You are on page 1of 4

REAL ESTATE

A GUIDE FOR PROJECT PARTNERS


LIFE CYCLE OF A CIVIL WORKS PROJECT
Steps Leading to a Civil Works Project

INTRODUCTION Infrastructure, Subcommittee on Water


Resources and Environment, for an authority for
the Corps to study the problem. The
During its lifetime, a Civil Works subcommittees then send a Docket letter to the
project passes through six basic phases: Corps requesting information about the study
reconnaissance, feasibility, pre- area, problems, and potential solutions. If we
construction engineering and design, have previously investigated and reported on
water resource problems in the area, the
real estate acquisition, construction and committee may adopt a study resolution to
operations and maintenance. provide the necessary authority to take another
look at the area and review the earlier study. If
The following six steps will initiate the process we have not previously investigated problems in
that results in a reconnaissance investigation: the area, legislation containing a study authority
1. A local community, or some particular is usually required. Your local Corps District
element of a community, perceives or staff can show you examples of previous study
experiences a water resources problem that is authorities, and may, upon request, help you
beyond their ability to solve. Examples of draft language that will provide the desired
problems are major flooding, and hazardous or authority.
inadequate navigation conditions in a harbor or 5. Once a Congressional study authority is
waterway; and/or degraded environmental available, the study will be assigned to the local
conditions. Corps District. The District may then, through
2. Community representatives, whom often may the normal Federal budget process, ask for
be or include members of the possible money to conduct the first phase of the study,
sponsoring agency, meet with their local Corps called the reconnaissance.
District staff to discuss available forms of help, 6. When Federal funds to conduct the
including Federal programs. Before we can get reconnaissance study are included in an annual
involved in providing assistance, we need two Energy and Water Development Appropriations
types of authority from the Congress: study Act, the local District may begin the Corps
authority and budget authority. A study study of the community's water resource
authority authorizes the conduct of an problems.
investigation into the identified problems. Once
a study authority is available, a budget authority RECONNAISSANCE PHASE
to spend Federal funds for the study can be
provided in an annual Appropriations Act. In
certain cases, we can provide technical The reconnaissance phase of the project
assistance or relief through some smaller studies normally requires less than twelve
or projects without further Congressional months to complete, but in no case can it
authorization.
3. If there is no available authority for us to
take longer than eighteen months. The
investigate the problem, the community work and level of detail during this phase,
representatives may contact their Congressional which is limited by the amount of time
delegation to request a study authority. available to complete the study, is funded
4. A member of Congress may then ask the entirely by the Federal government. The
Senate Committee on Environment and Public purposes of the study are:
Works, Subcommittee on Transportation and
Infrastructure, or the House of Representatives
Committee on Transportation and  To define the water resource

11
problems and opportunities, such as Costs of this work are normally cost
flooding or navigational needs; and to shared equally between the Federal
identify potential solutions, such as government and the Non-Federal
channels or levees. Sponsor. Major planning steps are:

To assess the potential sponsor’s level  Specify the problems and
of interest and support for the identified opportunities that are relevant to the
potential solutions. planned setting, and are associated with
the Federal objective and specific state
To decide whether to proceed into the and local concerns.
feasibility phase based on a preliminary
evaluation of Federal interest, economic  Inventory, forecast and analyze
costs and benefits, and environmental conditions in the area that are relevant to
impacts of potential solutions. the identified problems and
opportunities.
To develop a cost sharing agreement
between the government and the Non- Formulate alternative plans that would
Federal Sponsor for the feasibility resolve the identified problems and
phase, were it to proceed. realize identified opportunities.

If, for any number of reasons, further study is Evaluate the economic, environmental
not recommended, we will prepare a final report and other effects, both beneficial and
and no further Corps work will be conducted.
adverse, of alternative plans.
Key events during the reconnaissance phase are:
*Begin reconnaissance when the District  Compare alternative plans and their
obligates funds. effects.
*District Engineer signs reconnaissance report.
*Reconnaissance Review Conference (RRC).
This mandatory conference is to ensure that the
Select a recommended plan based on
report is consistent with current policies and the comparison of alternative plans. The
budgetary priorities, prior to release of the alternative plan with the greatest net
report to the public and prior to approval of the economic benefit, consistent with
reconnaissance report and feasibility cost protecting the nation’s environment
sharing agreement.
*The appropriate Non-Federal Sponsor’s (referred to as the National Economic
representative and the District Engineer sign the Development, or NED plan) must be
feasibility cost sharing agreement (if the report selected as the recommended plan. The
is certified to continue into the feasibility feasibility report forms the basis for
phase). authorization of project construction and
the Project Cooperation Agreement. A
FEASIBILITY PHASE
draft report is coordinated with Federal,
The feasibility phase commences upon state and local agencies prior to final
funding by the Non-Federal Sponsor and release.
the Federal government following a Key events during the feasibility phase are:
signed Feasibility Cost Sharing *Begin feasibility when the District receives
Agreement. The study process may funds.
require up to three years for production *Feasibility Review Conference (FRC). This
and an additional year to secure all mandatory conference is designed to seek
Washington level commitment to the project
necessary approvals for authorization. before the final feasibility report is submitted to

