Professional Documents
Culture Documents
Ministry of Defence
LONDON: HMSO
© Crown Copyright 1996
Applications for reproduction should be made to HMSO, The Copyright Unit,
St Clements House, 2-16 Colegate, Norwich NR3 1BQ
ISBN 0 11 7724858
This document has been produced by Major R P Sheldon RE during his posting to
Defence Estate Organisation (Works), Airfields and Bulk Fuels Group. Notable
assistance has been received from White Young Consulting Engineers and Scott
Wilson Kirkpatrick and Partners. The publication has in part evolved from
documents produced previously by the Property Services Agency, the Royal
Engineers, United States Federal Agencies and the Australian Department of
Roads.
Foreword
This document is for the use of Top Level Budget Holders for application by their
Project Sponsors, Project Managers, Property Managers, Establishment Works
Consultants, Works Services Managers and other parties involved in the
provision of roads and hardstandings for tracked vehicles on the MOD estate.
This Defence Works Functional Standard was prepared under the patronage of
Headquarters Land Command. It supersedes the DOE/PSA document Technical
Instruction Civil Engineering (TICE) 48.
SO2 (W)
Airfields and Bulk Fuels Group
Defence Estate Organisation (Works)
St George's Barracks
Blakemore Drive
SUTTON COLDFIELD
West Midlands (0121) 311 3623
B75 7QB (0121) 311 2140
This Standard has been devised for the use of the Crown and its contractors in
the execution of contracts for the Crown. The Crown hereby excludes all liability
(other than liability for death and personal injury) whatsoever and howsoever
arising (including but without limitation, negligence on the part of the Crown, its
servants or agents) for loss or damage however caused where the Standard is
used for any other purpose.
Compliance with the contents of this document will not in itself confer immunity
from legal obligations.
iv
References
5. DWS Functional Standard Hot Rolled Asphalt and Coated Macadam for
Airfield Pavement Works (1995).
11. Design of paved areas for industrial usage - Concrete Society Technical
Report No 24 (1983).
14. Road Aggregates and Skidding - Roger Hosking—TRL State of the Art
Review /4 (1992).
Page
Foreword iv
References
Abbreviations vi
Contents vii
1 Introduction 1
1.1 Background 1
1.2 Aim 1
1.3 Scope 1
1.4 Functional Requirements 2
1.5 Special Requirements of Tracked Vehicles 2
2 Principles of Design 4
2.1 General 4
2.2 Route Selection 4
2.3 Site Investigation 4
2.4 Geometric Layout 5
2.5 Choice of Construction Type 5
2.6 Reinforced Concrete 5
2.7 Unreinforced Concrete 6
2.8 Concrete Block Paving 6
2.9 Mastic Asphalt 6
2.10 Hot Rolled Asphalt 6
2.11 Grouted Macadam 7
2.12 Unbound Roads 7
3 Reinforced Concrete 9
3.1 General 9
3.2 Design 9
3.3 Materials 10
3.4 Laying 11
3.5 Joints 12
3.6 Surface Finish 12
4 Unreinforced Concrete 15
4.1 General 15
4.2 Design 15
4.3 Materials 15
4.4 Laying 15
4.5 Joints 15
4.6 Bay Layouts 16
4.7 Surface Finish 17
7 Mastic Asphalt 26
7.1 General 26
7.2 Design 26
7.3 Materials 26
7.4 Laying 27
7.5 Joints 27
7.6 Surface Finish 28
8 Grouted Macadams 29
8.1 General 29
8.2 Design 29
8.3 Materials 29
8.4 Laying 30
8.5 Surface Finish 30
8.6 Trafficking 30
9 Unbound Roads 32
9.1 General 32
9.2 Design 32
9.3 Materials 33
9.4 Laying 33
9.5 Surface Finish 33
9.6 Construction Sequence 33
9.7 Maintenance Regime 35
A.1 Scope 39
A.6 Procedure 41
A.8 Precision 43
B.2 Apparatus 44
B.3 Samples 44
B.4 Procedure 44
B.4.1 Test Procedure 44
B.4.2 Test Criteria 45
B.4.3 Check Tests 45
List of Figures
1/1 Typical Kerb Details 3
3/1 Foundations for Rigid Pavements 10
3/2 Permissible Test Limits for Fine Aggregate 10
3/3 Gradings 1 and 2 for Sand 11
3/4 Permissible Test Limits for Coarse Aggregates 11
3/5 Expansion Joints Reinforced and Unreinforced Concrete Slabs 13
3/6 Contraction Joints 14
4/1 Warping Joints 16
4/2 Typical Bay Layout at Road Junction 17
4/3 Joint Layout at Turning Bays 18
5/1 Edge Restraint for Precast Concrete Blocks 20
5/2 Concrete Block Laying Patterns 22
6/1 Foundations for Flexible Pavements 23
6/2 Coarse Aggregate Properties 24
6/3 Fine Aggregate Properties 24
6/4 HRA Filler 25
6/5 Asphalt Temperatures 25
7/1 Mastic Asphalt Coarse Aggregate Grading 26
7/2 Mastic Asphalt Fine Aggregate Grading 27
7/3 Mastic Asphalt Bitumen Properties 27
7/4 Mastic Asphalt Composition 27
8/1 Grouted Macadams 31
9/1 Unbound Pavement Thickness 32
9/2 Typical Cross Section 34
9/3 Intervention Levels for Unbound Roads 36
A.4/1 Mass of Each Test Specimen for Sand 40
A.5/1 Mass of Each Test Specimen for Coarse Aggregate 41
B.4/1 Mixing Temperatures 45
1 Introduction
1.1 BACKGROUND
This Defence Estate Organisation (Works) [DEO (Wks)] Functional Standard is a
design guide for pavements subjected to the passage of tracked vehicles. The
information contained within the guide is largely based on an update of the old
PSA Technical Instruction Civil Engineering Number 48 (Reference 9) which it
supersedes.
