations,
- determination of collection values in total number of inhabitants and population
equivalents.
9.2 Quantitative Determination for Cost Appraisal
- Quantitative determination on the basis of preplanning or the general drainage plan,
- determination of all important sewers according to length in m and profile size in mm,
- determination of usable tank volumes in m3 of storage volumes,
- determination of reconstructed volumes of structures, divided into above ground and
underground parts in m3,
- determination of the delivery flow of pump stations in l/s.
9.3 Quantitative Determination for the Cost Calculations
- Quantitative determination with the accuracy which stems from the draft documents.
With this, an accuracy sufficient for the request for tender documentation is still not
achieved.
9.4 Quantitative Determination for the Drawing Up of Articles and Conditions
(Cost Estimate
- Quantitative determination on the basis of implementation planning in accordance
with the Contract Procedure for Construction Services (VOB), Part C and the
Contract Procedure for Services (VOL).
May 1996
14
ATV A 101E
- ecological follow-on measures (maintenance of groundwater level, maintenance or
re-establishment of green areas, nature protection and marshy areas, balancing and
alternative measures),
- ancillary construction measures (e.g. site investigations, planning, construction
management, procedures for recording of evidence),
- other follow-on measures, compensation.
The costs are either to be calculated into the specific production costs or indicated
globally. They can be subdivided into construction sections. With this, if required,
administrative agreements and other cost drivers are to be taken into account.
The following classifications are differentiated based on DIN 276, Part 2, "Costs of
Buildings, Cost Determinations":
It includes costs for main items, e.g. for different types of excavation work in DM/m3,
trench support sheeting in DM/m2, raw materials in DM/m..
Equally the costs for ground purchase, release from special rights, ecological follow-on
costs, construction overheads (such as, for example, engineer costs, costs for
construction site investigations), taxes and unforeseen costs are to be listed specially.
It includes the investment costs by applying locally accepted prices in the articles and
conditions and thus represents the detailed allocation of costs. However, here care is to
May 1996
15
ATV A 101E
be taken that only the production costs for construction and delivery services are
recorded.
The accuracy of the cost determinations is greater the more price influencing cost factors
are taken into account. These depend, however, on the selected planning stage.
In such cases the alternative solutions are to be selected practically and clearly
differentiated against each other.
This can, for example, be the case with the following problems:
- combined, separate or special systems,
- collection/transport sewers or retention tanks/sewers with storage capacity and
overflow,
- low-lying interceptor sewers or pump stations,
- several stormwater overflows or combinations,
- connection of distant built-up areas to the actual sewer network or transfer to
neighbouring communities,
- retention of the old route or new sewer line,
- discharge, usage or percolation of stormwater.
The comparison and calculations for the solution of the above given tasks should be
based on comparable principles and cover the effects on the overall system.
The production costs are to be determined with appropriate accuracy (see Sect. 10).
The operating costs (personnel and material costs) should be taken into account, with
similar accuracy to the production costs, in the following groups:
- administration,
May 1996
16
ATV A 101E
- servicing and operation including monitoring,
- maintenance,
- operating means,
- supply and disposal (e.g. energy, water, sludge, screenings).
11.2 Investigations into Operational Efficiency
One obtains, as important result of the investigated planning alternatives, the investment
costs to be met and annual operating costs. Economic efficiency investigations are to be
carried out in order to obtain the most economic solution. They represent assessment
procedures which compare costs of a similar type. For this, the following are suitable:
- the annuity method, and
- the discounted cash flow method.
With the annuity method the annual costs (DM/a) are calculated from the capital costs
(annual write-off and calculated interest) and the annual operating costs.
With the discounted cash flow method the real value (DM) is determined from the
investment costs and the capitalised operating costs. In addition, one differentiates
according to statistic methods and dynamic methods, which take into account changing
price and cost developments.
The results of the respective economic efficiency investigations are to be set down in a
clearly visible form.
For the selection of a planning alternative a benefit-cost analysis can also be useful in
special cases.
