Grandspan Development Corporation And Kencana Joint Venture

Proposed Project Schedule


ID Task Name Duration April May June July August September October November December January February
3/20 4/3 4/17 5/1 5/15 5/29 6/12 6/26 7/10 7/24 8/7 8/21 9/4 9/18 10/2 10/16 10/30 11/13 11/27 12/11 12/25 1/8 1/22 2/5
1 A 380 Hangar 260 days 4/4 1/31
2 Start 0 days 4/4
3 Letter Of Award For Design & Build Works 0 days 4/4
4 Interfacing Works 7 days
5 Coordination Meeting 7 days 4/4 4/11
6 Procurement Stage 120 days 4/8 8/25
7 Civil Works 30 days 4/8 5/12
8 Structural Steelworks 90 days 4/8 7/21
9 Architecture Works 90 days 4/8 7/21
10 Mechanical 120 days 4/8 8/25
11 Construction Development 260 days 4/4 1/31
12 Civil Works 108 days 4/11 8/13
13 Mobilization/Site Preparation 7 days 4/11 4/18
14 Temfacil/Fencing Works 15 days 4/11 4/27
15 Earthworks 36 days 4/18 5/28
22 Lean Concrete (2500 psi ) 21 days 5/6 5/30
23 Backfilling/Compaction 14 days 5/16 5/31
24 Leveling Soil Rear End 14 days 5/12 5/27
25 Rebar Works 24 days 4/28 5/25
26 Formworks 15 days 5/3 5/19
27 Anchor Bolt Setting 13 days 5/20 6/3
31 Concreting 13 days 5/23 6/6
35 Curing/Finishing 35 days 5/24 7/2
36 Construction Zocalo Wall 22 days 6/4 6/29
37 Construction Door Rail Guide( Lower) 21 days 5/28 6/21
38 Construction Of Center Slab (34 m Wide ) 66 days 5/16 7/30
46 Construction Of Outer Slab (Left ) 59 days 5/25 8/1
54 Construction Of Outer Slab (Right ) 57 days 6/2 8/6
62 Restoration Of Slab 18 days 7/15 8/4
66 Fire Hydrant Works 16 days 5/28 6/15
71 Construction New Access Road ( Rear End ) 21 days 6/16 7/9
72 Requirement For Fire Protection 40 days 5/25 7/9
76 Storm Drainage 32 days 6/22 7/28
79 Additional Works 19 days 7/9 7/30
82 External Slab Works ( 3 sets ) 32 days 7/6 8/11
90 Inspection 12 days 8/1 8/13
91 Structural Steel Works 120 days 5/19 10/5
92 Blasting/Primer Painting Raw Materials 30 days 5/19 6/22
93 Materials Preparation 61 days 5/23 8/1
111 Fabrication 76 days 5/25 8/20
129 Blasting/Painting 70 days 6/2 8/22
147 Qa-QC Inspection/Acceptance 67 days 6/8 8/24
148 Delivery 63 days
153 Site Erection Works 99 days 6/13 10/5
154 Mobilization 2 days 6/13 6/14
155 Site Preparation 3 days 6/14 6/16
156 Survey 11 days 6/16 6/28
162 Temporary Support 30 days 6/17 7/21
166 Checking Alignment/Elev./Plumbness 7 days 7/22 7/29
167 Ground Assembly 77 days 6/21 9/17
168 Zone 1 15 days 6/21 7/7
169 Zone 3 15 days 7/11 7/27
170 Zone 2 25 days 8/5 9/2
171 Door Frames 18 days 8/29 9/17
172 Alignment/Bolting/Tightening 85 days 6/13 9/19

Task Summary Rolled Up Progress Project Summary


Project:A 380 HANGAR
Progress Rolled Up Task Split Group By Summary
Date: Mon 4/11/11
Milestone Rolled Up Milestone External Tasks Deadline

Prepared By:G.D.E. Checked By: R. V. Santiago Noted By: C. E. Rmero Conforme:


