METHOD OF STATEMENT FOR FOR COMMUNICATION EQUIPMENT FOR FACILITATING ENERGY BILLING SYSTEM (EBS) AT 3RD FLOOR AND

10TH FLOOR, WISMA SESB

CONTRACT TITLE:
Supply,Delivery,Installation,Testing and Comissioning of Communication Equipment for Facilitating Energy Billing System (EBS) at 3rd Floor and 10th Floor, WISMA SESB.

Project Code: T.

ISRINA RESOURCES SDN. BHD Sabah Electricity Sdn. Bhd. Project Code: T.6015

T.6015Supply,Delivery,Installation,Testing and Comissioning of Communication Equipment for Facilitating Energy Billing System (EBS) at 3rd Floor and 10th Floor, WISMA SESB.

INTRODUCTION The Method Statement for Wisma SESB Level 10 Installation describes the detail method of installation works that will be carried out for the new OLTE System T6015. The areas that will be involved in this project covers MTCC and Wisma SESB level 10.

SCOPE The following method statement describes the installation of SDH and Multiplexer for project T.6015.

2.1

Wisma SESB Level 10 2 nos of 19 Equipment Rack will be installed for SDH and Multiplexer equipment containing o One (1) new sub rack of Loop SDH O9400S o One (1) new sub rack of AM3440A o One (1) Fiber Optic Tray o One (1) new Rectifier- 48VDC

2.2

Wisma SESB MTCC o One (1) new sub rack of Loop SDH O9400S o One (1) new sub rack of AM3440A

T.6015Supply,Delivery,Installation,Testing and Comissioning of Communication Equipment for Facilitating Energy Billing System (EBS) at 3rd Floor and 10th Floor, WISMA SESB.

METHOD OF WORK 3.1 Duration Day 1 to 4

Start installation for New Metering Room Level 10 1. Install new DB at new Metering Room.(To be determined by SESB) 2. Make an opening (hacking) on the floor with the at Metering room for the power cable access between the the rectifier and the subrack inside the room. 3. Make an opening (hacking) on the wall with the size of 75mm x 50mm at DB room for the power cable access between the EE Room and DB room. 4. 5. 6. 7. 8. Install cable trunking between the wall and the MDF. Verify the location and path to install the cable trunking. Prepare the trunking and form for the installation. Mark the location for the wall plugs to secure the trunking onto the wall. Drill the marked location for the wall plugs. Before drilling, its suggested to tapereasonable size of plastic bag just below the drilling hole. A vacuum cleaner will be used to suck the drilling dust, dirt and flings as they are created. -Insert plastic wall plugs into the drilled holes. 9. Secure the trunking by screwing in screws into the wall plugs. 10. The activities above to be done during non-revenue hours. 11. The cable trunking will be installed:

3.2

Duration Day 1 to 4

Start installation for Wisma SESB MTCC 1. Install new SDH and Multiplexer inside existing Panel inside MTCC room. 2. Install cable trunking between DB CR/1 to new DB CR/3. 3. Install power cable between newly installed subracks to existing rectifier.

SAFETY Safety is of paramount importance during installation works and must be adhered to at all times by personnel involved in the work.

T.6015Supply,Delivery,Installation,Testing and Comissioning of Communication Equipment for Facilitating Energy Billing System (EBS) at 3rd Floor and 10th Floor, WISMA SESB.

In the event of emergency, the first point of contact should be the as per SESB site safety plan. All personnel shall attend and hold valid Construction Industry Development Board Malaysia (CIDB) qualification (also known as the green card).

4.1

Awareness Potential of risk and danger for this works are as follows: Falling at works area. Dust exposure. Electrocuted when doing power supply connection. Hand injury when install cable trunking or conduit.

4.2

Limitation The following is the limitation that all workers shall be follow: Do not work without SESB confirmation and authorization. Do not leave any tools etc inside the work area or anywhere else that could affect the SESB revenue services.

5 5.1

RESOURCES Manpower Requirement Six (6) persons will be involved; the work is expected to be completed within eight (8) days.

5.2

Machinery & Tools The following are the tools that will be used in the installation works of Radio Communications System: Screwdriver Marker & Measuring tape RJ45 connector crimping tool Cutter

T.6015Supply,Delivery,Installation,Testing and Comissioning of Communication Equipment for Facilitating Energy Billing System (EBS) at 3rd Floor and 10th Floor, WISMA SESB.

Multimeter Test Pen Knife Ladder Electronic Drill Insulation Resistance Test Gear

Procedure Prepared:

Person In Charge Abdul Rafiq Engineer Khairil Technical Manager Shariman Project Manager

Signature

Date 2011-02-21

Verified:

2011-02-21

Approved:

2011-02-21