The Ministry of Defence (MOD) is expanding its use of tracked vehicles in the UK
as a result of the reduction of forces in Germany. At the same time, most types of
tracked armoured fighting vehicles (AFVs) are becoming bigger and heavier with
more powerful engines. The consequence of these changes is a growing
requirement to provide adequate roads and hardstandings resistant to the
damaging effects of tracked vehicles.
This design guide does not cover short term or temporary requirements for
tracked vehicle crossings or roads, for which a variety of expedients including
Class 60 trackway, timber baulks or hardcore ramps would be appropriate. There
is ample guidance available for these situations in the Military Engineering
publications (References 1-4).
1.2 AIM
The aim of this functional standard is to provide guidance on the design and
construction of pavements to be used by tracked vehicles.
1.3 SCOPE
The design guide covers a wide range of subjects associated with the provision of
a new road or hardstanding. Thus, guidance is given on the essentials of road
design as well as the factors to be considered when siting a road or when
selecting a suitable type of construction. Further guidance is available from the
references quoted at the beginning of the guide or from DEO (Wks) ABFG.
May 1996
Roads for Tracked Vehicles 1 Introduction
The paved surface must protect the subgrade from damage caused by traffic. To
achieve this, the pavement must provide a suitable running surface and
sufficient additional strength to protect the underlying soil.
The pavement must protect the vehicles from damage caused by sharp edges or
large pieces of loose material and excessive bumpiness. This requirement is
closely related to the need to provide reasonable rideability both for the comfort
of vehicle occupants and to reduce wear and tear to the vehicles themselves.
The paved surface must provide a suitable texture and skidding resistance
particularly in wet conditions. It must be shaped either in camber or crossfall to
achieve good drainage to reduce the risk of skidding and to prevent spray which
can reduce visibility.
Among a number of other criteria that a pavement must meet, a key requirement
is the ability to resist damage in use.
AFVs operate with relatively low ground bearing pressures compared to the
pressures under a modern commercial vehicle tyre. This is based on the
requirement for AFVs to operate off road in a variety of soil and weather
conditions. However, the overall load imposed by a main battle tank (MET) such
as Challenger 2 is high.
Tracked vehicles roads should be provided with kerbs or other visible edge
restraints to assist vehicle drivers and to prevent damage to adjoining areas.
Current experience suggests that no kerb can withstand frequent contact with
tracks without sustaining damage. Consequently, any kerb should be considered
as a form of sacrificial barrier. There are essentially two possibilities—a precast
concrete kerb or a cast in situ kerb. If it is essential to prevent a tracked vehicle
from leaving the carriageway, then a large cast in situ kerb with a substantial
upstand will be required. It is generally cheaper to use standard precast kerbs to
BS 340 than to cast in situ. Figure 1/1 shows typical kerb details.
May 1996
Roads for Tracked Vehicles 1 Introduction
FLUSH KERBS
FLUSH KERBS MAYBE USED WHERE THERE IS NO FOOTWAY AND NO REQUIREMENTS OR
SURFACE WATER TO BE TAKEN TO GULLIES BUT LATERAL SUPPORT IS REQUIRED TO THE
CARRIAGEWAY.
[NOTE: FLUSH KERBS TEND TO ENCOURAGE DRIVERS TO LEAVE THE CARRIAGEWAY CAUSING
DAMAGE TO THE VERGES]
FLEXIBLE CONSTRUCTION
STANDARD CROSS-SECTIONS
May 1996
2 Principles of Design
2.1 GENERAL
All roads are designed to spread vehicle loading sufficiently so that the pressure
at foundation level is less than the maximum allowable bearing capacity of the
soil.
Where tracked vehicles routes have to cross other roads, the designer must
ensure that the tracked route is clearly and immediately obvious even to
personnel unfamiliar with the area. This may conflict with a military training
desire to make the tracked vehicle routes blend in with the landscape as much as
possible.
It is recommended that at least one trial pit should be dug per kilometre, with
augered holes at more frequent intervals. There should be further investigations
where changes in the ground are detected and where any structures such as
culverts are to be built.
May 1996
Roads for Tracked Vehicles 2 Principles of Design
The ability of tracked vehicles to negotiate very steep slopes means that
gradients steeper than 10% can be used, particularly for short sections. Indeed,
training needs may require special climbing sections with gradients of up to 35%.
Clearly, such slopes would be dangerous for two way traffic so they should not
form part of a major through route and they must be sited with great care.