Grandspan Development Corporation And Kencana Joint Venture
Proposed Project Schedule
ID Task Name Duration April May June July August September October November December January February
3/20 4/3 4/17 5/1 5/15 5/29 6/12 6/26 7/10 7/24 8/7 8/21 9/4 9/18 10/2 10/16 10/30 11/13 11/27 12/11 12/25 1/8 1/22 2/5
173 Checking 85 days 6/14 9/20
174 Erection Works 72 days 6/25 9/16
175 Zone 1 ( Conventional ) 18 days 6/25 7/15
176 Front Wall 15 days 7/16 8/2
177 Door Rail Guide Frame 10 days 8/3 8/13
178 Zone 3 ( Low level Erection ) 24 days 7/13 8/9
179 Zone 2 ( Low Level Erection ) 35 days 8/8 9/16
180 Crane Beams 10 days 8/25 9/5
181 Rear Wall 15 days 8/10 8/26
182 Alignment/Bolting/Tightening 75 days 6/29 9/23
183 Qa-Qc Inspection/Acceptance 75 days 6/30 9/24
184 Jacking System 30 days 9/1 10/5
185 Preparation/Erection Tower For Heavy Lift 14 days 9/1 9/16
186 Heavy Lifting Zone 2 3 days 9/17 9/20
187 Heavy Lifting Zone 3 3 days 9/22 9/24
188 Release/Remove Jacks 5 days 9/26 9/30
189 Disassembly Tower 10 days 9/23 10/4
190 Demobilization Jacking System 5 days 9/30 10/5
191 Installation Bet. Zone 2 & 3 4 days 9/26 9/29
192 Installation Bet. Zone 1 & 2 4 days 9/21 9/24
193 Door Installation 6 days 9/19 9/24
194 Architectural Works 54 days 9/20 11/21
195 Roofing 52 days 9/20 11/18
196 Zone 1 21 days 9/20 10/13
197 Zone 2 24 days 10/6 11/2
198 Zone 3 21 days 10/26 11/18
199 Cladding 51 days 9/23 11/21
200 Sidewalls 22 days 9/23 10/18
201 Rear Walls 18 days 10/15 11/4
202 Doors 18 days 11/1 11/21
203 Installation Windows/Doors 12 days 10/19 11/1
204 Installation Downspouts 5 days 11/2 11/7
205 Installation Drain Pipes 5 days 11/8 11/12
206 Construction Elect'l/Mech'l Room 25 days 8/1 8/29
207 Construction Fire Protection Room 25 days 8/30 9/27
208 Installation Water Supply Lines 14 days 11/5 11/21
209 Installation Compress Airlines 14 days 11/22 12/7
210 Installation Ladder/Platform 14 days 10/1 10/17
211 Electrical Works 241 days 4/4 1/9
212 Mobilization 2 days 4/4 4/5
213 Engineering Review And Approval 5 days 4/6 4/11
214 Procurement/Delivery 120 days 4/12 8/29
217 Pits/Encasement Construction 87 days 4/27 8/5
222 Fabn./Install Support/Brackets For High Beam Lamp 35 days 6/21 7/30
223 Electrical Wiring/Conduits 89 days 9/26 1/6
229 Testing/Commissioning 35 days 11/29 1/7
230 Inspection 7 days 1/2 1/9
231 Mechanical Works 172 days 4/12 10/28
232 Overhead Cranes 155 days 4/12 10/8
239 Mechanical For Front Door 48 days 9/3 10/28
243 Testing And Handover 30 days 12/27 1/30
244 Demobilization 15 days 1/14 1/31
245 End 0 days 1/31

Task Summary Rolled Up Progress Project Summary


Project:A 380 HANGAR
Progress Rolled Up Task Split Group By Summary
Date: Mon 4/11/11
Milestone Rolled Up Milestone External Tasks Deadline

Prepared By:G.D.E. Checked By: R. V. Santiago Noted By: C. E. Rmero Conforme: