You are on page 1of 7

Design Documentation Guidelines Structural

Concept Design Phase


Design Process Deliverables Commentary

r r
Inputs: Drawings: 1. Costing only on square metre rate basis.
• Client briefing, including budget and time schedule.
r
• Sketch drawings. 2. Concept and preliminary design phases are often
• Geotechnical information on types of foundation systems.
r
combined on smaller projects.

r
Reports:
• Survey information, including legal and physical.
Architectural sketch concept drawings (e.g., bulk and location). r
• Sketch drawings where necessary within report. 3. Agree roles and responsibilities for all participants in

r

r
project procurement process.
• Structural concept design brief, including floor loadings.

r
• Site constraints, including planning and fire issues.
r
4. Discuss with client the requirements and programme
• Conditions of consents. • Key risks and assumptions.

r r
for client information and approvals.
• Existing building and site information/records. • Concept report outlines key issues and options considered.
5. Establish project procedures for communication,

r
Design: document issue, approvals, etc. Note: larger projects
• Structural type and form.
r
may have a project procedure manual or web-based
• Main gravity and lateral load resisting systems. document control systems.
• Floor system. r
r
6. Establish a design programme for key milestones and
• Ground retention systems. deliverables including design team co-ordination.
• Foundation system. r
• Façade support systems. r
• Roof support systems. r
• Identify structural scheme options. r
• Special project features concepts, (e.g., large canopies). r
• Design co-ordination of key elements with other disciplines. r
• Identify responsibility for control and set-out of dimensions. r
• Identify responsibility for design co-ordination and r
management.

DDG Structural New Zealand Construction Industry Council © August 2008 Page 45
Design Documentation Guidelines Structural

Preliminary Design Phase


Design Process Deliverables Commentary

r
Inputs:
r
Drawings: 1. Where appropriate carry out discussion with a
• Client approval of concept design, including ratification of • Drawings outline primary members as mark-ups of architectural ‘preferred’ contractor on construction methodology.
cost estimate.
r
drawings (1:200).
2.* Consultation with Building Consent Authority is
• Preliminary fire engineering (where appropriate).
r
• Proposed primary framing. recommended on key aspects of the design that may

r
• Preliminary wind studies (where appropriate).
r
• Prelim. sizes of primary members only with reinforcing as kg/m3 be considered outside the ‘Acceptable Solution’, and
• Preliminary acoustic advice (where appropriate).
r
and steel as kg/m. unusual/contentious issues.

r
• Preliminary geotechnical report, including preliminary 3. Cost estimates at this stage generally cannot be on
• Preliminary foundation layout.

r
design parameters.
r
full elemental basis, as secondary elements are not
• Design programme. • Indicative structural connection types.

r
well defined.
• Outline system for secondary elements.

r r
Design: 4. Contribute to value management session, if required.
• Evaluate and select primary structural systems. • Outline durability/coating systems.
r r
5. Agree the scale of drawing deliverables for each
• Define grid layout (with architect).
r
• Indicative surface finish for exposed concrete. phase according to project type.
• Preliminary analysis to establish critical member sizes for
• Critical details that may have significant cost implication. r 6. A specialist façade design consultant may need to be

r
primary elements.
engaged, if the façade system is particularly complex

r
• Define key serviceability criteria. • Proposed primary elements of strengthening for existing
buildings (where appropriate). or demanding.

r
• Design co-ordination of key elements with other disciplines.

r
• Define floor to floor heights. Specifications:
• Preliminary assessment of floor vibration and building r • Outline specification of key structural elements.
movement.
r
r
Reports:
• Preliminary assessment of primary members of existing
buildings (where appropriate). • Design brief, including fire protection requirements for

r
structural members.

r
• Address durability requirements.
r
• Design features (options) report, with recommended option to
• Preliminary input to Architect on ‘architectural’ elements.
take to developed design.
• Identify high risk and/or high cost elements in structure.