May 1996
17
ATV A 101E
12 Plans
12.1 Types and Scales of Plans
For the individual planning stages the following plans come into consideration, which are
to be agreed beforehand between those concerned (see also DIN 2425, Part 4):
Type and scale Study GDP IP DP IMP
General plans (Appx. 5, Sect. 1))
Scale = 1:5000 to 1:1000 x x x x -
General site plans (Appx. 5, Sect. 2)
Scale = 1:5000 to 1: 2000 o x x o -
Site plans (Appx. 5 ,Sect. 3
Scale = 1:2000 to 1:500 o o o x x
or Scale = 1:250 - - o o x
Computer network plans (Appx. 5, Sect. 4)
Scale = 1:2500 to 1:500 - x o o -
Flow diagrams (Appx. 5, Sect. 5)
Not to scale x x x x -
General longitudinal sections (Appx. 5, Sect 6)
Scale = 1:10000/100 to 1:2000/100 o o o o -
Longitudinal sections (Appx. 5, Sect. 6)
Scale 1:1000/100 to 1:500/100 o o o x x
or Scale 1:250/100 - - - o x
Structure and special plans (Appx. 5, Sect. 7)
Scale = 1:100 - o o o o
Scale = 1:50 or greater - - o o x
Time and cost plans (Appx. 5, Sect.7)
Construction time plan - - - o o
Cash flow plan o o o o o
x = necessary,
o = possibly necessary or desirable,
- = not necessary
The contents of plans depend on the respective objective and the planning phase. The
scale of the plan is to be selected accordingly.
Proposals for the structure and the contents of the plans are given in Appendix 5.
May 1996
18
ATV A 101E
13 Potential for Cost savings
With the disposal of wastewater the potential for cost savings is greater in the
conceptional, planning area than in the later constructional design and construction. The
detailing and assessment of alternatives with different drainage solutions and demands
on the ease of drainage is an essential prerequisite for this.
The necessary planning is therefore to be selected directly towards the type and scope
of the respective planning tasks. Here the design possibilities and planning flexibility of
the technical rules and standards should be fully utilised. To this extent this Advisory
Leaflet - applied correctly - can contribute considerably to cost savings with the
construction of drainage systems.
Bibliography
[Where there is a known translation the title is given in English. For other titles a courtesy translation is
given in square brackets.]
[1] ATV: Planung einer Ortsentwässerung, Grundlagen und Hinweise [Planning Local
Drainage, Fundamental Data and Notes], ATV-KfK-Arbeitsblatt A 101, 2. Auflage,
Februar 1972, GFA, Bonn
[2] ATV: Selection of the Drainage System ATV Standard A 105, January 1996, GFA,
Hennef
[3] ATV: Standards for the Hydraulic Dimensioning and Performance Verification of
Sewers and Drains, ATV Standard A 110, 1988, GFA, Hennef
[4] ATV: Standards for Dimensioning, Design and Operation of Stormwater Retention
Tanks, ATV Standard A 117, June 1977, GFA, Hennef
[5] ATV: Standards for the Hydraulic Calculation of Wastewater, Stormwater and
Combined Wastewater Sewers, ATV Standard A 118, June 1977, GFA, Hennef
[6] ATV: Principles for the Computation of Drainage Networks using Electronic Data
Processing Systems, ATV Standard A 119, October 1984, GFA, Hennef
[7] ATV: Richtlinien für das Prüfen elektronischer Berechnungen von Kanalnetzen
[Standards for the Verification of Electronic Calculations for Sewer Networks],
Arbeitsblatt A 120, August 1979, GFA, Hennef
[8] ATV: Niederschlag-Starkregenauswertung nach Wiederkehrzeit und Dauer,
Niederschlags-messungen, Auswertung [Precipitation and Heavy rainfall Evaluation
According to Repetition Time and Duration, Precipitation Measurements,
Evaluation], Arbeitsblatt A 121, Dezember 1985, GFA, Hennef
[9] ATV: Standards for the Dimensioning and Design of Stormwater Structures in
Combined Sewers, ATV Standard A 128, 1992, GFA, Hennef
[10] ATV: Construction and Dimensioning of Facilities for the Decentralised Percolation
of Non-harmful Polluted Surface Water, ATV Standard A 138, January 1990, GFA,
Hennef
[11] ATV: Local Drainage Structures, ATV Standard A 241, March 1994, GFA, Hennef
May 1996
19
ATV A 101E
[12] ATV: Lehr- und Handbuch der Abwassertechnik 4. überarbeitete Auflage, Band 1,
Band 2 [Handbook of Wastewater Engineering, 4th Revised Edition, Vols 1 and 2],
