You are on page 1of 92

Rajasthan State Pollution Control Board

Sector Specific Guidance Manual

Zero Draft
for
Townships & Area Development Projects

Prepared by

Administrative Staff College of India


Hyderabad
==============================================================
SECTOR SPECIFIC GUIDANCE MANUAL
FOR
TOWNSHIPS AND AREA DEVELOPMENT PROJECTS
==============================================================
Contents
Chapter No. Title Page No.

Foreword
Acknowledgements
Team
List of Annexures
About the Manual

Chapter 1 Introduction
1.0 About RPCB
1.1 Townships and area development projects-
Classification by RPCB for Consent Management purpose
1.2 Townships and area development projects-
Classification by MoEF for EC applicability

Chapter 2 Environmental Acts and Legal Requirements


2.0 Legal requirements under the provisions of the
Water (Prevention & Control Pollution) Act, 1974 as amended
2.1 Requirement under the provisions of
Air (Prevention & Control Pollution) Act, 1981 as amended
2.2 Requirement under the provisions of the
Environmental (Protection) Act, 1986 and as amended
2.3 Requirement for ground water extraction
2.4 Notification for the integrated township dated 29.03.07
Urban development & Local Self Department,
Government of Rajasthan
2.5 Requirements under the Notification No. S.O. 319 (E) dated
7th May 1992 and S.O. 1189 (E) dated 29th November 1999-
Restriction of certain activities in specified area of Aravalli Range
2.6 Requirements under the Notification No. S.O. 1545
dated 25th June 2009-Mount Abu Eco-sensitive Zone

Chapter 3 Statutory Clearance Process


3.0 Environmental Clearance Process
3.1 Public Consultation
3.2 Validity of Environmental Clearance
3.3 Post Environmental Clearance Monitoring
3.4 Transferability of Environmental Clearance
3.5 Criteria for EIA consultants
3.6 Authorized signatory
3.7 Participation of the project proponent during the EAC meeting
3.8 Projects requiring recommendation of the Chief Wildlife Warden
3.9 Consent management system – RPCB

Chapter 4 Environmental Aspects and Guidance


4.0 Environmental Checklist
4.1 Environmental norms
4.2 Guidance for the project developer

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 1
Chapter 5 Guidelines for sector specific projects
5.0 Guidelines for stipulating sector specific condition
in the CTE order

Chapter 6 Environmental Management Plan


6.0 General
6.1 Components of EMP

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 2
Foreword
(To be given by RPCB)

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 3
Acknowledgements
(To be given latter by ASCI)

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 4
Project Team

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 5
Annexures

1. FORM 1 (EIA Notification dated 14th September 2006 as amended 1st December 2009)
2. FORM-1 A (only for construction projects listed under item 8 of the Schedule of EIA
Notification)
3. Application for Consent To Establish
4. Application for Consent To Establish
5. Consent Fee Under the Provisions of Water Act
6. Consent Fee Under the Provisions of Air Act
7. Areas as identified by CGWA as – safe areas, semi – critical areas, critical areas & over
exploited areas
8. General Standards for Discharge of Effluents
9. National Ambient Air Quality Standards (NAAQS)
10. Noise Ambient Air Quality Standards
11. Noise Limits for Generator Sets run with Diesel
12. Effluent Standards for Hotel Industry notified under E (P) Act, 1986
13. Estimation of Water Demand
14. Code of Practices for Parking Requirements
15. BIS Code of Practices
16. Ground Water Scenario of Rajasthan
17. Rain Water Harvesting Structures
18. Water Quality Inlets
19. Availability of Rain Water Through Roof Top Rain Water Harvesting
20. Wind Towers
21. Checklist - Construction Phase

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 6
About the Manual

The purpose of developing sector specific guidance manual for Township and Area
Development projects is to provide clear and concise information to all the stakeholders i.e
project proponent, environmental consultant, Rajasthan State Pollution Control Board
officials and the public to have a better understanding on the relevant environmental aspects
in the initial stage itself. This manual covers the legal requirements, clearance process,
environmental standards and maintenance of statutory records. The manual will also
covers the environmental aspects due the Township and Area Development projects. The
project proponent may use this manual to ensure that all the aspects of the environment due
to the project are addressed and adequate mitigation measures are planned in the proposed
environmental management plan and he will be fully aware of the environmental process
and requirements. The consultants will have similar understanding of the sector and the
procedures involved, so that the quality EIA or EMP reports will be improved. The
reviewers across the board may have same understanding about the sector and helps them
in the process of review and appraisal. Public who are concerned about a new or expansion
project, will have information about the environmental aspects, standards, regulatory
requirements etc., and have a better understanding about the developmental project. To
ensure effective utilization by different stakeholders this manual is divided into the
following chapters:

The preparation of sector specific guidance manual by Rajasthan State Pollution Control
Board is in line with National Environmental Policy 2006, which emphasizes on:

- Formulate and periodically update, codes of good practices for environment for
different category of industries
- Ensure faster decision making with greater transparency and access to information,
together with necessary capacity building

The manual is meant to serve as a guidance purpose. In case of interpretation of any


question related to law, the provisions of the original law and the rules made thereunder
with various government directions/resolutions will have to be read and followed. In case
of amendment to the original Act/Rules/Notifications made thereunder, the provisions as
amended from time to time shall be applicable.

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 7
CHAPTER I
Introduction

1.0 About RSPCB

The Rajasthan State Pollution Control Board (RPCB) is a statutory authority entrusted to
implement environmental laws & rules within the jurisdiction of the State of Rajasthan. The
Board ensures proper implementation of the statues, judicial and legislative
pronouncements related to environmental protection within the state. The Board was
established in the year 1975 under the provisions of Water (P&C of Pollution) Act 1974. Over
the years, RSPCB was entrusted with various responsibilities under different enactments
made. Currently RSPCB is responsible completely or partially for the implementation of
following Acts and rules:

• The Water (Prevention & Control of Pollution) Act, 1974 and Rules made there off
• The Air (Prevention & Control of Pollution) Act, 1981 and Rules made there off
• The Water (Prevention & Control of Pollution) Cess Act 1976 and Rules made there off
• The Public Liability Insurance Act, 1991 and Rules made there off
• The Environmental Protection Act, 1986 and Rules made there off

‐ Hazardous Wastes (Management, Handling & Transboundary Movement) Rules


2008
‐ Manufacture, Storage and Import of Hazardous Chemical Rules, 1989 as amended
‐ Municipal Solid Waste (Management and Handling) Rules, 2000
‐ Bio Medical Waste (Management and Handling) Rules, 1998 as amended
‐ Ozone Depleting Substances (Regulation) Rules, 2000
‐ The Batteries (Management and Handling) Rules, 2001
‐ Fly Ash Notification as amended S.0. 2804(E) dated 3rd November 2009
‐ Environmental Impact Assessment Notification, 2006 as amended
‐ The Chemical Accidents (Emergency Planning, Preparedness and Response) Rules,
1996
‐ The Recycled plastic (Manufacture and Usage) Rules, 1999 as amended
‐ The Manufacture, Use, Import, Export and Storage of Hazardous Micro Organisms,
Genetically Engineered Organism or Cells Rules, 1989
‐ Notification No. S.O. 319 (E) dated 7th May 1992 (Restricting certain activities in
special specified area of Aravalli Range)
‐ Notification No. S.O. 1545 (E) dated 25th June 2009 declaring Mount Abu Eco
Sensitive Zone
‐ The Noise Pollution (Regulation and Control) Rules, 2000
‐ The EIA Notification S.O. 1533 dated 14th September 2006 as amended 1st December
2009

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 8
1.1 Townships and Area Development projects - Classification by RPCB for consent
management purpose

The RPCB had categorized based on pollution causing potential, the Township and Area
Development projects for consent management purpose as follows:

No. Project Description


Red category
S.No.30 of Red Building/construction projects having built up area equal to or
category more than 20,000 Sq. meters
S.No.31 of Red Township projects of more than or equal to 50 ha
category
S.No.37 of Red Hotels:
category - Having capacity of 100 beds and above
- Hotels and all tourism projects irrespective of their capacity which
is amidst in any water body or which are located within 200 meters
of HFL of any lake, reservoir, river or water body
S.No.43 of Red Hospitals (50 or more beds)
category
Orange category
S.No.11 of Orange Hotels having capacity from 51 to 99 beds
category
S.No.30 of Orange Hospitals (less than 50 beds)
category
S.No.35 of Orange Water Treatment Plants of capacity more than 4.0 MLD
category
S.No.36 of Orange Multiplexes or building/construction projects having built up area
category less than 20, 000 sq. meters but more than or equal to 2500 sq.
meters
Other category
S.No. A of Other - All other industries which are not covered under the ‘Red’ or
category ‘Orange’ categories and are discharging waste, water and/or air
emissions
- All mines not included in Red & Orange categories and having
area less than 1.0
- Water Treatment Plants of capacity up to 4.0 MLD
- Hotel having capacity up to 50 beds
- Fixed D.G sets with total capacity of more than or equal to 200
KVA
Reference: RPCB office order dated 03.04.2008

1.2 Townships and Area Development projects – Classification by MoEF for EC


applicability

Environmental Impact Assessment Notification S.O.1533 (E) of 14th September 2006 as


amended in 2009 has made it mandatory to obtain prior environmental clearance for
scheduled development projects. As per these notifications, Townships and Area

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 9
Development projects are classified as category B projects. The following is the
categorization made for the applicability of EIA Notification:

Project or activity Category with threshold Conditions


Category A Category B
8 Building and --- ≥20, 000 sq. meters # Built up area for
(a) Construction and < 1,50,000 sq. covered construction; in
projects meters of built-up case of facilities open to
area# the sky, it will be the
activity area
8 Townships and --- Covering an area ≥50 ++ All projects under
(b) Area ha and or built up item 8(b) shall be
Development area ≥1, 50,000 sq. appraised as Category B1
projects meters ++
7(c) Industrial If at least one industry Industrial estates Special conditions shall
estates/parks/c in the proposed housing at least one apply
omplexes/areas, industrial estate falls Category B industry
export under the Category A, and area <500ha Note:
processing zones entire industrial area Industrial estate of area
(EPZs), special shall be treated as below 500ha. and not
economic zones Category A, housing any industry of
(SEZs), Biotech irrespective of the area Category ‘A’ or ‘B’ does
parks, Leather not require clearance
complexes Industrial estates with Industrial estates of
area greater than 500ha. area >500ha. and not If the area is less than
and housing at least housing any industry 500ha. but contains
one Category B belonging to Category building and
industry A or B construction projects
>20,000 sq.mtr and or
development area more
than 50ha it will be
treated as activity listed
at serial no. 8(a) or 8(b)
in the Schedule, as the
case may be
Reference: EIA Notification S.O 1533 dated 14th September 2006 and amended Notification S.O 3067 (E) dated
1st December 2009

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 10
CHAPTER 2
Environmental Acts and Legal requirements

2.0 Legal requirements under the provisions of the Water (Prevention & Control of
Pollution Act) 1974 as amended

The Water (Prevention & Control of Pollution) Act, 1974 and as amended
Section 25 (1) Subject to the provisions of this section, no person shall, without the
previous consent of the State Board
Restrictions on
new outlets and a. Establish or take any steps to establish any industry, operation or
discharges process, or any treatment and disposal system or an extension or
addition thereto, which is likely to discharge sewage or trade effluent
into a stream or well or sewer or on land (such discharge being
hereafter in this section referred to as discharge of sewage); or

b. Bring into use any new or altered outlets for the discharge of
sewage; or

c. Begin to make any new discharge of sewage


Section 44 Whoever contravenes the provision of section 25 shall be punishable
with imprisonment for a term which shall not be less than two years
Penalty of but which may extend to six years and with fine
contravention of
section 25

2.1 Requirements under the provisions of the Air (Prevention & Control of
Pollution Act) 1981 as amended

The Air (Prevention & Control of pollution) Act, 1981 and as amended
Section 21 (1) Subject to the provisions of this section, no person shall, without the
previous consent of the State Board, establish or operate any
Restrictions on industrial plant in an air pollution control area
use of certain
industrial plants
Section 37 (1) Whoever fails to comply with the provisions of section 21, be
punishable with imprisonment for a term which shall not be less than
Penalty of one year and six months but which may extend to six years and with
contravention of fine
Section 21

2.2 Requirements under the provisions of the Environment (Protection) Act, 1986
and as amended

S.O. 1533 dated Projects listed in the schedule shall obtain prior environmental
14th September clearance from the concerned regulatory authority.
2006
Section 15 of E Punishable with imprisonment up to 5 years with fine up to one lakh
(P) Act 1986 or with both
Section 16 of E When a company has committed offence under E (P) Act, and it is

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 11
(P) Act 1986 proved that the offence has been committed with the consent or
connivance of, or neglect on the part by any director, manager,
secretary or other officials shall be deemed to be guilty and shall be
liable for punishment.

2.3 Requirements for Ground Water Extraction

Keeping in view of the requirements stated in the Policy guidelines for clearance of ground
water abstraction for various uses issued by the Central Ground Water Authority, Ministry
of Water Resources, GoI vide their letter dated 14.10.2009, the following guidelines
regarding the requirement of NOC from CGWA for abstraction of ground water by any
industry/ infrastructure project/ mine (proposed/existing) are being followed:

S. No Guidelines
1. NOC from CGWA shall not be required for abstraction of ground water in the
following cases:
• In case of over-exploited areas abstraction<25m3/day
• In case of critical areas abstraction <50 m3/day
• In case of semi critical areas abstraction <100 m3/day
2. The exemption shall not be applicable to industries, which are using water as
raw material such as packaged drinking water industries, distilleries and
breweries
3. Industry/infrastructure project/time (proposed/existing) located in safe
category areas, are required to obtain NOC from CGWA if ground water
abstraction exceeds 1000 m3/day for hard rock areas and 2000 m3/day for
alluvial areas
4. For the industry/infrastructure project/mine which proposed to abstract ground
water more than the exempted quantity referred above, the Consent to Establish
application will be considered only after submission of NOC from CGWA
5. The following conditions shall be imposed while issuing Consent to Establish
• The artificial recharge proposal shall be vetted by the component authority
viz. Regional Director, Central Ground Water Board (WR), Jaipur/State
Ground Water Department, Jaipur
• Industry shall undertake artificial recharge measures
• Recycled and /or treated water shall not be used for recharge to ground
water
• Industry shall provide suitable meter system and maintain proper record of
the daily abstraction of ground water
6. A copy of consent letter containing will be endorsed to Regional Director,
Central Ground Water Board (WR), 6A, Jhalana Institutional Area, Jaipur for
their information and necessary action by RPCB
Please refer RPCB Circular dated 08.01.2010 for further information

2.4 Notification for Integrated Township dated 29.03.2007, Urban Development &
Local Self Department, Government of Rajasthan

The Government of Rajasthan had issued certain directions in their order dated 29.03.2007 to
promote integrated development in future growth of the urban areas of the Rajasthan and to
encourage private sector investment/foreign direct investment (FDI) in real estate sector.

