You are on page 1of 15

MOBILIZATION PLAN

CAM-D DEW Line Environmental Remediation SIMPSON LAKE, NUNAVUT

Presented to

Public Works and Government Services Canada

Review: January 2010

KUDLIK CONSTRUCTION LTD. P.O. BOX 727, 1519 FEDERAL ROAD IQALUIT, NUNAVUT

MOBILIZATION PLAN
CAM-D DEW Line Environmental Remediation SIMPSON LAKE, NUNAVUT

January 2010

TABLE OF CONTENTS
PAGE 1. 2. INTRODUCTION ................................................................................................................................1 MOBILIZATION STRATEGY ..........................................................................................................2 2.1 2.2 2.3 2.4 3. 3.1 3.2 4. 4.1 4.2 5. 6. 5.1 PRE-MOBILIZATION.........................................................................................................................2 MOBILIZATION ................................................................................................................................2 FUEL MANAGEMENT .......................................................................................................................2 SCHEDULE .......................................................................................................................................3
EQUIPMENT TO BE TRANSPORTED FROM SHEPHERD BAY ...............................................................4 EQUIPMENTS TO BE TRANSPORTED FROM KUGAARUK....................................................................5

EQUIPMENT AND MATERIAL .......................................................................................................4

MOBILIZATION ROUTES................................................................................................................6 MOBILIZATION FROM SHEPHERD BAY ...........................................................................................6 MOBILIZATION FROM KUGAARUK ..............................................................................................7 SHEPHERD BAY CAMP FACILITIES DESCRIPTION ...................................................................8

SHEPHERD BAY CAMP FACILITIES ............................................................................................8 CAM-D CAMP AND STAGING AREA LOCATION ...................................................................10

APPENDIX 1: Gant chart schedule

Mobilization Plan

Remediation of CAM-D DEW Line Site Simpson Lake, Nunavut

1.

INTRODUCTION
The CAM-D DEW line site remediation project was awarded to Kudlik Construction Ltd. in December 2008. CAM-D is located in the middle of the Boothia Peninsula (Nunavut), approximately 4.5 km south of Simpson Lake and approximately 120 km southwest of Taloyoak in Nunavut. Since no road exists between the coast and the DEW line station, all project equipments must be mobilized from Shepherd Bay to CAM-D during winter by CAT train. In August 2009, heavy equipments, camp facilities, materials and all consumables were delivered by sealift on the Shepherd Bay coast, located about 70 km northwest of CAM-D. The actual document presents the mobilization plan. It describes the mobilization

methodology, the equipment and presents the activities schedule. Figure 1: Localization map

N Taloyoak

Shepherd Bay CAM-D Site

Boothia Peninsula

1 Kudlik Construction Ltd.

Mobilization Plan

Remediation of CAM-D DEW Line Site Simpson Lake, Nunavut

2.

MOBILIZATION STRATEGY
Most of the equipments and materials required to achieve the contract activities will be transported from Shepherd Bay. However, some of our equipments are located in Kugaaruk and they will be transported to CAM-D once the mobilization from Shepherd Bay will have been completed.

2.1

PRE-MOBILIZATION
A pre-mobilization crew will be sent to Kugaaruk at the beginning of March 2010. Their role will be to travel by snowmobile from Kugaaruk to Shepherd Bay in order to open the mobilization camp, dewinterize the equipment, prepare the runway, mark and open the route between Shepherd Bay and CAM-D. The emergency shelter will be installed halfway, as shown in Figure 2. The temporary camp will be setup at CAM-D. We anticipate that all pre-mobilization activities will be completed within two weeks.

2.2

MOBILIZATION
Once the pre-mobilization activities will have been completed, the mobilization crew will be sent to Shepherd Bay. The CAT Train between Shepherd Bay and CAM-D will be initiated. The mobilization activities will be performed on 24 hours per day. For most of the equipment to be transported, we anticipate that each back and forth trip between CAM-D and Shepherd Bay will be completed within 20 hours. About 60 trips between Shepherd Bay and CAM-D will be required. Considering that we are using 3 tractors pulling 2 sleighs most of the time, the mobilization from Shepherd Bay should be completed within 4 weeks. This schedule includes 5 days for time lost due to weather conditions or mechanical breakdowns. Once the mobilization will have been completed from Shepherd Bay, the camp will be closed and most of the employees will be demobilized. However, we will keep a small crew in order to mobilize two dump trucks and miscellaneous equipments from Kugaaruk. This operation should last about 5 days.