* Amended August 2008

DDG Structural New Zealand Construction Industry Council © August 2008 Page 46
Design Documentation Guidelines Structural

Preliminary Design Phase continued


Design Process continued Deliverables continued Commentary

• Define key elements of ground retention system r • Outline of elements not covered in preliminary design drawings or r
(if required). design features report.
• Define design parameters for façade systems. r r
r
• Define assumed construction methodology governing design
• Incorporate additional structural implication of fire and (where appropriate).
acoustic requirements.
r
r
• Highlight ‘significant’ buildability issues and significant/unusual
• Assess implication of dynamic motion of building health and safety issues arising from the structure.
services equipment.
• Consider buildability of primary structural system, including r
significant health and safety issues during construction.
• For unusual structures or existing structures where stability r
may be affected by the sequence of construction, consider
significant health and safety issues.
• Assess maintenance requirements of structural components, r
including health and safety issues.
• Coordinate relevant design information between disciplines. r

DDG Structural New Zealand Construction Industry Council © August 2008 Page 47
Design Documentation Guidelines Structural

Developed Design Phase


Design Process Deliverables Commentary

r
Inputs: Drawings: 1. Separate primary reinforcement from secondary
• Client approval of preliminary design, including ratification • Drawings (1:100 plans) defining all primary framing members, r stirrup or ties in quantity estimates.
of the cost estimate. with reinforcing as kg/m3.

r r
2. Cost estimates at this stage can be produced by
• Final geotechnical report. • Layout and size of secondary framing members (e.g., lift, stairs, quantity surveyor on elemental basis, with secondary

r
canopies, and platforms).

r
• Final wind report (if required). elements estimated on typical details.

r
• Generic reinforcing details for typical primary elements. 3.* Developed design generally provides the level
r
• Final fire report.
• Typical connection details for primary elements. of documentation to define the scope of all

r r
Design: building elements.
• Define elements covered by proprietary design (e.g., precast floor
• Determine sizes of all primary and most secondary and piling). 4.* Where appropriate carry out discussions with a
structural members; however, there may be some
architectural and services secondary support members not ‘preferred’ contractor on construction methodology.

r
Specifications:
defined at this stage.

r
• Preliminary technical specifications, including durability and 5.* Consultation with Building Consent Authority may be
• Generic connection details. serviceability issues. helpful on key aspects of the design that may be

r
considered outside the ‘Acceptable Solution’, and
• Agree serviceability performance criteria with client

r
Reports: unusual/contentious issues.
(e.g., floor vibration, interstorey drifts, etc).

r
• Updated design brief, including fire protection requirements for
• Structural input to architectural elements. structural members.
• Confirm building movements with the design team. r • Updated design features report, including serviceability and r
r
maintenance issues.

r
• Incorporate likely erection/construction requirements
(where appropriate), including consideration of significant/ • Define key risks and assumptions, including erection/buildability
unusual health and safety issues arising from the structure. and significant/unusual health and safety issues arising from

r
the structure.

r
• Key support details for façade elements.

r
• List elements where the scope has not been fully defined
• Structural support requirements for building maintenance elsewhere in the documents.

r
systems (e.g., BMU and abseil anchor points).

r
• Highlight significant health and safety issues.
• Coordinate relevant information with other disciplines.

* Amended August 2008

DDG Structural New Zealand Construction Industry Council © August 2008 Page 48
Design Documentation Guidelines Structural

Detailed Design Phase


Design Process Deliverables Commentary

r r
Inputs: Drawings: 1. Detailed design generally provides a level of
• Client approval of completed developed design, including • Drawings defining all structural elements, including plans, documentation to clearly define the design of all
ratification of the cost estimate. elevations, sections and details, with adequate cross-referencing. structural elements. Design details should be
• Define all connections by either defining specific connection r coordinated with other disciplines. However, the

r
Design:
details or referencing to industry standard connection details documents produced in this phase may not directly be
• Complete the design and coordination of all structural (e.g., HERA connection details) or specifying forces for a propriety able to be ‘built’ from.
elements, including connection details, except for connection system.

r
elements that can be adequately covered by non-specific 2. Structural drawings should dimension the main
design codes. • Construction sequences and positions of control/construction joints.

r r
building grids, critical structural elements, and other
• Address serviceability and maintenance criteria in • Includes stairs, plant platforms and façade system support. elements that are the direct responsibility of the

r
the design. structural engineer.

r
• Reinforcing details defined (see commentary).

r
• Highlight significant/unusual health and safety risks 3. Reference the architectural plans or other disciplines
• Precamber/set established for members.

r
arising from the structure that were identified through the for other dimensions (unless agreed otherwise).
design process (if any).

r
• Include seismic and gravity support of ceiling/partition systems
4. HERA report DR4-106, Structural Steelwork
• Co-ordinate relevant information with other disciplines. (optional).
documentation ‘Specification’, sections vi, vii, and ix

r
Specifications: outline documentation details that need to be
• Detailed specifications for each structural trade. addressed in the working drawings and specifications.