For low speed roads it is normal practice to use circular curves and to dispense
with transition curves. However, it remains important that superelevation is
introduced on curves for design speeds of 30 mph or greater. Superelevation
assists tracked vehicles when cornering at speed so it is particularly important
when wheeled traffic shares the road. Roads should be widened for sharp bends
to allow tracked vehicles plenty of room to slew round.
A road across a training area can often be constructed satisfactorily from locally
supplied stone despite the fact that it requires significantly more maintenance
and does not provide a very smooth ride.
May 1996
Roads for Tracked Vehicles 2 Principles of Design
resistance, even in the more onerous situations, and it provides a smooth ride for
vehicles. It has proved to be a long lasting material when well built with a life of
up to 40 years.
RC roads can be built without any joints using extra reinforcement to form a
continuously reinforced concrete pavement (CRCP). Although it is more
expensive, CRCP construction should produce a high quality finish and should
produce a virtually maintenance-free road.
Where the underlying soil conditions are good, an unreinforced slab can be
considered and it is likely to be cheaper, though thicker, than a reinforced
alternative. It suffers from the same disadvantages as RC apart from being less
expensive.
Concrete blocks have a number of advantages over other surfacing materials, not
least being a lower overall cost. They require a firm level base, normally of
drylean concrete, for heavy duty use. They provide good rideability and excellent
skid resistance. Concrete blocks have proved to be resistant to thermal
movements, settlement and heavy wear.
May 1996
Roads for Tracked Vehicles 2 Principles of Design
the UK for all categories of traffic although tracked vehicles are not normally
permitted to use UK roads. Where HRA has been used for straight roads it has
performed fairly well under tracked vehicle loading.
DEO (Wks) has recently published a new Functional Standard (FS) entitled Hot
Rolled Asphalt and Coated Macadams for Airfield Pavement Works (Reference 5).
Although not written for roads, this standard provides an excellent basis for the
design of HRA for tracked vehicle roads. It should be appreciated that modern
aircraft loading with its high tyre pressures causes scuffing and wear of a similar
order of magnitude to a rubber track pad.
HRA has a number of advantages over alternative materials for tracked vehicle
roads. It is widely available in the UK, a large number of British contractors are
experienced in laying it and it can be obtained and laid at a competitive price. It
can be laid in small, awkward areas by hand but major areas are machine laid.
Repairs are comparatively simple and can be carried out by a large number of UK
contractors. It should be noted that HRA is rarely used outside the UK and so it
would not be recommended for overseas stations including Germany.
Although it would not be appropriate to use grouted macadams for long lengths of
road, due to their cost, they are well suited to use in small heavily trafficked
areas particularly workshops and garages where the possibility of fuel spills and
oil leaks is high.
The major disadvantages of grouted macadams are their relatively high cost and
irreparable failure of the pavement surface where the grouting is deficient. They
have been used successfully in the UK and abroad for areas subject to
particularly heavy use such as locked track turns on firing ranges.
However, the ability of a tracked vehicle to cross rough ground easily does not
mean that it does so without damage to the ground surface. In fact, even strong
natural subgrades suffer damage rapidly when trafficked by AFVs. This can be
seen on any tracked vehicle training area.
Unbound roads can provide excellent, economic roads for tracked vehicles
provided that they are properly designed and built and, most importantly, that
they are properly maintained. By definition, an unbound road is one where the
surface is not held together by bitumen or cement so the road surface will
deteriorate with natural weathering and by the action of traffic. The only way
that such a road can continue to serve satisfactorily without disintegrating is by
being maintained correctly. The maintenance regime following initial
construction is an integral part of the design and funding of an unbound road.
Where the ground conditions are suitable and only military vehicles are involved,
an unbound road should always be considered as an option for tracked vehicles.
This is because unbound roads can be built at a considerably lower capital cost
than a bound alternative.
May 1996
Roads for Tracked Vehicles 2 Principles of Design
This inherent flexibility can be most useful when planning new roads through
training areas. The client may not be certain beforehand which routes are going
to be most heavily used. A simple track layout can be built, monitored and altered
at comparatively low cost. If maintenance costs become too high, it is easy to
upgrade parts of the track network.
May 1996
3 Reinforced Concrete
3.1 GENERAL
A properly designed and constructed reinforced concrete road has a design life of
40 years. The ability of a road to survive for that length of time is critically
dependent on the quality of the materials used, good substructure including
drainage, good concrete detailing and carefully controlled placing, compacting
and finishing.
3.2 DESIGN
Reinforced concrete slabs for use by heavy tracked vehicles are recommended to
be not less than 200 mm thick and reinforced with long mesh reinforcement of
not less than 4.34 kg/m2. (C503 mesh to BS 4483).
Reinforced concrete slabs are recommended to be not more than 30 metres long
and 6 metres maximum width.
Reinforced concrete slabs trafficked only by smaller AFVs (ie. CVR(T) and 430
Series or similar) may have the slab thickness reduced to 175 mm.
In areas designed for particularly heavy use such as turnouts, the slab depths
should be increased by 25 mm.
For strength and durability under exposure to UK weather, the specified design
strength of the concrete is recommended to be 40 N/mm2 with a minimum cement
content of 320 kg/m3 and 5% ± 1% air entrainment for the full depth of the slab or
at least for the layer above the reinforcement. A maximum water/cement ratio of
0.45 is also recommended.