2.3

FUEL MANAGEMENT
A total of 2928 drums of arctic diesel were delivered to Shepherd Bay. We estimate that about 170,000 litres of diesel will be required for the mobilization activities, which

2 Kudlik Construction Ltd.

Mobilization Plan

Remediation of CAM-D DEW Line Site Simpson Lake, Nunavut

represents 830 barrels. For the first cleanup season at CAM-D, we anticipate that 266,000 litres of fuel, including 20% for contingency, will be needed. The balance of the fuel drums will be left at Shepherd Bay. They will be transported to CAM-D during the contaminated soils demobilization in March 2011. A total of 80 gasoline drums were transported to Shepherd Bay. The gasoline will be mainly used for snowmobile, ATVs and small tools. All barrels will be transported to the CAM-D staging area. During the mobilization, the heavy equipments will be refilled at CAM-D from a mobile tank having a capacity of 18,000 litres. The tank is equipped with a dispensing unit as well as a vacuum pump. The vacuum pump will be used to refill the mobile tank from the fuel drums. One ISO tank having a capacity of 23,000 litres will be transported nearby the mid-route safety shelter. It will be used as an intermediate refilling station for tractors. The second ISO tank will be transported at the CAM-D staging area. It will also be used as a refilling station as well as for the temporary camp needs. The 1300 fuel drums and the 80 gasoline drums will be transported gradually with other materials during the mobilization. The balance of the 1380 drums that cant be transported with regular loads will be brought at the end. All barrels are strapped four by four on a wooden pallet. They will be stored at the CAM-D staging area, stacked two rows high.

2.4

SCHEDULE
The Gant chart schedule presented in Appendix 1 includes the pre-mobilization and the mobilization activities.

3 Kudlik Construction Ltd.

Mobilization Plan

Remediation of CAM-D DEW Line Site Simpson Lake, Nunavut

3.

EQUIPMENT AND MATERIAL


All materials and equipments will be transported on sleighs pulled by tractors. A total of 8 steel sleighs were fabricated for this purpose. Three (3) tractors CAT Challenger 855D equipped with 36 wide tracks will be used to pull the sleighs. One tractor is equipped with a 4 metres wide adjustable blade and a 25 metric tons winch. A snow groomer attachment was fabricated in order to maintain the route in good conditions.

3.1

EQUIPMENT TO BE TRANSPORTED FROM SHEPHERD BAY


All equipments brought to Shepherd Bay, except the mobilization camp and about 1000 fuel barrels, will be transported to the CAM-D staging area. The following table is showing the equipments to be transported from Shepherd Bay:

Equipments to be transported from Shepherd Bay to CAM-D


Qty 2 2 1 18 1300 78 1 1 1 1 1 1 1 54 1 2 1 1 5 1 ATV ATV Compactor Culverts Drums Drums Excavator Excavator Flatbed Grader Foldable building Loader Loader Marine container Marine container Off-road dump truck Off-road trailer Off-road trailer Pickup crew cab Screener Description Honda foreman 500 Gator SD 70 Closed cab Various diameters, 3 bundles Diesel Gasoline PC 300 LC-6 + 3 buckets + ripper PC 400 LC-8 + 3 buckets+ ripper + Dolly Champion 740 Habitaflex WA-500 + bucket & forks WA-420 + bucket & forks 20x8x8 40x8x8 Komatsu HM300-2 Fuel tank and vacuum pump, 18,000 l Water tank 10,000 l F350 4x4, diesel Power Screen Titan

4 Kudlik Construction Ltd.

Mobilization Plan

Remediation of CAM-D DEW Line Site Simpson Lake, Nunavut

1 2

Tank 4,000 litres Tank 23,000 litres

Aboveground horizontal dyke tank ULC-S653 ISO tank

3.2

EQUIPMENTS TO BE TRANSPORTED FROM KUGAARUK


The following table is showing the equipments to be transported from Kugaaruk:

Equipments to be transported from Kugaaruk to CAM-D


Qty 2 1 1 1 Off-road dump truck Drilling rig Air compressor Misc equipments Description Volvo A-25 Worthington

5 Kudlik Construction Ltd.

Mobilization Plan

Remediation of CAM-D DEW Line Site Simpson Lake, Nunavut

4.
4.1

MOBILIZATION ROUTES
MOBILIZATION FROM SHEPHERD BAY
The selected mobilization route, as shown in Figure 2, has a total length of 84 kilometres. From the Shepherd Bay camp, the route is heading east for about 48 kilometres before reaching the Naqsanajuk Valley. This first section is mainly flat with occasional river crossings and drainage depressions. The elevation gain from the camp to the valley entrance is about 60 metres. From there, about 14 kilometres are necessary to reach the Angmaloqtuq river valley. This section climbs to the highest point of the route, reaching an altitude of 120 metres nearby the east end of the Naqsanajuk Valley. The third section goes down the Angmaloqtuq river valley for about 16 kilometres before reaching the Murchison River, at an altitude of about 55 metres. After crossing the Murchison River, the last section follows the east river bank for about 6 kilometres in the south direction before arriving to the staging area located nearby the borrow area 2. Figure 2: Mobilization route from Shepherd

