1. General

New works and modifications to Building Engineering Services within WSCC


Buildings shall only be undertaken by suitably qualified and experienced
contractors.

All works shall be designed, installed, tested and commissioned to meet best
industry standards and in compliance with the relevant current British and / or
European Standards for the work being undertaken.

2. Some of the key standards are listed below but others may be relevant
depending on the nature of the work being carried out.

Electrical Work
The Electricity at Work Regulations 1989
The IEE Wiring Regulations current edition (BS 7671)
The Building Regulations 2000
The current relevant specific British Standard Code of Practice.

Fire Alarms
BS 5839-1-2002 Fire Detection and Fire Alarm Systems for Buildings

Emergency Lighting
BS 52661 1999 Emergency Lighting

Lightning Protection
BS 6651 1992 Protection of Structures Against Lightning

Passenger Lifts
EN 81-1 1998 Safety Rules for the Construction and Installation of Lifts:
Part1 Electric Lifts
EN 81-2 1998 Safety Rules for the Construction and Installation of Lifts :
Part 2 Hydraulic Lifts
BS 5655 Part 11 1989 Recommendations for the installation of new, and the
modernisation of electric lifts in existing buildings
BS 5655 Part 12 1989 Recommendations for the installation of new, and
modernisation of hydraulic lifts in existing buildings
BS 8300 2001 Design of buildings and their approaches to meet the needs
of disabled people. Code of Practice
PAS 32 – 1 –1999 Specification for examination and test of new lifts before
putting into service. – Electric traction Lifts
PAS 32 – 1 –1999 Specification for examination and test of new lifts before
putting into service. – Hydraulic Lifts

Platform Lifts
BS 6400 1999 Powered lifting platforms for use by disabled persons. Code
of Practice.
BS 8300 2001 Design of buildings and their approaches to meet the needs
of disabled people. Code of Practice.
-1-

NOTE:
THIS DIRECTIVE IS APPLICABLE TO THE MAJORITY OF SCHEMES BUT IT WILL NOT NECESSARILY
BE APPROPRIATE TO ALL WORKS AND THEREFORE ON EACH SCHEME IT WILL BE NECESSARY
TO CHECK THE SPECIFIC REQUIREMENTS.
BCD.30

REFERENCE

2 cont. Mechanical Work


The Building Regulations 2000
The current relevant specific British Standard Code of Practice.

Natural and LPG Gas Installations


The Gas Safety (Installation and Use) Regulations 1998

Water Installations
The Water Supply (Water Fittings) Regulations 1999

Heating and Cooling Installations


The Building Regulations 2000
CIBSE design and commissioning guides and / or, the relevant codes of practice.

Ventilation Installations
The Building Regulations 2000
CIBSE design and commissioning guides and / or, the relevant codes of practice.

3. On completion of all works, testing and commissioning shall be carried out to


confirm that all systems and associated equipment are safe for use, and
operating within the anticipated design parameters.

This testing and commissioning shall be fully documented and certificates shall
be provided for each system before they will be accepted as complete.

New installations and modifications shall not be put into use unless the
necessary certifications have been received.

Guidance on the likely documentation required for each system / installation is


contained within the schedule in Appendix 1 of this BCD.

CONCLUSION

-2-
BCD 30 Appendix 1

West Sussex County Council Property Services


Guidance on Engineering Completion Documentation and Certification
(Summarised below is some of the key documentation necessary to demonstrate compliance with legislation and / or good current practice. The list is not
exhaustive and further documentation, record drawings and information, will be required for the Operating and Maintenance manuals as detailed within the
WSCC Property Services Construction Guide and Building Contract Directives)

Item Reference Standard On completion of a new On modification of an existing On routine periodic inspection
installation and at Handover installation and testing

Electrical Installation
Certificate
Periodic Inspection Report for an
Record of Inspection and Test Electrical Installation
Results Schedule of Inspections
Electrical Installation Certificate
Record of Inspection and Test Results Schedule of Test Results
Electrical BS 7671 2001 Note. a separate Electrical
Installations IEE Wiring Installation Certificate will be required (Note. Where periodic inspection is
th for each specialist installation where OR
Regulations 16 carried out as part of the
Edition additional mains circuits have been Maintenance Contract by the Area
provided.(ie Lifts, Electrical circuits Minor Electrical Installation Works
Certificate Maintenance Contractor a Service
for the mechanical Installation, Return / daywork sheet will only be
controls, Fire alarms, Security alarms (dependent on extent of the works)
required
CCTV, etc unless the wiring has
been installed by the Electrical
Contractor who has been responsible
for the main electrical installation and
it is included on the main electrical
installation certificate.

Gas Installations Gas Safety Gas Tightness Testing Certificate Gas Tightness Testing Certificate Gas tightness Testing Certificate
Pipework and (Installation and Use ) (Note. Where routine inspection is
Fittings Regulations1998 carried out as part of the
ACOP Maintenance Contract by the Area
Maintenance Contractor a Service
Return / daywork sheet will also be
required)
-3-

NOTE:
THIS DIRECTIVE IS APPLICABLE TO THE MAJORITY OF SCHEMES BUT IT WILL NOT NECESSARILY BE APPROPRIATE TO ALL WORKS AND
THEREFORE ON EACH SCHEME IT WILL BE NECESSARY TO CHECK THE SPECIFIC REQUIREMENTS.
BCD.30

Item Reference Standard On completion of a new On modification of an existing On routine periodic inspection
installation and at Handover installation and testing

For each appliance, (ie boilers, water For each appliance, (ie boilers, water
Gas Safety heaters, cookers etc.) heaters, cookers etc.) Landlords Gas Safety Record
(Installation and Use )
Gas Boilers and Regulations1998 Gas Safety Inspection Report Gas Safety Inspection Report (Note. Where routine inspection is
Gas Appliances ACOP carried out as part of the
Commissioning data Commissioning data Maintenance Contract by the Area
Maintenance Contractor a Service
Manufacturers Operating Instructions Manufacturers Operating Instructions Return / daywork sheet will also be
required

Included on Periodic Inspection


Included on Electrical Installation Included on Electrical Installation Report (where relevant )
BS 7671 2001 Certificate (as above where relevant) Certificate (as above where relevant)
Fixed Electrical IEE Wiring (Note. Where periodic inspection is
th
Equipment Regulations 16 Manufacturers Operating Instructions Manufacturers Operating Instructions carried out as part of the
Edition Maintenance Contract by the Area
Maintenance Contractor a Service
Return / daywork sheet will only be
required)

Electrical Installation Certificate Electrical Installation Certificate Included on Periodic Inspection


Report (where relevant )
BS 7671 2001 Record of Inspection and Test Record of Inspection and Test Results
IEE Wiring Results (Note. Where periodic inspection is
External lighting Regulations 16th carried out as part of the
Edition Written Confirmation of satisfactory Maintenance Contract by the Area
Written Confirmation of satisfactory functional test Maintenance Contractor a Service
functional test Return / daywork sheet will only be
required)

-4-
BCD.30

Item Reference Standard On completion of a new On modification of an existing On routine periodic inspection
installation and at Handover installation and testing

Water Supply (Water


fittings) Regulations
1999 Flushing / Chlorination Certificate Flushing / Chlorination Certificate
(pipe work, fittings and tanks) (pipe work, fittings and tanks)
CIBSE TM 13 As detailed within Site Water
Cold Water Pipe work pressure test Certificate Pipe work pressure test Certificate Logbooks
Systems CIBSE Commissioning
Codes Approved Contractors Certificate Approved Contractors Certificate

BSRIA Commissioning Water test certificate (Chemical /


Guides Bacteriological)

HSC Approved Code


of Practice and
Guidance L 8

Water Supply (Water


fittings) Regulations Flushing / Chlorination Certificate
1999 (pipe work, fittings and tanks)

CIBSE TM 13 Pipe work pressure test Certificate Flushing / Chlorination Certificate


(pipe work, fittings and tanks) As detailed within Site Water
CIBSE Commissioning Approved Contractors Certificate Logbooks
Hot Water Codes Pipe work pressure test Certificate
Systems Commissioning details for Blending
BSRIA Commissioning valves, recorded temperature Approved Contractors Certificate
Guides measurements for stored water and
distribution temps etc.

HSC Approved Code


of Practice and
Guidance L 8

-5-
BCD.30

Item Reference Standard On completion of a new On modification of an existing On routine periodic inspection
installation and at Handover installation and testing

Pipe work pressure test Certificate Pipe work pressure test Certificate
CIBSE Commissioning (Note. Where periodic inspection is
Codes Chemical Dosing Certificate Chemical Dosing Certificate carried out as part of the
Heating Systems Maintenance Contract by the Area
BSRIA Commissioning Commissioning Data, (details of flow Commissioning Data, (details of flow Maintenance Contractor a Service
Guides rates, measured temperatures, rates, measured temperatures, Return / daywork sheet will only be
pressures, balancing etc) balancing etc) required)

Fire Alarm Design Certificate Fire Alarm Modification Certificate


Fire Alarm Installation Certificate
Fire Alarm Commissioning Certificate Electrical Installation Certificate (for Fire Alarm Inspection and
Fire Alarm Acceptance Certificate any new power supplies) Servicing Certificate
BS 5839-1:2002
Fire Alarms Fire Detection and Fire Electrical Installation certificate (for (Note. Where periodic inspection is
Alarm Systems for any new power supplies) Written confirmation that all functional carried out as part of the
Buildings switching and inter links to other Maintenance Contract by the Area
Written confirmation that all services are fully operational Maintenance Contractor a Service
functional switching and inter links to Return / daywork sheet will only be
other services are fully operational Manufacturers Operating Instructions required

Manufacturers Operating Instructions

Periodic Inspection and test


Certificate
Emergency Lighting Completion Emergency Lighting Completion
Certificate Certificate (Note. Where periodic inspection is
Emergency BS 5266-1:1999 carried out as part of the
Lighting Emergency Lighting Electrical Installation certificate (for Electrical Installation certificate (for any Maintenance Contract by the Area
any new power supplies) new power supplies) Maintenance Contractor a Service
Return / daywork sheet will only be
Manufacturers Operating Instructions Manufacturers Operating Instructions required

-6-
BCD.30

Item Reference Standard On completion of a new On modification of an existing On routine periodic inspection
installation and at Handover installation and testing

The Lifting Operations


and Lifting equipment
Regulations 1998
Commissioning certificate
Lifts Lift Regulations 1997 Commissioning certificate Service report
Commissioning data (from a specialist Contractor)
Electric Traction EN 81 1998 Commissioning data
PAS 32 test certificates Log cards
Electric Hydraulic PAS 32 1999 Manufacturers Operating Instructions
Declaration of Conformity Risk assessment
SAFed Guidance Operating and Maintenance Manuals
Manufacturers Operating Instructions
BS 7255
Operating and Maintenance Manuals
BS 5655
( Technical Dossier)
BS 8300

Certificate of test and examination


The Lifting Operations Certificate of test and examination
Lifts and Lifting equipment Commissioning data
Regulations 1998 Commissioning data Service report
Platform Declaration of Conformity (from a specialist Contractor)
BS 6440 Manufacturers Operating Instructions
Manufacturers Operating Instructions
BS 8300 Operating and Maintenance Manuals
Operating and Maintenance Manuals

Lightning BS 6651:1992
Protection Protection of Lightning Protection Commissioning Lightning Protection Commissioning Periodic Inspection and test
Structures Against Certificate Certificate Certificate
Lightning

-7-
BCD.30

Item Reference Standard On completion of a new On modification of an existing On routine periodic inspection
installation and at Handover installation and testing

Commissioning certificate Commissioning certificate


Service report
CCTV BS EN 50132 Electrical Installation certificate (for Electrical Installation certificate (for any (generally from a specialist
any new power supplies) new power supplies) Contractor)

Manufacturers Operating Instructions Manufacturers Operating Instructions

BS 4737 1986 Commissioning certificate Commissioning certificate


Security systems Service report
intruder BS EN 50131-1 Electrical Installation certificate (for Electrical Installation certificate (for any (generally from a specialist
any new power supplies) new power supplies) Contractor)
Manufacturers Operating Instructions
Manufacturers Operating Instructions

Commissioning certificate Commissioning certificate


Access Control Service report
BS EN 50133 Electrical Installation certificate (for Electrical Installation certificate (for any (generally from a specialist
any new power supplies) new power supplies) Contractor)
Manufacturers Operating Instructions
Manufacturers Operating Instructions

TV aerial systems Commissioning certificate Commissioning certificate Service report


(generally from a specialist
Electrical Installation certificate (for Electrical Installation certificate (for any Contractor)
any new power supplies) new power supplies)

-8-
BCD.30

Item Reference Standard On completion of a new On modification of an existing On routine periodic inspection
installation and at Handover installation and testing

Commissioning certificate Service report


Commissioning certificate (generally from a specialist
Nurse call / first Electrical Installation certificate (for any Contractor
aid alarms Electrical Installation certificate (for new power supplies)
any new power supplies) Manufacturers Operating Instructions
Manufacturers Operating Instructions

Service report
Written confirmation of visual Written confirmation of visual (generally from a specialist
BS 7671 2001 inspection and satisfactory functional inspection and satisfactory functional Contractor
IEE Wiring test test
Kilns Regulations 16th Electrical Installation certificate (for Electrical Installation certificate (for any (Note. Where periodic inspection is
Edition any new power supplies) new power supplies) carried out as part of the
Manufacturers Operating Instructions Manufacturers Operating Instructions Maintenance Contract by the Area
Maintenance Contractor a Service
Return / daywork sheet will only be
required