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 12
These directions were issued under Section 297 of the Rajasthan Municipal Act
1959, Section 90 of the Jaipur Development Authority Act 1982, Section 60 of the Raj
Housing Board Act, 1970 and Rule 31 of the Rajasthan Urban Improvement (Disposal of
urban lands) Rules 1974. Some of the provisions of this notification are listed below:

A. Integrated Township Schemes of Private Developers


1. Minimum area for integrated township shall be 10 hectares in Jaipur, 6 hectares in
Divisional Headquarters and 4 hectares in other Municipal Towns and District Head
quarters
9 (a). The following land use distribution shall be ensured at scheme level

Residential Up to 50% Plotted apartments (of the scheme area 7.5% land be
reserved for EWS and 0.5% land shall be reserved
under “Jan Sathi” scheme/informal sector in the
scheme
Commercial Up to 5% Available to developer for disposal
Institutional Up to 10% Available to developer for disposal
(Educational
/Medical etc)
Facilities Not less To be developed as per approved planning. At least
(Roads, parks than 35% 10% area for parks & open spaces shall be reserved.
& open (including This entire area under roads, parks & open spaces to
spaces) sector level be surrendered to local authority after development.
roads) The Local authority would ensure reservation of
adequate land for games and sports facilities
9 (b). Local authorities would develop sector parks on the lines of sector roads as per zonal
plans
10. No road shall be less than 40ft. and all the roads shall provide for standard street
lighting and essential street furniture. Road connectivity shall be ensured by the
developer
12. Gross residential density shall be prescribed on the basis of level of available external
development infrastructure. Configuration of plotted/Group housing shall be
developer’s option
14. Separate Building Regulations shall be framed for integrated township projects.
Suggested points for inclusion in the Building Regulations are as under. The Local
Authority shall prepare/amend Building Regulations accordingly:
(i). Group housing projects to be encouraged in which all provisions for a decent
communities living would be ensure, such securities arrangements, power/water
backing backup shops for daily needs, provisions for service class, space for
communities gathering, gyms, health club etc
(ii). All public areas to have provisions for physically handicapped
(iii). Rain water harvesting provisions will be compulsory in all group housing
projects and township schemes
(iv). Separate regulations for Group housing/malls to be proposed. The regulations so
prepared shall provide for the provisions of parking and open spaces which shall be
surrendered in favor of the Local Authority
15. In township schemes “community water harvesting strictures” will be constructed by
local authority and all water outlets and drainages will be connected to this structure.
This shall be strictly enforced by the local authority
21. An “Eco-cess” at the rate of Rs. 1/- per sq.yd. shall be charged by the local bodies for

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 13
the lands to be developed under this scheme which shall be utilized for greening the
city
22. The design of the township shall aim at water and energy conservation. This would
mean
7. Proper orientation of building blocks
ii. Use of appropriate building material
iii. Use of non conventional energy sources, particularly solar energy
iv. Recycling of waste water and water harvesting
23. The FAR of the entire gross area of township shall be 1.0. this would encourage proper
mix of plotted development and group housing and would also encourage vertical
development
B. Township Schemes of Local Authorities
1. The Jaipur Development Authority in case of Jaipur and local authority in consultation
with Town Planning Department of the State for other towns of Rajasthan shall declare
a well-defined area in appropriate zone as “Town Planning Scheme”. The master plans
would be suitably amended to accommodate such schemes
3. Sector plans shall be prepared indicating the sector road network and sector level uses
6. After deducting area of sector road, commercial strips, developer’s land and FDI
pockets from the project area, the redistribution of the available area shall be done in
the following manner

Use Percentage Detailed Break up


Residential/Plot 63% 35% To be made available to khatedar in his own
ted land or in the vicinity
15% To be retained by local authority towards cost
of Internal Development
5% To be retained by local authority towards
external development / augmentation of
infrastructure
7.5% To be developed by local authority for
EWS/LIG housing
0.5% Would be reserved for convenient
shopping/kiosks/informal sector under “Jan
Sathi” scheme
Internal Roads 20%
Sectoral facilities 7%
Local/level 10%
facilities/open
spaces/parks
C. General Conditions
3.i. Local authority would issue NOC to the developers as per provisions of Master plan
and land use plan
3.iii. Conversion of land would be allowed according to master plan provisions. Wherever
required, change in land use would be first ensured before conversion is permitted
5. Pollution Control Board norms for townships with respect to provisions of
Environmental Clearance as required under Ministry of Environment and Forests (GoI)
Notifications shall be applicable
7. The provisions will also apply in the entire NCR Region of Rajasthan state
App If in case of individual khatedar schemes, the entire internal development will be done

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 14
endi by the local authority for which plots of equal value would be handed over by the
x-1 khatedar developer to the local authority
App Time limit foe completion of project
endi
x-1 Type Time period from date of sanction
Land development with Up to 10 ha - 3 years
respect to roads, drains,
sewerage, power & water 25% development by the end of the I year
supply etc 50% development by the end of the II year
100% development by the end of III Year

For more than 10 ha - one additional year for


each additional 10 ha
Land development & Up to 10 ha - 4 years
construction works
(minimum of 25% on every 33% development by the end of the II year
earmarked plot) 66% development by the end of the III year
100% development by the end of IV Year

For more than 10 ha - one additional year for


each additional 10 ha
Please refer to the Notification dated 29.03.2007 for details

2.5 Requirements under the Notification No. S.O.319 (E) dated 7th May 1992 and
S.O. 1189 (E) dated 29th November 1999 – Restriction of certain activities in
specified area of Aravalli range:

The MoEF, GoI had stipulated restrictions on certain activities in specified area of Aravalli
Range vide Notification No. S.O. 319 (E) dated 7th May 1992 and as amended. As per the
Notification the Central Government prohibits the carrying on the following processes and
operations, except with its prior permission, in the specified area.

Processes and • Location of new industry including expansion/modernization


activities which • A. All new mining operations including renewals of mining lease
require prior B. Existing mining leases in sanctuaries/national park and areas
permission covered under Project Tiger and/or
C. Mining is being done without permission of the competent
authority
• Cutting of trees
• Construction of any clusters of dwelling units, farms houses,
sheds, community centres, information centres and any other
activity connected with such construction (including roads a part of
any infrastructure relating thereto)
• Electrification (laying of new transmission lines)
Areas covered • All reserved forests, protected forests or any other area shown as
under the “forest in the land records maintained by the State Government as on
Notification the date of this notification in relation to Gurgaon District of the State
of Haryana and the Alwar District of the State of Rajasthan
• All areas shown as

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 15
a. Gair Mumkin Pahar, or
b. Gair Mumkin Rada, or
c. Gair Mumkin Behed, or
d. Banjad Beed, or
e. Rundh
In the land records maintained by the State Government as on the date of
this notification in relation to Gurgaon district of the State of Haryana
and the Alwar district of the State of Rajasthan
• All areas covered by notifications issued under Section 4 and 5 of the
Punjab Land Preservation Act, 1900, as applicable to the State of
Haryana in the district of Gurgaon up to the date of this notification
• All areas of Sariska National Park and Sariska Sanctuary notified
under the Wildlife (Protection) Act, 1972 (53 of 1972)
Clearance Any person desirous of undertaking any of the activities mentioned in
process the Notification No. 319 (E) dated 7th May 1992 shall submit an
application to the Secretary, Department of Environment of the
Government of Haryana/Rajasthan, as the case may be. The applicant
shall also furnish environment impact statement and an environment
management plan and such other information as may be prescribed by
such State Governments. The application after due scrutiny shall be
placed before the Expert Committee for its recommendations. Based on
the recommendations of the Expert Committee, the Department of
Environment in the State Government concerned shall take a final
decision and convey the same to the applicant within the three months
from the date of receipt of application or when further information has
been asked for from the applicant within three moths from the date of
receipt of such information
Monitoring Monitoring Committee, under the Chairmanship of District Collector
mechanism concerned (Gurgaon in Haryana and Alwar in Rajasthan) shall inter alia
monitor the compliance of the conditions stipulated while according
Environmental Clearance by State Government

The District collectors of Gurgaon in Haryana and Alwar in Rajasthan


shall be authorized by the respective State Governments to take
necessary action under section 5 of the said Act in respect of cases where
the project proponents fail to implement the conditions
Appeal The MoEF retains appellate power against rejection of any proposal and
provision the National Environmental Appellate Authority constituted under the
National Environment Appellate Authority Act, 1997 (22 of 1997) shall
continue as an Appellate Authority against approval
Note: Refer the Notification for details

2.6 Requirements under the Notification No. S.O. 1545 dated 25th June 2009 –
Mount Abu Eco Sensitive Zone

Mount Abu area has significant ecological importance comprising of tropical dry deciduous
forests at lower altitude and evergreen forests at higher altitude and the flora and fauna of
the region comprise of several endemic and rare species; besides Mount Abu has natural
heritage such as Nakki Lake and man-made heritage like Dilwara temples and other

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 16
heritage buildings and structures. To conserve and protect the area from
ecological and environmental point of view, the MoEF had issued Notification No. S.O. 1545
dated 25th June 2009 regulating certain activities in the eco-sensitive zone

Regulated Pending the preparation of the Zonal Master Plan for Eco-sensitive zone and
Activities approval thereof by the Central Government in the MoEF, there shall be no
increase in the existing parameters of permissible floor area ratio,
permissible ground coverage, maximum number of floors and maximum
height and all new constructions shall be allowed only after the proposals
are scrutinized and approved by Monitoring Committee and all other
development activities including additions, alterations, demolitions, repairs,
renovations and restorations of buildings shall require prior approval of the
Monitoring Committee provided that these do not involve structural
changes and are on the existing authorized plinth areas in the Mount Abu
Municipal Limits and there shall be no consequential reduction in Tribal
area, Forest area, Green area and Agricultural area
Boundaries a. The said eco-sensitive zone is situated in the southern area of Rajasthan in
of the eco- Sirohi District between 240 33’42’’ and 240 39’ 00’’ North latitude and
sensitive between 720 41’ 36’’ and 720 48’ 06’’ East longitude and the configuration of
zone land is hilly and rugged with high altitudinal variation ranging from 300
meter to 1727 meter. Gurushikar, the highest peak of the Aravalli, is the
highest peak between the Himalayas and the Nilgiris. The boundaries of the
said eco-sensitive zone comprise

North - Southern boundary of Abu Forest Block No.3


South - Northern Boundary of Abu Forest Block No. 1
East - Western and Southern Boundary of Abu Forest Block No.2
West - Eastern boundary of Abu Forest Block No. 3

b. The Eco-sensitive zone covers the entire area of Notified Urban Area
Limit, including Mount Abu Municipal Limits adjoining Forest Block Areas.

c. The list of the villages in the eco-sensitive zone – Sanigaon, Machgaon,


Goagaon, Delwara, Oriya, Jawal, Achalgarh, Salgaon, Torna, Dudhai,
Hetamji, Ama

d. All activities in the Forest Block Areas (both within and outside Municipal
Areas) shall be governed by the provisions of the Rajasthan Forest Act, 1953
and the Forests (Conservation) Act, 1980 (69 of 1980) and all the activities in
the Protected Areas (Sanctuary) shall be governed by the provisions of the
Wildlife (Protection) Act, 1972 (53 of 1972)
Trees There shall be no felling of trees whether on Forest, Government, Revenue
or Private lands within the Eco-sensitive zone without the prior permission
of the State Government in case of forest land and the respective District
Collector in case of Government, Revenue and Private land as per the
procedure which shall be laid down by the State Government
Tourism The tourism activities shall be as per the Tourism Master Plan to be prepared
by the Department of Tourism of the Rajasthan State Government
Water • All future and existing buildings, where possible, in the Municipal Are
shall provide roof-top rain water harvesting structures with plinth area

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 17
and the Institutional and commercial buildings shall not draw water
from existing water supply schemes in a manner that adversely affects
water supply especially to local villages or settlements
• In Non-Municipal Areas rain water harvesting shall be undertaken
through such structures as percolation tanks and storage tanks and only
other means. Ground water aquifer recharge structures shall be
constructed wherever such structures do not lead to slope instabilities
• The rain water collected through storm water drains shall be used to
recharge the ground water or to clean the waste disposal drains and
sewers
• The extraction of ground water shall be permitted only for the bona-fide
agricultural and domestic consumption of the occupier of the ply and the
extraction of ground water for industrial or commercial or residential
estates or complexes shall require prior written permission, including of
the amount that can be extracted, from the State Ground Water
Department. However, the areas rich in ground water may not be
delivered for construction activities
Use of No person shall use plastic carry bags within the notified area
Plastics
Development • The zonal Master Plan shall indicate areas o hill slopes where
on and development shall not be permitted
protection of • No development shall be undertaken in areas having a steep slope or
hill slopes areas which fall in fault or hazard zones or areas falling on the spring
lines and first order streams or slopes with a high degree of erosion as
identified by the State Government on the basis of available scientific
evidence
• No development on existing steep hill slopes or slopes with a high
degree of erosion shall be permitted
Discharge of No untreated sewage or effluent shall be permitted to be discharged into
sewage and any water body or forests within the eco-sensitive zone and the local
effluents authority shall provide proper drainage and treatment system for collection,
treatment and disposal of untreated/and treated effluent in accordance with
the provisions of the Water (Prevention and Control of Pollution) Act, 1974.
Moreover, the treated sewage and treated effluent shall be disposed only at
or into a point(s) identified and approved by the local authorities and the
Monitoring Committee
Monitoring Under the provisions of sub-section (3) of Section 3 of the Environment
Committee (Protection) Act, 1986 (29 of 1986), the Central Government shall constitute a
committee to be called the Monitoring Committee to monitor the compliance
of the provisions of this notification
In case of activities requiring prior permission on environmental clearance,
such activities shall be referred to the State Level Environmental Impact
Assessment Authority, which shall be the Competent Authority for grant of
such clearances
Note: Refer the Notification for complete details

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 18
CHAPTER 3
Statutory Clearance Process

3.0 Environmental Clearance process

The Township and Area Development project covering an area ≥50 ha and or built up area
≥1, 50,000 sq. meters, attracts the provisions of EIA Notification dated 14th September 2006
and amended in 2009. All such projects are categorized as B1 projects. The process of
environmental clearance involves submission of Form I (Annexure 1), Form IA (Annexure
2), copy of the conceptual plan along with proposed TOR to the State Environmental Impact
Assessment Authority (SEIAA). Figure 3.1 shows process involved in the prior
environmental clearance for Township and Area Development projects.

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 19
Project Concept and Site selection*

Form 1, Form 1 A, conceptual plan


with proposed TOR to SEAC

Scoping by SEAC (site visit by EC- rejected by SEIAA on the


sub group of SEAC, if necessary) recommendation of SEAC

TOR approved by SEAC

Display
on the Draft EIA report to
SEIAA SPCB/UTPCC by project Clarifications by SEAC
website proponent /Modifications by
project proponent

Appraisal and
recommendation by SEAC

Referred back to SEAC


Approval by SEIAA under communication to
the project proponent

Display on the
SPCB/UTPCC website &
Rejected Approved
project proponent website

Post EC monitoring Submission of half


yearly compliance
report to SEIAA

Display of compliance
report on SEIAA
website

* The proponent should apply for CRZ clearance, as per applicability

Figure 3.1 Prior Environmental clearance process for category B projects

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 20
3.1 Public Consultation

As per Para No 7 (i) (III) (d) of EIA Notification dated 14th September 2006 as amended 1st
December 2009, all building/construction projects/area development projects and
townships are not required to undertake public consultation process.

3.2 Validity of Environmental Clearance

The prior environmental clearance granted is valid for a period of five years. The regulatory
authority concerned may extend this validity period by a maximum period of five years.
However, in the case of Area development projects and Townships [item 8(b)], the validity
period shall be limited only to such activities as may be the responsibility of the applicant as
a developer. This validity period may be extended by the regulatory authority concerned by
a maximum period of 5 years provided an application is made to the regulatory authority by
the applicant within the validity period, together with an updated Form I, and
supplementary Form IA, for construction projects or activities.

3.3 Post Environmental Clearance Monitoring

The project proponent shall prominently advertise in the newspapers indicating the project
has been accorded environmental clearance and the details of regulatory authority website
where it is displayed. To the regulatory authority concerned all such reports shall be public
documents. The latest such compliance report shall also be displayed on the website of the
concerned regulatory.

3.4 Transferability of Environmental Clearance

A prior Environmental Clearance granted for a specific project or activity to an applicant


may be transferred during its validity to another legal person entitled to undertake the
project or activity on application by the transferor or the transferee with a written “no
objection” by the transferor, to, and by the regulatory authority concerned, on the same
terms and conditions under which the prior environmental clearance was initially granted,
and for the same validity period.

3.5 Criteria for EIA consultants

The MoEF, GoI had stipulated certain criteria for EIA consultants as per the Ministry’s office
memorandum dated 2nd December 2009, and the same is kept in the public domain of
Ministry’s website (www.envfor.nic.in). Accordingly, the EIA consultants shall have
accreditation with Quality Control of India (QCI)/National Accreditation Board of
Education and Training (NABET). The consultants shall include the copy of the accreditation
certificate and that provided by the other organizations/laboratories including their status
of approvals etc. the EIA/EMP reports prepared by the consultants who are not registered
with NABET/QCI shall not be considered by the Ministry after 30th June 2010.

3.6 Authorized Signatory

All correspondence with the regulatory authority including submission of application for
TOR/Environmental Clearance, subsequent clarifications, as may be required from time to

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 21
time, participation in the EAC Meeting on behalf of the project proponent shall
be made by the authorized signatory only. The authorized signatory shall also submit a
document in support of his claim of being an authorized signatory for the specific project
(EIA amendment Notification dated 1st December 2009).

3.7 Participation of the project proponent during the EAC meetings

As per the office memorandum dated 25th February 2010 of MoEF, the authorized
representative of the project proponent shall only attend the EAC meetings. The authorized
representative of the project proponent should be a reasonably senior officer / executive
duly authorized in writing. In case, a consultant is to be nominated as the authorized
representative, it should be through a irrevocable power of attorney executed and formally
registered with the Sub-Registrar concerned. A copy of the authorization / registered power
of attorney, as the case may be should be submitted to the ministry for record. The
authorized representative, so nominated should only participate in the EAC meetings on
behalf of the project proponent. The consultant (s) and other experts may, however, assist
the authorized representative during the meeting. In the absence of the authorized
representative, the proposal will not be considered by the EAC.

3.8 Projects requiring recommendation of the Chief Wildlife Warden

If the project is located within 10 km radial distance from the national parks, sanctuaries,
biosphere reserves, migratory corridors of wild animals, the project proponent shall submit
the map duly authenticated by Chief Wildlife Warden showing these features vis-à-vis the
project location and the recommendations or comments of the Chief Wildlife Warden
thereon at the stage of EC (EIA amendment Notification dated 1st December 2009).

3.9 Consent Management System – RPCB

The project proponent is required to obtain consent of the Board, before start of the project.
The consent management process adopted at RPCB is explained below in the form of
different questions and answers to facilitate better understanding for the project proponent
as well as other stakeholders.

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 22
01. What projects are Township and Area Development Projects covering all or any of
required to apply for the following shall apply for CTE:
CTE?
Red category
Building/construction projects having built up area equal to or
more than 20,000 Sq. meters
Township projects of more than or equal to 50 ha

Hotels:
• Having capacity of 100 beds and above
• Hotels and all tourism projects irrespective of their capacity
which is amidst in any water body or which are located
within 200 meters of HFL of any lake, reservoir, river or water
body

Hospitals (50 or more beds)

Orange category
• Hotels having capacity from 51 to 99 beds
• Hospitals (less than 50 beds)
• Water Treatment Plants of capacity more than 4.0 MLD
• Multiplexes or building/construction projects having built up
area less than 20, 000 sq. meters but more than or equal to
2500 sq. meters

Other category
• Water Treatment Plants of capacity up to 4.0 MLD
• Hotel having capacity up to 50 beds
• Fixed D.G sets with total capacity of more than or equal to
200 KVA
02. What to apply? The project proponent shall apply in the prescribed CTE
application form along with requisite enclosures, CTE fee and
data. The CTE application is as given in Annexure 3 & 4. It can be
downloaded from RPCB web also (www.rpcb.nic.in)
03. What is the fee to be CTE fee is to be paid along with CTE application as notified by
submitted? the DoE, Government of Rajasthan under section 64 of the Water
(P&CP) Act, 1974 as amended and under section 54 of the Air
(P&CP) Act, 1981 as amended (Annexure 5 & 6).
The CTE fee is to be paid on the following basis as per the
Notification dated 25th May 2009.
• Capital investment
• Categorization of the project
• Whether the project attracts the provision of the Hazardous
Waste (Management & Handling) Rules, 1989? If yes, then fee
equal to one and half times fee prescribed in the schedule of
the Notification shall be paid
• Whether the project requires environmental clearance under
the provisions of E (P) Act, 1986? If yes, shall pay an extra
amount of Rs 15,000/-, as one time consent fee to establish in
addition to the fee mentioned in the schedule under the

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 23
provisions of Water Act & Air Act

Points for discussion


Whether HW Rules 1989 or HW Rules 2008 are to be considered
for fee purpose?
04. What is meant by For calculating the investment in plant and machinery, the cost of
capital investment of pollution control, research & development, industrial safety
the industry? devices and such other items as may be specified by the
notification, shall be excluded (RSPCB office order amendment
dated 18.12.2008).

Points for discussion with Core Team of RPCB:

• What type of documents, the project proponent shall


submit in support of the capital investment mentioned in
the CTE application?
• Incase of expansion, whether the capital investment of the
expansion only to be considered for arriving applicable fee
slab
• Whether the Land cost component is to be added or not?
• Whether the depreciation should be considered or not while
calculating the capital investment
05. What is the mode of Instrument :
payment of CTE fee? Infavour of :
Online payment :
(Inputs requested from RPCB)
06. Whom to submit the Inputs requested from RPCB
CTE application?

07. Is there any Inputs requested from RPCB


provision to apply CTE
application on-line?
08. What is the Inputs requested from RPCB
procedure to apply on
line?
09. Who will issue Inputs requested from RPCB
acknowledgment
towards receipt of the
application?

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 24
10. Whether NOC from Yes, in the following cases:
CGWA is a pre- • If the abstraction of ground water is ≥ 25 m3/day, in case of
requisite for processing over exploited areas
CTE application? • If the abstraction of ground water is ≥ 50 m3/day, in case of
critical areas
• If the abstraction of ground water is ≥ 100 m3/day, in case of
semi critical areas
• The exemption shall not be applicable to industries, which are
using water as raw material such as packaged drinking water
industries, distilleries and breweries
• Industry/infrastructure project/mine (proposed/existing)
located in safe category areas, are also required to obtain
NOC from CGWA if ground water abstractions exceeds
1000m3/day for hard rock areas and 2000m3/day for alluvial
areas
• CTE application will be considered by RPCB only after
submission of NOC from CGWA in above cases
(Please refer RPCB Circular Guidelines dated 08.01.2010)

Points for discussion:

As per the circular dated 30.04.2008, CTE for the units, which
propose to extract ground water more than 200 KLD, the CTE
application will be considered only after submission of NOC
from CGWA…whether this circular instruction is still in practice
in view of the latest circular dated 08.01.2010 on the subject
matter or not?
11. What are the areas The details are given in Annexure 7
as identified by CGWA
as – safe areas, semi –
critical areas, critical
areas & over exploited
areas?
12. Whether prior Inputs requested from RPCB
environmental
clearance is a pre-
requisite to submit the
CTE application?
13. Whether NOC from Inputs requested from RPCB
Local authority is a pre
– requisite to submit
CTE application?
14. Whether conversion Inputs requested from RPCB
of land, wherever
required, is a pre –
requisite to submit CTE
application?
15. Who will process Inputs requested from RPCB
the CTE application?

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 25
16. Who is the Red Category projects Chairperson
authority to accord Orange category Regional officer
the CTE application? Other category Assistant Environmental
Engineer*
*As per RPCB office order dated 18.12.2009
The consent to the units covered by the Aravalli Notification will be
dealt at Head Office level and not at R.O level
Points for discussion:
Whether AE at RO level or AE at HO level are authorized to accord
CTE
17. What is the Statutory time limit:
maximum time
period to process the Section 25(7) of Water (P&CP) Act, 1974 as amended: Four months
CTE application? on submission of application, complete in all aspects

Section 21(4) of Air (P&CP) Act, 1981 as amended: Four months after
receipt of the application

Administrative time limits of RPCB:

Red category projects 6 weeks


Orange category projects 4 weeks
Other category projects 4 weeks
18. Is there any YES, there is provision under the Water Act
deemed provision? Section 25 (7) of the Water (P&CP) Act, 1974 as amended: Deemed to
have been given unconditionally on the expiry of four months of
making of an application complete in all respects to the Board

AIR ACT ….to be discussed with RPCB


19. What is the mode RPCB to confirm the following:
of communication of
the approval / Hard copy: By RPAD
rejection order of Soft copy: By mail
CTE? Down loads: From RPCB web
20. Is there any Section 28 (1) of Water (P&CP) Act, 1974 as amended:
appeal mechanism? Any person aggrieved by the order made by the State Board under
section 25, 26 and 27 may within 30 days from the date on which is
communicated to him, prefer an appeal before Appellate Authority
constituted by the State Government.

The appellate authority may entertain the appeal after the expiry of
the said period of thirty days, if such authority is satisfied that the
appellant was prevented by sufficient cause from filing the appeal in
time

Section 31 (1) of Air (P&CP) Act, 1981 as amended:


Any person aggrieved by an order made by the State Board under
this Act may, within thirty day from the date on which the order is
communicated to him, prefer an appeal to Appellate Authority

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 26
constituted by the State Government

The appellate authority may entertain the appeal after the expiry of
the said period of thirty days if such authority is satisfied that the
appellant was prevented by sufficient cause from filing the appeal in
time
21. Whether the CTE Section 21 (7) of the Air (P&CP) Act, 1981 as amended:
obtained from the
board can be Where a person to whom consent has been granted by the State
transferred to any Board under section 21 (4) transfers his interest in the industry to nay
other person? other person, such consent shall be deemed to have been granted to
such other person and he shall be bound to comply with all the
conditions subject to which it was granted as if the consent was
granted to him originally

Points for discussion under the provisions of the Water Act


22. What is the CTE will be valid for a period of three years or till the commissioning
validity period for of the unit (RPCB Office order dated. 10.08.2001)
CTE?
23. What is the For inputs from RPCB
procedure for
extension of CTE?
24. Is there any For inputs from RPCB
criterion for
consultant for
preparation of
EIA/EMP?
25. Are there any The MoEF, GoI vide Notification No.G.S.R 422 (E) dated 19.05.1993
standards notified and G.S.R 801 dated 31.12.1993 had notified general standards for
for discharge of discharge of effluents (Annexure 8)
wastewater?
26. Are there are any Notification No. 371(E) dated 27.05.2002 - E (P) Act, 1986:
specific noise
standards applicable Noise limit for Diesel Generator Sets (up to 1000 KVA)
to D.G. Sets? manufacture on or after the 1st July, 2003

• The maximum permissible sound pressure level for new diesel


generator (DG) sets with rated capacity up to 1000 KVA,
manufactured on or after the 1st July, 2003 shall be 75 dB (A) at 1
meter from the enclosure surface
• The diesel generator sets should be provided with integral
acoustic enclosure at the manufacturing stage itself

Noise limit for DG sets not covered above

Noise from the DG set should be controlled by providing an acoustic


enclosure on by treating the room acoustically, at the users end

The acoustic enclosure or acoustic treatment of the room shall be


designed for minimum 25 dB (A). Insertion Loss or for meeting the

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 27
ambient noise standards, whichever is on the higher side (if the
actual ambient noise is on the higher side, it may not be possible to
check the performance of the acoustic enclosure/acoustic treatment.
Under such circumstances the performance may be checked for noise
reduction up to actual ambient noise level, preferably, in the
nighttime. The measurement for Insertion Loss may be done at
different points at 0.5m from the acoustic enclosure/room, and then
averaged

The DG set shall be provided with proper exhaust muffler with


Insertion Loss of minimum 25 dB (A)

Requirement of certification

Every manufacturer or importer of DG set to which these regulations


apply must have valid certificates of type approval and also valid
certificates of conformity of production for each year, for all the
product models being manufactured or imported from 1st July 2003
with the noise limit specified in the Notification.

The conformance label must contain the following information


a. Name and address of the supplier (if the address is described in
the owner’s manual, it may not be included in the label)
b. Statement “This product confirms to the Environment (Protection)
Rules, 1986”
c. Noise limit viz. 75 dB (A) at 1m
d. Type approval certificate number
e. Date of manufacture of the product

Notification No. S.O. 50(E) dated 11th January 2010 – E (P) Act 1986:

A loud speaker or a public address system r any sound producing


instrument or a musical instrument or sound amplifier shall not be
used at night time (10.00 pm to 6.00 am) except in closed premises for
communication within, like auditoria, conference rooms, community
halls, banquet halls or during public emergency
27. Is there any The CPCB had evolved the minimum height of the stack to be
guideline to calculate provided to the DG set and published in Emission Regulations Part
the minimum IV: COINDS/26/1986-87.
requirement of the
stack of D.G set? H= h+0.2 x ÖKVA

H Total height of stack in meter


h Height of the building in meters where the
generator set is installed
KVA Total generator capacity of the set in KVA

Based on the above formula the minimum stack height to be


provided with different range of generator sets may be categorized
as follows:

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 28
For generator Sets Total height of stack in meter
50 KVA Ht. of the building +1.5 meter
50-100 KVA Ht. of the building +2.0 meter
100-150 KVA Ht. of the building +2.5 meter
150-200 KVA Ht. of the building +3.0 meter
200-250 KVA Ht. of the building +3.5 meter
250-300 KVA Ht. of the building +3.5 meter
28. Is there any CPCB notified National Ambient Air Quality Standards dated 18th
standards notified November 2009 (Annexure 9)
for ambient noise
level?
29. Where shall the The ambient air quality standards in respect of noise as notified
ambient noise levels under E (P) Act, 1986 shall be monitored at the boundary of the
be monitored for project for compliance
compliance?
30. Whether any MoEF had notified procedures and standards for handling municipal
procedures notified solid waste vide Municipal Solid Waste (Handling &Management)
for handling solid Rules, 2000
waste?
31. What are the post Inputs requested from RPCB
project monitoring
requirements after
obtaining CTE?
32. Whether Inputs requested from RPCB
Township and Area
Development
Projects are required
to apply for Consent
To Operate?
33. Whether Inputs requested from RPCB
Township and Area
Development
Projects are required
to apply for
Hazardous Waste
Authorization?
34. Whether Inputs requested from RPCB
Township and Area
Development
Projects are required
to file water cess
returns?

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 29
CHAPTER 4
Environmental Aspects and Guidance

4.0 Environmental checklist

The project proponent, reviewer and the public to have a better understanding on the
environmental aspects, can use the following checklist:

S. No Description Yes No Remarks


Land Environment
01. Whether the proposed project is in conformity with the
approved master plan / development plan of the area?
02. Whether the proposed project requires change of land
use and if so, the status in obtaining statutory approval
from the competent authority?
03. Whether the existing land use will be significantly
altered due to the proposed project activity?
04. Whether the proposed project disturbs sites with heritage
and cultural values such as protected monuments?
05. Whether topsoil management is prepared for storing and
using the topsoil excavated during the construction
work?
06. Whether any natural stream is passing through the
project area? If yes, whether it will be blocked?
07. Whether the natural drainage system will be altered?
08. Whether it is proposed to construct any compound wall
along the project boundary? If yes, whether any storm
water management plan is prepared?
Water Environment
09. Whether estimation of water demand for peak and
ultimate project requirement is assesses as per the
norms?
10. Whether reliable source of water for peak and ultimate
demand has been identified?
11. Whether the stress, if any, on the ground water/surface
water availability has been assessed and to see there is no
pressure on the existing users of the water?
12. Whether the quality of the water is assessed, in case of
own arrangements by the project developer i.e. the
source of water supply is not by the local authority?
13. Whether any on-site water treatment facility is proposed?
14. Whether adequate safe drinking water facility and
proper sanitary facilities are planned for the construction
workers?

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 30
S. No Description Yes No Remarks
15. Whether dual plumbing system for using treated
wastewater for flushing the toilets or any other usage is
explored?
16. Whether it is proposed to have on-site sewerage
treatment plant with reuse/disposal for green belt?
17. Whether construction of internal sewerage network is
proposed as a part of the project?
18. Whether sewerage network with treatment system
already exists in the area? If yes, any assessment is made
on the adequacy of the sewer network and STP to
handle the additional domestic liquid waste from the
proposed development?
Solid Waste
19. Whether a plan has been prepared for proper disposal of
construction debris and waste?
20. Whether estimation of solid waste generation for the
peak and ultimate project stage is assessed as per the
norms?
21. Whether segregation of solid waste is planned?
22. Whether the possibility of providing on-site treatment of
organic waste to convert the biodegradable waste into
manure, is examined?
23. Whether final disposal point for municipal solid waste is
identified? Incase, if it proposed to dispose at secured
landfill maintained by the local authority, whether
details of the secured landfill such as authorization
obtained from the Board, distance from the project area,
mode of disposal, responsibility for transportation and
disposal are furnished?
Air Environment
24. Whether dust generation during excavation, blasting
and construction is addressed and planned with
mitigation measures?
25. Whether dust generated during the transportation and
storage of the raw materials is addressed and planned
with mitigation measures?
26. Whether mitigation of automobile air emissions is
planned?
Noise Environment
27. Whether noise due to blasting of the rocks at project site
and due to operation of equipments such as DG sets is
addressed?
Biological Environment
28. Whether the project involves cutting of trees?
29. Whether green belt plan is prepared along with
implementation schedule and responsibility for
maintenance?

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 31
S. No Description Yes No Remarks
30. Whether any forest area is covered in the proposed
project site?
31. Whether there is any threat to bio diversity due to the
project?
Planning
32. Whether road connectivity to the project site is planned
as a part of the development project?
33. Whether diverse use facilities needed in layout
development have been assessed?
34. Whether the land use distribution at scheme level is
planned as per the norms?
35. Whether parking requirements is assessed and provision
made for the peak and ultimate project stage as per the
norms? What are the norms followed?
36. In case of provision of community halls, stadiums,
theatres etc., where huge gathering is expected, whether
assessment on parking requirement and adequacy of the
road network is made or not?
37. Whether fire fighting installations are planned as
recommended in the code of practice i.e. National
Building Code of India 2005, BIS
38. Whether construction of internal roads is proposed as a
part of the project?
39. Whether construction of internal storm water drains is
proposed as a part of the project?
40. Whether the project area likely to have moderate to high
intensity of earthquake, or cyclonic storm, or significant
flood flow or inundation, or land slides / mud flows /
avalanches, or one or more of hazards? If yes, whether
appropriate safety measures are incorporated in the
project?
Natural Resources
41. Whether provision for rainwater harvesting is
proposed?
42. Whether provision to collect the rooftop is explored?
43. Whether the possibility of providing solar heating
system for water heating, cooking etc, is examined?
44. Whether the possibility of providing solar lighting for
streetlights and timer based lighting management in
common area, is assessed?
45. Whether the usage of glasses at external portion of the
building is kept at optimal to reduce the electricity
consumption and load on air – conditioning system?
Whether the use of double glass with special reflective
coating is examined?
46. Whether the usage of thermal insulation for the rooftop
is examined to reduce the energy requirement?

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 32
47. Whether the usage of fly ash or alternate building
materials is explored?

4.1 Environmental Norms

S. No Description of the norms Notification


01 General Standards for Discharge Notification No. G.S.R 422 (E) dated 19.05.1993
of Effluents and G.S.R 801 (E) dated 31.12.1993 issued under
the provisions of E (P) Act 1986
(Annexure 8)
02 National Ambient Air Quality CPCB Notification No. B-29016/20/90/PCI-I
Standards dated 18th November 2009
(Annexure 9)
03 National Noise Ambient Air The Noise Pollution (Regulation & Control)
Quality Standards Rules, 2000 – S.O. 123 (E) dated 14th February
2000 and as amended in S.O. 1046 (E) dated
22.11.2000
(Annexure 10)
04 Noise Limit for Generator Sets Notification No. G.S.R 371 (E) dated 17th May,
Run With Diesel 2002
(Annexure 11)
05 Standards for discharge of Notification No G.S.R 794 (E) dated 4th
effluents for hotel industry November, 2009
(Annexure 12)
06 The Ozone Depleting Substances The Ozone Depleting Substances (Regulation &
Control) Rules, 2000 – S.O. 670 (E) dated
19.07.2000

4.2 Guidelines for the project developer

The project developer is advised to refer to the following documents:

• EIA guidance manual for Building construction, Townships and Area Development of
MoEF
• National Building Code of India 2005
• Development Control Rules – Town and Country Planning

Design layout should ensure adequate solar access and ventilation

Depending upon the geographical latitude and sky conditions a precise analysis of the local
climate; surroundings, urban development and surrounding terrain in relation to solar
access, daylight availability and predominant air movement should be carried out. This
would control minimum distances to be kept between the built up volume and open spaces.
The design of the layout should allow for wind protection and solar access in winter, and at
the same time provide adequate sun protection and ventilation in summer months. The size
and density of the layout should provide desired comfort levels maximum from natural
resources. Solar path analysis and wind pattern assessment should be carried out in the
design stage that would help developers decide upon the alternatives for the type of layout
and the proportion of the built volume and open space in the layout.

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 33
The submittals should be provided only to indicate the optimized layout of buildings on the
site with respect to sun path and optimized solar access and availability of wind for natural
ventilation. Following are the factors, may be considered during the lay out design.

Open spaces

The proportion of open space and its built-up edges should be designed such that it ensures
winter solar access and summer ventilation. Vegetation may provide as shading and
promote evaporative cooling. In hot dry climates, evaporative cooling through appropriately
sized wet surfaces or fountains have a desirable effect.

Design layout should ensure the following

• Area allotted for Sewage Treatment plant


• Area allotted for of Garbage Segregation
• Area allotted for of DG Sets
• Parking requirement should meet the local body requirements
• Area for visitors parking
• Area for green belt and lawns

Sustainable site planning

Site planning is a vital component of any type of development activity and is the first
step. However, ideally the design team should be involved in site selection and
should assess the appropriateness of the site relative to the proposed development. Analysis
and assessment of the site characteristics in terms of its capacity to provide natural resources
inside the building such as light, air and water without damaging the natural environment
should be carried out during site selection and analysis process

Sustainable site planning is a critical phase of the green design process. When selecting a
potential site, you should look to eliminate or minimize the disruption of the existing
environment as much as possible. Using the topography of the site is paramount. This
allows for detailed planning that outline the existing and proposed design concepts to
include the home location, vegetation, land slope, setbacks, and other crucial factors

Cut and fill: Preserve natural slopes to aid natural drainage. The amount of excavation
should be minimized as far as possible. Removing or importing soil (also known as cut and
fill) adds to environmental emissions via the transporting of the soil. Furthermore,
rearranging the landscape may disturb the flow of water being directed away from the
project. This may affects the original contours of the surrounding areas

Landscaping: Preserve natural landscaping whereever possible and use vegetation of native
to the environment. Layout and form of the project must conform to the landscape of
the area without unduly affecting the scenic features of that place.

Land use distribution at scheme level: Land use distribution at scheme level shall be
planned while designing the project lay out.

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 34
Ambient environment quality in the region: Levels of air, noise and water pollution should
be surveyed and considered carefully before implementing the building design. For
example: High level of air, noise and water pollution and location near pollution sources
such as heavy traffic roadways should be considered carefully to implement developing the
area.

Availability of infrastructure: Infrastructure requirement should be properly assessed such


as:

ƒ Development of Roads
ƒ Development of Drainage
ƒ Providing Water supply
ƒ Providing Power and Telecom facilities
ƒ Planting trees along with roads
ƒ Storm water management and Rain water Harvesting System
ƒ Street lights

Site Location: Urban infrastructure and facilities, public transport, infrastructure for power,
water supply to meet the estimated requirement, sewage system network should be
available nearby or should be made available with minimum environment impact. The
following information may help in assessing requirements of infrastructure:

ƒ Distance from Highway


ƒ Distance from Municipal road
ƒ Width of Road adjacent to the site
ƒ Nearest Bus Stop and Railway Station
ƒ Distance from facilities like post office, police station, fire station
ƒ Distance from nearest bank, school, college, market etc.

Onsite management of waste: The following requirements are very important from
environmental consideration

ƒ Land acquired should be minimum but sufficient to provide for a green belt wherein the
treated wastewater, if possible/ suitable, could be utilized from wastewater treatment
systems.
ƒ Adequate space may be provided for storing solid wastes. The space and the waste can
be made available for possible reuse in future.
ƒ Adequate space shall be provided for construction of STP

Diverse Use Facilities in the layout development: The diverse use facilities such as Bank,
Community /civic center, Convenience store, Hair care, Hardware store, Health club or
outdoor recreation facility, Laundry/dry cleaner Library, Medical/dental office, Pharmacy
(stand-alone), Place of worship, Police/fire station, Restaurant, School, Supermarket,
Theater, Over Head Tank, Sewage treatment plant, Garbage segregation point should be
assessed

Estimation of water demand: The water demand should be estimated by adopting the
WHO guideline of minimum water requirement of 135 LPCD for a family of 5 for each
dwelling. Care must be taken to adopt maximum possible number of dwellings in a plot.

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 35
The water requirements for different types of buildings should be estimated as given in
Annexure 13

Estimation of solid waste generation

The garbage quantity needs to be estimated by adopting 0.5 kg/head for residential areas
and 0.3 kg/head for commercial areas. Other solid wastes anticipated are STP sludge, waste
oils, batteries, bio medical wastes.

Construction Phase: The following should be considered during the construction stage:

ƒ Road construction
ƒ Storm water drainage construction
ƒ Other infrastructure
ƒ Material requirement and lead distances
ƒ Cut and fill quantities (excavation)
ƒ Disposal of excess cut material and or source of fill materials including lead distances.
ƒ Walkable streets
ƒ Street network
ƒ Access to surrounding vicinity
ƒ Heat island reduction
ƒ Water recycling
ƒ Composting of garbage and use of manure
ƒ Use of solar lighting and street lighting
ƒ Use of solar heating

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 36
CHAPTER 5
Guidelines for Sector Specific Projects

5.0 Guidelines for stipulating sector specific conditions in the CTE order

Mandatory EMP requirements


Storm water Provision of rain water harvesting structure/ground water recharge pits
Management Storm water drains along the internal roads should be provided and the
same should be clearly marked in the project lay out plan
Water Should submit water availability certificate / letter from the concerned
Management authority, if the source of water is from the local authority
NOC from Central Ground Water Authority, if the source of water is
ground water and as per the applicable norms
Provision of water meters to record the water consumption
Dual plumbing system for collection of grey and other effluent
Design details of the Sewerage Treatment System, if on site STP is
proposed and norms as per the final disposal point shall comply the
general standards for discharge of effluent notified under the provisions
of E (P) Act, 1986
Provision of energy meter for STP, to assess the continuous operation of
STP
Standard Operation Practice (SOP) of STP shall be submitted as and
when finalized
Provision of stand by power for continuous operation of the STP
Reuse of treated waste water for flushing and or land application
Incase, the final disposal is through local area sewer net work, the
permission letter from the concerned authority clearly stating the
quantity, standards for receiving and compliance mechanism
Provision for common toilets
Solid Waste Garbage segregation area should be provided with in the site
Garbage collections bins green and blue bins for biodegradable and non-
biodegradable wastes respectively shall be provided
Final disposal point and permission letter from the concerned, in case, if
it is proposed to dispose in the off site secured landfill
DG Sets Provision of integral acoustic enclosure or treating the room acoustically
as per the G.S.R 371 (E) dated 17th May 2002 as amended
Provision of minimum stack as per the CPCB guidelines
To comply the requirement of certification and requirement of
conformance labeling as per G.S.R 371 (E) dated 17th May 2002 as
amended. Details shall be submitted to RPCB after installing the D.G set
Energy Use of solar energy for hot water or as submitted in the EMP
Timer based lighting management in Common areas
Solar lighting for street lights (1 in 3)
Roof should meet regulatory requirement as per Energy Conservation
Building Code by using appropriate thermal insulation material
Use of glass should be optimal to reduce the electricity consumption and
load on air conditioning in community buildings

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 37
Parking Adequate provision for parking
Requirement Adequate provision for visitors parking
In case of provision of community halls, stadiums, theatres etc., where
huge gathering is expected, adequate parking and strengthening road
infrastructure
Land and Site To be developed as per approved plan
Lay Out Adequate area for parks & green area shall be reserved
The entire area under roads, parks and open spaces should to be
surrendered to local Authority after development
No road shall be less than 40 ft. and all roads shall provide for standard
street lighting and essential street furniture
The area earmarked for the parking shall be used for parking only. No
other activity shall be permitted in this area
The area earmarked as green area shall be used only for greenbelt and
shall not be altered for any other purpose
Traffic congestion near the entry and exit points on the roads adjoining
the proposed project site must be avoided
Road connectivity to the site shall be ensured by the developer
Ozone Ozone Depleting Substances (Regulation & Control) Rules shall be
Depleting followed while designing the air conditioning system of the project
Substances
Construction Sediment control during construction
Management Avoiding stockpiles of materials near natural drains
All transport vehicles should have valid PUC
Provision of toilets for site workers connected to septic tank followed
by soak pit
Hotels The guidelines of RPCB shall be followed for hotels
The standards notified by MoEF vide G.S.R 794 (E) dated 4th November
2009 shall be complied
Hospitals Biomedical wastes generating from the hospital if any, shall be disposed
as per the Bio-medical Wastes (Management and Handling Rules), 1998
amended from time to time

Suggestive EMP requirements


Storm water Rain water harvesting pond/water body may be provided subject to site
Management availability and suitability
Roof top rain water collection system and reuse after pre treatment
Roof top rain water may also be diverted to a bore well
The drainage in the area may be planned in accordance with the natural
slopes as per the contour plan without much disturbing the contour levels
Water Management Install low-volume toilets and sensors
Use low water consuming taps and sensors
Solid Waste Onsite treatment of organic waste and to generate manure
Management
Energy CFL in common areas
Use of solar energy for room heating, cooking etc
Land and Site Lay Out Cut and fill operation to be done during non-monsoon season
Development
Water sprinkling on the roads to control the road dust

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 38
CHAPTER 6
Environmental Management Plan
6.0 General

The objective of Environmental Management Plan is to:

• Ensure the identified mitigation measures are implemented


• Establish systems and procedures for this purpose
• Monitor the effectiveness of the mitigation measures and
• Take necessary action when unforeseen impacts occur

6.1 Components of EMP

The EMP should contain:

• Summary of potential impacts and proposed mitigation measures


• An independent expert should certify the installation of the Sewage Treatment Plant
(STP) and a report in this regard should be submitted to RPCB before the project is
commissioned for operation
• Water conservation measures proposed in the project
• Provision of adequate parking facilities
• Usage of solar energy in the project development
• Energy efficient practices proposed in the project
• Usage of alternative building materials such as fly ash bricks, PPC etc.,
• Allocation of budgetary resources
• Details of environment cell

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 39
ANNEXURES

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 40
Annexure 1
FORM 1 (EIA Notification dated 14th September 2006 as amended 1st December 2009)

(I) Basic Information

S. No Item Details
1. Name of the project/s
2. S. No in the schedule
3. Proposed capacity/area/length/tonnage to be
handled/command area/lease area/number of wells
to be drilled
4. New/expansion/modernization
5. Existing capacity/area etc
6. Category of project i.e. ‘A’ or ‘B’
7. Does it attract the general condition? If yes, please
specify
8. Does it attract the specific condition? If yes, please
specify
9. Location
Plot/survey/khasra No
Village
Tehsil
District
State
10. Nearest railway station/airport along with distance
in kms
11. Nearest town, city, district head quarters along with
distance in kms
12. Village Panchayats, Zilla Parishad, Municipal
Corporation, Local body (complete postal addresses
with telephone no.s to be given)
13. Name of the applicant
14. Registered address
15. Address for correspondence:
Name
Designation (Owner/partner/CEO)
Address
Pin code
E-mail
Telephone No.
Fax No.
16. Details of alternative sites examined, if any. Location Village-District-State
of these sites should be shown on a topo sheet 1.
2.
3.
17. Interlinked projects
18. Whether separate application of interlinked project
has been submitted?

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 41
19. If yes, date of submission
20. If no, reason
21. Whether the proposal involves approval/clearance
under: if yes, details of the same and their status to
be given
a. The Forest (Conservation) Act, 1980?
b. The Wildlife (Protection) Act, 1972?
c. The CRZ Notification, 1991?
22. Whether there is any Government order/policy
relevant/relating to the site?
23. Forest land involved (hectares)
24. Whether there is any litigation pending against the
project and/or land in which the project is propose
to be set up?
a. Name of the Court
b. Case No.
c. Orders/directions of the Court, if any and its
relevance with the proposed project

(II) Activity

1. Construction, operation or decommissioning of the Project involving actions, which


will cause physical changes in the locality (topography, land use, changes in water
bodies, etc.)

S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate


quantities /rates, wherever
possible) with source of
information data
1.1 Permanent or temporary change in land
use, land cover or topography
including increase in intensity of land
use (with respect to local land use plan)
1.2 Clearance of existing land, vegetation
and buildings?
1.3 Creation of new land uses?
1.4 Pre-construction investigations e.g.
bore houses, soil testing?
1.5 Construction works?
1.6 Demolition works?
1.7 Temporary sites used for construction
works or housing of construction
workers?
1.8 Above ground buildings, structures or
earthworks including linear structures,
cut and fill or excavations
1.9 Underground works including mining
or tunneling?
1.10 Reclamation works?

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 42
1.11 Dredging?
1.12 Offshore structures?
1.13 Production and manufacturing
processes?
1.14 Facilities for storage of goods or
materials?
1.15 Facilities for treatment or disposal of
solid waste or liquid effluents?
1.16 Facilities for long term housing of
operational workers?
1.17 New road, rail or sea traffic during
construction or operation?
1.18 New road, rail, air waterborne or other
transport infrastructure including new
or altered routes and stations, ports,
airports etc?
1.19 Closure or diversion of existing
transport routes or infrastructure
leading to changes in traffic
movements?
1.20 New or diverted transmission lines or
pipelines?
1.21 Impoundment, damming, culverting,
realignment or other changes to the
hydrology of watercourses or aquifers?
1.22 Stream crossings?
1.23 Abstraction or transfers of water form
ground or surface waters?
1.24 Changes in water bodies or the land
surface affecting drainage or run-off?
1.25 Transport of personnel or materials for
construction, operation or
decommissioning?
1.26 Long-term dismantling or
decommissioning or restoration works?
1.27 Ongoing activity during
decommissioning which could have an
impact on the environment?
1.28 Influx of people to an area in either
temporarily or permanently?
1.29 Introduction of alien species?
1.30 Loss of native species or genetic
diversity?
1.31 Any other actions?

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 43
2. Use of Natural resources for construction or operation of the Project (such as land,
water, materials or energy, especially any resources which are non-renewable or in short
supply):

S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate


quantities /rates, wherever
possible) with source of
information data
2.1 Land especially undeveloped or
agricultural land (ha)
2.2 Water (expected source & competing
users) unit: KLD
2.3 Minerals (MT)
2.4 Construction material – stone,
aggregates, sand / soil (expected source
– MT)
2.5 Forests and timber (source – MT)
2.6 Energy including electricity and fuels
(source, competing users) Unit: fuel
(MT), energy (MW)
2.7 Any other natural resources (use
appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could


be harmful to human health or the environment or raise concerns about actual or
perceived risks to human health.

S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate


quantities /rates, wherever
possible) with source of
information data
3.1 Use of substances or materials, which
are hazardous (as per MSIHC rules) to
human health or the environment
(flora, fauna, and water supplies)
3.2 Changes in occurrence of disease or
affect disease vectors (e.g. insect or
water borne diseases)
3.3 Affect the welfare of people e.g. by
changing living conditions?
3.4 Vulnerable groups of people who could
be affected by the project e.g. hospital
patients, children, the elderly etc.,
3.5 Any other causes

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 44
4. Production of solid wastes during construction or operation or decommissioning
(MT/month)

S.No. Information/Checklist confirmation Yes/No Details thereof (with Approximate


quantities /rates, wherever
possible) with source of
information data
4.1 Spoil, overburden or mine wastes
4.2 Municipal waste (domestic and or
commercial wastes)
4.3 Hazardous wastes (as per Hazardous
Waste Management Rules)
4.4 Other industrial process wastes
4.5 Surplus product
4.6 Sewage sludge or other sludge from
effluent treatment
4.7 Construction or demolition wastes
4.8 Redundant machinery or equipment
4.9 Contaminated soils or other materials
4.10 Agricultural wastes
4.11 Other solid wastes

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate


quantities /rates, wherever
possible) with source of
information data
5.1 Emissions from combustion of fossil
fuels from stationary or mobile sources
5.2 Emissions from production processes
5.3 Emissions from materials handling
including storage or transport
5.4 Emissions from construction activities
including plant and equipment
5.5 Dust or odours from handling of
materials including construction
materials, sewage and waste
5.6 Emissions from incineration of waste
5.7 Emissions from burning of waste in
open air (e.g. slash materials,
construction debris)
5.8 Emissions from any other sources

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 45
6. Generation of Noise and Vibration, and Emissions of Light and Heat:

S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate


quantities /rates, wherever
possible) with source of
information data
6.1 From operation of equipment e.g.
engines, ventilation plant, crushers
6.2 From industrial or similar processes
6.3 From construction or demolition
6.4 From blasting or piling
6.5 From construction or operational traffic
6.6 From lighting or cooling systems
6.7 From any other sources

7. Risks of contamination of land or water from releases of pollutants into the ground or
into sewers, surface waters, groundwater, coastal waters or the sea:

S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate


quantities /rates, wherever
possible) with source of
information data
7.1 From handling, storage, use or spillage
of hazardous materials
7.2 From discharge of sewage or other
effluents to water or the land (expected
mode and place of discharge)
7.3 By deposition of pollutants emitted to
air into the land or into water
7.4 From any other sources
7.5 Is there a risk of long term build up of
pollutants in the environment from
these sources?

8. Risk of accidents during construction or operation of the Project, which could affect
human health or the environment

S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate


quantities /rates, wherever
possible) with source of
information data
8.1 From explosions, spillages, fires etc
from storage, handling, use or
production of hazardous substances
8.2 From any other causes
8.3 Could the project be affected by natural
disasters causing environmental
damage (e.g. floods, earthquakes,
landslides, cloudburst etc)?

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 46
9. Factors which should be considered (such as consequential development) which could
lead to environmental effects or the potential for cumulative impacts with other existing
or planned activities in the locality

S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate


quantities /rates, wherever
possible) with source of
information data
9.1 Lead to development of supporting.
lities, ancillary development or
development stimulated by the project
which could have impact on the
environment e.g.
• Supporting infrastructure (roads,
power supply, waste or waste water
treatment, etc.)
• Housing development
• Extractive industries
• Supply industries
• Other
9.2 Lead to after-use of the site, which
could havean impact on the
environment
9.3 Set a precedent for later developments
9.4 Have cumulative effects due to
proximity to other existing or planned
projects with similar effects

(III) Environmental Sensitivity

S. No. Areas Name/ Aerial distance (within 15 km.)


Identity Proposed project location
boundary
1 Areas protected under international
conventions, national or local
legislation for their ecological,
landscape, cultural or other related
value
2 Areas which are important or sensitive
for ecological reasons - Wetlands,
watercourses or other water bodies,
coastal zone, biospheres, mountains,
forests
3 Areas used by protected, important or
sensitive species of flora or fauna for
breeding, nesting, foraging, resting,
over wintering, migration
4 Inland, coastal, marine or underground
waters

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 47
5 State, National boundaries
6 Routes or facilities used by the public
for access to recreation or other tourist,
pilgrim areas
7 Defence installations
8 Densely populated or built-up area
9 Areas occupied by sensitive man-made
land uses (hospitals, schools, places of
worship, community facilities)
10 Areas containing important, high
quality or scarce resources (ground
water resources, surface resources, forestry,
agriculture, fisheries, tourism, minerals)
11 Areas already subjected to pollution or
environmental damage. (Those where
existing legal environmental standards are
exceeded)
12 Areas susceptible to natural hazard
which could cause the project to
present environmental problems
(Earthquakes, subsidence, landslides,
erosion, flooding or extreme or adverse
climatic conditions)

(IV). Proposed Terms of Reference for EIA studies

……………………………………………………………………………………………………………
……………………………………………………………………………………………………………

I hereby given undertaking that the data and information given in the application and
enclosures are true to the best of my knowledge and belief and I am aware that if any part of
the data and information submitted id found to be false or misleading at any stage, the
project will be rejected and clearance give, if any to the project will be revoked at our risk
and cost:

Date: __________________

Place: _________________

Signature of the applicant


With Name and Full Address
(Project proponent/Authorized signatory)

Note:

1. The projects involving clearance under Coastal Regulation Zone Notification, 1991 shall
submit with the application a CRZ map duly demarcated by one of the authorized agencies,
showing the project activities, w.r.t CRZ (at the stage of TOR) and the recommendations of
the State Coastal Zone Management Authority (at the stage of EC).

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 48
Simultaneous action shall also be taken to obtain the requisite clearance under the
provisions of the CRZ Notification, 1991 for the activities to be located in the CRZ

2. The projects to be located within 10km of the National Parks, Sanctuaries, Biosphere
Reserves, Migratory corridors of the Wild animals, the project proponent shall submit the
map duly authenticated by Chief Wildlife Warden showing these features vis-à-vis the
project location and the recommendations of comments of the Chief Wildlife Warden
thereon (at the stage of EC)

3. All correspondence with the Ministry of Environment & Forests including submission of
application for TOR/Environmental Clearance, subsequent clarifications, as may be
required from time to time, participation in the EAC meeting on behalf of the project
proponent shall be made by the authorized signatory only. The authorized signatory should
also submit a document in support of his claim of being an authorized signatory for the
specific project.”

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 49
Annexure 2

FORM-1 A (only for construction projects listed under item 8 of the Schedule of EIA
Notification)

Check List of Environmental Impacts

(Project proponents are required to provide full information and wherever necessary attach
explanatory notes with the Form and submit along with proposed environmental
management plan & monitoring programme)

1. Land Environment

(Attach panoramic view of the project site and the vicinity)

1.1. Will the existing landuse get significantly altered from the project that is not consistent
with the surroundings? (Proposed landuse must conform to the approved Master Plan
/Development Plan of the area. Change of landuse if any and the statutory approval from
the competent authority be submitted). Attach Maps of (i) site location, (ii) surrounding
features of the proposed site (within 500 meters) and (iii) the site (indicating levels &
contours) to appropriate scales. If not available attach only conceptual plans.

1.2. List out all the major project requirements in terms of the land area, built up area, water
consumption, power requirement, connectivity, community facilities, parking needs etc.

1.3. What are the likely impacts of the proposed activity on the existing facilities adjacent to
the proposed site? (Such as open spaces, community facilities, details of the existing landuse,
and disturbance to the local ecology).

1.4. Will there be any significant land disturbance resulting in erosion, subsidence &
instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc
may be given).

1.5. Will the proposal involve alteration of natural drainage systems? (Give details on a
contour map showing the natural drainage near the proposed project site)

1.6. What are the quantities of earthwork involved in the construction activity-cutting,
filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill
materials from outside the site etc.)

1.7. Give details regarding water supply, waste handling etc during the construction period

1.8. Will the low lying areas & wetlands get altered? (Provide details of how low lying and
wetlands are getting modified from the proposed activity)

1.9. Whether construction debris & waste during construction cause health hazard? (Give
quantities of various types of wastes generated during construction including the
construction labour and the means of disposal)

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 50
2. Water Environment

2.1. Give the total quantity of water requirement for the proposed project with the breakup
of requirements for various uses. How will the water requirement met? State the sources &
quantities and furnish a water balance statement.

2.2. What is the capacity (dependable flow or yield) of the proposed source of water?

2.3. What is the quality of water required, in case, the supply is not from a municipal source?
(Provide physical, chemical, biological characteristics with class of water quality)

2.4. How much of the water requirement can be met from the recycling of treated
wastewater? (Give the details of quantities, sources and usage)

2.5. Will there be diversion of water from other users? (Please assess the impacts of the
project on other existing uses and quantities of consumption)

2.6. What is the incremental pollution load from wastewater generated from the proposed
activity? (Give details of the quantities and composition of wastewater generated from the
proposed activity)

2.7. Give details of the water requirements met from water harvesting? Furnish details of the
facilities created.

2.8. What would be the impact of the land use changes occurring due to the proposed project
on the runoff characteristics (quantitative as well as qualitative) of the area in the post
construction phase on a long term basis? Would it aggravate the problems of flooding or
water logging in any way?

2.9. What are the impacts of the proposal on the ground water? (Will there be tapping of
ground water; give the details of ground water table, recharging capacity, and approvals
obtained from competent authority, if any)

2.10. What precautions/measures are taken to prevent the run-off from construction
activities polluting land & aquifers? (Give details of quantities and the measures taken to
avoid the adverse impacts)

2.11. How is the storm water from within the site managed?(State the provisions made to
avoid flooding of the area, details of the drainage facilities provided along with a site layout
indication contour levels)
2.12. Will the deployment of construction labourers particularly in the peak period lead to
unsanitary conditions around the project site (Justify with proper explanation)

2.13. What on-site facilities are provided for the collection, treatment & safe disposal of
sewage? (Give details of the quantities of wastewater generation, treatment capacities with
technology & facilities for recycling and disposal)

2.14. Give details of dual plumbing system if treated waste used is used for flushing of
toilets or any other use.

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 51
3. Vegetation

3.1. Is there any threat of the project to the biodiversity? (Give a description of the local
ecosystem with it’s unique features, if any)

3.2. Will the construction involve extensive clearing or modification of vegetation? (Provide
a detailed account of the trees & vegetation affected by the project)

3.3. What are the measures proposed to be taken to minimize the likely impacts on
important site features (Give details of proposal for tree plantation, landscaping, creation of
water bodies etc along with a layout plan to an appropriate scale)

4. Fauna

4.1. Is there likely to be any displacement of fauna- both terrestrial and aquatic or creation of
barriers for their movement? Provide the details.

4.2. Any direct or indirect impacts on the avifauna of the area? Provide details.

4.3. Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on
fauna

5. Air Environment

5.1. Will the project increase atmospheric concentration of gases & result in heat islands?
(Give details of background air quality levels with predicted values based on dispersion
models taking into account the increased traffic generation as a result of the proposed
constructions)

5.2. What are the impacts on generation of dust, smoke, odorous fumes or other hazardous
gases? Give details in relation to all the meteorological parameters.

5.3. Will the proposal create shortage of parking space for vehicles? Furnish details of the
present level of transport infrastructure and measures proposed for improvement including
the traffic management at the entry & exit to the project site.

5.4. Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian
pathways, footpaths etc., with areas under each category.

5.5. Will there be significant increase in traffic noise & vibrations? Give details of the sources
and the measures proposed for mitigation of the above.

5.6. What will be the impact of DG sets & other equipment on noise levels & vibration in &
ambient air quality around the project site? Provide details.

6. Aesthetics

6.1. Will the proposed constructions in any way result in the obstruction of a view, scenic
amenity or landscapes? Are these considerations taken into account by the proponents?

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 52
6.2. Will there be any adverse impacts from new constructions on the existing structures?
What are the considerations taken into account?

6.3. Whether there are any local considerations of urban form & urban design influencing
the design criteria? They may be explicitly spelt out.

6.4. Are there any anthropological or archaeological sites or artefacts nearby? State if any
other significant features in the vicinity of the proposed site have been considered.

7. Socio-Economic Aspects

7.1. Will the proposal result in any changes to the demographic structure of local
population? Provide the details.

7.2. Give details of the existing social infrastructure around the proposed project

7.3. Will the project cause adverse effects on local communities, disturbance to sacred sites or
other cultural values? What are the safeguards proposed?

8. Building Materials

8.1. May involve the use of building materials with high-embodied energy. Are the
construction materials produced with energy efficient processes? (Give details of energy
conservation measures in the selection of building materials and their energy efficiency)

8.2. Transport and handling of materials during construction may result in pollution, noise
& public nuisance. What measures are taken to minimize the impacts?

8.3. Are recycled materials used in roads and structures? State the extent of savings
achieved?

8.4. Give details of the methods of collection, segregation & disposal of the garbage
generated during the operation phases of the project.

9. Energy Conservation

9.1. Give details of the power requirements, source of supply, backup source etc. What is the
energy consumption assumed per square foot of built-up area? How have you tried to
minimize
energy consumption?

9.2. What type of, and capacity of, power back-up to you plan to provide?

9.3. What are the characteristics of the glass you plan to use? Provide specifications of its
characteristics related to both short wave and long wave radiation?

9.4. What passive solar architectural features are being used in the building? Illustrate the
applications made in the proposed project.

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 53
9.5. Does the layout of streets & buildings maximise the potential for solar energy devices?
Have you considered the use of street lighting, emergency lighting and solar hot water
systems for use in the building complex? Substantiate with details.

9.6. Is shading effectively used to reduce cooling/heating loads? What principles have been
used to maximize the shading of Walls on the East and the West and the Roof? How much
energy saving has been effected?

9.7. Do the structures use energy-efficient space conditioning, lighting and mechanical
systems? Provide technical details. Provide details of the transformers and motor
efficiencies, lighting intensity and air-conditioning load assumptions? Are you using CFC
and HCFC free chillers? Provide specifications.

9.8. What are the likely effects of the building activity in altering the micro-climates? Provide
a self assessment on the likely impacts of the proposed construction on creation of heat
island & inversion effects?

9.9. What are the thermal characteristics of the building envelope? (a) roof; (b) external walls;
and (c) fenestration? Give details of the material used and the U-values or the R values of the
individual components.

9.10. What precautions & safety measures are proposed against fire hazards? Furnish details
of emergency plans.

9.11. If you are using glass as wall material provides details and specifications including
emissivity and thermal characteristics.

9.12. What is the rate of air infiltration into the building? Provide details of how you are
mitigating the effects of infiltration.

9.13. To what extent the non-conventional energy technologies are utilised in the overall
energy consumption? Provide details of the renewable energy technologies used.

10. Environment Management Plan

The Environment Management Plan would consist of all mitigation measures for each item
wise activity to be undertaken during the construction, operation and the entire life cycle to
minimize adverse environmental impacts as a result of the activities of the project. It would
also delineate the environmental monitoring plan for compliance of various environmental
regulations. It will state the steps to be taken in case of emergency such as accidents at the
site including fire.

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 54
Annexure 3
FORM I
APPLICATION FOR CONSENT TO ESTABLISH

Application for consent to establish industry, operation or process any treatment and
disposal system under Section 25/26
of the Water (Prevention & Control of Pollution) Act, 1974

(TO BE SUBMITTED IN TRIPLICATE)

(See Rule 29)

From:
…………………………………………….. Dated:…………………………………

……………………………………………..

To:
…………………………………………….

…………………………………………….
Sir,

I/we hereby apply for consent under section 25/26 of the Water (Prevention and control of
pollution) Act, 1974 (No. 6 of 1974) for establishing or taking any steps for establishment of
industry/operation/process or any other treatment/disposal system on land/premises
owned by………………………………………………………………………………………………..
……………………………………………………………………………………………………………

The relevant details are as below:

Part-I, General

a. Name of the industry ………………………………………………


b. Address ………………………………………………
………………………………………………
c. Location (also enclose copy of land allotment ………………………………………………
/land conversion order and site map)
d. Category of industry (Red/Orange/Others) ………………………………………………
e. Scale of industry (Large/Medium/Small) ………………………………………………
f. Whether the unit would generate hazardous waste (s) ……………………………………..
as defined in the Hazardous Waste (Management and
Handling) Rules, 1989. If so, the Category No ……………………………………..

Part-II, Surrounding Details

a. Area of the land proposed to be acquired (in square meter) …………………………….


b. Which of the following features exist within 25kms of the site …………………………….
i. Human settlement (specify population) …………………………….

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 55
ii. Forest/sanctuary/national park/Hill resort/
…………………………….
National monument
iii. Nallah/Stream/River/Pond/Dam/ …………………………….
any other water body
iv. Industries, specify ……………………………..

Part-III, Process Details

a. Manufacturing process with flow diagram ………………………………………..


b. Details of raw materials, products, by products ………………………………………..
and their storage capacity

S.No Particulars Name Nature Quantity


(Unit/Day)
i. Raw materials
ii. Products
iii. By products
iv. Hazardous chemicals

c. Energy consumption
d. Details of fuel

S.No Plant/Auxillary machines Name and Quantity (TPD)


where fuel is used Coal, Diesel, other (specify)
1 2 3
i.
ii.
iii.
iv.
v.

Part-IV, Water Pollution (Process-wise)

a. Water consumption per day ……………………………………


i. Boiler/Cooling/Industrial spray/Mining ……………………………………
ii. Domestic ……………………………………
iii. Industrial Process ……………………………………
b. Total waste water generation per day ……………………………………
c. Total waste water discharge per day ……………………………………
d. Water balance ……………………………………
e. Indicate wastewater and sludge characteristics, before ……………………………………
And after treatment – (physical/chemical)
f. Type of treatment proposed to be adopted ……………………………………
(enclose details, design and schematic diagram)
g. How do you propose to discharge the waste water ……………………………………
(specify mode of disposal)
h. What method do you propose to adopt for treatment ……………………………………
Handling & disposal of sludge

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 56
Part-V, Details of Air Pollution

S. No Stack attached to Stack details Volume Pollution concentration


plant Temp Dia Ht (NM3/hr) SPM/others (Mg/NM3)
(0C) (m) (m)
i.
ii.
iii.
iv.
v.
Note: Enclose lay out plan indicating location of each stack

Part-VI, Sludge/Solid Wastes/Hazardous Wastes (Process-wise) and their proposed


treatment

a. Total quantity of wastes (kg/day) ………………………………………………….


b. Nature of wastes ………………………………………………….
c. Method proposed for treatment & disposal ………………………………………………….

Part-VII, Other type of Pollution

a. Is your industry likely to cause noise pollution? ………………………………………….