N SHEPHERD BAY CAMP

Section 1 (60km)

Section 2 (14km) Naqsanajuk Valley

MID ROUTE STATION


Section 3 (16km) Angmaloqtuq river valley

Section 4 (5km) Murchison River

CAM-D STAGING AREA

6 Kudlik Construction Ltd.

Mobilization Plan

Remediation of CAM-D DEW Line Site Simpson Lake, Nunavut

4.2

MOBILIZATION FROM KUGAARUK


The mobilization route will be the same as the one used during winter 2009, where an excavator, a bulldozer and a safety shelter were transported to CAM-D. The route starts directly from the Kugaaruk hamlet and crosses the Pelly Bay. This section represents 30 kilometres on the bay ice. The second section follows the north branch of the Becher River for about 30 kilometres before reaching the east end of the Kuutsinaaq Lake. From that point, about 38 kilometres must be travelled on the Simpson Lake to reach the CAM-D staging area. Figure 3: Mobilization route from Kugaaruk

Section 3 (38km)

Kugaaruk

Section 1 (30km)

CAM-D STAGING AREA

Section 2 (30km)

7 Kudlik Construction Ltd.

Mobilization Plan

Remediation of CAM-D DEW Line Site Simpson Lake, Nunavut

5.

SHEPHERD BAY CAMP FACILITIES


As shown in Figure 4, the camp was installed on a previously disturbed area located about 400 metres south of the CAM-3 DND reserve. At the camp location, the calcareous bedrock, dipping to the west, is covered with a layer of sand and gravel. An area of about 100 metres long per 40 metres wide was reshaped to install the camp and set up the staging area. Figure 4: Camp Location

N DND RESERVE (CAM-3)

INAAC LAND CAMP LOCATION 68 47 48 N 93 37 16 W

MOBILIZATION ROUTE TO CAM-D

5.1

SHEPHERD BAY CAMP FACILITIES DESCRIPTION


The camp includes 10 individual rooms, a kitchen, a laundry room, a washroom with two toilets and a shower. When needed, room modules can be added to the camp. All facilities were made out of insulated marine containers especially fitted for rugged conditions. All camp rooms are heated with electric baseboard and have their own thermostat for temperature control. The camp layout was made to accommodate a 30x60 feet garage in the central area, as shown in Figure 6.
8

Kudlik Construction Ltd.

Mobilization Plan

Remediation of CAM-D DEW Line Site Simpson Lake, Nunavut

Figure 5: Shepherd Bays Camp Layout

The washroom includes a shower, a sink and two electric incinerating toilets. The kitchen comes with all cooking devices, appliances, and a sink. The eating room is adjacent to the kitchen. The camp is powered with a 90 kw diesel generator connected to a 4,000 litres stationary dyke tank. A 250 kw backup generator will be available until the end of the mobilization. The fuel barrel storage is located on the west side of the existing road. The generator fuel tank will be refilled with a mobile tank pulled by a tractor. The mobile tank will be refilled from the barrels with a vacuum pump. The camp communication devices are located in the kitchen and include a satellite phone, a VHF radio and a wireless internet system. A Bgan satellite terminal will be kept at the camp as backup communication system. Phone numbers, radio frequency and email addresses will be listed in the health and safety plan.

9 Kudlik Construction Ltd.

Mobilization Plan

Remediation of CAM-D DEW Line Site Simpson Lake, Nunavut

6.

CAM-D CAMP AND STAGING AREA LOCATION


The CAM-D camp will be installed inside the borrow area no.2 boundaries, nearby an unnamed river, which is a tributary of the Murchison River. The camp location is showed in Figures 6 and 7. Once mobilized, the equipments and materials will be parked at the camp location where a 4,200 square metres pad was prepared in September 2009. Figure 6: CAM-D camp location

MOBILIZATION ROUTE

CAM-D WORKING AREA

CAMP AND STAGING AREA

10 Kudlik Construction Ltd.

Mobilization Plan

Remediation of CAM-D DEW Line Site Simpson Lake, Nunavut

Figure 7: CAM-D camp location

Fuel Storage Camp location

Borrow area 2

11 Kudlik Construction Ltd.

Mobilization Plan

Remediation of CAM-D DEW Line Site Simpson Lake, Nunavut

APPENDIX 1 GANT CHART SCHEDULE

1 Kudlik Construction Ltd.

You might also like