Periodic Inspection Report for an


Electrical Installation

Safety switching BS 7671 2001 Schedule of Inspections


systems IEE Wiring Written confirmation of visual Written confirmation of visual Schedule of Test Results
Regulations 16th inspection and satisfactory functional inspection and satisfactory functional
Edition test test (Note. Where periodic inspection is
carried out as part of the
Maintenance Contract by the Area
Maintenance Contractor a Service
Return / daywork sheet will only be
required

-9-
BCD.30

Item Reference Standard On completion of a new On modification of an existing On routine periodic inspection
installation and at Handover installation and testing

Service report
Commissioning certificate Commissioning certificate (generally from a specialist
Contractor
Electrical Installation certificate (for Electrical Installation certificate (for any
Intercom systems any new power supplies) new power supplies) (Note. Where carried out as part of
the Maintenance Contract by the
Manufacturers Operating Instructions Manufacturers Operating Instructions Area Maintenance Contractor a
Service Return / daywork sheet will
only be required

Service report
Commissioning certificate Commissioning certificate (generally from a specialist
Contractor
BS 6259 ; 1997 Electrical Installation certificate (for Electrical Installation certificate (for any
PA systems any new power supplies) new power supplies) (Note. Where carried out as part of
the Maintenance Contract by the
Manufacturers Operating Instructions Manufacturers Operating Instructions Area Maintenance Contractor a
Service Return / daywork sheet will
only be required

Commissioning certificate Commissioning certificate


WSCC Standard Service report
Data installations Specification for ICT Warrantee Certificate Warrantee Certificate ( from a specialist Contractor)
Installations
Electrical Installation certificate (for Electrical Installation certificate (for any
any new power supplies) new power supplies)

- 10 -
BCD.30

Item Reference Standard On completion of a new On modification of an existing On routine periodic inspection
installation and at Handover installation and testing

Service report
Building regulations Commissioning certificate Commissioning certificate (generally from a specialist
2000 Contractor
Written Confirmation of satisfactory Written Confirmation of satisfactory
Heating Controls CIBSE Commissioning functional test functional test (Note. Where carried out as part of
Codes the Maintenance Contract by the
Manufacturers Operating Instructions Manufacturers Operating Instructions Area Maintenance Contractor a
BSRIA Commissioning Service Return / daywork sheet will
Guides Schedule of control settings Schedule of control settings only be required

Commissioning certificate Commissioning certificate


Service report
Powered Doors BS 7036 1996 Electrical Installation certificate (for Electrical Installation certificate (for any (generally from a specialist
any new power supplies) new power supplies) Contractor

Manufacturers Operating Instructions Manufacturers Operating Instructions

Building regulations Commissioning certificate Commissioning certificate


2000 Service report
Electrical Installation certificate (for Electrical Installation certificate (for any (generally from a specialist
Air conditioning CIBSE Commissioning any new power supplies) new power supplies) Contractor
Codes
Manufacturers Operating Instructions Manufacturers Operating Instructions
BSRIA Commissioning
Guides

- 11 -
BCD.30

Item Reference Standard On completion of a new On modification of an existing On routine periodic inspection
installation and at Handover installation and testing

Service report
Building regulations Commissioning certificates Commissioning certificates (generally from a specialist
2000 (fans, Air handling units, controls etc) (fans, Air handling units, controls etc) Contractor)

Ventilation CIBSE Commissioning Commissioning data ( details of air Commissioning data ( details of air (Note. Where carried out as part of
Codes flow rates / velocities, balancing, flow rates / velocities, balancing, the Maintenance Contract by the
pressure measurements etc) pressure measurements etc) Area Maintenance Contractor a
BSRIA Commissioning Service Return / daywork sheet will
Guides only be required)

Pipe work Pressure Test Certificate

Commissioning certificate for Pumps


and filtration plant
Managing Health and (to include commissioning data flow Pipe work Pressure Test Certificate
safety in swimming rates, pressure readings etc.)
Pools Commissioning certificate for Pumps
HSE Maintenance and Operating and filtration plant
Instructions (to include commissioning data flow Service report / checklist
Swimming Pool Water (to include Pool Operators Check rates, pressure readings etc.) (generally from a specialist
Swimming pools treatment and Quality List) Contractor)
Standards Maintenance and Operating
(Pool Water Treatment Water quality bacteriological test Instructions
Advisory Group) certificate (to include Pool Operators Check List) Pool Operators water quality
checks
Hygiene for Water quality chemical balance test Water quality bacteriological test
Hydrotherapy Pools certificate certificate
(Public Health
Laboratories Services) Note Water quality chemical balance test
Where gas and electrical installations certificate
are carried out as part of the Pool
Installation, certification requirements
should be as listed previously for
these services

- 12 -