Verlag W. Ernst & Sohn, Berlin, München 1995
[13] ATV: Hinweise zur Auswahl unabhängig beratender Ingenieure für Aufgaben im
Bereich der Abwasser- und Abfalltechnik, Arbeitsbericht des ATV-
Fachausschusses 6.6 "Qualitätsmerkmale bei der Planung und Bauausführung"
[Notes on the Selection of Independent Consultant Engineers in the Field of
Wastewater and Waste Engineering, Report of the ATV Specialist Committee 6.6
"Quality Characteristics with Planning and Execution of Construction Measures"],
Korrespondenz Abwasser 38 (1991), Heft 4, S. 517
[14] ATV: Planning and Construction of Wastewater Pump Stations with Small Inflows,
ATV Standard A 134, August 1982, GFA, Hennef
[15] ATV: Hydrologie der Stadtentwässerung, Arbeits-bericht der ATV-Arbeitsgruppe
1.2.6 gemeinsam mit dem DVWK [Hydrology of Municipal Drainage, Report of the
ATV Working Group 1.2.6 together with the DVWK], Korrespondenz Abwasser 33
(1986), Heft 2, S. 57 und Korrespondenz Abwasser 34 (1987), Heft 3, S. 263
[16] DVGW: Richtlinien für Wasserschutzgebiete, 1. Teil: Schutzgebiete für
Grundwasser [DVGW Standards for Water Protection Zones, Part 1: Protected
Areas for Groundwater],
W 101, 1995, DVGW, Bonn, 1995
[17] Emschergenossenschaft: Wohin mit dem Regenwasser? Arbeitshilfe für einen
ökologisch ausgerichteten Umgang mit Regenwasser in Baugebieten [Where do
We Put Stormwater? Aid for an Ecological Handling of Stormwater In Built-up
Areas], Eigenverlag, Essen 1993
[18] Geiger, W., Dreiseitl, H.: Neue Wege für das Regenwasser, Handbuch zum
Rückhalt und zur Versickerung von Regenwasser in Baugebieten [New Ways with
Stormwater, Handbook on the Retention and Percolation of Stormwater in Built-up
Areas], Oldenbourg Verlag, München, Wien, 1993
[19] Imhoff, K., Imhoff, K. R.:Taschenbuch der Stadtentwässerung [Handbook of
Municipal Drainage], 28. Auflage,
Verlag R. Oldenbourg, München, Wien, 1993
[20] Lautrich, R.: Der Abwasserkanal, Handbuch für Planung, Ausführung und Betrieb
[The Sewer, Handbook for Planning, Implementation and Operation], 4. Auflage,
Verlag Paul Parey, Hamburg, Berlin, 1980
[21] DIN 276, Part 3, Building Costs, Cost Determination
[22] DIN 2425, Teil 4, Planwerke für die Versorgungswirtschaft, die Wasserwirtschaft
und für Fernleitungen, Kanal-netzpläne öffentlicher Abwasserleitungen [Planning
Instrument for Supply Management, the Economy and for Pipelines, Sewer Network
Plans of Public Sewers] Mai 1980
[23] DIN 4045, Wastewater Engineering Vocabulary, December 1985
[24] DIN 19525, Sewerage, Guidelines for Design Development, Febuary 1957
[25] LAWA Leitlinien zur Durchführung von Kostenvergleichsrechnungen [Guidelines on
the Execution of Cost Comparison calculations], 1986
[26] DIN prEN 752, Drainage Systems Outside Buildings
May 1996
20
ATV A 101E
Appendix 1
Structure and Build-up of a Explanatory Report
1 Ordering and Tasking
- Reason
• new concept of the drainage system
• new building area
• rehabilitation of defects
• further requirements on water pollution control
- Object of planning
• significance
• aims
- Planning agreement
• agency for the measure
• approval authority
• technical specialist authority
• others
- Legal questions
• drainage bylaws
• public statutory agreements
• private legal contracts
May 1996
21
ATV A 101E
2 Local Conditions
- Population conditions
• present status
• development
• tourism
- Precipitation conditions
• measurement points
• data
• evaluation
- Underground conditions
• site properties
• groundwater levels
• properties of the groundwater
• correspondence between groundwater and receiving
waters water levels
- Water supply
• protective areas
• extracting plants
• drinking water barrage
• mineral springs
May 1996
22
ATV A 101E
- Existing wastewater installations
• Location
• type
• condition and efficiency
- Special problems
• nature and landscape conservation
• flooding protection
• scattered settlements
• camping sites
• small garden facilities
• traffic routes (road, rail, water)
• mining subsidence
3 Technical Principles
May 1996
23
ATV A 101E
- Hydraulic characteristic values for sewers and special structures
