MindView Project Reports

1z3

file:///C:/Users/Adam/Documents/MindView_Project_Reports.html

collapse all

Who Does What


ID

Task Name

Duration

Start

Finish

% Completion

BTH Student Portal Application


Adam
9

Creating the project plan

22 days

01/11/2011

30/11/2011

0%

11

Closing

29 days

21/06/2012

31/07/2012

0%

40

Creation of product backlog

5 days

28/12/2011

03/01/2012

0%

43

Planning the work for iterations

2 days

04/01/2012

05/01/2012

0%

47

Risk revision

1 day

06/01/2012

06/01/2012

0%

48

Coding

30 days

09/01/2012

17/02/2012

0%

50

Work progress reporting

1 day

27/01/2012

27/01/2012

0%

56

Coding

30 days

20/02/2012

30/03/2012

0%

58

Product integration with testing

5 days

02/04/2012

06/04/2012

0%

65

Coding

30 days

09/04/2012

18/05/2012

0%

67

Product integration with testing

5 days

21/05/2012

25/05/2012

0%

75

Bug fixing

18 days

28/05/2012

20/06/2012

0%

78

Product installation

5 days

21/06/2012

27/06/2012

0%

217 days

03/10/2011

31/07/2012

0%

Jackson
10

Monitoring and controlling

Janette
41

Code quality rules establishment

2 days

28/12/2011

29/12/2011

0%

42

Architecture influencing requirements selection

3 days

30/12/2011

03/01/2012

0%

43

Planning the work for iterations

2 days

04/01/2012

05/01/2012

0%

46

Burn down chart preparation

1 day

06/01/2012

06/01/2012

0%

48

Coding

30 days

09/01/2012

17/02/2012

0%

56

Coding

30 days

20/02/2012

30/03/2012

0%

58

Product integration with testing

5 days

02/04/2012

06/04/2012

0%

65

Coding

30 days

09/04/2012

18/05/2012

0%

67

Product integration with testing

5 days

21/05/2012

25/05/2012

0%

75

Bug fixing

18 days

28/05/2012

20/06/2012

0%

Jason
14

Objectives recognition

4 days

03/10/2011

06/10/2011

0%

16

Stakeholders identification

3 days

07/10/2011

11/10/2011

0%

17

Resources identification

3 days

12/10/2011

14/10/2011

0%

21

Requirements specification

8 days

20/10/2011

31/10/2011

0%

22

Requirements verification and acceptance

5 days

01/11/2011

07/11/2011

0%

29

Identification of products deliverables

4 days

14/11/2011

17/11/2011

0%

31

Creation of projects Gannt chart

3 days

21/11/2011

23/11/2011

0%

79

User manual preparation

15 days

14/05/2012

01/06/2012

0%

80

Training

40 days

04/06/2012

27/07/2012

0%

2011-10-13 17:46

MindView Project Reports

2z3

file:///C:/Users/Adam/Documents/MindView_Project_Reports.html

Jobson
15

Business problem analysis

7 days

03/10/2011

11/10/2011

0%

20

Requirements identification

6 days

12/10/2011

19/10/2011

0%

21

Requirements specification

8 days

20/10/2011

31/10/2011

0%

26

Preparing the reports

8 days

02/11/2011

11/11/2011

0%

30

Creation of complete WBS

5 days

14/11/2011

18/11/2011

0%

31

Creation of projects Gannt chart

3 days

21/11/2011

23/11/2011

0%

79

User manual preparation

15 days

14/05/2012

01/06/2012

0%

80

Training

40 days

04/06/2012

27/07/2012

0%

Johnny
4

Risk identification

4 days

17/10/2011

20/10/2011

0%

Risk assessment

4 days

21/10/2011

26/10/2011

0%

Creating risk management plan

4 days

27/10/2011

01/11/2011

0%

Creating quality management plan

8 days

02/11/2011

11/11/2011

0%

Creating change management plan

10 days

14/11/2011

25/11/2011

0%

11

Closing

29 days

21/06/2012

31/07/2012

0%

23

Software use cases modeling

7 days

10/10/2011

18/10/2011

0%

34

Global software design

12 days

24/11/2011

09/12/2011

0%

35

Module software view design

7 days

12/12/2011

20/12/2011

0%

36

Execution software view design

12 days

21/12/2011

05/01/2012

0%

46

Burn down chart preparation

1 day

06/01/2012

06/01/2012

0%

47

Risk revision

1 day

06/01/2012

06/01/2012

