ltem Description Qty Unit Rate Amount

CONSTRUCTION OF 6-UNIT CLASSROOM BLOCK


AT DWOMO PRIMARY SCHOOL

VALUATION FOR IPC NO. 1

BILL NO. 2

(As measured on site)

Site Preperation

Clear site of all bushes, shrubs and undergrowth and


A. cut down trees and remove from site and burn 1500 m2 3,500.00 5,250,000.00

Cut using bulldozer existing terrain to approved


formation level, transport and deposit excavated
B. materials at sites as directed for filling 750 m3 35,000.00 26,250,000.00

Excavate foundation trench not exceeding 1.5 deep


C. commencing from strip level 76 m3 55,000.00 4,180,000.00

D. Ditto column base 28 m3 60,000.00 1,680,000.00

Backfill and compact selected excavated material


E. around foundation aid bases 54 m3 30,000.00 1,620,000.00

TO COLLECTION 38,980,000.00
ltem Description Qty Unit Rate Amount
2/1

A. Remove surplus excavated material from site 50 m3 30,000.00 1,500,000.00

Hardcore filling

Bed of approved imported hardcore under bed well


rammed and consolidated in layers not exceeding
B. 150mm thick 253 m2 120,000.00 30,360,000.00

Concreteworks
Plain insitu concrete (1:4:8-38mm agg) in:-

C. 50mm thick blinding 29 m2 60,000.00 1,740,000.00

Plain insitu concrete (1:3:6-38mm agg) in:-

D. Foundations 19 m3 950,000.00 18,050,000.00

E. 150mm Thick bed 440 m2 118,750.00 52,250,000.00

Reinforced insitu Vibrated Concrete(1:2:4-19mm agg)


in:-

F. Column bases 7 M3 1,250,000.00 8,750,000.00

G. Columns 2 M3 1,250,000.00 2,500,000.00

Mild Steel bar

H. 12mm Diameter bar in columns bases 537 kg 13,000.00 6,981,000.00

J. 12mm Diameter bar in column 418 kg 13,000.00 5,434,000.00

K. 6mm Diameter bar in links and strip 47 kg 16,000.00 752,000.00

Sawm formwork to:-

M. Vertical sides of columns 43 m2 65,000.00 2,795,000.00

N. Edges of floor bed 150mm wide 129 m 9,750.00 1,257,750.00

TO COLLECTION 132,369,750.00
ltem Description Qty Unit Rate Amount

2/2

BLOCKWORK
Solid sandcrete blockwork in cement and sand (1:3)
mortar

A. 150mm wall 169 m2 105,000.00 17,745,000.00

B. 225mm wall 102 m2 120,000.00 12,240,000.00

TO COLLECTION 29,985,000.00

TO COLLECTION

Page No. 2/1 38,980,000.00

Page No. 2/2 132,369,750.00

Page No. 2/3 29,985,000.00

SUBSTRUCTURE
To Summary ¢ 201,334,750.00
ltem Description Qty Unit Rate Amount

2/3

SUPERSTRUCTURE

CONCRETEWORKS

Reinforced insitu vibrated concrete (1:2:4-19mm agg)


in:-

A. Columns 6 m3 1,250,000.00 7,500,000.00

B. Lintel level Beams 5 m3 1,250,000.00 6,250,000.00

Reinforcement
Mild steel bar reinforcement to BS 4449

C. 12mm Diameter mild steel bar in columns 696 kg 13,000.00 9,048,000.00

D. Ditto Lintel level 490 kg 13,000.00 6,370,000.00

E. 76mm Diameter rod in links and strips 93 kg 16,000.00 1,488,000.00

Formwork
Sawn formwork to:-

F. Vertical sides of columns 126 m2 65,000.00 8,190,000.00

G. Sides and soffit of lintel level beams 64 m2 65,000.00 4,160,000.00

CONCRETEWORKS
To Summary ¢ 43,006,000.00
ltem Description Qty Unit Rate Amount

2/4

BLOCKWORK
Sandcrete blockwork in cement morter (4:4)in:-

A. 150mm Thick solid walls 428 m2 105,000.00 44,940,000.00

BLOCKWORK
To Summary ¢ 44,940,000.00

SUMMARY

SUBSTRUCTURE 201,334,750.00

CONCRETEWORKS 43,006,000.00

BLOCKWORK 44,940,000.00

289,280,750.00

Add:- Preliminaries 23,142,460.00

TOTAL:- ¢ 312,423,210.00
ltem Description Qty Unit Rate Amount

2/5
ltem Description Qty Unit Rate Amount
ltem Description Qty Unit Rate Amount
ltem Description Qty Unit Rate Amount

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
89,880,000.00