If so, what measures are proposed to be taken?

b. Is your industry likely to cause any other pollution?………………………………………….


If so, what measure are proposed to be taken?

Part-VIII, Management of Pollution Control

a. Give details of the organizational setup proposed for ………………………………………….


Pollution control & monitoring

Part-IX, Cost of Pollution Control Measures

a. Total capital expenditure proposed for pollution control …………………………………


b. Annual recurring expenditure …………………………………
c. Has any financial outlay been proposed in the project? …………………………………
Report for pollution control measures? If so, mention the cost

1. I/We declare that the information furnished above is correct to the best of/my/our
knowledge

2. I/We undertake to furnish any other information within one month of its being called by
the State Board

I/We enclose herewith Bank Draft No…………………………..Dated………………………for


Rs………………..(Rs. in words………………………………………………………………… in
favor of the Member Secretary, Rajasthan Pollution Control Board, Payable under section
25/26 of the Act.

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 57
(In support of amount paid as fee, document on capital investment on the industry must be
enclosed)

Yours faithfully,

Signature…………………………….

Name………………………………..

Designation…………………………

Applicant

Note:

i. In case information required to be furnished is lengthy, separate sheet can be used &
attached
ii. Consent fee: Each consent application (under Air Act, 1981 or Water Act, 1974) must be
accompanied by the fees as given in schedule below. An application not accompanied with
the prescribed fee shall not be entertained by the Board
iii. Consent fees shall be paid through Bank Draft payable in favor of the Member Secretary,
Rajasthan State Pollution Control Board

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 58
Annexure 4
FORM I
APPLICATION FOR CONSENT TO ESTABLISH

Application for consent to establish industrial plant under Section 21


of the Air (Prevention & Control of Pollution) Act, 1981

(TO BE SUBMITTED IN TRIPLICATE)

(See Rule 4)

From:
…………………………………………….. Dated:…………………………………

……………………………………………..

To:
…………………………………………….

…………………………………………….
Sir,
I/we hereby apply for consent under section 21 of the Air (Prevention and control of
pollution) Act, 1981 for establishing the industrial plant owned
by………………………………………………………………………………………………………
……………………………………………………………………………………………………………

The relevant details are as follows:

Part-I, General

c. Name of the industry ………………………………………………


d. Address ………………………………………………
………………………………………………
c. Location (also enclose copy of land allotment ………………………………………………
/land conversion order and site map)
d. Category of industry (Red/Orange/Others) ………………………………………………
e. Scale of industry (Large/Medium/Small) ………………………………………………

Part-II, Surrounding Details

a. Area of the land proposed to be acquired (in square meter) …………………………….


b. Which of the following features exist within 25kms of the site …………………………….
i. Human settlement (specify population) …………………………….
ii. Forest/sanctuary/national park/Hill resort/ …………………………….
National monument
iii. Nallah/Stream/River/Pond/Dam/ …………………………….
any other water body
iv. Industries, specify ……………………………..

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 59
Part-III, Process Details

a. Manufacturing process with flow diagram …..……………………………….


b. Details of raw materials, products, by products ……………………………………
and their storage capacity

S.No Particulars Name Nature Quantity


(Unit/Day)
i. Raw materials
ii. Products
iii. By products
iv. Hazardous chemicals

c. Energy consumption
d. Details of fuel

S.No Plant/Auxillary machines Name and Quantity (TPD)


where fuel is used Coal, Diesel, other (specify)
1 2 3
i.
ii.
iii.
iv.
v.

Part-IV, Water Pollution (Process-wise)

a. Water consumption per day ……………………………………


i. Boiler/Cooling/Industrial spray/Mining ……………………………………
ii. Domestic ……………………………………
iii. Industrial Process ……………………………………
b. Total waste water generation per day ……………………………………
c. Total waste water discharge per day ……………………………………
d. Water balance ……………………………………
e. Indicate waste water and sludge characteristics, before ……………………………………
And after treatment – (physical/chemical)
f. Type of treatment proposed to be adopted ……………………………………
(enclose details, design and schematic diagram)
g. How do you propose to discharge the wastewater ……………………………………
(specify mode of disposal)
h. What method do you propose to adopt for treatment ……………………………………
Handling & disposal of sludge

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 60
Part-V, Details of Air Pollution

S. No Stack attached to Stack details Volume Pollution concentration


plant Temp Dia Ht (NM3/hr) SPM/others (Mg/NM3)
( C)
0 (m) (m)
i.
ii.
iii.
iv.
v.
Note: Enclose lay out plan indicating location of each stack

Part-VI, Sludge/Solid Wastes/Hazardous Wastes (Process-wise) and their proposed


treatment

a. Total quantity of wastes (kg/day) ………………………………………………….


b. Nature of wastes ………………………………………………….
c. Method proposed for treatment & disposal………………………………………………….

Part-VII, Other type of Pollution

a. Is your industry likely to cause noise pollution? ………………………………………….


If so, what measures are proposed to be taken?
b. Is your industry likely to cause any other pollution?………………………………………….
If so, what measure are proposed to be taken?

Part-VIII, Management of Pollution Control

a. Give details of the organizational setup proposed for………………………………………….


Pollution control & monitoring

Part-IX, Cost of Pollution Control Measures

a. Total capital expenditure proposed for pollution control …………………………………


b. Annual recurring expenditure …………………………………
c. Has any financial outlay been proposed in the project? …………………………………
Report for pollution control measures? If so, mention the cost

1. I/We declare that the information furnished above is correct to the best of/my/our
knowledge

2. I/We undertake to furnish any other information within one month of its being called by
the State Board

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 61
I/We enclose herewith Bank Draft No…………………………..Dated………………………for
Rs………………..(Rs. in words………………………………………………………………………
in favor of the Member Secretary, Rajasthan Pollution Control Board, Payable under section
25/26 of the Act.

(In support of amount paid as fee, document on capital investment on the industry must be
enclosed)

Yours faithfully,

Signature…………………………….

Name………………………………..

Designation…………………………

Applicant

Note:

i. In case information required to be furnished is lengthy, separate sheet can be used &
attached
ii. Consent fee: Each consent application (under Air Act, 1981 or Water Act, 1974) must be
accompanied by the fees as given in schedule below. An application not accompanied with
the prescribed fee shall not be entertained by the Board
iii. Consent fees shall be paid through Bank Draft payable in favor of the Member Secretary,
Rajasthan State Pollution Control Board

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 62
Annexure 5
Consent Fee Under the Provisions of Water Act
SCHEDULE IV (See rule 29) Part I Fee for Industries other than Mining Units

One Time Consent Fee to


S. Capital Investment of Annual Consent Fee to Operate
Establish
No the Industry (in Rs.)
(in Rs)
(in Rs.) Red Orange Other Red Orange Other
1 Upto 5 Lacs 3,000 2,000 1,000 1,400 1,200 1,000
More than 5 Lacs upto
2 4,500 3,000 1,500 2,100 4,800 1,500
10 Lacs
More than 10 Lacs
3 6,000 4,000 2,000 2,800 2,400 2,000
upto 25 Lacs
More than 25 Lacs
4 9,000 6,000 3,000 4,000 3,500 3,000
upto 50 Lacs
More than 50 Lacs
5 15,000 10,000 5,000 4,800 4,200 3,600
upto 1 Crore
More than 1 Crore
6 18,000 12,000 6,000 6,400 5,600 4,800
upto 5 Crore
More than 5 Crore
7 24,000 16,000 8,000 8,000 7,000 6,000
upto 10 Crore
More than 10 Crore
8 30,000 20,000 10,000 9,600 8,400 7,200
upto 25 Crore
More than 25 Crore
9 37,500 25,000 12,500 12,000 10,500 9,000
upto 50 Crore
More than 50 Crore
10 45,000 30,000 15,000 22,000 19,000 15,000
upto 100 Crore
More than 100 Crore
11 1,05,000 70,000 35,000 31,000 26,000 21,000
upto 250 Crore
More than 250 Crore
12 1,27,500 85,000 42,500 44,000 38,000 30,000
upto 500 Crore
More than 500 Crore
13 1,50,000 1,00,000 50,000 53,000 45,000 36,000
upto 750 Crore
More than 750 Crore
14 1,87,500 1,25,000 62,500 57,000 49,000 39,000
upto 100 Crore
15 Above 1000 Crore 2,25,000 1,50,000 1,50,000 75,000 53,000 42,000

Note:
1. The categorization of the industries / mining units into Red, Orange and Other categories shall be
as specified by the State Board.
2. All industries and mining units requiring environmental clearance under the Environmental
(Protection) Act, 1986 shall pay an extra amount of Rs. 15,000/- as one time consent fee to establish in
addition to that mentioned in Schedule IV.
3. Provided that where a person who is establishing or carrying on any industry, operation or process
and is generating hazardous waste as defined under the Hazardous Wastes (Management &
Handling) Rules, 1989; and requiring authorization thereunder; the application for consent shall be
accompanied with a fee equal to one and half times of the amount of fee prescribed under Schedule
IV.
(Please refer Notification dated 25th May 2007 of Dept. of Environment, Govt. of Rajasthan)

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 63
Annexure 6
Consent Fee Under the Provisions of Air Act
SCHEDULE (See rule 5) Part I Fee for Industries other than Mining Units

One Time Consent Fee to


S. Capital Investment of Annual Consent Fee to Operate
Establish
No the Industry (in Rs.)
(in Rs)
(in Rs.) Red Orange Other Red Orange Other
1 Upto 5 Lacs 3,000 2,000 1,000 1,400 1,200 1,000
More than 5 Lacs upto
2 4,500 3,000 1,500 2,100 4,800 1,500
10 Lacs
More than 10 Lacs
3 6,000 4,000 2,000 2,800 2,400 2,000
upto 25 Lacs
More than 25 Lacs
4 9,000 6,000 3,000 4,000 3,500 3,000
upto 50 Lacs
More than 50 Lacs
5 15,000 10,000 5,000 4,800 4,200 3,600
upto 1 Crore
More than 1 Crore
6 18,000 12,000 6,000 6,400 5,600 4,800
upto 5 Crore
More than 5 Crore
7 24,000 16,000 8,000 8,000 7,000 6,000
upto 10 Crore
More than 10 Crore
8 30,000 20,000 10,000 9,600 8,400 7,200
upto 25 Crore
More than 25 Crore
9 37,500 25,000 12,500 12,000 10,500 9,000
upto 50 Crore
More than 50 Crore
10 45,000 30,000 15,000 22,000 19,000 15,000
upto 100 Crore
More than 100 Crore
11 1,05,000 70,000 35,000 31,000 26,000 21,000
upto 250 Crore
More than 250 Crore
12 1,27,500 85,000 42,500 44,000 38,000 30,000
upto 500 Crore
More than 500 Crore
13 1,50,000 1,00,000 50,000 53,000 45,000 36,000
upto 750 Crore
More than 750 Crore
14 1,87,500 1,25,000 62,500 57,000 49,000 39,000
upto 100 Crore
15 Above 1000 Crore 2,25,000 1,50,000 1,50,000 75,000 53,000 42,000

Note:
1. The categorization of the industries / mining units into Red, Orange and Other categories shall be
as specified by the State Board.
2. All industries and mining units requiring environmental clearance under the Environmental
(Protection) Act, 1986 shall pay an extra amount of Rs. 15,000/- as one time consent fee to establish in
addition to that mentioned in Schedule IV.
3. Provided that where a person who is establishing or carrying on any industry, operation or process
and is generating hazardous waste as defined under the Hazardous Wastes (Management &
Handling) Rules, 1989; and requiring authorization thereunder; the application for consent shall be
accompanied with a fee equal to one and half times of the amount of fee prescribed under Schedule
IV.
(Please refer Notification dated 25th May 2007 of Dept. of Environment, Govt. of Rajasthan)

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 64
Annexure 7

Areas as identified by CGWA as – safe areas, semi – critical areas, critical areas & over
exploited areas

S.No District No of Blocks Safe Semi-Critical Critical Over-Exploited


1 2 3 4 5 6 7
8 Bikaner 5 1. Lunkaransar - 1. Dungargarh 1. Bikaner
2. Kolayat - 2. Nokha
9 Bundi 4 - 1. Kesorai Patan 1. Hindoli
2. Talera 2. Nainwa

10 Chittorgarh 14 - 1. Bhainsrorgarh - 1. Amod


2. Bari Sadri
3. Begun
4. Bhadesar
5. Bhopalsagar
6. Chhotisadri
7. Chittorgarh
8. Dungla
9. Gangrar
10. Kapasan
11. Nimbahera
12. Pratapgarh
13. Rashmi

11 Churu 6 1. Churu 1. Sujangarh 1. Rajgarh


2. Atangarh
3. Sardarshahar -
1. Bandikui
12 Dausa 5
2. Dausa
3. Lalsot
4. Mahua
5. Sirai

1. Dholpur
13 Dholpur 4 1. Bari 1. Baseri
2. Rajakhera

14 Dungarpur 5 1. Aspur 1. Bichhiwara 1. Sagwara


2. Dungarpur 2. Simalwara

15 Ganganagar 7 1. Anupgarh
2. Ganganagar
3. Karanpur
4. Padampur
5. Raisingh nagar
6. Sadulshahar
7. Suratgarh

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 65
16 Hanumangarh 3 1. Bhadra
2. Hanumangarh
3. Nohar

17 Jaipur 13 1. Dudu 1. Amer


2. Phagi 2. Bairath
3. Bassi
4. Chaksu
5. Govindgarh
6. Jamwa Ramgarh
7. Jhotwara
8. Kotputli
9. Sambher
10. Sanganer
11. Shahpura

18 Jaisalmer 3 1. Sam 1. Jaisalmer


2. Sankra

19 Jalore 7 1. Ahore
2. Bhinmal
3. Jalore
4. Jaswantpura
5. Raniwara
6. Sanchore
7. Sayla

20 Jhalawar 6 1. Bakani 1. Manoha Thana


2. Dag 2. Pirawa
3. Jhalra Patan
4. Khanpur

21 8
Jhunjhunu 1. Alsisar 1. Bhuhana
2. Chirawa
3. Jhunjhunu
4. Khetri
5. Nawalgarh
6. Surajgarh
7. Udaipurwati
22 Jodhpur 9 1. Bap 1. Phalodi 1. Luni 1. Balesar
2. Shergarh 2. Bhopalgarh
3. Bilara
4. Mandore
5. Osaian
23 Karauli 5 1. Nadauti 1. Sapotra 1. Hindaun
2. Karauli
3. Todabhim
24 Kota 5 1. Sultanpur 1. Itawa
2. Khairabad
3. Ladpura
4. Sangod

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 66
1. Nagaur 1. Ladnu
25 11
Nagaur 1. Jayal 1. Degana
2. Makrana 2. Didwana
3. Kuchaman
4. Merla
5. Mundwa
6. Parbaisar
7. Riyan
26 Pali 10 1. Bali 1. Jaitaran
2. Desuri 2. Kharchi
3. Pali 3. Rani
4. Raipur 4. Sojat
5. Rohit 5. Sumerpur
27 Rajsamand 7 1. Railmagra 1. Amet
2. Rajsamand 2. Bhim
3. Deogarh
4. Khamnor
5. Kumbhalgarh
28 Sawaimadhopur 5 1. Bamanwas 1. Gangapur
2. Bonli 2. Sawai Madhopur
3. Khandar
29 8
Sikar 1. Fatehpur 1. Danta Ramgarh
2. Dhod
3. Khandella
4. Lachhmangarh
5. Neem Ka Thana
6. Piprali
7. Sri Madhopur
30 Sirohi 5 1. Abu Road 1. Reodar
2. Pindwara 2. Sheoganj
3. Sirohi
31 Tonk 6 1. Deoli 1. Untara
2. Malpura
3. Newai
4. Toda Rai Singh
5. Tonk
32 11
Udaipur 1. Kherwara 1. Badgaon
2. Kotra 2. Bhinder
3. Sarada 3. Dhariawad
4. Girwa
5. Gogunda
6. Jhadot
7. Mavli
8. Salumber
Total 237 32 14 50 140
(Source: CGWA No: 21-4/Guidelines/CGWA/2009-832 dated 14.10. 2009)

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 67
Annexure 8

General Standards for Discharge of Effluents 


S. Parameter Standards
No Inland surface Public sewers Land for Marine coastal
water irrigation areas
(a) (b) (c) (d)
1 Color & odour * ------- * *
2 Suspended solids 100 600 200 1. For process waste
mg/l, Max water-100
2. For cooling water
effluent 10% above
total suspended
matter of influent
3 Particle size of Shall pass 850 -- -- 1. Floatable solids
suspended solids Micron IS sieve max. 3 mm
2. Settleable solids
max. 850 microns
4 pH Value 5.5 to 9.0 5.5 to 9.0 5.5 to 9.0 5.5 to 9.0
5 Temperature Shall not exceed 50 -- -- Shall not exceed 50 C
C above the above the receiving
receiving water water temperature
temperature
6 Oil and grease 10 20 10 20
mg/l Max.
7 Total residual 1.0 -- -- 1.0
chlorine mg/l Max.
8 Ammonical 50 50 -- 50
Nitrogen (as N),
mg/l Max.
9 Total Kjeldahl 100 -- -- 100
nitrogen (as NH3),
mg/l Max.
10 Free ammonia (as 5.0 -- -- 5.0
NH3), mg/l Max.
11 Bio-chemical 30 350 100 100
oxygen demand (3
days at 270 C), mg/l
max.
12 Chemical oxygen 250 -- -- 250
demand, mg/l
max.
13 Arsenic (as As), 0.2 0.2 0.2 0.2
mg/l max.
14 Mercury (as Hg), 0.01 0.01 -- 0.01
mg/l max.
15 Lead (as Pb), mg/l 0.1 1.0 -- 2.0
max.
16 Cadmium (as Cd), 2.0 1.0 -- 2.0
mg/l max.
17 Hexavalent 0.1 2.0 -- 1.0
chromium (as Cr
+6), mg/l max.