• operating roughness
• coefficient according to Manning-Strickler kSt
• loss coefficient
• overflow coefficient µ
- Calculation methods
• type of procedure or model
• principles of the surface and transport model
• model parameters (e.g. peak discharge coefficients)
• pollution load formulation
4 Results of Planning
- Presentation of individual variants
- Evaluation of variants into technical, economic, operational and ecological aspects
- Selected solution
• new construction, renewal, rehabilitation
• abolition of wastewater installations (sewers, special structures, sewage treatment
plants)
• line direction determination
• locations
• effects on the environment
- Technical design
• functional description
• cross-section and length of sewers
• regulation, control
• storage volumes
• inflows and discharges
• pump delivery flow
• delivery heights
• energy supply
• critical combined wastewater discharges.
- Sewers
• gradient
• depth
• cross-section shape
• material
• connection
• coating
• corrosion protection
May 1996
24
ATV A 101E
- Regulating and special structures
• material
• corrosion protection
• water and energy supply
• disposal
• mechanical and electrical equipment (throttles, pumps, transformers, emergency
power
equipment, flushing devices, scrapers, measurement and remote control facilities)
- Operational aspects
• personnel
• monitoring
• servicing
• maintenance
• safety facilities (e.g. accident prevention, ventilation and air extraction, fault
reporting)
• transfer of measured data
• disposal of residue
6 Costs
- Production costs
- Total costs
- Operating costs
- Cost comparisons
• annual costs
• current values
9 References
May 1996
25
ATV A 101E
Appendix 2
Details and Given Planning Details on lakes and Rivers and
Verification
1 Details on Lakes and Rivers
1.1 Hydrography
- Designation of the lake or river (receiving waters)
- Description of the lake or river (course, expansion condition, retention, usage)
- Description of the catchment area (watersheds, morphology, usage, catchment
surfaces)
- Changes to the discharge conditions for the forecast
• changes of usage in the catchment area such as, for example, cultivation,
afforestation
• changes in the lake or river such as, for example, expansion, retention, renaturing.
1.2 Discharges, Water Levels
- Discharge/water level relationship (discharge curve) at the points of introduction
- Situation of water levels in the planning area (longitudinal sections)
- Average and extreme discharges and water levels
- Continuity lines, high and low water statistics
- High-water discharge hydrographic curves from the catchment area
- Long-term discharge hydrographic curves (discharge continuum or extreme
discharge periods).
- Expected changes to the water-level situations and discharges for the forecast.
1.3 Data on Quality of Lakes and Rivers
- Existing water quality class
- Measured values (e.g. oxygen content, COD, heavy metals, nutrients)
- Preloading and/or existing upstream wastewater discharges
- Existing wastewater discharges in the planning area, e.g. from combined sewer
systems, separate sewer systems, sewage treatment plants
- Expected changes to the water quality through
• planned additional wastewater discharges
• rehabilitation planning.
2 Given Planning Data
May 1996
26
ATV A 101E
- Drainage bylaws
- ATV Rules and Standards
- DVGW*) Standards
- DVWK**) Rules
- DIN Standard Specifications.
2.2 Project-Specific Given Planning Data
- Overall water management plan
- Water protection areas
- Wastewater disposal plan and/or concept
- Management plan
- Desired water quality class
- Requirements for discharges (minimum, increased requirements)
- Relevant parameters of water quality
- Ecological constraints
- Acceptance capability of the receiving water (qualitative, quantitative)
- Given data on overflow frequency and duration, and annual pollution load
- Given data on water level situations and discharges
- Given data on frequency of the coincidence of overflows from heavy rainfall and
extreme receiving water discharges
- Given data on surveillance and self-monitoring the drainage operation.