The precise mix design remains the responsibility of the supplier and
alternatives to the recommended cement content are permissible. Volume 1 of the
DoT Specification for Highway Works (Reference 8) gives rules for the use of
cement replacements and blends which would be appropriate for tracked vehicle
pavements. The use of pfa or microsilica may well produce a more dense and
durable concrete.
May 1996
Roads for Tracked Vehicles 3 Reinforced Concrete
Figure 3/1 gives guidance on foundations below rigid pavements. The thicknesses
should be treated with some caution. On frost susceptible subgrades, a minimum
thickness of 450 mm of non frost-susceptible material is recommended.
Subgrade CBR < 2% 2% < CBR < 5% 5% < CBR <15% CBR > 15%
[Optional Capping thickness] [600 mm] [350 mm] [150mm] [No capping]
3.3 MATERIALS
Capping material should be a granular material with a CBR of 15% or greater as
defined in the DoT Specification (Reference 8).
Wet Lean Concrete (C10) is a weak concrete which has to be mixed, placed and
compacted in the same way as a high strength concrete. It should have a
maximum water/cement ratio of 0.6 and a minimum cement content of 130 kg/m3.
C10 has a characteristic strength of 10.0 N/mm2 at 28 days.
Fine aggregate should be natural sand, crushed rock or gravel or a blend of these.
The properties of the fine aggregate should fall within the limits of Figure 3/2.
10 May 1996
Roads for Tracked Vehicles 3 Reinforced Concrete
Notes: (1) A total tolerance of up to 5% may be applied to the percentages in square brackets in the Figure. The
tolerance may be split up. For example, it could be 1% on each of three sieves and 2% on another.
(2) For crushed rock sand, the permissible limit on the 150 micron sieve may be increased to 20%.
The properties of the coarse aggregate should fall within the limits of Figure 3/4.
(1) Testing is required only if crushed rocks other than limestone are used. Reinforcement used in RC
roads should comply with the DoT Specification (Reference 8) which lays down the material
standards, sizes and spacing for reinforcing steel, tie bars and dowel bars.
3.4 LAYING
The concrete should normally be machine laid and compacted except on small
jobs where such a requirement would be uneconomic. The suitability of the plant
which the Contractor proposes to use should be proved by laying a sample slab
before the main concreting commences.
The trial slab should be checked by taking four 150 mm diameter cores and
testing them in accordance with BS 1881: Part 4. If any of the cores show
honeycombing as defined in the BS, or more than 10 voids having a dimension
greater than 3 mm in the top 40 mm, the trial slab should be deemed to have
failed and a new trial slab should be laid by the Contractor and tested at his
expense.
May 1996 11
Roads for Tracked Vehicles 3 Reinforced Concrete
The trial is set to ensure that the Contractor is able to produce consistently
strong, well compacted concrete, free from defects and capable of being finished to
the specified requirements. It should be noted that these requirements are no
more onerous than a Contractor would face when laying any concrete road to DoT
standards.
Concrete compliance should be tested in situ by taking a set of 2 cores from every
1,000 m2 of finished pavement (or part thereof).
3.5 JOINTS
Transverse and longitudinal joints should be as for normal concrete road
construction with transverse joints at 90° to the longitudinal axis of the
pavement. Dowel bars and tie bars should be incorporated. Where joints are
hand-finished, the edges should have a 5 mm radius arris. Details of joint
spacing can be found in Reference 8.
12 May 1996
Roads for Tracked Vehicles 3 Reinforced Concrete
May 1996 13
Roads for Tracked Vehicles 3 Reinforced Concrete
14 May 1996
4 Unreinforced Concrete
4.1 GENERAL
The general comments on reinforced concrete apply equally to unreinforced
concrete. There is no substitute for good design and good construction and if they
are done well, unreinforced concrete roads can also serve for 40 years.
4.2 DESIGN
Unreinforced slabs are normally constructed approximately 25 mm thicker than
equivalent reinforced slabs. Given the cost of buying and fixing reinforcing steel,
it is nearly always less expensive to use an unreinforced slab.
In order to prevent premature failure of the slabs from cracking, it essential that
they are cast in short, approximately square bays. For slabs less than 225 mm
thick, the bays should be no longer than 4 m. For slabs 225 mm thick or greater,
the bays should not exceed 5 m in length.
4.3 MATERIALS
Advice on material specifications is provided in Chapter 3. The only difference for
unreinforced slabs is the absence of reinforcing mesh. It is standard practice to
use tie bars and dowel bars with unreinforced concrete slabs.
4.4 LAYING
The procedures for laying unreinforced concrete should be identical to those for
reinforced concrete, including the production and testing of a trial slab and the in
situ testing of the pavement.
4.5 JOINTS
Joint details are similar to those for reinforced concrete except for the absence of
the reinforcement and the spacing of joints. Details can be seen in Figures 3/5
and 3/6.
An unreinforced slab requires warping joints. A typical warping joint detail can
be seen in Figure 4/1.