• Performance specifications where appropriate, including r 5. Design and documentation of secondary architectural
performance criteria for proprietary design. elements are generally shown on the architect’s
• Method statements for critical construction processes governing r drawings; the structural engineer will have input
design. where requested by the architect.

• Design loadings for design of proprietary non-structural elements r 6. Reinforcing details defined means that all reinforcing
e.g., glazing, seismic bracing of services. required to construct the project is defined on the
• Define deliverables from contractor e.g., producer statements, shop r drawings, in quantum and size, such that shop drawings
and/or bar bending schedule can be produced by others
drawings, and testing requirements.
without further additional information.

DDG Structural New Zealand Construction Industry Council © August 2008 Page 49
Design Documentation Guidelines Structural

Detailed Design Phase continued


Design Process Deliverables continued Commentary continued

• Coating requirements for structural elements that are not r 7. The level of design detail shown on drawings in this
addressed by the architect or other disciplines. phase, particularly for concrete and masonry
• Define required tolerances where different from industry standards. r elements, varies in the industry between regions,
building types and procurement methodologies. A

r
Reports: * major factor is the capability of the local building
• Design Features Report including explanation of structural systems industry to efficiently provide the construction phase
and load paths, design standards used, key design parameters documentation. The level of detail outlined in these
and assumptions.
guidelines is appropriate where the contractor has
the skills and resources to efficiently provide
construction phase documentation. For some
projects, a greater level of detailing may need to be
produced by the design consultant. The appropriate
level of detailing required should be agreed with the
client prior to the commencement of the project.
8. Define in the appropriate specification the significant/
unusual health and safety risks that arising from the
structurewere identified in the design.
9. The contractor is responsible for managing health
and safety risks during the construction phase.
10.*Detailed design documentation is recommended for
building consent submissions.

* Amended August 2008

DDG Structural New Zealand Construction Industry Council © August 2008 Page 50
Design Documentation Guidelines Structural

Construction Design Phase


Design Process Deliverables Commentary

r r
Inputs: Drawings: 1. Before the commencement of construction drawings
• Construction programme and methodology, including • Drawings (incl. shop drawings and rebar schedules) on an elemental the following need to be in place; contract details
craneage or access restrictions. basis, including position, dimension, materials and finish of all details, confirmed and tender accepted; sub-contract

r
including relevant material specifications (steel, timber, precast, etc.).
r
• Client approved (‘for construction’) drawings and agreements confirmed; and owner supplied
specifications. • Site management plans and/or method statements defining the components available.

r
construction sequencing and temporary erection requirements.
r
• Design and performance requirements for propriety elements. 2. Deliverables contain sufficient details for elements to
• Details of the temporary works.
r
be manufactured/constructed without reference to

r
Design: • Revision of drawings, details and specifications arising from contract other documents, i.e. ,‘the details have co-ordinated
• Design of proprietary systems, e.g., flooring, glazing, plant agreement, building consent, and construction requirements. the relevant design information across all disciplines
support, etc.

r
and can be built from’.

r
Concrete:
• Detailed co-ordination required with other disciplines, site 3. Final determination of some dimensions may be
•* Precast concrete shop drawings generally as defined in Precast
conditions, proprietary elements, erection requirements, and NZ Code of Practice and AS/NZS1100.

r
dependent on proprietary design of non-structural
shop details.

r
•* Proprietary system layout drawings and connection details. elements (e.g., mechanical services duct sizes). Such

r
• Prepare structural construction sequence, temporary erection proprietary design may need to be advanced to
and heath and safety plans. •* Embedded items and penetrations defined and located.

r r
enable structural dimensions to be completed.
• Determine the impact of temporary erection loads and •* For non-standard conditions the following are to be provided
4. The constructor is responsible for managing health
r
construction sequence on structural members and where applicable.
and safety risks during the construction phase.

r
connections. • formwork
r
r
• Check the design of structural members and connections for • propping and bracing 5.* Significant changes or clarifications to the structural
temporary construction conditions and loads, and redesign • scaffolding and access work in relation to the initial building consent
if required. documentation should be submitted to the Building
r r
Steel:
• Liaise with the design and construction teams to coordinate Consent Authority and if necessary an amended
any revisions to the detailed design. • Shop drawings generally as defined in Australian Detailer Handbook building consent obtained to cover these changes
ASDH101 or the American Institute of Steel Retailers Guidelines.

r
Review:
• Review shop drawings, technical specification, and construction
method statement submissions for consistency with detailed design.

* Amended August 2008

DDG Structural New Zealand Construction Industry Council © August 2008 Page 51

You might also like