0%

53

Requirements selection and burn down chart


preparation

2 days

20/02/2012

21/02/2012

0%

54

Architecture redesign

3 days

22/02/2012

24/02/2012

0%

62

Requirements selection and burn down chart


preparation

2 days

09/04/2012

10/04/2012

0%

63

Architecture redesign

3 days

11/04/2012

13/04/2012

0%

Lorenzo
48

Coding

30 days

09/01/2012

17/02/2012

0%

56

Coding

30 days

20/02/2012

30/03/2012

0%

58

Product integration with testing

5 days

02/04/2012

06/04/2012

0%

65

Coding

30 days

09/04/2012

18/05/2012

0%

67

Product integration with testing

5 days

21/05/2012

25/05/2012

0%

68

Work progress reporting

1 day

27/04/2012

27/04/2012

0%

75

Bug fixing

18 days

28/05/2012

20/06/2012

0%

Monica
41

Code quality rules establishment

2 days

28/12/2011

29/12/2011

0%

42

Architecture influencing requirements selection

3 days

30/12/2011

03/01/2012

0%

43

Planning the work for iterations

2 days

04/01/2012

05/01/2012

0%

46

Burn down chart preparation

1 day

06/01/2012

06/01/2012

0%

48

Coding

30 days

09/01/2012

17/02/2012

0%

56

Coding

30 days

20/02/2012

30/03/2012

0%

58

Product integration with testing

5 days

02/04/2012

06/04/2012

0%

65

Coding

30 days

09/04/2012

18/05/2012

0%

67

Product integration with testing

5 days

21/05/2012

25/05/2012

0%

2011-10-13 17:46

MindView Project Reports

3z3

75

Bug fixing

file:///C:/Users/Adam/Documents/MindView_Project_Reports.html

18 days

28/05/2012

20/06/2012

0%

18 days

03/10/2011

26/10/2011

0%

Pablo
3

Project initiation

Creating quality management plan

8 days

02/11/2011

11/11/2011

0%

11

Closing

29 days

21/06/2012

31/07/2012

0%

25

Risk revision

5 days

08/11/2011

14/11/2011

0%

34

Global software design

12 days

24/11/2011

09/12/2011

0%

37

Architecture evaluation

19 days

12/12/2011

05/01/2012

0%

46

Burn down chart preparation

1 day

06/01/2012

06/01/2012

0%

47

Risk revision

1 day

06/01/2012

06/01/2012

0%

53

Requirements selection and burn down chart


preparation

2 days

20/02/2012

21/02/2012

0%

55

Risk revision

3 days

22/02/2012

24/02/2012

0%

62

Requirements selection and burn down chart


preparation

2 days

09/04/2012

10/04/2012

0%

64

Risk revision

3 days

11/04/2012

13/04/2012

0%

Tiago
9

Creating the project plan

22 days

01/11/2011

30/11/2011

0%

11

Closing

29 days

21/06/2012

31/07/2012

0%

40

Creation of product backlog

5 days

28/12/2011

03/01/2012

0%

43

Planning the work for iterations

2 days

04/01/2012

05/01/2012

0%

47

Risk revision

1 day

06/01/2012

06/01/2012

0%

48

Coding

30 days

09/01/2012

17/02/2012

0%

56

Coding

30 days

20/02/2012

30/03/2012

0%

58

Product integration with testing

5 days

02/04/2012

06/04/2012

0%

59

Work progress reporting

1 day

08/03/2012

08/03/2012

5%

65

Coding

30 days

09/04/2012

18/05/2012

0%

67

Product integration with testing

5 days

21/05/2012

25/05/2012

0%

75

Bug fixing

18 days

28/05/2012

20/06/2012

0%

78

Product installation

5 days

21/06/2012

27/06/2012

0%

Tonio
24

Preparation of acceptance tests plan

5 days

08/11/2011

14/11/2011

0%

49

Software verification

5 days

13/02/2012

17/02/2012

0%

57

Software verification

5 days

26/03/2012

30/03/2012

0%

58

Product integration with testing

5 days

02/04/2012

06/04/2012

0%

66

Software verification

5 days

14/05/2012

18/05/2012

0%

67

Product integration with testing

5 days

21/05/2012

25/05/2012

0%

71

Test cases preparation

3 days

28/05/2012

30/05/2012

0%

72

Functional testing

5 days

31/05/2012

06/06/2012

0%

73

Integration testing

5 days

07/06/2012

13/06/2012

0%

74

Acceptance testing

5 days

14/06/2012

20/06/2012

0%