May 1996 15
Roads for Tracked Vehicles 4 Unreinforced Concrete
16 May 1996
Roads for Tracked Vehicles 4 Unreinforced Concrete
UNREINFORCED C O N C R E T E REINFORCED C O N C R E T E
NOTES
1. X = 6.0m, 6.75m OR
Y = 4.0m, 5.0m, 5.5m OR 6.0m
2. JOINT L A Y O U T S ARE T Y P I C A L O N L Y .
3. JOINT POSITIONS MAY BE VARIED IN ORDER TO POSITION THEM AT GULLIES, PROVIDED
T H A T THE MAXIMUM WIDTH AND LENGTH OF S L A B S IS NOT G R E A T E R THAN THE PRESCRIBED LIMITS.
RIGID C O N S T R U C T I O N
JOINT L A Y O U T A T JUNCTION OF A C C E S S
AND DISTRIBUTOR R O A D S
May 1996 17
Roads for Tracked Vehicles 4 Unreinforced Concrete
NOTES
1. W = 4.0m, 5.0m OR 5.5m
2. JOINT L A Y O U T S ARE TYPICAL ONLY
3. JOINT POSITIONS MAY BE VARIED IN ORDER TO POSITION THEM AT GULLIES, PROVIDED
THAT THE MAXIMUM WIDTH AND LENGTH OF SLABS IS NOT THAN THE PRESCRIBED LIMITS.
RIGID CONSTRUCTION
JOINT L A Y O U T AT TURNING B A Y S
18 May 1996
5 Concrete Block Paving
5.1 GENERAL
Concrete block pavements can be expected to have a design life of 20 years
providing that they are correctly designed and built and are properly maintained
when there are any signs of distress such as excessive deflection, loss of joint
sand etc.
DEO (Wks) FS 035 on Concrete Block Paving for Airfields contains useful design
guidance (Reference 7).
5.2 DESIGN
The general design process for concrete blocks follows the procedures for the
design of flexible pavements. It is generally agreed that a properly built layer of
80 mm thick blocks on a 35 mm bed of compacted sand is at least equivalent to
the structural strength of 50 mm of bituminous surfacing.
Concrete blocks for tracked vehicle use should be plain rectangular blocks 200 x
100 x 80 mm thick. The blocks should be laid on a sand bed of 35 mm nominal
depth. Research has shown that concrete block paving performs best with a sand
bed of 20- 40 mm.
The sand bed should be supported by a bound sub-base selected from the
following list:
a. DoT CBM 3.
b. DoT CBM 2.
c. Drylean concrete.
d. Bituminous basecourse.
5.3 MATERIALS
The concrete blocks should be to BS 6717: Part 1.
The sand bedding should be a sharp sand, or crushed rock fines, evenly graded
and with not more than 10% retained on a 5 mm BS sieve. Clay, silt and fine dust
content should not be more than 3% by mass.
May 1996 19
Roads for Tracked Vehicles 5 Concrete Block Paving
The jointing sand should be a clean, dry sand with 100% passing a 1.18 mm BS
sieve and up to 10% passing the 75 microns sieve.
The most common type of edge restraint uses in situ concrete of sufficient width
and depth to prevent outward movement of the blocks.
NOTE
A SIMILAR EDGE RESTRAINT IS
RECOMMENDED EVEN WHERE
THERE IS NO UPSTAND.
EDGE RESTRAINT
PRECAST CONCRETE BLOCKS
20 May 1996
Roads for Tracked Vehicles 5 Concrete Block Paving
5.5 LAYING
The sub-base should be laid accurately by a paving machine to a tolerance of
± 10 mm. It is essential that the sub-base is fully compacted to leave a smooth,
dense surface on which to lay the bedding sand.
The sand bed should be laid to a smooth finish to achieve an average depth of
35 mm after final compaction.
Blocks should be cut by sawing not by splitting. No cut blocks smaller than half a
block should be permitted. Manufactured half blocks should be used where
available. Mitre blocks are useful as starter blocks set against edge restraints.
See Figure 5/2 for laying pattern details.
After the blocks have been laid hand tight with average joints of 2 mm, they
should be compacted using a vibrating plate compactor to achieve a smooth even
surface.
After initial compaction, the joints should be sealed using a suitable sharp sand
which should be brushed into place. It is normal practice to compact the surface
again and to leave excess jointing sand on the surface for the first few days to
ensure that a good mechanical interlock is established.
May 1996 21
Roads for Tracked Vehicles 5 Concrete Block Paving
22 May 1996
6 Hot Rolled Asphalt
6.1 GENERAL
Hot rolled asphalt surfacing can be expected to have a design life of about 20
years before it must be replaced.
6.2 DESIGN
The design mix should achieve a stability of not less than 7 kN, a flow of not
more than 4.00 mm and a void content in the total mixture of between 2% and
4%.
The hot rolled asphalt should be laid on a basecourse of hot rolled asphalt to a
thickness of 60 mm. The lower layers of the pavement should consist of a bound
roadbase and a sub-base.
The sub-base should consist of either DoT Type 1 granular material or CBM 1.
Thicknesses will vary with the subgrade CBR as shown in Figure 6/1.
6.3 MATERIALS
The hot rolled asphalt courses should be produced in accordance with BS 594:
Parts 1 and 2 except where noted in a particular specification.
May 1996 23
Roads for Tracked Vehicles 6 Hot Rolled Asphalt
Aggregates should be clean, hard and durable and should not contain deleterious
materials in such a form or quantity to affect adversely the strength or
durability of the asphalt.