3 Verification for the Fulfilment of the Given Planning Data
- Evaluations from available drawings
- Calculated verification for actual status and forecast with alternative solutions
- Verification of necessary measures for expansion or retention of the lake or river
- Effects on the environment
- Establishment of preconditions for official approval and monitoring
- Initiation of a recognised measurement programme
- Given data for the drainage operation.
____________________
*) DVGW = German Association of Gas and Water Engineers
**) DVWK = German Association of Hydroponic Engineers
May 1996
27
ATV A 101E
Appendix 3
Quantitative and Qualitative Initial Data
1 Quantitative Data
For the above given dry weather components the following statistics are to be carried out
- individually and superimposed in time - (if necessary by the installation of measurement
facilities):
- extreme and individual values (day, week, month, year)
- hydrographic curves (day, week, year)
- trend analysis of previous development
- forecast of future development
May 1996
28
ATV A 101E
1.2 Amount of Wastewater Produced with Wet Weather
The following are to be defined for the sub-catchment areas of the sewer system and of
the lake or river:
- degree of compacting
- terrain slope (surface gradient)
- type of surface, differentiated by permeability and usage
- pre-wetting by initial rainfall
- rainfall losses (usage, trough, percolation and evaporation losses)
The influence of the season on the discharge constitution is to be taken into account
The following are to be defined for the sub-catchment areas of the sewer system and of
the lake or river:
- surface size of the sub-catchment areas
- surface roughness
- terrain slope
- flow length from centre of area to catchment point
- characteristic flow times, e.g. longest flow time in the sub-catchment area.
May 1996
29
ATV A 101E
1.3 Discharge Conveyance
The following are to be determined for the calculation sections and special structures of
the sewer system and of the lake or river:
- length of the calculation sections
- connection of the calculation elements
- terrain heights
- sole heights
- sole gradients
- cross-section dimensions and shapes
- operational roughness and/or Manning-Strickler coefficient
- discharge relevant data of special structures such as, for example, tank volumes,
inflows, discharges
2 Data for Water and Wastewater Quality
2.1 Domestic and Industrial Wastewater
May 1996
30
ATV A 101E
Appendix 4
Given Details on Precipitation, Surface Runoff and Sewer
Discharge, Results of the Hydraulic and Hydrologic
Calculations
1 Given Details on Precipitation
- Definition of relevant rainfall intensities according to available precipitation statistics
- Determination of dimensioning rainfall (block and other model rainfall) from available
precipitation statistics
- Evaluation and statistic analysis of local precipitation records
- Special investigations
• area precipitation statistics
• point and area rainfall relationships
• statistically defined rainfall events, e.g. rainfall point diagram
• precipitation statistics for dimensioning of stormwater overflows, stormwater tanks
and
high water pump stations
• determination of relevant precipitation events from the discharge statistics
2 Surface Run-off
2.1 Preparatory Work
- Task-specific catchment area division
- Determination of the non-pervious and pervious and partially pervious areas in the
sub-areas
- Definition of the drainage areas not in the sewer network
2.2 Normal Processes
- Definition of peak discharge values, e.g. for time coefficient procedures, time-
discharge factor procedures, sum line procedures
May 1996
31
ATV A 101E
3 Discharge in the Sewer Network
- Selection of the practical calculation method
• normal calculation methods such as, for example, time coefficient procedure, time-
discharge
factor procedure, sum line procedure, flood plan procedure
• newer calculation methods hydrological transport model with transfer functions
such as, for
example, unit flow curve, linear single reservoir, storage cascade
- Accounting for the hydraulic constraints and network properties
• receiving water conditions (discharges, water levels)
• discharges from other drainage areas
• overflows into other drainage areas or receiving
waters
• special structures with, for example, regulation and
control devices, pumps
• networking, branching, high points, emergency
overflows
4 Results
In addition to input data the following calculation results, each in the respectively
necessary scope, are given in the form of lists and, if required, graphically.