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 68
18 Total chromium (as 2.0 2.0 -- 2.0
Cr), mg/l max.
19 Copper (as Cu), 3.0 3.0 -- 3.0
mg/l max.
20 Zinc (as Zn), mg/l 5.0 15 -- 15
max.
21 Selenium (as Se), 0.05 0.05 -- 0.05
mg/l max.
22 Nickel (as Ni), 3.0 3.0 -- 5.0
mg/l max.
23 Cyanide (as CN), 0.2 2.0 0.2 0.2
mg/l max.
24 Fluoride (as F), 2.0 15 -- 15
mg/l max.
25 Dissolved 5.0 -- -- --
phosphates (as P),
mg/l max.
26 Sulphide (as S), 2.0 -- -- 5.0
mg/l max.
27 Phenolic 1.0 5.0 -- 5.0
compounds (as
C6H5OH), mg/l
max.
28 Radio active materials:
a. Alpha emitter 10-7 10-7 10-8 10-7
micro curie/ml
b. Beta emitter 10-6 10-6 10-7 10-6
micro curie/ml
29 Bio-assay test 90% survival of fish 90% survival of 90% survival of 90% survival of fish
after 96 hours in fish after 96 fish after 96 after 96 hours in
100% effluent hours in 100% hours in 100% 100% effluent
effluent effluent
30 Manganese (as 2 2 -- 2
Mn), mg/l
31 Iron (as Fe), mg/l 3 3 -- 3
32 Vanadium (as V), 0.2 0.2 -- 0.2
mg/l
33 Nitrate nitrogen, 10 -- -- 20
mg/l
* All efforts should be made to remove colour and unpleasant odour as far as practicable
These standards shall be applicable for industries, operations or processes other than those industries,
operations or process for which standards have been specified of the Environment Protection Rules, 1989
Source: G.S.R 422 (E) dated 19.05.1993 and G.S.R 801 (E) dated 31.12.1993 issued under the provisions of E
(P) Act 1986

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 69
Annexure 9
National Ambient Air Quality Standards (NAAQS)

S. Pollutant Time Concentration in Ambient Air


No Weighted Industrial, Ecologically Methods of
Average Residential, sensitive area measurement
Rural and (notified by
other areas central
government)
(1) (2) (3) (4) (5) (6)
1 Sulphur dioxide Annual* 50 20 -Improved West & Gaeke
(SO2), μg/m3 -Ultraviolet fluorescence
24 hours** 80 80
2 Nitrogen Dioxide Annual* 40 30 -Modified Jacob &
(NO2), μg/m3 Hochheiser (Na-
24 hours** 80 80 arsenite)
-Chemiluminescence
3 Particulate Matter Annual* 60 60 - Gravimetric
(Size less than - TOEM
10μm) or 24 hours** 100 100 - Beta attenuation
PM10μg/m3
4 Particulate Matter Annual* 40 40 - Gravimetric
(Size less than - TOEM
2.5μm) or 24 hours** 60 60 - Beta attenuation
PM2.5μg/m3
5 Ozone (O3) 8 hours** 100 100 - UV photometric
μg/m3 - Chemiluminescence
1 hour** 180 180 - Chemical method
6 Lead (Pb) μg/m3 Annual* 0.50 0.50 -AAS/ICP method after
sampling on EPM 2000
24 hours** 1.0 1.0 or equivalent filter paper
-ED-XRF using Teflon
filter
7 Carbon 8 hours** 02 02 -Non Dispersive Infra
Monoxide (CO) Red (NDIR)
mg/ m3 1 hour** 04 04 spectroscopy
8 Ammonia (NH3) Annual* 100 100 - Chemiluminescence
μg/m3 24 hours** 400 400 - Indophenol blue
method
9 Benzene (C6H6) Annual* 05 05 -Gas chromatography
μg/m3 based continuous
analyzer
-Adsorption and
Desorption followed by
GC analysis
10 Benzo(a)Pyrene Annual* 01 01 -Solvent extraction
(BaP) – followed by HPLC/GC
particulate phase analysis

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 70
only, ng/m3
11 Arsenic (As) Annual* 06 06 -AAS/ICP method after
ng/m3 sampling on EPM 2000
or equivalent filter paper
12 Nickel (Ni) Annual* 20 20 -AAS/ICP method after
ng/m3 sampling on EPM 2000
or equivalent filter paper

* Annual arithmetic mean of minimum 104 measurements in a year at a particular site taken
twice a week 24 hourly at uniform intervals
** 24 hourly or 08 hourly or 01 hourly monitored values, as applicable, shall be complied
with 98% of the time in a year. 2% of the time, they may exceed the limits but not on two
consecutive days of monitoring.

Note:

Whenever and wherever monitoring results on two consecutive days of monitoring exceed
the limits specified above for the respective category, it shall be considered adequate reason
to institute regular or continuous monitoring and further investigation

(Source: National Ambient Air Quality Standards, CPCB Notification dated 18th November 2009)

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 71
Annexure 10
Noise Ambient Air Quality Standards

Area code Category of area Limits in db (A) Leq


Day time Night time
A Industrial area 75 70
B Commercial area 65 55
C Residential area 55 45
D Silence zone 50 40

Note:

1. Day time shall mean from 6.00 a.m. to 10.00 p.m.


2. Night time shall mean from 10.00 p.m. to 6.00 a.m.
3. Silence zone is an area comprising not less than 100 meters around hospitals, educational
institutions, courts, religious places or any other area, which is declared as such by the
competent authority.
4. Mixed categories of areas may be declared as one of the four above-mentioned categories
by the competent authority.

* dB(A) Leq denotes the time weighted average of the level of sound in decibels on scale A
which is relatable to human hearing.

A “decibel” is a unit in which noise is measured.

“A”, in dB(A) Leq, denotes the frequency weighting in the measurement of noise and
corresponds to frequency response characteristics of the human ear.

Leq: It is an energy mean of the noise level over a specified period.

(Source: Noise pollution (Regulation and control) Rules, 2000)

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 72
Annexure 11
Noise Limits for Generator Sets run with Diesel

1. Noise limit for diesel generator sets (up to 1000 KVA) manufacture on or after the 1st
July 2003

The maximum permissible sound pressure level for new diesel generator (DG) sets with
rated capacity up to 1000 KVA, manufactured on or after the 1st July, 2003 shall be 75 dB (A)
at 1 meter from the enclosure surface

The diesel generator sets should be provided with integral acoustic enclosure at the
manufacturing stage itself

The implementation of noise limit for these diesel generator sets shall be regulated as given
in paragraph 3 below

2. Noise limit for DG sets not covered by paragraph 1

Noise limits for diesel generator sets not covered by paragraph 1, shall be as follows:

2.1 Noise from DG set shall be controlled by providing an acoustic enclosure or by treating
the room acoustically, at the users end

2.2 The acoustic enclosure or acoustic treatment of the room shall be designed for minimum
25 dB (A) insertion loss or for meeting the ambient noise standards, whichever is on the
higher side (if the actual ambient noise is on the higher side, it may not be possible to check
the performance of the acoustic enclosure/acoustic treatment. Under such circumstances the
performance may be checked for noise reduction up to actual ambient noise level,
preferably, in the nighttime). The measurement for insertion loss may be done at different
points at 0.5m from the acoustic enclosure/room, and then averaged

2.3 The DG set shall be provided with proper exhaust muffler with insertion loss of
minimum 25 dB (A)

2.4 these limits shall be regulated by the State Pollution Control Boards and the State
Pollution Control Committees

2.5 Guidelines for the manufacturers/users of Diesel Generator sets shall be as under:

01 The manufacturer shall offer to the user a standard acoustic enclosure of 25 dB (A)
insertion loss and also a suitable exhaust muffler with insertion loss of 25 dB(A)

02 The user shall make efforts to bring down the noise levels due to the DG set; outside
hid premises, within the ambient noise requirements by proper siting and control
measures

03 Installation of a DG set must be strictly in compliance with the recommendations of


the DG set manufacturer

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 73
04 A proper routine and preventive maintenance procedure for the DG set should be set
and followed in consultation with the DG set manufacturer which would help prevent
noise levels of the DG set from deteriorating with use

3. Limits of noise for DG Sets (Up to 1000 KVA) Manufactured on or after the 1st July 2003

3.1 Applicability

01. These Rules apply to DG sets up to 1000 KVA rated output, manufactures of
imported in India, on or after 1st July 2003

02. These rules shall not apply to

a. DG sets manufactures or imported for the purpose of exports outside India;


and
b. DG sets intended for the purpose of sample and not for sale in India

(Please refer Notification No. G.S.R. 371 (E) dated 17th May, 2002 for details)

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 74
Annexure 12

Effluent Standards for Hotel Industry notified under E (P) Act, 1986

S. No Industry Parameter Standards


1 2 3 4
39 Hotel Effluent standards
industry i. Hotel with at least 20 bedrooms
Limiting concentration in mg/l except for pH
Inland surface water On land for irrigation
PH 5.5-9.0 5.5-9.0
BOD 3 days 27 C 0 30 100
Total suspended solids 50 100
Oil & grease 10 10
Phosphates as P 1.0 -
ii. Hotel with less than 20 bed rooms or a Banquet Hall with minimum
floor area of 100m2 or a Restaurant with a minimum seating capacity of
36
PH 5.5-9.0 5.5-9.0
BOD 3 days 27 C 0 100 100
Total suspended solids 100 100
Oil & Grease 10 10
Note:
i. Hotels, banquet halls, restaurants etc., located in coastal area shall
also comply with the provisions of the Coastal Regulation Zone, as
applicable
ii. If the effluent is discharged into a municipal sewer leading to a
Sewage Treatment Plant, the hotel or restaurant or banquet hall, as the
case may be, shall provide a proper Oil and Grease trap for effluent
arising from its kitchen and laundry and shall have to comply with the
‘General standards for discharge of environmental pollutants Part A
effluents’ notified under Schedule VI

(Source: G.S.R. 749 (E) under Environmental (Protection) Act dated 4th November 2009 - MoEF,
GoI)

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 75
Annexure 13

Estimation of Water Demand

S. No Type of Building Consumption liters/day

1. Factories with bath rooms 45 per head

2. Factories without bath rooms 30 per head

3. Hospital (including laundry):

4. a) Number of beds not exceeding 100 340 per head

5. b) Number of beds exceeding 100 450 per head

6. Nurses’ homes and medical quarters 135 per head

7. Hostels 135 per head

8. Hotel (up to 4 star) 180 per head

9. Hotel (5 star and above) 320 per head

10. Offices 45 per head

11. Restaurants 70 per seat

12. Cinemas, concert halls and theaters 15 per seat

13. Schools

14. a) Day schools 45 per head

15. b) Boarding schools 135 per head

In addition, water demand of visitors to these building is considered as 15 LPCD


Source: Manual on norms and standards for environment clearance of large construction
projects,MoEF

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 76
Annexure 14
Code of Practices for Parking Requirements

Area Requirements for Parking in Different Types of Cities

One Car Parking Space for Every


Population Population Population
Sl. Population Population
Occupancy between between between
No less than above
50,000 to 2,00,000 to 10,00,000 to
50,000 50,00,000
2,00,000 10,00,000 50,00,000
(1) (2) (3) (4) (5) (6) (7)
a) Residential ---- ---- 2 tenements 1 tenement of 1 tenement of
having built- 100 m2 built up 75 m2 built up
up area 101 area area
to 200 m 2

b) Lodging 12 guest rooms 8 guest 4 guest 3 guest rooms 2 guest rooms


1
establishments, rooms rooms
tourist homes and
hotels, with
lodging
accommodation
70 m2 area or 50 m2 area or 35 m2 area or
fraction fraction thereof fraction
thereof of the of the thereof of the
2 Educational administrativ administrative administrative
e office area office area and office area and
and public public service public service
service areas areas areas
20 beds 15 beds 10 beds 5 beds 2 beds
(Private) (Private) (Private) (Private) (Private)
Institutional
3 30 beds 25 beds 15 beds 10 beds (Public) 5 beds (Public)
(Medical)
(Public) (Public) (Public)

a) Assembly Halls, 20 seats 80 seats 25 seats 15 seats 10 seats


Cinema Theatres
b) Restaurants 60 seats 40 seats 20 seats 10 seats 5 seats
4 c) Marriage Halls, 600 m2 plot 400 m2 plot 200 m2 plot 50 m2 plot area 25 m2 plot area
Community Halls area area area
d) Stadia and 240 Seats 160 seats 50 seats 30 seats 20 seats
Exhibition Center
a) Business Offices 300 m2 area or 200 m2 area 100 m2 area 50 m2 area or 25 m2 area or
and Firms for fraction thereof or fraction or fraction fraction thereof fraction
Private Business thereof thereof thereof
5
b) Public or semi- 500 m2 area or 300 m2 area 200 m2 area 100 m2 area or 50 m2 area or
public Offices fraction thereof or fraction or fraction fraction thereof fraction
thereof thereof thereof
Mercantile (See 300 m2 area or 200 m2 area 100 m2 area 50 m2 area or 25 m2 area or
6 Note 2) fraction thereof or fraction or fraction fraction thereof fraction
thereof thereof thereof
Industrial 400 m2 area or 300 m2 area 200 m2 area 100 m2 area or 50 m2 area or
7 fraction thereof or fraction or fraction fraction thereof fraction
thereof thereof thereof

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 77
Storage ---- ---- 500 m2 area 250 m2 area or 125 m2 area or
8 or fraction fraction thereof fraction
thereof thereof

Area requirements for different types of parking

Vehicle type Area required for parking (m) Clear height (m)
Car 2.5x5 2.2
Scooter cycle 3x1.4 2.2
Trucks 3.75x10 4.75

Parking requirements for per Car space is as per the floor type

Basement 35 sq.m
Stilts 30 sq.m
Open 25 sq.m

(Source: National Building Code of India, 2005)

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 78
Annexure 15
BIS Code of Practices

S.
BIS Code Description
No
Genera Structural Safety
1 IS: 456:2000 Code of Practice for Plain and Reinforced Concrete
2 IS: 800-1984 Code of Practice for General Construction in Steel
IS: 801-1975 Code of Practice for Use of Cold Formal Light Gauge Steel Structual
3
Members in General Building Construction
Members in General Building Construction
IS: 875 (Part 2): Design loads (other than earthquake) for buildings and structures Part 2
4
1987 Imposed Loads
IS: 875 (Part 3): Design loads (Other than earthquake) for buildings and structures Part 3
5
1987 Wind Loads
IS: 875 (Part 4): Design loads (Other than earthquake) for buildings and structures Part 4
6
1987 Snow Loads
IS: 875 (Part 5): Design loads (Other than earthquake) for buildings and structures Part 5
7
1987 Special loads and load combination
8 IS: 883: 1966 Code of Practice for Design for Structural Timber in Building
9 IS: 1904: 1987 Code of Practice for Structural Safety of Buildings: Foundation
10 IS: 1905: 1987 Code of Practice for Structural Safety of Buildings: Masonry Walls
IS: 2911 (Part 1) Code of Practice for Design and Construction of Pile Foundation Section1
Section 1: 1979
Part 1: Section 2 Based Cast-in-situ Piles
Part 1: Section 3 Driven Precast Concrete Piles
11
Part 1: Section 4 Based precast Concrete Piles
Part 2: Timber Piles
Part 3 Under Reamed Piles
Part 4 Load Test on Piles
Cyclone/Wind Storm Protection
IS: 875 (3)-1987 Code of Practice for Design Loads (other than Earthquake) for Buildings and
12
Structures, Part 3, Wind Loads
IS: IS Guidelines for improving the Cyclonic resistance of Low rise houses ad
13
other building
Earthquake Protection
14 IS: 1893-2002 Criteria for Earthquake Resistant Design of Structures (Fifth Revision)
IS: 13920-1993 Ductile Detailing of Reinforced Concrete Structures subjected to Seismic
15
Forces – Code of Practice
IS: 4326-1993 Earthquake Resistant Design and Construction of Buildings – Code of
16
Practice (Second Revision)
IS: 13828-1993 Improving Earthquake Resistance of Low Strength Masonry Buildings –
17
Guidelines
18 IS: 13827-1993 Improving Earthquake Resistance of Earthen Buildings – Guidelines
19 IS: 13935-1993 Repair and Seismic Strengthening of Buildings - Guidelines
Protection of Landslide Hazard
IS: 14458 (Part 1): Guidelines for retaining wall for hill area: Part I Selection of type of wall
20
1998

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 79
IS: 14458 (Part 2): Guidelines for retaining wall for hill area: Part 2 Design of retaining / Breast
21
1997 walls
IS: 14458 (Part 3): Guidelines for retaining wall for hill area: Part 3 Construction of dry stone
22
1998 walls
IS: 14496 (Part 2): Guidelines for preparation of landslide – Hazard zonation maps in
23
1998 mountainous terrains: Part 2 Macro-zonation.