11
Washington for review. The purpose is to proportions as construction costs.
minimize the potential for significant
modification of the remaining studies and the The major documents prepared during this
final feasibility report recommendations after phase are the design memorandum (DM), which
the report is submitted for review. includes the results of technical engineering
*Public review of the draft feasibility report studies and design; the plans and specifications,
and environmental document (usually an which are the detailed drawings and instructions
environmental impact statement, EIS). for building the project; and the project
*Project management plan approved. cooperation agreement (PCA), which describes
*District Engineer signs final feasibility report. sponsor and Corps responsibilities for project
*Division Engineer's public notice issued (pre- construction, operation and maintenance.
construction engineering and design may begin;
see below). Key events during the phase are:
*Final environmental impact statement filed. *Begin pre-construction engineering and design
*Chief of Engineers report signed. (PED) phase when the District receives funds.
*Feasibility phase ends with the Assistant *Update Real Estate Plan (REP).
Secretary of the Army for Civil Works, *Design memorandum approved (DM).
ASA(CW) transmittal to Office of Management *Plans and specifications approved (P&S).
and Budget (OMB). *Project cooperation agreement (PCA)
*OMB clearance provided. prepared.
*Assistant Secretary sends report to Congress.
*Congress authorizes construction of a project. REAL ESTATE ACQUISITION PHASE
A Real Estate Plan (REP) will be prepared in
conjunction with the Feasibility Study. The Real estate acquisition is usually the
Real Estate Plan will include a description of most critical phase for the Non-Federal
the minimum real property interests (estates and Sponsor since it is largely your
acreage) needed for the project; a determination
regarding any facilities which must be
responsibility. The succeeding sections
relocated; an estimate of the number of address the issues and timing for this
displaced persons; a Baseline Cost Estimate for activity. The phase commences
lands and damages, relocation assistance formally upon delivery by the Real
payments, required substitute facilities, Estate Division of the final project real
mapping/surveying, title evidence,
administrative costs, and contingencies; and a estate drawings (see Section 3,
detailed schedule. paragraph 1) and ends after certification
of the acquisition by the local sponsor
PRE-CONSTRUCTION and the crediting process is completed (See
ENGINEERING AND DESIGN PHASE Section 3, paragraph 9). Real estate costs are
solely the responsibility of the Non-Federal
Sponsor but are creditable against the Non-
The pre-construction engineering and Federal Sponsor’s share of project costs.
design phase (PED) commences upon
authorization of project construction by Ordinarily, sponsors acquire any necessary real
Congress, which at times will overlap property interests, however you may request the
with completion of the feasibility phase. Corps to acquire them on your behalf. If we
elect to perform this service, you will be solely
Generally, the acquisition phase responsible for all costs of the requested
commences during this phase as well services and must provide sufficient funds in
and frequently runs concurrently with advance of our incurring any financial
construction phases as well. This phase obligation associated with this work. You are
will vary in length depending on project ultimately responsible for acquiring the
necessary real estate, seeking assistance when
scope. The focus is to complete all of needed, and seeing to it that all legal
the detailed technical studies and design requirements are met. In either case, title to
needed to begin construction of the real property interests is normally retained by
project. Costs are shared in the same the sponsor. The time required for real estate
acquisition varies from project to project

11
depending upon the acreage, number of tracts *Construction completed.
and ownerships, and experience and capability *Project accepted and transferred to you.
of sponsors. Advertisement of the construction
contract may proceed when we certify that you
have obtained adequate real property interests.
OPERATION AND MAINTENANCE
You typically need only provide the Corps with PHASE
authorization for entry and proof that you have
sufficient interest in the necessary lands. In Operation and maintenance begins when
addition you will be responsible for: the project is turned over to the Non-
*Preparing surveys, maps and legal
descriptions. Federal Sponsor and generally continues
*Performing individual tract appraisals. indefinitely. The ongoing costs
*Obtaining title evidence and performing associated with these activities are the
curative work. responsibility of the Non-Federal
*Conducting negotiations and eminent domain Sponsor, except for certain fish and
proceedings.
*Providing relocation assistance services and wildlife enhancement projects. An
processing relocation assistance claims and Operation and Maintenance Manual is
appeals by displaced persons. prepared for each project and delivered
*Performing or ensuring the performance of to the Non-Federal Sponsor prior to final
relocations of utilities and public facilities.
*Submitting lands, easements, rights-of-way,
project turnover. Periodic inspections
relocations, and disposal areas (LERRD)s credit will be made by the Corps of Engineers
requests for approval and documenting same. to ensure that the project is functioning
correctly and is being properly
CONSTRUCTION PHASE maintained. If it is determined that
design or construction deficiencies
The construction phase begins after should be corrected, the Corps of
Congress appropriates funds specifically Engineers may undertake further action.
for the initiation of the project and
contracts are awarded. Real estate
acquisition must be completed before
construction contracts are advertised.
The duration of the construction is
dependent upon the complexity and
extent of the project. This phase is
completed when the project is accepted
from the contractor and turned over to
the Non-Federal Sponsor for operation.
Costs are shared between the Federal
government and the Non-Federal
Sponsor according to the Congressional
project authorization.

Key construction events are:


*Construction funds are appropriated.
*PCA approved and executed.
*Construction contract advertised.
*Construction contract awarded.
*Various project-specific construction events,
such as: land clearing, rock placement, fill
placement on embankment, and test of water
release gates.
*Operation and maintenance manual approved.

11

You might also like