4.1 Area
- Total lengths
- Total areas
- Total number of inhabitants
- Average degree of compacting.
- Other statistical details such as, for example, sewer volumes, type and number of
special structures
4.2 Sewers
- Discharge capacity
- Sewer volumes
- Results for different loading conditions such as, for example, dry weather, wet
weather, actual status, forecast
• discharges
• flow rates
• filling heights, water level positions
• flow times
• degree of utilisation
• pressure line gradients
• flow conditions (streaming, gushing)
• discharge - water level flow curves
May 1996
32
ATV A 101E
- Special verification such as, for example,
• drag stress
• water spreading and overdam) frequencies
4.3 Special Structures
- Pump stations
• relevant discharges
• delivery height (manometric, geodetic)
• delivery stream
• pump characteristic curves
• structure data
• usage volumes of the pump sump
• operational data of the pressure pipelines
• switch-on and switch-off heights
• switching frequencies
• energy requirement
• emergency power supply
• overall degree of efficiency
• emergency overflow
• functional diagram
- Stormwater tanks
• type of tank (e.g. stormwater overflow tank, stormwater retention tank, storage
sewer,
stormwater sedimentation tank)
• relevant tank inflows and discharges
• dimensioning frequency
• associated drainage areas with degree of compacting
• calculated flow time in the catchment area
• structure data
• tank volumes
• throttling (regulation, control) of tank discharge
• filling, throughflow and emptying times
• surface flow rate
• inflow and discharge flow curves
• water level flow curves
• overflow data (overflow discharge sums, overflow frequency, overflow duration)
• overflow pollution load, possibly for given time period
• emergency overflow
• functional diagram
- Stormwater overflows
• type of design
• relevant inflows and discharges
• critical rainfall intensity
• calculated flow time in the catchment area
• structure data
• dimensions of the throttle stretch
• overflow data (overflow discharge sums, overflow frequency, overflow duration)
• overflow pollution load, possibly for given time period
- Other structures
May 1996
33
ATV A 101E
For future not yet implemented special structures such as, for example, release
structures, inverted siphons, pressure pipelines, pipe bridges, branches, appropriate
representation is to be selected in a visible manner.
Appendix 5
Breakdown and Content of Plans
1 General Plans
The general plans should show how the project is to be related to the broader
surroundings, to other projects, to other usages and to protective areas. The following
inputs are, in accordance with the tasking, recommended for the scales 1:50000,
1:25000 and 1:10000:
- catchment areas (overall, partial, external)
- protective areas (water, mineral springs, nature, landscape)
- receiving waters with flooding areas
- main collector sewers
- sewage treatment plants
- special structures
- contour lines
2 General Site Plans
The general site plans in the scales 1:5000, 1:2500 and 1:2000 should present the
project in more detail. Following inputs are recommended:
- catchment areas (overall, partial, external)
- protective areas (water, mineral springs, nature, landscape)
- water catchment areas
- receiving waters with flooding areas
- discharge points into the receiving water
- areas identified in legally effective area usage and building plans
- partial drainage areas
- available, planned and disused main collector sewers with details of flow direction,
- type, cross-section and gradient of the sewers
- special structures with pump stations, stormwater tanks, stormwater overflows,
inverted siphons, outlet structures
- sewage treatment plants
3 Site Plans
They should contain all essential measured details, limitations, line directions and
structures according to the task. Apart from the arable land boundaries, boundary points,
official fixed points and buildings they should include all important topographic details,
street names and house numbers. Insofar as inputs which are of significance for the local
situation are missing (e.g. street limitation lines, supporting walls), they are to be
May 1996
34
ATV A 101E
supplemented correspondingly with observation of DIN 18702. 1:2000, 1.1000, 1:500,
and, if required, 1:250 are recommended as scales.
The computer network plans should present the essential structure of the sewer network
including all special structures. With this, the hydraulic calculations carried out can be
checked for their logic and the effects of possible sewer network modifications on the
discharge conditions can be viewed better and more quickly.
According to the task and the scope of planning the scales 1:2500, 1:2000, 1:1000, and,
if required, 1:500 are recommended.
May 1996
35
ATV A 101E
- back-up areas
- expansion stages of the sewers to be renewed.