The coarse aggregate should be crushed rock. The coarse aggregate should be a
minimum of 40% of the total aggregate. It should conform to the limits given in
Figure 6/2.
Gravel n/a 30
Maximum aggregate crushing BS 812: Part 110 Crushed rock 30 30
value (%)
Gravel n/a 25
Maximum absorption (%) BS 81 2: Part 2 All except slag 2 2
Slag n/a 4
Stripping Appendix B All Not greater than 6
particles from a 150
particle test sample
should indicate evidence
of stripping
Minimum polished stone value BS 81 2: Part 114 Wearing course 45 n/a
Maximum sulfur content (%) BS1047 Slag n/a 2
The fine aggregate should be either sand or crushed rock or a blend of these. Sea-
dredged sand should not be used. The fine aggregate should conform to the limits
given in Figure 6/3.
The filler should be either OPC or crushed limestone or crushed rock. It should
meet the grading requirements set out in Figure 6/4.
24 May 1996
Roads for Tracked Vehicles 6 Hot Rolled Asphalt
Minimum Maximum
300 100
75 85 100
6.4 LAYING
Apart from small, irregular shaped areas the hot rolled asphalt should be
machine laid. The surface to receive the hot rolled asphalt should be swept clean
of debris and standing water.
The material should be mixed, delivered, laid and compacted within the material
temperature limits given in Figure 6/5.
The chippings should be evenly distributed at the rate of 7.5 kg/m to 10.0 kg/m
for 14 mm chippings or 10.0 kg/m to 13.0 kg/m for 20 mm chippings.
The chippings should then be rolled into the surface of the asphalt with a
suitable hand or mechanical roller.
The finished surface of the hot rolled asphalt should be measured using a 3 m
straightedge laid parallel to the centreline of the road. The maximum allowed
surface depression under the straight edge is 7 mm.
May 1996 25
7 Mastic Asphalt
7.1 GENERAL
Mastic asphalt surfacing can be expected to have a design life of about 20 years
before it must be replaced.
7.2 DESIGN
The mastic asphalt should normally be 40 mm thick. Exceptionally, where
particularly heavy wear is expected, the wearing course may be increased to
50 mm.
The sub-base should consist of either DoT Type 1 granular material or CBM 1.
Thicknesses will vary with the subgrade CBR as shown in Figure 6/1.
7.3 MATERIALS
The mastic asphalt wearing course should have coarse aggregate made with
crushed aggregate conforming to the grading shown in Figure 7/1. The aggregate
should be from a clean, hard igneous or siliceous rock with an aggregate abrasion
value (AAV) of not more than 12 when tested in accordance with BS 812.
Percentage by Mass
Passing BS Sieve Min Max
20mm 100
14 mm 95 100
3.35 mm 0 5
26 May 1996
Roads for Tracked Vehicles 7 Mastic Asphalt
Percentage by Mass
Passing BS Sieve Min Max
2.36mm 100
600 75 100
212 55 85
75 45 60
The overall composition of the mastic asphalt should fall within the limits of
Figure 7/4.
Percentage by Mass
Material__________________Min__________________Max
Coarse aggregate 45 50
Limestone powder 41.7 48.5
(45-60% passing 75 urn sieve)
Soluble bitumen 6.5 8.3
7.4 LAYING
The surface to receive the mastic asphalt wearing course should be swept clean of
debris and standing water.
7.5 JOINTS
Care should be taken to ensure that all joints are properly and truly made.
May 1996 27
Roads for Tracked Vehicles 7 Mastic Asphalt
The joints between sections of work should be made by warming the existing
mastic asphalt by the application of an excess of hot mastic asphalt which is
subsequently trimmed off to form an accurately level joint.
All projections into the road surface should be prepared before laying mastic
asphalt. Vertical surfaces of manholes, gully frames, boxes etc against which the
mastic asphalt is to abut should be cleaned and painted with a thin coat of hot
bitumen.
The finished surface of mastic asphalt should be kept flush with or not exceeding
3 mm above any projections. Where surfacing is to abut kerbs, these should also
be treated with hot bitumen.
The chippings should be evenly distributed at the rate of 7.5 kg/m to 10.0 kg/m
for 14 mm chippings or 10.0 kg/m to 13.0 kg/m for 20 mm chippings.
The chippings should then be rolled into the surface of the asphalt with a
suitable hand or mechanical roller.
28 May 1996
8 Grouted Macadams
8.1 GENERAL
Resin or grouted macadam surfacing can be expected to have a design life of
about 20 years before it must be replaced.
The grouted macadam should be one which is the subject of a current certificate
issued by the British Board of Agrement as being suitable for use by tracked
vehicles.
8.2 DESIGN
The grouted macadam should be laid 40 mm thick.
The grouted macadam should be laid on a basecourse of hot rolled asphalt or
dense bitumen macadam to a thickness of 60 mm. The lower layers of the
pavement should consist of a bound roadbase and a sub-base.
Where the roadbase is of bituminous construction it should be constructed of
dense bitumen macadam not less than 150 mm thick. A 100 pen binder should be
used with coarse aggregate of either crushed rock or slag aggregate.
Where a cement bound roadbase is chosen it should be laid as a composite base
consisting of a minimum of 150 mm of CBM 3 overlaid by a 60 mm course of
HRA. To control reflective cracking through the HRA, the thickness of CBM
should not exceed twice the overall thickness of overlying blacktop.