Note:

1: Whenever an Indian Standard including those referred in the National Building Code or
the National Building Code is referred, the latest revision of the same shall be followed
except specific criteria, if any, mentioned above against that code.

2. Codal Provisions/Guidelines Pertaining to Protection for Cyclone or Landslide Hazard


cam be omitted whenever not applicable

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 80
Annexure 16
Ground Water Scenario of Rajasthan
Hydrogeology

The State can be divided into three hydrogeological units namely, unconsolidated
sediments, semi-consolidated sediments and consolidated rocks. The unconsolidated
sediments are of two types- alluvial sediments and aeoline deposits. The Alluvial deposits
are confined to Barmer, Jalore and Jodhpur district, consisting of sand, clay, gravel and
cobbles. Valley fills have been reported from Jhunjhunu, Ajmer, Bhilwara and Udaipur
district. The Aeoline sediments constitute one of the major aquifers east of major fault, east
of Bikaner. It occupies an area of 1400 sq.k m. The aquifer thickness is 40 to 80 m. The yield
of wells ranges from 100 to 150 m3/hr. Semi-consolidated formations include sandstones,
limestones and Aur beds, covering Jaisalmer and Barmer districts. The dugwells in Jaisalmer
limestones yield 13 to 68 m3/day. The yield of wells in Lathi sandstone varies from 50-150
m3/hr. The consolidated rocks includes gneiss, granites, schist, phyllites, marble and
Vindhyan sandstones, limestone, quartzite and basaltic flows, mostly restricted to eastern
part of the State. The yield prospect is limited unless the well is located near major
lineaments or any other weak planes. The ground water quality is in general poor (brackish
to saline) at deeper levels.

Ground Water Exploration/Sources Findings

Dynamic Resources
Annual Replenishable Ground water 11.56 BCM
Resource
Net Annual Ground Water Availability 10.38 BCM
Annual Ground Water Draft 12.99 BCM
Stage of Ground Water Development 125 %
Developmental Monitoring
Over Exploited 140 Blocks
Critical 50 Blocks
Semi- critical 14 Blocks
Exploratory Tube wells Constructed (as on 1383
31.03.2009)
No. of ground water observation wells 1373
Ground Water User Maps 32 districts
Ground Water Quality Problems
Contaminants Districts affected (in part)
Salinity (EC > 3000 µS/cm at 25 ° C) Ajmer, Alwar, Barmer, Bharatpur, Bhilwara,
Bundi, Bikaner, Churu, Chittaurgarh, Dhaulpur,
Dausa, Ganganagar, Hanumangarh, Jaipur,
Jaisalmer, Jalor,Jhunjhunun, Karoli, Nagaur,
Neemuch, Raja Samand, Sirohi, Sikar, Swai
Madhopur, Tonk, Udaipur
Fluoride (>1.5 mg/l) Ajmer, Alwar, Banaswara, Barmer, Bharatpur,
Bhilwara, Bikaner, Bundi, Chittaurgarh, Churu,
Dausa, Dhaulpur, Dungarpur, Ganganagar,
Hanumangarh, Jaipur, Jaisalmer,

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 81
Jalor,Jhunjhunu, Jodhpur, Karauli, Kota, Nagaur,
Pali, Rajasamand, Sirohi, Sikar, SawaiMadhopur,
Tonk, Udaipur
Chloride (> 1000 mg/l) Barmer, Bharatpur, Bikaner, Churu, Ganganagar,
Hanumangarh, Jaipur, Jaisalmer, Jalor,
Jhunjhunun, Jodhpur Nagaur, Sirohi, Nagaur,
Sikar, Tonk
Iron (>1.0 mg/l) Ajmer, Alwar, Banswara, Baran, Bharatpur,
Bhilwara, Bikaner, Chittaurgarh, Churu, Dausa,
Dhaulpur, Dungarpur, Ganganagar,
Hanumangarh, Jaipur, Jaisalmer, Jhalawar,
Jhunjhunu, Jodhpur, Karauli, Kota, Nagaur, Pali,
Rajasamand, Sikar, Sawai Madhopur, Tonk,
Udaipur
Nitrate (>45 mg/l) Ajmer, Alwar, Banaswara, Baran, Barmer,
Bharatpur, Bhilwara, Bikaner, Chittaurgarh,
Churu, Dausa, Dhaulpur, Dungarpur,
Ganganagar, Hanumangarh, Jaipur, Jaisalmer,
Jalor, Jhalawar, Jhunjhunu, Jodhpur, Karauli,
Kota, Nagaur, Pali, Partapgarh, Rajasamand,
Sirohi, Sikar, Swai Madhopur, Tonk, Udaipur

Inclusion of Roof Top Rain Water Harvesting (RTRWH) in building by laws

Roof Top RWH has been made mandatory in state owned buildings of plot size more than
300 sq.m with effect from 03.01.2006. For violation of building bye-laws, punitive measures,
viz. disconnection of water supply, has also been made. The Govt. has made provision of
compulsory installation of rainwater harvesting system in all newly and existing
construction building and Govt. offices vide order dated 31.05.2000 and 12.12.2005. The State
Government is also considering to modify Municipal Corporation Act making provisions of
RWH.

Areas Notified for Regulation of ground water development

ƒ Jhotwara block of Jaipur district


ƒ Pushkar Valley, Ajmer district
ƒ Jalore block, Jalore district
ƒ Raniwara block, Jalore district
ƒ Budhana block, Jhunjunu district
ƒ Chirawa block, Jhunjunu district
ƒ Mundwa block, Nagaur district
ƒ Behror block, Alwar district
ƒ Bhinmal block, Jalore district
ƒ Surajgarh block, Jhunjunu district
ƒ Dhod block, Sikar district
ƒ Shri Madhopur block, Sikar district

Source: http://cgwb.gov.in down loaded on 10th March 2010

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 82
Annexure 17
Rain Water Harvesting Structures

Rainwater available from rooftops of buildings, paved and unpaved areas goes waste. This
water can be recharged to aquifer and can be utilized gainfully at the time of need. The
rainwater harvesting system needs to be designed in a way that it does not occupy large
space for collection and recharge system. A few techniques of roof top rainwater harvesting
in urban areas are described below.

Roof Top Rain Water Harvesting Through Recharge Pit

• In alluvial areas where permeable rocks are exposed on the land surface or at very
shallow depth, roof top rainwater harvesting can be done through recharge pits.
• The technique is suitable for buildings having a roof area of 100 sq.m. and are
constructed for recharging the shallow aquifers.
• Recharge Pits may be of any shape and size and are generally constructed 1.0 to 2.0 m.
wide and 2.0 to 3.0 deep, which are back filled with boulders (5 - 20 cm), gravels (5 – 10
mm) and coarse sand (1.5 - 2.0 mm) in graded form. Boulders at the bottom, gravels in
between and coarse sand at the top so that the silt content that will come with runoff will
be deposited on the top of the coarse sand layer and can easily be removed. For smaller
roof area, pit may be filled with broken bricks/ cobbles.
• A mesh should be provided at the roof so that leaves or any other solid waste / debris is
prevented from entering the pit and a desilting /collection chamber may also be
provided at the ground to arrest the flow of finer particles to the recharge pit.
• The top layer of sand should be cleaned periodically to maintain the recharge rate.
• By-pass arrangement be provided before the collection chamber to reject the first
showers.

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 83
Roof Top Rain Water Harvesting Through Recharge Trench

• Recharge trenches are suitable for buildings having roof area of 200-300 sq. m. and
where a permeable stratum is available at shallow depths
• Trench may be 0.5 to 1.0 m wide, 1.0 to 1.5 m deep and 10 to 20 m. long depending upon
availability of water to be recharge
• These are back filled with boulders (5-20cm), gravel (5-10 mm) and coarse sand (1.5-2.0
mm) in graded form – boulders at the bottom, gravel in between and coarse sand at the
top so that the silt content that will come with runoff will be coarse sand at the top of the
sand layer and can easily be removed
• A mesh should be provided at the roof so that leaves or any other solid waste/debris is
prevented from entering the trenches and a desilting/collection chamber may also be
provided on ground to arrest the flow of finer particles to the trench
• By-pass arrangement be provided before the collection chamber to reject the first
showers
• The top layer of sand should be cleaned periodically to maintain the recharge rate

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 84
Roof Top Rain Water Harvesting Through Existing Tube wells

• In areas where the shallow aquifers have dried up and existing tube wells are tapping
deeper aquifer, roof to rain water harvesting through existing tube well can be adopted
to recharge the deeper aquifers
• PVC pipes of 10 cm dia are connected to roof drains to collect rainwater. The first roof
runoff is let off through the bottom of drainpipe. After closing the bottom pipe, the
rainwater of subsequent rain showers is taken through a T to an online PVC filter. The
filter may be provided before water enters the tube wells. The filter is 1 –1.2 m. in length
and is made up of PVC pipe. It’s diameter should vary depending on the area of roof, 15
cm if roof area is less than 150 sq m and 20 cm if the roof area is more. The filter is
provided with a reducer of 6.25 cm on both the sides. Filter is divided into three
chambers by PVC screens so that filter material is not mixed up. The first chamber is
filled up with gravel (6-10mm), middle chamber with pebbles (12-20 mm) and last
chamber with bigger pebbles (20-40 mm)
• If the roof area is more, a filter pit may be provided. Rainwater from roofs is taken to
collection/desilting chambers located on ground. These collection chambers are
interconnected as well as connected to the filter pit through pipes having a slop of 1:15.
The filter pit may vary in shape and size depending upon available runoff and are back-
filled with graded material, boulder at the bottom, gravel in the middle and sand at the
top with varying thickness (0.30- 0.50m) and may be separated by screen. The pit is
divided into two chambers, filter material in one chamber and other chamber is kept
empty to accommodate excess filtered water and to monitor the quality of filtered water.
A connecting pipe with recharge well is provided at the bottom of the pit for recharging
of filtered water through well

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 85
Roof Top Rain Water Harvesting Through Trench With Recharge Well

• In areas where the surface soil is impervious and large quantities of roof water or surface
runoff is available within a very short period of heavy rainfall, the use of trench/ pits is
made to store the water in a filter media and subsequently recharge to ground water
through specially constructed recharge wells
• This techniques is ideally suited for area where permeable horizon is within 3m below
ground level
• Recharge well of 100-300 diameter is constructed to a depth of at least 3.0 to 5.0 m below
the water level. Based on the lithology of the area well assembly is designed with slotted
pipe against the shallow and deeper aquifer
• A lateral trench of 1.5-to 3.0 m width and 10 to 30 m length, depending upon the
availability of water is constructed with the recharge well in the centre
• The number of recharge wells in the trench can be decided on the basis of water
availability and local vertical permeability of the rocks
• The trench is backfilled with boulders, gravels and coarse sand to act as a filter media for
the recharge wells
• If the aquifer is available at greater depth say more than 20 m, a shallow shaft of 2.0 to
5.0 m diameter and 3.0 –5.0 meters deep may be constructed depending upon
availability of runoff. Inside the shaft a recharge well of 100-300 mm dia is constructed
for recharging the available water to the deeper aquifers. At the bottom of the shaft a
filter media is provided to avoid choking of recharge well

(Source: Rainwater Harvesting Techniques to Augment Ground Water - 2003, Central


Ground Water Board)

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 86
Annexure 18
Water Quality Inlets

Water quality inlets (WQIs), also commonly called oil/grit separators or oil/water
separators, consist of a series of chambers that promote sedimentation of coarse materials
and separation of free oil (as opposed to emulsified or dissolved oil) from storm water. Most
WQIs also contain screens to help retain larger or floating debris, and many of the newer
designs also include a coalescing unit that helps to promote oil/water separation. WQIs
typically capture only the first portion of runoff for treatment and are generally used for
pretreatment before discharging to other best management practices (BMPs).

A typical WQI, as shown in following Figure, consists of a sedimentation chamber, an oil


separation chamber, and a discharge chamber. The basic WQI design is often modified to
improve performance.

Advantages and Disadvantages

WQIs can effectively trap trash, debris, oil and grease, and other floatables that would
otherwise be discharged to surface waters (Schueler, 1992). In addition, a properly esigned
and maintained WQI can serve as an effective BMP for reducing hydrocarbon contamination
in receiving water sediments. While WQIs are effective in removing heavy sediments and
floating oil and grease, they have demonstrated limited ability to separate dissolved or
emulsified oil from runoff. WQIs are also not very effective at removing pollutants such as
nutrients or metals, except where the metals removal is directly related to sediment removal.

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 87
Annexure 19

Availability of Rain Water Through Roof Top Rain Water Harvesting

Rainfall
100 200 300 400 500 600 800 1000
(mm)
Roof Top Area (Sq.m) Harvested Water from Roof Top (Cum)
20 1.6 3.2 4.8 6.4 8 9.6 12.8 16
30 2.4 4.8 7.2 9.6 12 14.4 19.2 24
40 3.2 6.4 9.6 12.8 16 19.2 25.6 32
50 4 8 12 16 20 24 32 40
60 4.8 9.6 14.4 19.2 24 28.8 38.4 48
70 5.6 11.2 16.8 22.4 28 33.6 44.8 56
80 6.4 12.8 19.2 25.6 32 38.4 51.2 64
90 7.2 14.4 21.6 28.8 36 43.2 57.6 72
100 8 16 24 32 40 48 64 80
150 12 24 36 48 60 72 96 120
200 16 32 48 64 80 96 128 160
250 20 40 60 80 100 120 160 200
300 24 48 72 96 120 144 192 240
400 32 64 96 128 160 192 256 320
500 40 80 120 160 200 240 320 400
1000 80 160 240 320 400 480 640 800
2000 160 320 480 640 800 960 1280 1600
3000 240 480 720 960 1200 1440 1920 2400

(Source: Rainwater Harvesting Techniques to Augment Ground Water - 2003, Central


Ground Water Board)

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 88
Annexure 20
Wind Towers

Wind towers are generally used in hot and dry climates for cooling. Wind towers operate in
many ways depending on the time of day wind availability. Wind towers work on the
principle of changing air density in and around the tower.

During daytime, hot ambient air comes into contact with the cool, top part of the tower and
gets cooled. Cool, dense air sinks through the tower and into living species (through vents
and openings). Increased wind velocity improves the performance of wind towers. During
the night the reverse takes place. Cool air comes in contact with the warm inner surface of
the tower. This air in turn gets warmed up, rises and is exhausted through openings. The
pressure difference thus created pulls the cool night air through the doors and windows into
the building.

Due to small storage capacities, sensible cooling may stop after several hours of operation on
hot summer days. In order to improve the efficiency of its operation, evaporating cooling is
used in conjunction with sensible cooling. Wind towers can bring about a difference of 10-
150C in arid climates. Wind towers can be combined with ground cooling to give better
performance and have been used effectively in several buildings in the Middle East and
West Asia.

It may be noted that wind towers are used only for summer cooling. Proper care should be
taken to close the vents and openings during the winter.

(Source: Manual on norms and standards for environment clearance of large construction projects,
MoEF)

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 89
Annexure 21
Checklist - Construction Phase
1. First Aid facility should be provided. Adequate drinking water and sanitary facilities
should be provided for construction workers. The safe disposal of wastewater and solid
wastes generated during the construction phase should be ensured.

2. Topsoil excavated during construction activities should be stored for use in


horticulture/landscape development within the project site.

3. Disposal of debris /muck during construction phase should not create any adverse
effect on the neighboring communities and be disposed taking the necessary
precautions for general safety and health aspects of people, only in approved sites with
the approval of competent authority.

4. Soil and ground water samples should be tested to ascertain that there is no threat to
ground water quality by leaching of heavy metals and other toxic contaminants from
the site

5. Any hazardous waste including biomedical waste should be disposed of as per


applicable Rules & norms with necessary approvals of the Pollution Control Board

6. The diesel generator sets to be used during construction phase should be low sulphur
diesel type and should conform to E (P) Rules prescribed for air and noise emission
standards.

7. Vehicles hired for bringing construction material to the site should be in good condition
and should conform to applicable emission standards

8. Storm water control and its re-use as per CGWA and BIS standards for various
applications should be planned

9. Separation of grey and black water should be done by the use of dual plumbing line.
Treatment of grey water by decentralized treatment

10. Fixtures for showers, toilet flushing and drinking should be of low flow either by use of
aerators or pressure-reducing devices of sensor based control.

11. Optimal use of glass to reduce the electricity consumption and load on air-conditioning.
If necessary, use high quality double glass with special reflective coating in window
should be planned

12. Roof should meet prescriptive requirement as per Energy Conservation Building Code
by using appropriate thermal insulation material to fulfill requirement.

13. Adequate measures to reduce air and noise pollution during construction keeping in
view of MoEF/CPCB norms

14. Rain water harvesting for roof run-off and surface run-off, as plan submitted should be
implemented

 
TOWNSHIPS & AREA DEVELOPMENT PROJECTS 90

You might also like