5 Flow Diagrams
The flow diagrams should allow a rapid and comprehensive review of the overall concept
of the drainage planning with the inclusion of the receiving water and of the sewage
treatment plants.
The flow diagrams are developed from the general plans and general site plans and
must be matched with the computer network plans. This schematic presentation should
give overall visibility of where and under what conditions the run-off from which areas is
discharged into the most important collector sewers and/or receiving waters. This
information is, for example, of particular significance with regard to the necessary extra-
local method of consideration of the receiving water mentioned in Sect. 3.1.
The flow diagrams should be built up from the elements area, pipe or channel length and
structure. They should show, in very simplified but relevantly related form, the following
inputs whereby the same, most important designations and numbers as in the above-
mentioned fundamental plans are to be used:
- catchment areas (overall, partial, external)
- receiving water
- main collector sewer, transport stretches
- special structures such as pump stations, stormwater tanks, stormwater overflows
- control and regulating facilities
- sewage treatment plants
- discharge points (outlet structures) into the receiving water with stationing in
kilometres
6 General Longitudinal Sections and Longitudinal Sections
All general longitudinal sections and longitudinal sections should be presented with
decline from left to right and have the same scale as the site plans.
As a rule the scale 1:100 is to be selected for the height. All height details are to be
referred to MSL. It can be practical to show the longitudinal section for the receiving
water in another scale to that of the sewers.
The general longitudinal sections with longitudinal scales of 1:10000, 1:5000, 1:2500 and
1: 2000 should allow a good overview of the complete planning measure. Therefore in
these plans only the most important inputs appear.
On the other hand, the longitudinal sections with longitudinal scales of 1:1000, 1:500
and, if required, 1:250 allow a comprehensive representation of the planning criteria and
results.
May 1996
36
ATV A 101E
6.1 Receiving Waters
- River floor heights (in the valley line)
- Heights of banks
- Existing and planned dikes
- Important water levels for processing and hydraulic calculation such as, for example
• mean low water level MLWL (with MLQ)
• mean high water level MHWL (with MHQ)
• highest known high water level HHWL (with HHQ) with details of annual
occurrence
• calculated water levels of certain annual occurrences
• tidal water levels
- Discharge points from public and private sewers
- Junctions and branches of natural and artificial lakes and rivers
- Position of cross-sections
- Bridges
- Sewers, inverted siphons, pipelines, cables
- Stationing in kilometres
6.2 Sewers
- Heights of sewer base (water flow), of the manhole cover lip and the terrain
- Relevant cellar floor heights
- Cross-sections (profiles), clear diameters
- Materials, pipe connections
- Base gradients and, if required, energy line gradients
- Discharge capacities
- Backflow lines
- Calculated discharge
- Shafts and special structures with designations
- Measurement points, control and regulation installations
- Weir heights
- Subsoil according to DIN 18196
- Sewer section lengths
- Groundwater level
- Inflows and discharges from side sewers (also from future building areas)
- Total lengths of partial sections
- Transverse pipelines
- Street names
- Stationing
- Special construction measures, e.g. pile foundation, pipe driving
- Water level of receiving waters MLWL, MHWL, HHWL at the discharge points (outlet
structures)
May 1996
37
ATV A 101E
- Pump and lifting stations
7 Structure and Special Plans
The necessary inputs into these plans can be different according to the purpose of the
plans and the scope of the planning task.
1:100, 1:50 or greater can be chosen as scale. The following inputs are recommended:
- type and quality of materials
- dimensions
- heights
- mechanical and electrical installations
- measurement facilities
- measurement and reference points
- relevant water levels of the receiving water
- groundwater levels with details of measurement periods
- profiles of subsoil investigations
- protective measures
7.2 Special Plans
From the large number of special plans only a few can be named as examples which can
be produced in the most varied of scales as diagrams or lists:
- co-ordinating plans (co-ordination with city works, supply agencies, post and similar)
- pegging plans
- static and constructive plans
- register of owners
- ecological inventory
- recultivation plans
- plans on ecological compensating measures
- landscape preservation attendant plans
- traffic diversion plans
- plans for provisions
- plans for usage rights, work and buffer strips
- cash flow plans
- construction time plans
May 1996
38