The sub-base should consist of either DoT Type 1 granular material or CBM 1.
Thicknesses will vary with the subgrade CBR as shown in Figure 6/1.
8.3 MATERIALS
The grouted macadam consists of a coated macadam of 14 mm or 20 mm size
open graded wearing course to BS 4987: Part 1 with 20-25% void content filled
with a high penetration proprietary grout.
Aggregates should be clean, hard and durable and should not contain deleterious
materials in such a form or quantity to affect adversely the strength or durability
of the macadam.
The coarse aggregate should be crushed rock. The coarse aggregate should be a
minimum of 40% of the total aggregate. It should conform to the limits given in
Figure 6/2.
The fine aggregate should be either sand or crushed rock or a blend of these. Sea-
dredged sand should not be used. The fine aggregate should conform to the limits
given in Figure 6/3.
May 1996 29
Roads for Tracked Vehicles 8 Grouted Macadams
8.4 LAYING
The Contractor should prepare and lay the grouted macadam in accordance with
the Agrement certificate.
The material is laid using conventional machinery except for the grouting
process. Once the coated macadam has been laid and compacted, the grout is
poured onto the open textured macadam and a vibrating roller, or plate
compactor, is used to achieve maximum penetration. The laying process is shown
in diagrammatic form in Figure 8/1.
The success of the grouting process should be confirmed using cores taken from
the completed pavement.
8.6 TRAFFICKING
Grouted macadams should not be subjected to traffic until the grout has fully
cured.
30 May 1996
Roads for Tracked Vehicles 8 Grouted Macadams
SUPPORT C O A T
BASE C O U R S E .
GROUTED M A C A D A M S
May 1996 31
9 Unbound Roads
9.1 GENERAL
An unbound or unsealed road can have an almost unlimited design life provided
it is properly maintained.
9.2 DESIGN
The design thickness of unbound roads for use by heavy AFVs is governed by the
subgrade CBR and frost resistance criteria. Design pavement thicknesses for
different CBRs are shown in Figure 9/1.
Thicknesses less than 450 mm are based on the subgrade being non frost
susceptible or that frost damage is acceptable to the user.
The pavement design of an unbound road should be checked for all user traffic
not just for tracked vehicles. However, the thicknesses given in Figure 9/1 exceed
the requirements for heavy commercial vehicles so there should be no problem
with mixed traffic.
Haul roads have to be designed with care since they are trafficked by heavily
laden vehicles. It is particularly important to ensure that construction traffic on a
partly built road is minimised as such loading can easily damage the subgrade.
32 May 1996
Roads for Tracked Vehicles 9 Unbound Roads
9.3 MATERIALS
The preferred material for the surfacing is a well graded crushed rock DoT Type 1
sub-base.
Thicknesses below the top 200 mm can be made up using DoT Type 2 material.
Where particularly poor ground is encountered, a capping layer may be used.
Material specifications are contained in the DoT Specification (Reference 8). A
typical design is shown at Figure 9/2.
9.4 LAYING
Materials should be spread evenly, without damaging the formation and
compacted to 100% of Optimum Dry Density.
The shaped and compacted surface should be free from roller marks, excess fines
or loose stone.
Clearance and site preparation which includes stripping and stacking of topsoil
for reuse. It is normal to remove tree roots to 300 mm below ground level.
Unsuitable fill material should be removed and stored separately for use in
landscaping.
Drainage which is often done in stages. It is essential to keep water away from
excavations so drainage is usually done in conjunction with earthworks. Side
drains and culverts should be completed early in the construction period to
improve land drainage and to prevent damage to the unfinished road.
May'1996 33
Roads for Tracked Vehicles 9 Unbound Roads
34 May 1996
Roads for Tracked Vehicles 9 Unbound Roads
After stripping, the formation should be checked for soft spots which should be
dug out and backfilled with suitable material. Where a substantial length of poor
material is encountered, it may well be more efficient for the earthworks
contractor to take another cut ie increase the depth of the pavement over the
section, than to dig out individual soft spots.
The sub-base should be placed and compacted in layers as soon as possible once
the formation has been checked. It is important that the subgrade is covered
early to prevent deterioration from exposure to the weather. Although speed is
important at this stage, it is essential to maintain the design shape of the cross
section at every level from formation upwards. A grader is recommended for use
after initial compaction to trim the bottom layer to shape.
The Contractor may choose to construct a road from one end or both or indeed he
may work on several sections concurrently. Without unnecessarily restricting the
Contractor's freedom of action, it is essential that activities are confined to as
narrow a strip as possible to build the road. The plan for haul roads should be
checked to see that unnecessary land take is minimised and that heavy
earthmoving plant and laden dump trucks do not run on incomplete sections of
road.
May 1996 35
Roads for Tracked Vehicles 9 Unbound Roads
Windrows, channels, Safe travelling speed less than >20% of any Safe travelling speed less Grade or
corrugations, soft spots, 85% of design speed section of road than 70% of design speed resurface
loose material
Wheel ruts and potholes Depth of 80 mm Any Defect depth of 150 mm Resurface
Insufficient crossfall Water ponds or 2% less than >20% of any Crossfall of 1% or less, Grade
design crossfall section of road water ponds
Excessive crossfall Crossfall of 6% or steeper >20% of any Crossfall of 8% or steeper Grade
Insufficient height above At natural ground level in rolling >20% of any Water ponds and surface is Heavy grade
surrounding ground country or 100mm in flat terrain section of road lower than natural ground and import fill
(measured at the point of the level (measured at the point
shoulder) of the shoulder)
36 May 1996
10 Special Surface Treatments
The materials can be considered in 2 main groups; those which involve the use of
a resin and those which use a shake-on product to the wet concrete. Typical of the
resin based products are materials like Addagrip and Flowshield which can be
used to rehabilitate old concrete slabs using a hot, thixotropic resin and sprinkled
aggregate. Shake-on products include MasterTop which involves the use of
special malleable iron aggregate to produce a surface capable of resisting metal-
on-metal scraping contact.
Guidance is available from DEO (Wks) ABFG on the use of these proprietary
products.
DEO (Wks) would welcome the opportunity to be involved in some trial areas,
using the latest fibres, which can be trafficked by tracked vehicles.
May 1996 37
Roads for Tracked Vehicles 10 Special Surface Treatments
Where there is a threat of significant fuel or oil spills onto a concrete block
surface it may be necessary to seal the surface with a proprietary sealant. MOD
has some experience of using ACM PAVSEAL to seal concrete block pavements on
airfields.
It should be noted that commercial filling stations have used untreated blocks
successfully for many years. It is recommended that sealants are not normally
used on concrete block pavements.
Salviacim and Hardicrete have been used in the past under PSA supervision.
Both materials performed satisfactorily when carefully constructed. They are
more expensive than other materials and should be used only when oil and
chemical resistance is a particular requirement.
MOD has some experience of using ASHOPOL 2000 and Cariphalte DM.
Modified binders cost considerably more than standard penetration binders. They
should only be considered for areas of exceptional wear.
Advice is available from DEO (Wks) ABFG on the appropriate use of these
specialist products. While some materials have performed well, manufacturer's
claims should always be treated with caution.
38 May 1996
Appendix A Magnesium Sulfate
Soundness Test
A.1 SCOPE
This method shall be followed to determine the soundness of aggregate by
subjecting the aggregate to cycles of immersion in a saturated solution of
magnesium sulfate followed by oven drying.
b. At least two brass or stainless steel mesh baskets for immersing aggregate
specimens, for fractions other than 10 to 14 mm. The baskets are to have
maximum dimensions of apertures not more than half the maximum aperture of
the sieve on which the specimen is retained, but not less than 150
May 1996 39
Roads for Tracked Vehicles Appendix A
distribution shall be recorded giving the percentage of the mass of the test
portion retained between each pair of sieves, together with that passing the 300
urn sieve, to the nearest whole number.
40 May 1996
Roads for Tracked Vehicles Appendix A
A.6 PROCEDURE
The procedure for each test specimen is as in BS 812: Part 121, clause 8,
replacing '10.0 mm sieve' in clause 8.6 by the sieve relevant to the lower size of
the aggregate fraction.
a. The mean of the soundness values found by the tests on specimens of the
two fractions immediately adjacent to it in size; or
c. The mean soundness value found by the tests on specimens of the two fractions
next but one adjacent to it if both these fractions were tested and the adjacent
fractions were not; or
d. The soundness value found by the test on a specimen of the fraction, either
larger or smaller, in this order of priority, most nearly adjacent to it.
May 1996 41
Appendix B Stripping Test
B.1 SCOPE
This method details the procedure to be followed to determine the resistance of
aggregates to stripping.
B.2 APPARATUS
Shallow tray(s).
Distilled water.
B.3 SAMPLES
The binder shall comply with BS 3690: Part 1 and shall be a representative
sample of the binder to be used in the plant mixtures.
The test shall be carried out on a separate sample of aggregate from each source
of supply. The sample shall be taken from the bin or stockpile at the quarry in
which the 10 - 6.3 mm size predominates. It shall be a representative sample of
the rock that is to be used in the plant mixtures.
B.4 PROCEDURE
B.4.1 Test Procedure
The test procedure is as follows:
44 May 1996
Roads for Tracked Vehicles Appendix B
b. The aggregate and binder shall be hand mixed until coating of the
aggregate is complete. If coating is incomplete after 5 minutes of mixing,
this procedure shall be repeated with a fresh specimen and an increased
proportion of binder. The binder shall be increased by steps of 0.5% by
mass of the specimen until a mix giving complete coating of the aggregate
is obtained.
c. The coated specimen shall be placed in one or more trays which have been
previously treated with a mixture of equal parts of glycerol and dextrin or
similar agent to prevent adhesion of the binder to the tray. Each particle
shall be completely separated from adjacent particles.
d. After standing for one hour, the coated specimen shall be covered with
distilled water at 18°C to 20°C and maintained at that temperature. After
immersion for 48 hours the water shall be decanted and the coated
specimen allowed to dry at air temperature.
e. The dried sample(s) shall then be examined, particle by particle while still
in the tray(s).
If any one of the further 3 tests fails, by indicating stripping in excess of the
limits described in sub-clause B.4.2, the aggregate will not be acceptable for the
particular mixture, and supplies from its source shall be rejected.
May 1996 45